A. The scope of this standard includes recommendations for the specification of cast-in-place concrete.

Similar documents
SECTION CAST-IN-PLACE CONCRETE

A. Section includes cast-in-place concrete, including reinforcement, concrete materials, mixture design, placement procedures, and finishes.

Columbia Public Schools Shepard Elementary School Classroom Building Addition PWA I 1 CONCRETE REINFORCEMENT ~4 ASSURANCE

CONCRETE WORK CONCRETE WORK. Underground Electric Distribution Standards I. SCOPE APPLICABLE STANDARDS

SECTION RIGID PAVEMENT

SECTION PRECAST CONCRETE COVER SYSTEM

SECTION CAST IN PLACE CONCRETE PART 1 GENERAL 1.01 RELATED DOCUMENTS

SECTION MISCELLANEOUS CAST-IN-PLACE CONCRETE

SECTION CAST-IN-PLACE CONCRETE

Division 03 Concrete Section includes various guidelines for general concrete use, curing, forming, reinforcing, finishing and concrete accessories.

SECTION CAST IN PLACE CONCRETE FOR FLOOR SLABS ON GRADE THAT WILL RECEIVE SEMI-PERMEABLE OR IMPERMEABLE FLOOR FINISHES

SECTION SITE CONCRETE

A. Section includes cast-in-place concrete, including reinforcement, concrete materials, mixture design, placement procedures, and finishes.

PRESTON HEALTH SERVICES ARCHITECT'S NO MITCHELL-HOLLINGSWORTH NURSING & REHAB

SECTION CAST IN PLACE CONCRETE

SECTION PORTLAND CEMENT CONCRETE PAVEMENT. All subsurface utilities must be inspected, tested, and accepted prior to any paving.

SECTION US Patent 8,857,130 B1 CAST-IN-PLACE CONCRETE WITH ARDEX CONCRETE MANAGEMENT SYSTEMS (ACMS ) EARLY MC APPLICATION

SECTION MINOR CONCRETE

1. Cast-in place structural concrete including footers, foundations, and other non-slab applications. 2. Formwork 3. Reinforcement

GUIDE SPECIFICATIONS For STRUCTURAL PRECAST HOLLOW CORE SLABS SECTION 03410

FOR PROJECTS INITIATED AFTER FEBRUARY 1, 2010 REVISION 3 ITEM 530 CONCRETE CURB, GUTTER, CURB AND GUTTER SIDEWALKS AND DRIVEWAYS

SECTION RIGID PAVEMENT. 1. Portland Cement Concrete (PCC) pavement. 2. Section Aggregate Base Course.

1.02 RELATED WORK: Refer to the following sections for related work:

A. Prepare formwork shop drawings using qualified professional engineer. Include detail of fabrication, assembly, and support of formwork.

REINFORCED CONCRETE MASONRY SECTION

CELCORE CELLULAR INSULATING CONCRETE SPECIFICATION FOR RETROFIT PLACEMENT OVER EXISTING ROOF MEMBRANES

.1 Concrete mix shall be in accordance with the following:.1 The average of all tests shall exceed 25 MPa.

SECTION CONCRETE PAVING

ITEM 432 RIPRAP. Dry Riprap is defined as Stone Riprap of the required type with voids filled only with spalls or small stones.

Paragraph Description Page No General Materials Concrete Masonry Work Altitude Valve Vault Cover 25-4

STANDARD SPECIFICATION FOR CRIBLOCK CONCRETE CRIBWALL

1. Manufacturer certified according to NRMCA's "Certification of Ready Mixed Concrete Production Facilities."

SECTION UNIT MASONRY

SECTION ARCHITECTURAL PRECAST CONCRETE. A. American Society for Testing and Materials (ASTM):

DIVISION II CONSTRUCTION AND MATERIAL SPECIFICATIONS SECTION 2700 STRUCTURES

SPECIAL SPECIFICATION 2042 Decorative Colored Pattern Concrete Paving

CHAPTER 9 - PORTLAND CEMENT CONCRETE

A. Texas Department of Transportation 2004 Standard Specifications for Construction and Maintenance of Highways, Streets and Bridges (TxDOT).

***************************************************************************************************************

A. Section includes cast-in-place concrete, including formwork, reinforcement, concrete materials, mixture design, placement procedures, and finishes.

SECTION 434 HIGH PERFORMANCE CONCRETE (HPC)


SECTION CONCRETE. B. ACI 318 Building Code Requirements for Structural Concrete and Commentary

SECTION CONCRETE PAVING FOR PEDESTRIAN AREAS. A. This Section includes exterior cement concrete pavement for the following:

B. Reinforcing. Materials shall be as specified in Section 2000 Concrete or as indicated on the plans.

DMS REINFORCED CONCRETE PIPE FABRICATION AND PLANT QUALIFICATION

G. Shop drawing of wall with all dimensions, details, and finishes. Drawings must include post foundations.

UPRR INDUSTRIAL LEAD BRIDGE T-WALL RETAINING WALL SYSTEM 5.0 x 7.5 UNITS DESIGN UNIT 018 WORK PACKAGE 04

SECTION CONTROLLED LOW STRENGTH MATERIAL

SECTION PORTLAND CEMENT CONCRETE

SECTION 54 STRUCTURAL CONCRETE (FAA P-610) ITEM P-610 STRUCTURAL PORTLAND CEMENT CONCRETE DESCRIPTION MATERIALS

September 1, 2003 CONCRETE MANUAL SPECIAL TYPES OF CONCRETE

An Introduction to Concrete Pavements

COMPLETE REVISION May Process Industry Practices Structural. PIP STS03001 Plain and Reinforced Concrete Specification

SECTION 941 PRECAST REINFORCED CONCRETE BARRIERS

2001 SCOPE. This section covers all cast-in-place concrete, including reinforcing steel, forms, finishing, curing, and other appurtenant work.

3/4/2015 COLD WEATHER CONCRETE PRACTICES SUCCESSFUL COLD WEATHER CONCRETING

SECTION 1 TERMS, DEFINITIONS, ABBREVIATIONS, UNITS OF MEASURE, AND SYMBOLS 1-3 ABBREVIATIONS Common Usage.

SECTION 44 SHOTCRETE, CAST CONCRETE CHANNEL LINING, AND GROUTED COBBLE TABLE OF CONTENTS

SECTION CONCRETE FORM WORK PART 1 GENERAL:

2. Exterior Concrete Exposed to Freeze/Thaw: 4500 psi minimum. i. Water Cement Ratio < 0.45 for exterior concrete exposed to freeze/thaw

1 Exam Prep Guide to Shotcrete Questions

Beyond Water-Cement Ratio and Strength. Patrick Harrison Vice President Structural Services, Inc.

SECTION 44 SHOTCRETE, CAST CONCRETE CHANNEL LINING, AND GROUTED COBBLE TABLE OF CONTENTS

SPECIFICATIONS FOR FABRICATION OF PRECAST CONCRETE PANELS

DIVISION 03 CONCRETE. Number CONCRETE

This section applies to the design and installation of cast-in-place concrete, shotcrete, precast concrete, and post-tensioned concrete.

CONCRETE WALKS AND CURBS SECTION CONCRETE WALKS AND CURBS PART 1 - GENERAL

WACEL STUDY GUIDE. Reinforced Concrete Special Inspector (Concrete II)

Construction Standard Specification Section Exposed Aggregate Concrete. Exposed Aggregate Concrete

ATLANTIC TESTING LABORATORIES Hot Weather Concreting

ANN ARBOR SKATE PARK SECTION SHOTCRETE

SECTION 44 SHOTCRETE, CAST CONCRETE CHANNEL LINING, AND GROUTED COBBLE TABLE OF CONTENTS

DIVISION 3 CONCRETE SECTION CAST-IN-PLACE CONCRETE

Fundamentals of Concrete

DIVISION 03 CONCRETE CONCRETE REINFORCING Reinforcing Steel Welded Wire Fabric Reinforcing Fibrous Reinforcing

SECTION CAST-IN-PLACE CONCRETE

SECTION CAST-IN-PLACE CONCRETE

DIVISION 3 HEAVY DUTY CONCRETE FLOOR TOPPING SECTION 03340

SPECIAL PROVISION Concrete Pavement

Construction Standard Specification Section Exposed Aggregate Concrete

indicated on the Drawings include exterior curbing and walkways necessary for the repairs or of this portion of the Work and who shall be thoroughly

LITHOCRETE ARCHITECTURAL CONCRETE PAVING

Page 1 March 2014 Catholic District School Board of Eastern Ontario C&A Project No

ITEM 431 PNEUMATICALLY PLACED CONCRETE. All material shall conform to the pertinent requirements of the following items:

UNIVERSITY SERVICES ANNEX James Madison University Harrisonburg, Virginia State Project Code: Architect s Project Number:

SECTION CONCRETE REINFORCEMENT

A. Submittal Procedures: See Article 13 of the General Conditions.

SECTION 11 - REINFORCED AND PLAIN CONCRETE WORKS CONTENTS

SECTION CONCRETE CURB AND GUTTER, SIDEWALKS, AND DRIVEWAYS

2014 Capital Project Phase 3 Grand Island Central School District Cannon Design Project No SECTION PAVING PART 1 - GENERAL

SPECIAL SPECIFICATION 4491 Type CAC Concrete

TILT-UP PRECAST CONCRETE SANDWICH PANELS. A. Work includes, but is not limited to, the following:

SECTION CONCRETE CURBS, GUTTERS AND SIDEWALKS

CONCRETE PAVEMENTS GUELPH TRANSIT OPERATIONS & MAINTENANCE SECTION WATSON ROAD FACILITY PAGE 1 OF 7 WATER RECLAMATION PROJECT JUNE 2013

DIVISION 03 CONCRETE. Section Title Number CONCRETE

3/5/2014. Disclaimer and Waiver of Liability. Portland Cement Association. Learning Objectives. Why do concrete problems occur?

ITEM 6 CONCRETE CURBS, GUTTERS, AND SIDEWALKS

SAMPLE SPECIFICATION ONLY FOR INFORMATIONAL PURPOSES NOT INTENDED FOR DUPLICATION OR USE SECTION XX.XX WELDED WIRE REINFORCEMENT

.1 Formwork for cast-in-place concrete with shoring, bracing, and anchorage.

Transcription:

PART 1: GENERAL 1.01 Scope of Standard A. The scope of this standard includes recommendations for the specification of cast-in-place concrete. 1.02 Related Standards A. Structural Systems (currently The University of Texas Office of Facilities Planning and Construction Owner s Design Guidelines, Section K, Structural Criteria). 1.03 Reference Standards A. The current editions of the applicable American Concrete Institute (ACI) publications, to the extent applicable in each reference. B. The current editions of the applicable American Society for Testing and Materials (ASTM) specifications, to the extent applicable in each reference. C. Concrete Reinforcing Steel Institute (CRSI) Manual of Standard Practices. 1.04 Environmental Controls A. Rinsing out of the transit mix trucks, washing or wetting of concrete, site cleanup, or other activity related to water at the site shall be in strict conformance with all EPA requirements for the prevention of water runoff to stormwater sewers or creeks. PART 2: PRODUCTS 2.01 Materials A. All concrete shall be normal weight concrete weighing not more than 145 pcf, unless otherwise required. B. Cement 1. Cement shall conform to one of the following: Type/ASTM No. IA/C150 IIA/C150 Description Standard portland cement. Provides moderate sulfate resistance or moderate heat of hydration. Design and Construction Standards, Revised December 14, 2001 03300-1

IIIA/C150 IPA/C595 Produces high early strength. Type I cement blended with a pozzolan (20% by weight maximum of the cement/pozzolan blend). E-IKA/C845 Contains anhydrous calcium aluminosulfate, calcium sulfate, and uncombined calcium oxide. 2. Only one type and brand of each type of cement will be permitted in any one structure. C. Flyash 1. Conform to ASTM C618, Class F. Class F flyash is generally the best class of flyash to use. However, flyash varies from area to area and from year to year so the source and quality should always be checked carefully. 2. Flyash shall be produced from a single known and consistent source. 3. The amount of flyash used shall be no greater than 20 percent by volume of the specified cement volume (cement is specified by weight, which can be converted to an equivalent volume). 4. Flyash shall not be used in architecturally exposed concrete. D. Aggregates 1. Aggregates shall conform to ASTM C33. 2. Use coarse aggregate from only one source and fine aggregate from only one source for exposed concrete in a single structure. E. Mixing Water shall be potable. F. Admixtures 1. The use of a superplasticizer is recommended, especially where waterproofing is required since it helps to produce a denser, more water-resistant concrete. G. Chlorides are not permitted in any form. H. Reinforcing Steel 1. Conform to ASTM A615, Grade 60 (#3 bars shall be Grade 40). Design and Construction Standards, Revised December 14, 2001 03300-2

2. Welded wire fabric shall be supplied in flat sheets only. I. Waterstops 1. A major problem with flexible waterstops is that they are often displaced during concrete placement. Thus watertightness is impaired. The drawings and/or specifications should carefully address proper placement of flexible waterstops. Some waterstops are manufactured with wire embedded in them that allow the waterstops to be tied off more securely during concrete placement. Since waterstops are critical to watertightness in a structure, these reinforced waterstops should be considered. 2. Splices should be fused or "welded" in accordance with the material chosen and the manufacturer's recommendations. 3. Where adhesive or rope waterstops are specified, the products shall have a proven life consistent with expected life of the structure being designed. 2.02 Proportioning of Concrete A. Select proportions of ingredients to produce a concrete having proper workability, durability, strength, and appearance. Proportion ingredients to produce a mixture that will work readily into corners and angles of forms and around reinforcement by methods of placing and consolidation employed on the project. B. The maximum recommended allowable water/cement or water/cementpozzolan ratio shall not exceed 0.47. Include free water in the aggregate in all water/cement or water/cement-pozzolan ratio computations. C. Air entrainment shall be included in all concrete mixes, unless required otherwise. Design and Construction Standards, Revised December 14, 2001 03300-3

PART 3: EXECUTION 3.01 Rinsing Trucks A. Rinsing of transit mix trucks or other concrete mixing devices shall either be off of the Owner s site or onsite in a contained area, which does not allow run-off. If rinsed in a contained area onsite, run-off must be prevented until concrete dries, at which time it must be removed as solid debris. 3.02 Reinforcing A. Reinforcing bars field cut on the job shall be cut by shearing or sawing. Field cutting with a torch is not acceptable. B. Welding of reinforcing bars is prohibited. Mechanical methods for splicing bars are preferred. 3.03 Construction Joints A. Construction joints should be shown on the drawings to assure that the Contractor does not place joints where watertightness or strength of the structure will be impaired. A note should be placed on the drawings that all construction joints not shown on the drawings should be submitted to the Engineer for approval. B. Constructability is very important to assure good concrete placement. Therefore, the Engineer should be careful in reviewing proposed joints so that those necessary for constructability are not rejected. C. 100% of reinforcing shall be continuous across construction joints. 3.04 Control Joints A. Control joints are herein described as joints that are designed to allow for movement either from contraction or expansion. B. Contraction joints allow for contraction of the concrete and also function as construction joints. 1. Fifty percent of reinforcing shall be continuous across contraction joints. 2. If saw-cutting of contraction joints is allowed, the following shall be adhered to: Design and Construction Standards, Revised December 14, 2001 03300-4

a. During hot and dry periods, saw-cutting should occur within 4 to 12 hours of concrete placement. b. During cool and moist periods, saw-cutting should occur within 24 hours of concrete placement. 3. Where applicable, use waterstops to assure watertightness. C. Expansion joints allow for expansion of the concrete and also function as construction and contraction joints. 3.05 Concrete Finishing 1. Reinforcing shall not be continuous across expansion joints, except for shear transfer as noted below. 2. For shear transfer, use smooth dowels with expansion caps on one side. 3. Expansion joints should be considered at approximately 120 foot spacing as a general rule. 4. Where applicable, use waterstops to assure watertightness. A. Carefully specify the types of concrete finishing required for all areas of the structure to assure proper finishing and to avoid costly change orders due to lack of definition on the drawings or in the specifications. 1. Rough form finish shall be in accordance with ACI 301, Section 10.2.1. This is the roughest finish and is recommended for surfaces that will not be visible in the completed structure. 2. Smooth form finish shall be in accordance with ACI 301, Section 10.2.2. A smooth form finish is recommended for surfaces to be coated or where appearance is not important. 3. Smooth rubbed finish shall be in accordance with ACI 301, Section 10.3.1. A smooth rubbed finish requires an initial smooth form finish as required above. A smooth rubbed finish is recommended for surfaces that will not be coated and do not require a highly finished appearance. A smooth rubbed finish should also be used if recommended by the manufacturer of the specified protective coating(s). 4. Grout cleaned finish shall be in accordance with ACI 301, Section 10.3.2. A grout cleaned finish requires an initial smooth form finish as Design and Construction Standards, Revised December 14, 2001 03300-5

required above. A grout cleaned finish is recommended for surfaces that will not be coated but do require a highly finished appearance. A grout cleaned finish is labor intensive and requires some skill to produce the desired results. Therefore, the Contractor's procedure must be monitored carefully to assure that a proper finish is obtained. Depending on the project, a protective coating can be more cost effective. 5. Tops of walls and similar unformed surfaces occurring adjacent to formed surfaces shall be struck smooth after concrete is placed. Float unformed surfaces to a texture consistent with that of the formed surfaces. Final treatment on formed surfaces shall continue uniformly across the unformed surfaces. B. Carefully specify the finishing slabs and similar flat surfaces for all areas of the structure to assure proper finishing and to avoid costly change orders due to lack of definition on the drawings or in the specifications. 3.06 Testing and Control 1. Floated finish. Usually most slabs and flat surfaces receive a floated finish, except as noted below. 2. Troweled finish. Usually a troweled finish is specified where a nicer finished appearance is desired or where floor coverings will be applied. 3. To obtain a broom, belt, or rake finish, immediately upon completing a floated finish, draw a broom or rake across the surface to give a coarse transverse scored texture. Usually a broom, belt, or rake finish is specified for sidewalks and ramps. A. The Contractor shall be required to employ, at his expense, a commercial testing laboratory, acceptable to the Owner, to prepare and test the initial mix design for each class of concrete specified. B. In addition to the initial mix design(s), the Contractor shall be required to employ, at his expense, a commercial testing laboratory, acceptable to the Owner, to prepare and test the mix design for each class of concrete for which the material source has been changed. C. Field Test Cylinders During Construction. 1. Mold four cylinders for each set of tests specified. Design and Construction Standards, Revised December 14, 2001 03300-6

2. Test one specimen at 7 days and two at 28 days according to ASTM C39. If one, or both, of the 28-day tests indicate a compressive strength below the strength required, the fourth specimen shall be tested at 56 days. If all tests indicate a compressive strength below the strength required, the Engineer may, at his discretion, direct the Contractor to perform testing of in-place concrete at no additional cost to the Owner, regardless of the outcome of the tests. 3. The Contractor may, at no additional cost to the Owner mold additional cylinders for earlier strength testing or other reason as may be required by the Contractor. 3.07 Testing of Deficient In-place Concrete A. The strength of the concrete will be considered potentially deficient if the averages of two consecutive sets of strength test results fail to equal or exceed the specified strength or if any individual strength test result falls below the specified strength. Testing may be required as directed by the Engineer. B. Concrete work not having the required strength, as determined by the Engineer, shall be replaced at the Contractor's expense. C. The Contractor shall bear all costs incurred in providing the additional testing and/or analyses required as a result of deficient in-place concrete. All costs as a result of delays due to additional testing and/or analyses will be at the Contractor's expense, with no extension of contract length, regardless of the outcome of the testing. 3.08 Acceptance of Concrete Work A. Formed surfaces resulting in a configuration of members smaller than permitted under the tolerances specified shall be considered deficient and repaired or replaced as directed by the Engineer. B. Concrete members cast in the wrong location shall be rejected if the strength, appearance, or function of the structure is, in the Engineer's opinion, adversely affected or if misplaced members interfere with other construction. If rejected, remove members cast in the wrong location and repair or replace at the Contractor's expense as directed by the Engineer. C. All work required under this section shall be at the Contractor's expense, with no extension of contract length. END OF STANDARD 03300 Design and Construction Standards, Revised December 14, 2001 03300-7