M&V Fundamentals & the International Performance Measurement and Verification Protocol

Similar documents
Practical Experiences in Applying Savings M&V

International Performance Measurement and Verification Protocol. International Energy Efficiency Financing Protocol

Measurement & Verification for Performance Contracts Through Rebuild Colorado. January Rebuild Colorado

THE ROLE OF IPMVP IN ESCO M&V ACTIVITIES

Project Measurement and Verification Procedures

THE ROLE OF IPMVP IN ESCO M&V ACTIVITIES

MEASUREMENT AND VERIFICATION GUIDELINES FOR RETROFIT AND NEW CONSTRUCTION PROJECTS

Incentives. After work is complete:

M&V Guidelines for Colorado PC projects. You cannot manage what you do not measure

PROCESS & SYSTEMS PROCESS & SYSTEMS

PROVING THE SAVINGS: MEASUREMENT & VERIFICATION

ENERGY SAVINGS MEASUREMENT & VERIFICATION MANAGING THE RISKS

Measurement and Verification, Commissioning Applications

2012 CLEAResult All rights reserved. Industrial Facility

Methodologies for Determining Persistence of Commissioning Benefits

M&V Applications and Approaches Balancing Project Demands to Deliver an Accurate, Cost Effective, and Verifiable M&V Outcome

ROADMAP TOWARDS NEARLY ZERO ENERGY SPORT BUILDINGS

2015 Energy Efficiency Program for Business

7 Measurement and Verification for Generic Variable Loads

International Performance Measurement and Verification Protocol. Core Concepts. Prepared by Efficiency Valuation Organization

Energy Project Measurement and Verification Procedures

Measurement and Verification: Monitoring Lighting Systems for Optimal Performance

M&V M&V M&V M&V M&V M&V M&V M&V M&V. M&V Guidelines: Measurement and Verification for Federal Energy Projects. Version 2.2

How to measure change. The energy market experience

Strategies for Persistence: Measurement and Verification. Ryan Hughes PE, CEM, LEED AP Eaton Energy Solutions

Practical M&V for Recommissioning Projects

Success with MEASUREMENT & VERIFICATION

M&V Guidelines: Measurement and Verification for Federal Energy Projects. Version 3.0

ECONOMIC DEVELOPMENT BY GAINING EFFICIENCY: STRATEGIC DATA COLLECTION WORKSHOP ENERGY SUB-METERING FOR MEASUREMENT AND VERIFICATION

Energy Management Measures Evaluation and Financing Energy Management

STREET LIGHTING PROTOCOL

Electric Standard Offer Program

Improving Energy Retrofit Decisions by Including Uncertainty in the Energy Modelling Process

Energy Modeling Applications for Existing Buildings

Architect and Engineer Lunch and Learn

Preparing Your Prop 39 Application: The TerraVerde Energy Report Card

Commercial Retro-Commissioning Program Manual for 2015 SECTION 1

Truing-Up to Billing Data

Guidelines for Verifying Existing Building Commissioning Project Savings. Using Interval Data Energy Models: IPMVP Options B and C

LIST OF TABLES LIST OF FIGURES ACKNOWLEDGEMENTS ABSTRACT INTRODUCTION LITERATURE REVIEW STEEPLE

Energy savings reporting and uncertainty in Measurement & Verification

TARGETED TERTIARY PROTOCOL

Measurement and. Verification, Best Practices in Design and Implementation. Tom Martin CMVP, LEED AP. Homay Khatami CEM, LEED AP PMP, CMC

Permanent Load Shifting Program

Energy Audit Tool Manual. Client Name

Commissioning In Energy Savings Performance Contracts

M&V - the ESCO approach Measurement and Verification of Energy Efficiency Projects Association of Energy Engineers Technical Round Table Series, III

International Certification Scheme 1.0

Note 11: NOVEM target April 2016

AN INTRODUCTION TO WEATHER NORMALIZATION OF UTILITY BILLS FOR ALTERNATIVE ENERGY CONTRACTORS. John Avina, Director Abraxas Energy Consulting

MEASUREMENT AND VERIFICATION TOOLS Spiros Metallinos Regulatory Authority for Energy, Greece

SOLAR ASSISTED HVAC HVAC

Project Information. Measure Description

Financing Energy Efficiency as a Viable Alternative to New Energy Supply

Southwest Texas Junior College

D DAVID PUBLISHING. Optimizing Thermal Energy Storage Systems in the Hospitality Industry. 1. Introduction

Standardizing for Energy Measurement: Considerations, Challenges, & Reality. Jeremy Yon Current by GE / ANSI C137 ad hoc committee

Appendix D Example M&V Plans

International Performance Measurement and Verification Protocol

Creating Environmentally Sustainable Buildings TM

Energy Manager Quiz with Answers

2017 Energy Manager Quiz with Answers

ENERGY PERFORMANCE PROTOCOL

Building Operator Certification Level I

Incentives and Financing help to get your project paid for

4/30/2018. Connecticut Energy Efficiency Board C1630: Largest Savers Evaluation April 25, Overview

M&V 2.0: A User s Guide

How Much is Enough? Lessons Learned on Performance Periods for Monthly Whole Building Regression Modeling

Competency Certification for Energy Efficiency. Carmen Best California Public Utilities Commission

Both components are available to non-residential customers in Public Service s electric and natural gas service territory.

Investor Confidence Project

TARGETED TERTIARY PROTOCOL

A Case Study in Energy Modeling of an Energy Efficient Building with Gas Driven Absorption Heat Pump System in equest

Investor Confidence Project

COMPLEX INDUSTRY AND ENERGY SUPPLY PROTOCOL

Savings Estimation Methods for Energy Efficiency Programs: A Half-Hour Guide

Case Study. Vermont State Office Building: Advanced Analytics for Measurement and Verification

Share this ebook! How M&V Benefits You

Investor Confidence Project

EEOS Guidance To Authenticate Claim Energy Credits_V2

Investor Confidence Project

SUCCESS STORY ENERGY TO CARE RUSSELL REGIONAL HOSPITAL. Russell Regional Hospital Employs an ESCO to Build Enthusiasm and Achieve ENERGY STAR 100.

New Jersey Board of Public Utilities Clean Energy Program Incentives and Proposed Hurricane Sandy Storm Response

Performance Analysis of Hotel Lighting Control System

APPENDIX A MEASUREMENT TERMS AND DEFINITIONS

Energy Conservation Measure Development Identify, Screen, and Analyze

National Grid USA Service Company. Impact Evaluation Of 2006 Design2000plus Custom Comprehensive Projects. Final Report

Time to Move On: An Examination of Metering Periods for Small Business Direct Install Participants

Focus on Energy Calendar Year 2014 Evaluation Report Volume II May 27, 2015

Energy Efficiency Measurement and verification in South Africa for bigee. Authors Xianming Ye CNES University of Pretoria Approved by SANEDI

Measurement & Verification The Principles

EVALUATING THE ENERGY SAVINGS OF HIGH PERFORMANCE BUILDING ENCLOSRE RETROFITS Brittany Hanam, MASc, P.Eng. Graham Finch, MASc, P.Eng.

ENERGY MODELING FOR MEASUREMENT AND VERIFICATION

Investor Confidence Project

Investor Confidence Project

Common monitoring guidelines for the demonstration sites

Retro-commissioning and on-going commissioning 23 November 2016

Investor Confidence Project

Agenda October 20 th Meeting

SMART HVAC & LIGHTING SYSTEMS. Savings From Two Major C&I End Uses

Transcription:

M&V Fundamentals & the International Performance Measurement and Verification Protocol

What is M&V? Measurement & Verification (M&V) is the process of using measurements to reliably determine actual saving created within an individual facility by an energy management program. Ref: IPMVP Vol I, 2007, Section 9 Introduction 2

EVO Efficiency Valuation Organization (EVO) www.evo-world.org The home of the IPMVP A non-profit U.S. corporation Led by volunteers around the world Administrative office in Sofia, Bulgaria. Introduction 3

EVO Protocols M&V, Financing Training, Certification Certification (CMVP) is joint with the Association of Energy Engineers Building Community, Promoting Efficiency Subscriber services through www.evo-world.org: industry newsletter, blog, library, discounts, pre-release access to public documents World wide partnerships for communication, training and Introduction 4 development

IPMVP - Overview Presents a framework and defines terms used in determining savings after implementation of a project. Specifies the topics to be addressed in an M&V Plan for a specific project. Allows flexibility in creating M&V Plans, while adhering to the principles of: accuracy, completeness, conservativeness, consistency, relevance and transparency. Introduction 5

Why M&V? The Spectrum of M&V Purposes of M&V Your reasons?

The M&V Spectrum No M&V No extra cost (or more left to spend on retrofits) Most energy retrofits since 1975 K.I.S.S. (Low cost M&V without the M, just the V) Full M&V Maximize savings Savings persistence Energy users needing performance demonstration or guarantee (mostly utilities & public buildings) - since 1990 emission traders Introduction 7

The Purpose of M&V Simply M&V provides PROOF of the effectiveness of energy management Introduction 8

M&V Fundamentals & the International Performance Measurement and Verification Protocol For Energy Managers and Emission Traders Key Concepts

Key Concepts - Program Measurement? IPMVP s basic equation Four Options Common M&V issues Key Concepts 10

The M in M&V The M in M&V stands for: Measurement Not Monitoring (Monitoring is an activity which takes place after the Measurement of savings. Monitoring is the evaluation of the savings and taking any necessary action.) Key Concepts 11

Measure Savings? Savings are the absence of energy use. We can not measure what we do not have. We do not measure savings! We do measure energy use. We analyze measured energy use to determine savings. Key Concepts 12

A Notional Baseline Baseline + Adjustments 1,000,000 Energy 750,000 500,000 Savings 250,000 Baseline Period Reporting Period Metered Energy Key Concepts 13

IPMVP Basic Equation The Basic IPMVP Savings Equation #1: Savings reported for any period = Baseline Period energy - Reporting Period energy +/- Adjustments Key Concepts 14 Ref: IPMVP Volume I, 2007, Chapter 4.1

Adjustments An example of why we need Adjustments: An energy retrofit was performed but plant production was also lower this year than last. How much of the resultant cost reduction was due to the retrofit, and how much was due to the production change? Key Concepts 15

Adjustments (continued) Performance measurement requires an apples to apples comparison. Baseline Period Reporting Period We adjust baseline and reporting period energy use to the same set of conditions, for valid comparisons. Key Concepts 16

Savings or Avoidance? Energy users usually want to know how much their bills would have been if they had not taken energy efficiency action. They want to know how much energy or cost they avoided. To report avoided cost, M&V engineers adjust baseline period energy use to the conditions of the reporting period. They sometimes simply call cost avoidance savings, at risk of confusion with accountant reports. Key Concepts 17 Ref: IPMPV Vol I, 2007, Chapter 4.6.1

Accounting Savings Accountants often use the word savings to describe cost reductions. They make no adjustments. So, when talking about savings we have to be very careful to explain our meaning. We must report the common set of conditions (apples) we are using for stating savings. Key Concepts 18

Adjustments The Adjustments can be trivial, simple or complex. M&V budgets usually determine how simple or complex the Adjustments are. The extent of the Adjustments depends on: the need for accuracy, the complexity of factors driving energy use, and the amount of equipment having its performance assessed (i.e. measurement boundary ). Key Concepts 19

How Much to Measure? Motors + VSDs Retrofit Isolation Boundary Key Concepts 20 Whole Facility Measurement Boundary

Two Basic Methods Whole Facility Method: Measures all effects in the facility: Key Concepts 21 Retrofits AND other changes (intended and unintended) Often uses the utility meter Adjustments can be complex Retrofit Isolation Method: Measures the effect of the retrofit, only Savings are unaffected by changes beyond the measurement boundary Usually needs a new meter Adjustments can be simple

Selecting a Method Decide what you are concerned about! If you want to manage your total energy use: select the Whole Facility Method. If you want to assess a particular retrofit: select the Retrofit Isolation Method. Key Concepts 22

Terminology: Retrofit Isolation Option A or B Whole Facility Option C or D Two flavours of each method to allow flexibility for various situations Key Concepts 23

Retrofit Isolation Select between Options A and B: Option A Retrofit Isolation: Key Parameter Measurement Option B Retrofit Isolation: All Parameter Measurement Key Concepts 24

Retrofit Isolation (A and B) Key Concepts 25 Option A Option B Baseline period measurement 400 kw 200,000 kwh Reporting period measurement Estimated operating hours 300 kw 500 hrs 150,000 kwh 100kw x 500hrs 50,000 kwh Avoided Energy = 50,000 kwh A measure only the key part of the energy computation, for example: a contractor is only responsible for a load reduction (or only responsible for a reduction in operating hours, but not both) B measure all factors governing energy use, for example: a contractor is responsible for controls which dim lights automatically and control operating periods.

Option A - Uncertainty Option A (called Retrofit Isolation: Key Parameter Measurement) allows a possible reduction in measurement cost, but introduces some uncertainty in the estimated quantity. All parties must accept the uncertainty associated with the estimate. The choice between Options A and B allows flexibility to suit the situation. Key Concepts 26

Whole Facility Select Option C or D, based data availability: C Whole Facility Need both baseline and reporting period data D Calibrated Simulation When there is no meter (or facility) in the baseline, baseline data can be manufactured under controlled circumstances. Key Concepts 27

Option C - Example Baseline period electricity bill July 1999 (29 days) = 800,000 kwh Reporting period electricity bill July 2001 (31 days) = 600,000 kwh Raw difference = 200,000 kwh Adjustment of baseline for meter reading period length & weather = +100,000 kwh Avoided Energy = 300,000 kwh Key Concepts 28

Option D - Example Consider the case of a new building, designed to be more efficient than some Standard. To prove how much better actual energy performance is than the standard: 1. After full occupancy begins, gather actual utility metered data (= calibration data ). 2. Prepare a computer simulation of the energy use of the same as built conditions. 3. Compare simulated and actual energy use. Key Concepts 29

Option D - Example 4. Calibrate (or adjust) the simulation until the differences are acceptable. 5. The CALIBRATED SIMULATION now shows actual energy use of: 5,000,000 kwh 6. Modify this Calibrated Simulation to remove the energy efficiency enhancements (to reflect a building built to the Standard). Simulated Standard energy use is: 7,000,000 kwh 7. Avoided Energy = 2,000,000 kwh Key Concepts 30

Summary of IPMVP Options The IPMVP has four M&V Options: A, B, C, and D The Options are generic M&V approaches for energy and water saving projects. Four Options provide a range of approaches for determining energy savings, to suit the characteristics of the ECMs being implemented and the desired balance between reporting accuracy and cost. Key Concepts 31

Common M&V Issues: M&V Cost Performance Contracts

M&V Cost Key factors affecting M&V Cost: Meter quality Number of independent variables to be monitored Frequency of measurement and reporting Length of the baseline and reporting periods Sample size, if all equipment is not measured Other uses for meter information, to share costs Key Concepts 33

How Much M&V Is Enough? Total annual cost to determine savings should normally be less than 10% of the annual savings. (Ref: IPMVP Vol I, 2007 Chapter 8.5) (This maximum might be exceeded for special situations.) 3-5% is a more common expenditure (for ESCO projects) 0% is often chosen (= deemed savings ). No measurement means uncertain savings. This is NOT an IPMVP method The cost/accuracy tradeoff is made for each project Key Concepts 34

Performance Contracts M&V plays a critical role in performance contracts: maximizes the savings and the persistence of savings over the contract term documents what savings were achieved and acts as the cash register for the exchange of value Performance contracts allocate the costs and benefits of M&V accuracy between the ESCO and Owner. Carefully consider contract motivations of all parties before designing the M&V. Append the M&V Plan to the contract. Key Concepts 35

M&V Fundamentals & the International Performance Measurement and Verification Protocol For Energy Managers and Emission Traders Short Examples

Short Examples - Program Multiple ECM Building Retrofit (Option C) Lighting Efficiency Improvement (Option A) Short Examples 37

Sample M&V Project Commercial Building in Canada Energy Conservation Measures Simple Payback (years) Lighting retrofit 4.5 Energy efficient motors 5.6 HVAC modifications 5.4 Control system 3.4 Building leakage reduction 2.1 Training and awareness 0.5 Short Examples 38

Option C - Whole Facility Selected Option C to assess total performance Use data from utility meters (gas and electric). Analyze baseline gas meter data relative to weather, to determine the correct weather adjustments. Weather will be expressed in heating degree days (HDD). You will compute savings for two months. Short Examples 39

Sample Option C Baseline Data Short Examples 40 Meter Reading Gas Heating Date Consumption Degree February 5, 2004 units Days March 5, 2004 210,692 650 April 7, 2004 208,664 440 May 6, 2004 157,886 220 June 5, 2004 120,793 150 July 7, 2004 116,508 50 August 7, 2004 107,272 20 September 5, 2004 95,411 14 October 6, 2004 126,423 29 November 6, 2004 149,253 125 December 4, 2004 166,202 275 January 6, 2005 221,600 590 February 5, 2005 224,958 723 Total 1,905,662 3,286

Sample Option C Baseline Model The Gas vs Heating Degree Day relationship was found by regression analysis to be: 250,000 200,000 Gas 150,000 100,000 50,000 0 y = 173.27x + 111358 0 200 400 600 800 HDD Short Examples 41 Gas = 173.27 * HDD + 111,358 (Regression analysis techniques are not part of this course.)

Short Examples 42 Sample Option C Method 1. Record the current weather (HDD) 2. For each month after retrofit, compute what the baseline gas use would have been for those HDD by plugging HDD into the baseline model: Gas = 173.27 * HDD + 111,358 3. Compare the computed baseline gas with actual reporting period gas, to determine avoided gas. 4. Apply the current utility price to both baseline and actual to calculate cost avoidance.

Sample Option C Graphical View Of Savings 250,000 Baseline model 200,000 Gas 150,000 100,000 50,000 0 Reporting period gas 0 200 400 600 800 HDD Short Examples 43

Sample Option C Actual Post- Retrofit Data Computations Projected Baseline Savings Meter Reading Weather Baseload Date Sensitive Value Total Gas Consumption HDD Factors Price = (units) Units 111,358 173.27 $ 6.232 March 6, 2006 151,008 601 111,358 104,135 215,493 64,485 $ 401,871 April 4, 2006 122,111 420????? May 6, 2006 102,694 188 111,358 32,575 143,933 41,239 $ 257,001 June 5, 2006 111,211 250 111,358 43,318 154,676 43,465 $ 270,874 July 5, 2006 80,222 41 111,358 7,104 118,462 38,240 $ 238,312 August 6, 2006 71,023 15 111,358 2,599 113,957 42,934 $ 267,565 September 8, 2006 65,534 5 111,358 866 112,224 46,690 $ 290,972 October 9, 2006 77,354 12????? November 4, 2006 103,000 190 111,358 32,921 144,279 41,279 $ 257,251 December 10, 2006 115,112 300 111,358 51,981 163,339 48,227 $ 300,551 January 7, 2007 160,002 700 111,358 121,289 232,647 72,645 $ 452,724 February 4, 2007 145,111 612 111,358 106,041 217,399 72,288 $ 450,499 Short Examples 44

Option C - Best Applications Significant energy saving (10% or more of consumption measured by the utility meter) All parameters which significantly affect energy usage can be clearly identified (during baseline and after implementation) Adjustments factors are simple Individual ECM measurement is not required Multiple ECMs Complex ECMs Soft savings ECMs (eg. building leakage reduction, operator training, occupant/user awareness) Short Examples 45

Option C Advantages & Disadvantages Advantages: Evaluates performance of the entire facility Includes interactive effects amongst ECMs, and between ECMs and the rest of the facility Disadvantages: No separation of the impact of different ECMs Not a saving control method, since normal unexplained total facility energy variations may obscure individual months savings. However the method provides annual reconciliation. Short Examples 46

Sample M&V Project Hospital Energy Conservation Measures Simple Payback (years) Lighting power reduction 2.7 Water conservation 2.2 Steam system management 1.3 Power factor correction 2.3 Sterilizers and DHW 6.5 Chiller Plant 9.7 Short Examples 47

Sample M&V Project Retrofit Isolation ECM Lighting power reduction Short Examples 48 Item Measured Fixture kw demand Level Measured Random sample Water Water flow Sample toilets & showers Item Assumed Hours of Use (based on lighting logger data taken before retrofit) Toilets: # Flushes Showers: # & Time Steam Traps Steam Loss Sample Extrapolate to all Power Factor Utility Bill 100% Annual avoided utility bill cost penalty Sterilizer Steam Use 100% Annual usage Chiller Plant Efficiency kw/ton 100% Ton Hours

Sample M&V Project Retrofit Isolation As an example, consider the M&V design for the Lighting ECM, using Option A, Retrofit Isolation: Key Parameter Measurement. Before and after sample load measurements Assumed operating hours of lights. Short Examples 49

Sample Option A Lighting - Measurement Boundary To set the measurement boundary, consider: What affects energy use inside? lamp efficiency improvement operating hours fraction of lamps burned out What energy effects happen outside the boundary? less cooling more heating task lights added to un-measured circuits Short Examples 50

Measurement: Sample Option A Design measure at randomly selected light switches use clamp-on true RMS wattmeter, calibrated measure for 1 second before and 1 second after retrofit Assumptions: 100 hrs/month of operation in the savings reporting period, based on a measurement in the baseline. assume mechanical cooling adds 20% to savings ignore heating energy change and added task lights 5% of lamps/ballasts are burned out at any time Short Examples 51

Sample Option A Observations Pre-retrofit Post-retrofit # Samples 73 30 Measured average 193.1 102.1 watts per operating fixture Number of fixtures 2,000 1,950 Short Examples 52

Sample Option A Computations Total kw (95% of fixtures operating) Lighting load reduction Reduction adjusted for cooling savings Monthly energy savings Pre-retrofit Post-retrofit kw kw kwh/month Short Examples 53

Short Examples 54 Sample Option A Notes Option A is known as Retrofit Isolation: Key Parameter Measurement. The key parameter in this example is power change in the fixtures, so it is measured This sample was IPMVP 2007 Option A because we Assumed the operating hours, even though we logged operating hours in the baseline. Manufacturer supplied data is not field measured. IPMVP treats it as assumed. To adhere to IPMVP Option A the manufacturer data cannot be the key parameter, but it can be another (non-key) parameter.

Option A - Best Applications Operating conditions (eg occupancy) are regularly changing. A contractor is not responsible for all parameters affecting energy use. Able to Assume a parameter with a level of certainty acceptable to all parties. On-going measurement is not required. But to be sure savings are still happening in future, regularly verify that equipment remains in place and is operated properly. Short Examples 55

Option A Retrofit Isolation: Key Parameter Measurement Advantages: Cost effective where numerous energy influencing factors cannot be tracked (such as in a hospital or in a complex industrial process) Easy to administer Disadvantages: Assumed factor may introduce error Not reconciled to total facility utility usage Does not track on-going facility performance Short Examples 56