Best Practices. Dennis Clausen Director of Training GOMACO Corporation

Similar documents
Whitetopping: The Overlay Choice

Unparalleled quality and versatility. Slipform Paver SP 15

Field Evaluation of Stringless Portland Cement Concrete Paving

Stringless Concrete Slip Form Paving Using GPS Controlled Spreaders

CONSTRUCTION SURVEY. Construction survey includes personnel, equipment, and supplies required for, but not limited to, the following:

T-WALL Retaining Wall System

At Work 24/7 on the Channel

CONSTRUCTION MANUAL. T-WALL Retaining Wall System FOR RAILROAD PROJECTS. The T-WALL Solution...

2. Determine Random Numbers: Determine random numbers for testing locations using the Probing, Coring, Texture and MIT-SCAN T2 Report.

SPECIAL PROVISIONS - SP2014 BOOK Page 1 October 8, 2013

Section CONCRETE SIDEWALKS. 1. Payment for concrete sidewalks is on square foot basis.

(D) Surface Slope Bituminous patch in front of the truncated domes must not exceed 5% measured perpendicular to the flow line or edge of roadway.

CONSTRUCTION SPECIFICATION FOR CONCRETE SIDEWALK AND CONCRETE RAISED MEDIAN INDEX TS SCOPE...3 TS DEFINITIONS...3

FIELD REPORT: TEXAS EQUIPMENT LOAN EL Implementation Assistance Program. Tools to Improve PCC Pavement Smoothness During Construction (R06E)

About Power Curbers Our Commitment Shows

6 The Paving Operation

What s New in Concrete Paving? G o rdon K. R ay

Economical paving of 4.0-m to 12.0-m wide concrete slabs Slipform Paver SP 1200

SECTION CONSTRUCTION SERVICES

ITEM 6 CONCRETE CURBS, GUTTERS, AND SIDEWALKS

SECTION CONCRETE PAVING

Strengthened Soil Wall Construction Manual

Phone

How Munilla Construction Management Paves With Accuracy And Efficiency

50-Year Concrete Pavements

Suggested Best Practices for PAVER OPERATORS

The Worldwide Leader in Concrete Paving Technology

PERMEABLE INTERLOCKING PAVERS

1. Payment for concrete sidewalks is on square foot basis. a. Limits for measurement for trench excavation as follows:

Design and Construction of Concrete Overlays. By: James K. Cable, P.E. Cable Concrete Consultation

SECTION CURB RAMPS AND OTHER MINOR CONCRETE FACILITIES. Part 1 - General Work Included Related Requirements...

Job Report Slipform Paver SP 500. Airfields of premium quality for King Abdulaziz International Airport

Best Practices for Airfield Concrete Pavement Design and Construction

Technical specification Slipform Paver SP 1600

Solutions - for Non-Users Site. Tams Mullins Spectra Measuring Systems 6/10/09

COUNTY BLOCK. Construction Guidelines on County Block Steps. Special Considerations When Building Steps. Natural Beauty Absolute Strength

CONCRETE PAVEMENT THE INSPECTORS PERSPECTIVE. SWIFT 2015 Workshop - Chris Olidis, P.Eng.

APPENDIX D VTM Virginia Test Method For Determining Percent of Moisture and Density of Soils and Asphalt (Nuclear Method)

Traffic Management Guide to Concrete Overlay Solutions. Dale S. Harrington P.E. Representing CP Tech Center

EXCELLENCE IN CONCRETE PAVEMENT AWARDS NOMINATION FORM

SECTION CONCRETE CURBS, GUTTERS AND SIDEWALKS

PASSAIC COUNTY TECHNICAL INSTITUTE CCA 1422 NEW S.T.E.M. BUILDING 2017

CHAPTER 2. Restricted Residential ½ Street** Design Speed 25 MPH 25 MPH 25 MPH 25 MPH 40 MPH 50 MPH 55 MPH

1. Evolution of Screeds in the USA A. Fixed Screeds with Hydraulic Strike-off, Becoming Obsolete B. Rear Mount Screeds with & without strikeoff C. Fro

PAVING SLABS ON AGGREGATE BED FOR ROOF PLAZA DECKS

CONSTRUCTION MANUAL 2.5 x 5 UNITS

CONSTRUCTION SPECIFICATION FOR CONCRETE CURB AND GUTTER SYSTEMS

President. Myron Hillock. Sales Director

Horizontal Ellipse. Contact LSBC for additional sizes. Buried Ellipse for Pedestrian Traffic. Elliptical Stream Crossing

B. Reinforcing. Materials shall be as specified in Section 2000 Concrete or as indicated on the plans.

**************************************************************************

**************************************************************************

CONSTRUCTION STAKING GUIDELINES

City of Regina Standard Construction Specification SECTION 2350 PLACEMENT OF ASPHALTIC CONCRETE SURFACE 1.0 GENERAL. 1.1 Scope

Critical Structures Construction Issues

CONCRETE TILE PAVERS

Technical specification Slipform Paver SP 1500 / SP 1500 L

CONSTRUCTION SPECIFICATION FOR UNTREATED GRANULAR, SUBBASE, BASE, SURFACE SHOULDER AND STOCKPILING

Cement Stabilized Aggregate Base

RECONSTRUCTION OF DISTRESSED PAVEMENTS Full-Depth Rehabilitation (FDR) (Portland cement)

Review of Plans and Specs from a Constructability Perspective

Installation Manual. Orion. TL-3 Steel Barrier. VHD (v2)

Reinforced Earth wall Construction Manual

UNIVERSITY SERVICES ANNEX James Madison University Harrisonburg, Virginia State Project Code: Architect s Project Number:

603 - ASPHALT PAVEMENT SMOOTHNESS SECTION 603 ASPHALT PAVEMENT SMOOTHNESS

1993 Specifications CSJ'S & SPECIAL SPECIFICATION ITEM Tree Preservation and Treatment

SECTION MECHANICALLY STABILIZED EARTH RETAINING WALLS

SECTION PAVING SLABS ON AN AGGREGATE BASE

SECTION PAVING SLABS ON AN AGGREGATE BASE

SECTION RIGID PAVEMENT

Automated Machine Guidance

2399 Pavement Surface Smoothness

The work required for this project includes, but is not limited to, the following items, not listed in order of execution.

ENGINEERING DIVISION CONCURRENT PLAN CHECK PROGRAM

Uwall UNIVERSAL CONSTRUCTION MANUAL

Installation Guidelines

LAGRANGE TOWNSHIP 353 South center street p.o. box 565 lagrange ohio 44050

CONSTRUCTION SPECIFICATION FOR CONCRETE PAVEMENT AND CONCRETE BASE

Product Manual Release 05/17

Special Provision No. 103F31 January 2014

Single Post Anchor Part Number Spectrum Lane ~ Missoula MT ~

MSCAA /04 ITEM P-219 RECYCLED CONCRETE CRUSHED AGGREGATE BASE COURSE DESCRIPTION MATERIALS

StormPod Arch Installation Guide

Installation Manual. ArchCast Bridge. 3-Sided Precast Concrete Bridge Structure

T a b l e o f C o n t e n t s

McCarthy Improvement & C.W. Matthews Contracting Co., Inc. a Joint Venture. FC-6610 Runway 8L/26R Pavement Replacement Project

Cement Stabilized Soil (CSS) (Portland cement)

Section 1 OBC FADS /13 Access to Parking Areas

Special Provision No. 103F31 December 2014

KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, 1990 EDITION

MICHIGAN DEPARTMENT OF TRANSPORTATION

ArmorZone TL-2 Barrier

CITY OF ADA, PURCHASING 512 North Stockton Street Ada, Oklahoma / x256 Fax 580/ BID NOTICE.

Department of Building and Zoning Approaches and Sidewalks for ONE AND TWO FAMILY CONSTRUCTION

INCLUDE IN ALL PAVING PROJECTS UNLESS OTHERWISE DIRECTED BY TSB

SECTION GRAVITY WASTEWATER LINES

SECTION 26 - COLD PLANE ASPHALT CONCRETE PAVEMENT TABLE OF CONTENTS

ACI 330.2R-17 Nigel Parkes, PNA Construction Technologies

MagnumStone Specifications Gravity

SECTION UNCLASSIFIED EXCAVATION AND GRADING

Transcription:

Best Practices Dennis Clausen Director of Training GOMACO Corporation

Considerations for Profile Paving Stringline Installation & Maintenance Subgrade Stability and Accuracy Concrete Control & Placement Paving Basics Finishing Operations Other Considerations

Stringline Installation & Maintenance Setting & Maintaining Accurate Stringline Recommend 25 Surveyed Stations and Stringline Stakes, Closer Intervals in Horizontal and Vertical Curves.

Stringline Installation & Maintenance Setting & Maintaining Accurate Stringline Recommend 25 Surveyed Stations and Stringline Stakes, Closer Intervals in Horizontal and Vertical Curves. New Condition Cord, Wire, or Cable. Daily Maintenance & Checking of Stringline Elevation and Alignment. Daily Maintenance on Stringline Tightness.

Subgrade Stability Stability of Paving Grade Unstable Grade Causes Thickness Control Problems if Haul Trucks are Placing Concrete on Grade. Possible Profile Problems if Subgrade continues to Move.

Subgrade Stability Stability of Paving Grade Unstable Grade Causes Thickness Control Problems if Haul Trucks are Placing Concrete on Grade. Possible Profile Problems if Subgrade continues to Move. Stability of Track Line Track Line Failure may Occur Causing Profile Deviations.

Subgrade Stability Stability of Paving Grade Unstable Grade Causes Thickness Control Problems if Haul Trucks are Placing Concrete on Grade. Possible Profile Problems if Subgrade continues to Move. Stability of Track Line Track Line Failure may Occur Causing Profile Deviations. Stability of Haul Road Safety Important because of Possible Delays in Concrete Delivery. In Extreme Cases may Affect Paver Track Line Grade.

Subgrade Accuracy Accuracy of Paving Grade & Trackline. Fewer Changes in Elevation by the Paver, the higher probability of good profiles. Accurate Grade Elevation Makes Concrete Placement More Consistent.

Placing With Transit Mix Considerations if Transit Mix Must be Used Plant Should be Central Mix if Possible Mixer should be Designed as Paving Mixer Chutes Must be Kept Clean Control of Clean-out Water Must be Monitored Position and Placement of the Truck Mixer is Critical

Placing Central Mix Concrete Positive Factors of Central Mix Placement: Most Efficient Mixing System, helping make a more consistent mix. Faster to Unload End Dump & Bottom Dump Trucks. Use of Placers & Placer Spreaders May: Allow the Paver to Move at a Consistent Rate of Speed. Allow the Paver to Operate with a Consistent Head of Concrete. Eliminate Large Piles of Concrete, which vary loading on the paver. Require Close Monitoring if Concrete Slump varies or if Subgrade is no Accurate

Paving Basics

Paving Form Must be Clean Paving Basics For A Paver to Perform at Optimum it Must be: Designed for the Width to be Paved Maintained According to the Manufacturers Recommendations Assembled and Adjusted to the Manufacturers Recommendations Operated by Trained Personnel Operated by Motivated Personnel Paving Crew Must Operate as a Team Paving Team must have Pride in Their work

Extrusion Type Paving Form Must be Properly Adjusted for Good Paving Results. Establish a Set-Up Procedure and Follow it Religiously. Pan Should be Straight & True, Left to Right & Front to Rear. For Good Profile Results, Pan Should be Set Parallel to the Stringline Front to Rear. Check the Profile Pan for Accurate Setting after: Width Changes Moving the Machine Replace or Repair Damaged or Worn Parts When Necessary.

Good products Finish Procedures

Finish Procedures Good products Check product dimensions

Finish Procedures Good products Check product dimensions Problem areas

Finish Procedures Good products Check product dimensions Problem areas Start and finish headers

GSI The Contractor s Tool Before Paving Check smoothness of the sub-grade Check smoothness of the stringline setup Calculate yield of the paving materials based on sub-grade and stringline setup Pin point areas of cuts and fills in the sub-grade

Stringline Sensor

GSI Tools Analysis Software

Sub base analysis for McCarthy Improvement in South Carolina With the GSI you can collect the same sub grade measurements every 2 inches

GRADE CUT/FILL DETAILS STATION REFERENCE DEVIATION HEIGHT ROW INTERVAL RESOLUTION 2, 6, 1, 12, 25, 50, 100, ect. COLOR CODED CUT AND FILL PARAMETERS BLUE = FILL RED = CUT

SLAB VOLUME NOMINAL SLAB VOLUME VOLUME DEVIATION THEORETICAL VOLUME (NOMINAL + DEVIATION)

REPORT JOB INFORMATION TRACE DETAILS SLAB VOLUME PROJECT PARAMETERS GRADE CUT/FILL SUMMARY USER ADDED GRAPHS KNOWN FILE FORMAT FOR SHARING INFORMATION AND PRINTING (*.HTML FILE USES INTERNET EXPLORER FOR VIEWING AND PRINTING)

GSI The Contractor s Tool During paving process Provide paving crew immediate smoothness readings right out of the paver Corrections may be made to the pavement surface while concrete is still in plastic condition Adjustments can be made to paving operation before thousands of feet have been paved Separate machine can be backed over the repaired surface to take readings again

Check Profile of Poured Concrete Behind Paver

Check Profile of Poured Concrete Behind Paver

Check Profile of Poured Concrete Behind Paver

Check Profile of Poured Concrete Behind Paver

View 2 Traces

View Report in PI or IRI Format

3D Stringless Control System for Curb & Gutter, Trimming & Concrete Paving

What is Stringless 3D? A 3D Machine Control system that simplifies jobsite logistics, reduces costs and improves quality and safety Removes stringlines and pins from the jobsite Removes install, maintenance & removal costs Increases working safety, especially at night Puts the 3D job design directly onto the machine Eliminates setting-out errors and stringline influences No waiting for setting-out before production No dependency on setting-out work wherever you have 3D data Increases productivity, quality and performance bonuses Controls height, slope (and steer) of machines 58 Delivers a precisely-constructed product Optimises amount of new material needed Reduces over-trimming, overpouring Improves concrete yields and material cost savings

Working with Stringline Inspect design calculate setting-out lists for each lane Setup a theodolite, survey each hub or pin position with total station (or GPS if accuracy isn t important!) Reference Point Hammer (or drill) in each pin, minimum 1 line for each lane of concrete/asphalt Check pin alignment & adjust if required Survey and set stringline height on each pin (min. 2 men) Install & tension clamps and stringlines Walk left 5ft! Walk right 1ft! Up a bit! Down a bit! STOP! Reference Point Eyeball & adjust stringlines before paving Move machine into position, set sensors to stringline Check machine position relative to stringlines Start Production, monitor machine position 59 Ensure (or hope!) nothing disturbs or damages stringlines during paving/milling

Mainline Slipform Paving & Fine-Grade Trimming with Stringless 3D Click to return to Main Menu

Why go Stringless? Could your paving projects benefit from no marking-out and drilling to setup pins and guidewires? easier paving in zero clearance situations, e.g. bridge decks, urban streets, railway cuttings, tunnels, narrow motorway lanes? no special access/safety equipment to pave in tunnels? no pre-production planning just arrive, pave anywhere, any time? no human error from stringline setup? no inaccuracy of field model compared to original office design? lower material costs, improved concrete yield (less waste)? 61

Why go Stringless? Because stringlines are expensive, time-consuming and error-prone to install can be easily damaged during paving can be easily misaligned can be a significant site safety hazard interfere with site logistics, increase concrete delivery time, haulage costs, and reduce productivity. require pre-production planning & increase survey effort/cost don t always model the designed surface accurately 62

What is 3D? A 3D Machine Control system simplifying slipform jobsite logistics, reducing cost, improving quality and productivity Specifically designed for mainline (slab) pavers & trimmers The result of 16 years worldwide experience in 3D slipforming Developed in close cooperation with GOMACO Eliminates stringlines ( stringless control ) Controls paver elevation, steer, slope and draft Constructs directly from the 3D plans Removes need for stringline set-out crew Minimises pre-production planning and preparation 63

Stringless System for Gomaco Trimmers System Components Reference Point Prism Reference Point Machine Computer Radios Slope Sensor Theodolite #1 (Guidance) Theodolite #2 (As-builts & Leapfrog) 64

Stringless System for Gomaco Placer/Spreaders System Components Radio Machine Computer GPS or Prism GPS Reference Station Slope Sensor 65

Stringless System for Gomaco Pavers System Components Prism Machine Computer Prism Reference Point Radios Slope Sensors 66 Reference Point TPS #3 (As-builts & Leapfrog) TPS #2 (Guidance) TPS #1 (Guidance)

Faster, more accurate trimming Optimal subgrade saves concrete and improves rideability 67

Smoother airfield paving Increases runway life, reduces undercarriage & tyre wear 68

Smoother road paving Increases road life, reduces vehicle wear & passenger fatigue 69

70 Practical Issues In the field!

Practical Issues Checking concrete (or subgrade) level and position The third theodolite together with a prism measures the surface as-built behind the machine Errors (and adjustments) shown on theodolite Report stored on 3D computer 71

Practical Issues Adjusting the Machine If the level needs adjusting just like stringline control we can adjust all leg heights, and draft independently, without stopping paving 72

Practical Issues Adjusting the Machine If position needs adjusting just like stringline control we can adjust position at front and rear independently, without stopping paving 73

Practical Issues Moving the Theodolites ( Leapfrogging ) Maximum Range Theodolite-to-Paver is <= 200m (*depends on conditions) We don t want to stop the paver for too long! Before maximum range is reached, move 3 rd Theodolite to new position & setup (Position & Orientation Fix). Press Swap Theodolite on computer System switches control from #2 (or #1) to #3 Theodolite automatically Move old Theodolite to new position, setup and repeat procedure Ensure enough Reference Points visible for Setup (Position & Orientation Fix) * - temperature, humidity, air quality 74

Questions? Dennis Clausen Director of Training GOMACO Corporation