EXECUTIVE STEERING COMMITTEE MEETING

DEPARTMENT OF REVENUE BUILDING 2 APRIL 25, 2018

Monthly Independent Verification and Validation Assessment Report

PMI LUNCH AND LEARN OCTOBER 29, 2018

HOUSE OF REPRESENTATIVES KNOTT COMMITTEE ROOM 116 NOVEMBER 28, 2018

Florida PALM Quarterly Project Oversight Report: Comprehensive Review For April - June 2015

Monthly Independent Verification and Validation Assessment Report

Monthly Independent Verification and Validation Assessment Report

HOUSE OF REPRESENTATIVES KNOTT COMMITTEE ROOM 116 OCTOBER 24, 2018

DEPARTMENT OF REVENUE BUILDING 1 AUGUST 22, 2018

DEPARTMENT OF REVENUE BUILDING 2 SEPTEMBER 26, 2018

Monthly IV&V Assessment Report (December 1 31, 2015)

FLORIDA PALM PROJECT. Level 2 SME Workgroup Kickoff. April 7, 2015

Solution Analysis and Design Strategy (D18)

Design, Development and Implementation (DDI) Project Management Plan (PMP)

Pre-Design, Development and Implementation (DDI) Project Management Plan (PMP)

Project Charter For Florida PALM

PROCUREMENT TO PAYMENT OCTOBER 27, 2015

Attachment E - DecisionDirector Instructions Revised 12/19/2016 Addendum 1 Table of Contents

Attachment B Project Specifications

Modernization and Migration Management (M3) Playbook GSA, Unified Shared Services Management

ACCOUNTS RECEIVABLE AND BILLING TO RECEIPT (ARB) CASH INFLOW TO OUTFLOW (CSH) TREASURY MANAGEMENT (TRM) NOVEMBER 4, 2015

Addendum #2 DFS OIT ITN Enterprise Financial System Support Services

ENTERPRISE SECURITY, REPORTING, BUSINESS INTELLIGENCE & ANALYTICS NOVEMBER 4, 2015

Monthly Independent Verification and Validation Assessment Report

Title: Project Director Location: Tallahassee, FL Clearance: none required

Modernization and Migration Management (M3) Playbook GSA, Unified Shared Services Management

GENERAL SYSTEM, INTEGRATION ARCHITECTURE, AND WORKFLOW & USER INTERFACE NOVEMBER 6, 2015

Welcome. Facilities. Public Meeting. Restroom Cafe

Business Requirements Definitions

Attachment B Statement of Work

Monthly Independent Verification and Validation Assessment Report

Anticipated Completion Date and Contact. No. Finding Recommendations Previous Management Response(s) Status Update. Page 1 of 9

Welcome. Facilities. Public Meeting. Restroom Cafe

2. Services. The Scope of Work is amended by adding additional work. The additional work is detailed in the attached Exhibit A.

M3 Playbook Guidance. 1.1 Establish Initial Customer PMO and Processes. Human Resources (HR)/Staffing Plan

INFORMATION SERVICES FY 2018 FY 2020

Fixed scope offering. Oracle Fusion Financials Cloud Service. 22 February 2016 A DIVISION OF DIMENSION DATA

Modernization and Migration Management (M3) Playbook GSA, Unified Shared Services Management

I-BPS3: Supplemental Report of Changes to Level 2 Standardized Business Process Models

Information Services Group Public Sector

Information Services Group Public Sector

Citizens Property Insurance Corporation The Business Case for an Integrated ERP Solution Executive Summary

Information Services Group Public Sector

PRIVY COUNCIL OFFICE. Audit of PCO s Accounts Payable Function. Final Report

I - PROJECT STATUS OVERVIEW

Enterprise Data Strategy and Governance

DEPARTMENT OF ELDER AFFAIRS (DOEA) PROJECT CHARTER. ENTERPRISE CLIENT INFORMATION AND REGISTRATION TRACKING SYSTEM (ecirts) PROJECT FOR

Notice is hereby given of the following changes to the above-referenced SOLICITAITON:

State of Florida Department of Children and Families

facilitating predictable outcomes in a constantly changing environment Establishing a Standard Chart of Accounts (SCOA)

For. Planning and Research Related to Procurement of a Systems Integration, Enhancements to a MMIS, New Fiscal Agent, and a Replacement DSS

REQUEST FOR PROPOSALS For AUDIT SERVICES

State of Florida Department of Financial Services. Invitation to Negotiate DFS RM ITN 13/14-07 For Insurance Management System

PROGRESS ON THE COMMUNITY COLLEGES SYSTEM ERP PLAN, DESIGN AND IMPLEMENTATION PROGRAM. A Report to the:

. SAN RAFAEL CITY COUNCIL AGENDA REPORT

Administrative & Student Information Systems Refresh: Phase I Project Update

DRAFT. Fusion ERP Cloud Service October Oracle Fusion ERP Cloud Service. Magdalene Ritter

FINANCIAL SERVICES DEPARTMENT Strategic Business Plan

USDA Shared Services Journey

STATE OF ILLINOIS REQUEST FOR INFORMATION

CERTIFIED ADMINISTRATOR OF SCHOOL FINANCE AND OPERATIONS

ERP Project Update. Presented to City Council May 3, 2011

EXECUTIVE ERP. EVALUATION AND INVESTMENT ROADMAP Developed for the Modern Business

How to implement an ERP and still remain friends Cleveland Metropolitan School District & Navigator Management Partners.

Procurement Performance Review

Internal Audit Report

Business Plan

Anticipated Completion Date and Contact. No. Finding Recommendations Previous Management Response(s) Status Update. Page 1 of 6

Invitation to Negotiate (ITN) Statewide Travel Management System ITN No D. Questions and Answers ITN Amendments

1.0 PART THREE: Work Plan and IV&V Methodology

Request for Proposals (RFP) Information Technology Independent Verification and Validation RFP No IVV-B ADDENDUM NO.

INTERNAL AUDIT OF PROCUREMENT AND CONTRACTING

Fixed Scope Offering For Oracle Fusion HCM SaaS Implementation

I-SDS2: Florida PALM Pre-DDI Data Management Plan (DMP)

BOARD OF SUPERVISORS FINANCE/GOVERNMENT OPERATIONS and ECONOMIC DEVELOPMENT COMMITTEE INFORMATION ITEM

Acquisition of ERP. December 4, 2007

REQUEST FOR PROPOSAL PROFESSIONAL SERVICES AUTOMATION SOLUTION. Submittal Date: April 22, 11:00 AM (PST)

I - PROJECT STATUS OVERVIEW

Florida Department of Transportation 605 Suwannee Street Tallahassee, FL

Choosing The Right EHR For You: Best Practices In Vendor Selection & Contracting

Executive Overview Mark Campbell

Information Management Strategy

APPLICATION INFORMATION: 1. All five sections of the application must be completed.

SELECTION CRITERIA AND PROCESS

Business Process Services: A Value-Based Approach to Process Improvement and Delivery

Procurement and Contracting Operations Audit

URFinancials Project Project Kick-Off

10.2 Enter and Process Journals

RECORD TO REPORT (R2R) OCTOBER 26, 2015

Project Management. Risk Management

Third Party Fiduciary Agent. Guam Department of Education. In partial fulfillment of Contract: Monthly Project Status Report.

IT Consulting Solicitation: Pioneering the Next Generation June 22, 2015

Fixed scope offering. Oracle Fusion HCM Cloud Service. 22 February 2016 A DIVISION OF DIMENSION DATA

Our Services. Staff Augmentation Provision of quality resources Long term, medium term and short term engagements

Information Technology Services Project Management Office Operations Guide

Transcription:

Executive Steering Committee Meeting Department of Revenue Building 2, Room 1250

Roll Call and Opening Remarks Facilitator: Robert (Budd) Kneip, Chair

Review of June 2016 Meeting Minutes Facilitator: Robert (Budd) Kneip, Chair

Facilitators: Eric Adair, Danielle Kosberg, Angie Robertson, and Melissa Turner

Scope Business Requirements Per the 2016 Implementing Bill (HB 5003), DFS has the responsibility to ensure all business requirements have been: provided to all state agencies for their review and input approved by the ESC Per the 2016 GAA (HB 5001), all business requirements must be: reviewed by all agencies capable of reporting at a minimum expenditure and revenue data at the level currently reported in the FLAIR subsystem approved by the ESC 6

Scope Business Requirements Business Requirements and supporting documentation are on Florida PALM website Excel spreadsheets of Functional and Technical Business Requirements for ESC Review include the following fields: Requirement Type Number Category SubCategory Requirement Requirement Priority Comment (Optional field to provide feedback / questions by requirement) 7

Scope Business Requirements Business Requirements Definitions Provides description of the Priority field values and the Category and SubCategory values ESC Feedback Template for Business Requirements Provides ability to share general feedback or comments at the Requirement Category level Business Requirements Crosswalk Provides the original Requirement number, Category, and SubCategory and the updated values, where applicable 8

Scope Business Requirements 9 Priority is planned to be an element of the Requirements Scoring Formula used in the evaluation process for vendor responses Requirements Scoring Formula Requirement Priority Vendor Response Category Weight Weighted Score Static value assigned to each requirement by the State Value assigned to each requirement based on vendor s response Static value assigned by the State to all requirements in the category Score assigned to each requirement and composite score for all Functional and all Technical Business Requirements

Scope Business Requirements Priority assists the Project Team in identifying the requirement s functionality significance 10 Priority Definition 1 A requirement for functionality to replace FLAIR/CMS or technology necessary to support the new standard business processes for Florida PALM 2 A requirement for functionality to improve the business process from current FLAIR/CMS functionality or enhance the supporting technology 3 A requirement for functionality or technology that will either increase the performance or value of Florida PALM

Scope Business Requirements Meetings with Legislative partners Reviewed Budget, Payroll, and Procurement to Payment Reviewing Process Models and Business Requirements to understand current functionality and proposed future functionality Continuing to discuss areas where there may need to be adjustments in our business requirements and process models One-on-one Meetings with ESC Members Conducted five meetings Discussing the requirements review activities and expectations Providing support for questions 11

Scope Business Requirements 12 Functional Categories Accounts Payable Accounts Receivable and Billing Asset Management Budget Management Cash Management Contracts General Ledger Grants Payroll Projects Travel Treasury Management Technical Categories Business Intelligence and Analytics Data Management Enterprise Security General System Integration Architecture Operations Management Reporting Support Transaction System Workflow and User Interface

Schedule Business Requirements 13 Activity Timeframe Status Draft Completed and Reviewed with DFS Divisions (Cycle 1) All Agencies Review and Updates Incorporated (Cycle 2) Create Payroll and Amend Budget Requirements (Draft Cycle 3) All Agencies Review and Updates Incorporated (Cycle 3) October 7, 2015 April 28, 2016 June 15, 2016 July 20, 2016 Complete Complete Complete Complete ESC Review of Part 1 (Cycle 2) Beginning July 14 In Progress ESC Review of Part 2 (Cycle 3) Beginning July 21 In Progress Business Requirements updates based on feedback During August Planning ESC Approval Business Requirements During August 24, 2016 ESC Meeting Not Started

Scope Agency Business Case Per the 2016 GAA (HB 5001), the Business Case shall include: A detailed description of the functionality provided by the agency business system Confirmation that the agency business systems functionality is not planned to be included with Florida PALM Documentation, including federal and state law, rule, or policy, which validates that the agency is required to maintain the functionality currently provided by the agency business system instead of modifying its business processes 14

Scope Agency Business Case The activities for the Business Case will not include: A determination of the feasibility to keep, replace, or remediate any agency business system A recommendation to keep, replace, or remediate any agency business system An effort to gather additional Florida PALM Business Requirements Kickoff meeting with all agencies was held on July 21, 2016 An Agency Business System Functionality Profile was distributed to all agencies via email Interviews at agency sites are planned throughout August The Business Case shall be submitted no later than November 1, 2016 15

Scope Data Management Plan (DMP) Per the 2016 GAA (HB 5001), the Data Management Plan (DMP) shall include: An inventory of current system interfaces Migration activities required from the FLAIR subsystem and the CMS Data conversion requirements Objective of the DMP is to: Lay the strategic foundation for transitioning the State of Florida s existing financial accounting data management capabilities towards a modern way of managing data Provide guidance both during the Project and (eventually) after implementation 16

Scope Data Management Plan (DMP) The strategy to the DMP includes: Recognition that financial accounting data is a critical, strategic asset of the State and must be managed with the robustness commensurate with any other critical asset Use of industry best practices, modern approaches and tools An approach to ensure financial data is used reliably, ethically, openly, securely, and efficiently Collaboration with key stakeholders throughout the Solution s lifecycle (Project and Post-Implementation) Identification of a smooth, stakeholder-friendly migration strategy that minimizes impact to stakeholder data management operations 17

Scope Data Management Plan (DMP) The DMP will describe current-state challenges including: A lack of enterprise-wide data and application governance plans, policies, and procedures in place and in practice No clear enterprise-wide data strategy including clearly defined data definitions, ownership, and standards for usage and access Agency business processes designed and executed with the limitations of FLAIR and CMS in mind (e.g. lack of workflow capabilities, considerable manual data reconciliation processes) An architecture lacking critical, real-time interface capabilities 18

Scope Data Management Plan (DMP) Review of Architecture Principles Presume Data Openness Secure Enterprise Data Centralize Core Functions Federate Non-Core Functions Enable Fast Decisions Avoid Duplication Focus on Sustainability 19

Scope Data Management Plan (DMP) 11 Knowledge Areas of Data Management Governance Architecture Modeling and Design Storage and Operations Security Integration and Interoperability Documents and Content Reference and Master Data Data Warehousing and Business Intelligence Metadata Data Quality 20

Scope Data Management Plan (DMP) Other areas covered in the document Risk and Issue Management Migration Activities Considerations Strategy Execution and Roadmap References Attachment A: Florida PALM Architecture Principles Attachment B: FLAIR/CMS Current-State Interfaces Attachment C: FLAIR/CMS Current-State Data Inventory Attachment D: 2016 General Appropriations Act ( GAA ) DMP Requirements Traceability 21

Schedule Data Management Plan Activity Timeframe Status 22 Initial Draft Complete November 19. 2015 Complete Gartner, IV&V, BPS Contractor Review and Updates Incorporated November 30, 2015 Complete DFS Review and Updates Incorporated January 5, 2016 Complete AST and IV&V Review and Updates Incorporated Updates incorporated based on FFMIS Entities, FSU/FAMU, and other stakeholder review ESC Review February 17, 2016 August 31, 2016 Beginning September 1, 2016 ESC Approval of the Data Management Plan During Sept 28, 2016 ESC Meeting Complete In Progress Not Started Not Started

Scope Invitation to Negotiate (ITN) Project Goals Reduce the State s risk exposure by harnessing modern financial management technology built on the premises of scalability, flexibility, and maintainability 23 Improve State and agency-specific decision-making by capturing a consistent and expandable set of data Improve the State s financial management capabilities to enable more accurate oversight of budget and cash demands today and in the future Improve productivity, reduce operational complexity, and increase internal controls by enabling standardization and automation of business processes within and between DFS agencies

Scope Invitation to Negotiate (ITN) Procurement Approach DFS is planning to issue an ITN for Software and System Integrator Bundled approach aligns with recommendation in FLAIR Study due to complexity, cost, and best meets the needs of DFS DFS will request a Solution to meet requirements and specifications An ITN provides the ability to explore questions and negotiate a Solution with the best value 24

Scope Invitation to Negotiate (ITN) Procurement Objective Obtain the best and most appropriate means of providing enterprise resource planning (ERP) Software and System Integrator (SSI) services for the replacement of the four main components the of FLAIR subsystem which include central FLAIR, departmental FLAIR, payroll, information warehouse and the cash management and accounting management components of CMS Implement an integrated enterprise system that allows the State to organize, define, and standardize its financial management business processes and that complies with F.S. 215.90-215.96 25

Scope Invitation to Negotiate (ITN) Procurement Constraints Solicitation cannot be released prior to November 1, 2016 Solicitation must include all validated and approved business requirements for the replacement of all four main components of FLAIR and the cash management and accounting management components of CMS Replacement solution cannot include any functionality that duplicates any of the other information subsystems of the FFMIS, and agency business processes related to any of the functions included in the Personnel Information System, the Purchasing Subsystem or the Legislative Appropriations System/Planning and Budgeting Subsystem 26

Scope Invitation to Negotiate (ITN) Procurement Goals Goal # 1: Develop a procurement process which follows Florida s procurement laws 27 To achieve Goal # 1: Follow all Florida procurement and sunshine laws Utilize VBS for posting, addendums, and decisions Follow DFS procurement process which includes communications flowing through DFS Purchasing Utilize outside counsel firm specializing in Procurement Law for review of ITN documentation and support during procurement

Scope Invitation to Negotiate (ITN) Procurement Goals Goal # 2: Develop and conduct a clearly written document and transparent procurement process to minimize the risk of protest To achieve Goal # 2: Develop an ITN document that is clear and complete Allow vendors to submit questions about the ITN and provide answers to all vendors through VBS Provide in the ITN: Evaluation methodology, scoring, and questions Standard scoring guidelines for evaluators Selection Criteria for Award 28

Scope Invitation to Negotiate (ITN) Procurement Goals Goal # 3: Develop a sound procurement process giving DFS the ability to choose the right software and system integrator who form the right partnership resulting in the implementation of a successful FLAIR and CMS replacement To achieve Goal # 3: o Minimum Qualifications include the requirement for the System Integrator to have implemented the proposed software o Evaluation scores will include criteria for both the software and system integrator o Selection criteria will consider the ability of the software and system integrator to meet the solution goals 29

Scope Invitation to Negotiate (ITN) Procurement Goals Goal # 4: Complete the procurement process in a reasonable timeframe to allow DFS the ability to select the software vendor who meets the needs of DFS, as well as an system integrator who will successfully implement the software 30

Scope Invitation to Negotiate (ITN) Procurement Goals To achieve Goal # 4: Define a reasonable timeline for the procurement process based on other similar procurements Create flexibility in the timeline for the process Dedicate Evaluation and Negotiation Team Members Train the Evaluation Team prior to receiving proposals for evaluation Maintain a realistic pace of negotiations that keeps the teams engaged in the process 31

Scope Invitation to Negotiate (ITN) Procurement Goals Goal # 5: Develop a procurement process containing the proper tools to facilitate the Department s ability to manage a high volume of responses from the vendor community To achieve Goal # 5: Administrative review of Minimum Mandatory Requirements prior to Evaluators receiving proposals Use DecisionDirector for automated business requirements scoring Reports to compare responses across vendors and requirements Standard Scoring guidelines for evaluators 32

Scope Invitation to Negotiate (ITN) Procurement Goals Goal # 6: Require the system integrator to conduct the demonstration or presentation of the software proposed and show their ability to modify the software 33 To achieve Goal # 6: Complete the evaluation of responses after the software demonstrations and team presentations Presentation of key staff, experience with the solution and respond to evaluator questions

Scope Invitation to Negotiate (ITN) Procurement Goals Goal # 7: Consider the functionality of the software and how the software meets the Department s requirements during the evaluation phase of the procurement 34 To achieve Goal # 7: Evaluators and negotiators will utilize several sources to consider fit of the software to meet the unique needs of Florida: Vendor Responses through DecisionDirector Software Demonstrations Software Narratives Information about potential customizations including level of effort

Scope Invitation to Negotiate (ITN) Procurement Goals Goal # 9: Secure one contract with both the software vendor and the system integrator while retaining the ability to have direct contact with the software vendor 35 To achieve Goal # 9: Ability/approach for requesting direct access to the primary software vendor is currently in progress

Scope Invitation to Negotiate (ITN) Procurement Goals Goal # 8: Negotiate strong performance measures which can indicate when the product is on a path to success or to failure 36 Goal # 10: Develop a fixed price contract with checkpoints to evaluate the vendor s progress and provide optimal protection to the State To achieve Goal #s 8 and 10: Require a phased implementation approach Conduct go/no-go decisions throughout the Project Measure performance considering staffing, deliverable quality, and deliverable timeliness

Scope Invitation to Negotiate (ITN) ITN Document Attachment A Overview of the current Program Attachment B Project Specifications Attachment C Cost Reply Instructions and Workbook Attachment D Technical Reply Instructions Attachment E DD2 Instructions Attachment F Identical Tie Reply Instructions Attachment G Opinion of Out of State Respondents Attorney on Bidding Preferences Attachment H Standard Form of Contract Attachment I Definitions 37

Schedule SSI ITN Document Activity Timeframe Status 38 Draft ITN - Part 1 (PROC3) September 28, 2015 Complete Draft ITN - Part 2 (PROC13) November 16, 2015 Complete Draft ITN All Parts (PROC5) March 30, 2016 Complete Project Team Updates Incorporated May 31, 2016 Complete DFS Sponsor Review June 2016 Complete DFS Legal/Purchasing Review July 2016 In Progress Outside Counsel Review August 2016 Not Started ESC Review September 1 - October 15, 2016 Not Started

Scope Payroll Approach for SSI ITN Decision 85 was logged in October 2015 to determine the timing and approach for replacing the FLAIR Payroll subsystem Functionality of the FLAIR Payroll subsystem is included within the SSI ITN Vendors will be expected to propose a payroll replacement solution through the primary financial management software or another software that is integrated There are several options to consider for the timing/approach 39

Budget FY 2015-2016 (through end of June 2016, not including certified forward payments) Appropriated: $11,328,570 Released: $8,441,680 Incurred: $7,414,957.71 Actual: $7,314,793.26 FY 2016-2017 baseline Spend Plan created to reflect Appropriations $8,777,123 and monthly projections with a breakdown across Special Category, Salaries & Benefits, and DMS Transfer 40

Risks and Issues 18 Critical risks are being mitigated These are risks with highest probability and potential impact The Project tracks the trend (increasing, stable, or decreasing) for each of these risks monthly Critical risks will continue to be shared via monthly status reports and discussed (if necessary) with the ESC One issue is currently open related to the resources committed to the Business Case initiative with a resolution plan targeted for completion August 1, 2016 41

Decisions Facilitator: Robert (Budd) Kneip, Chair

Decision #85 Decision #85: Timing and approach for replacement of FLAIR Payroll Subsystem 43

Independent Verification and Validation Assessment Facilitator: Tony Hernandez

Independent Verification and Validation Assessment Overview Grant Thornton was engaged as the Project s IV&V provider in September 2015 Primary responsibilities: Initial and ongoing Project assessments Support of internal Project quality initiatives 45

Independent Verification and Validation Assessment Approach Initial assessment delivered November 2015 with additional assessments following monthly Assessment focus areas: High impact Project execution AST mandated criteria Project governance Medium impact Project execution Additional criteria Procurement and contracts Quality management Communications and outreach 46

Independent Verification and Validation Assessment Results Initial Assessment delivered November 2015 had 1 red (critical) and 18 yellow (significant) findings and observations Project had steady reduction in findings, prioritizing resolution by impact All high impact findings addressed by February 2016; all findings addressed by June 2016 47

Independent Verification and Validation Assessment What's Next Planning for FY16-17 Legislative Budget Request (LBR) Requirements approval and management Data Management Plan (DMP) Communications and outreach Continuous monitoring of: Project execution metrics Procurement and contracting Quality management 48

Upcoming Activities Facilitator: Melissa Turner

Upcoming Activities 50 Distribute any updates to Business Requirements to ESC Support ESC review of Business Requirements in preparation for August 24, 2016 approval Review and update Data Management Plan in preparation for submission to ESC Onboard Organizational Change Management Support Services Contractor Conduct Systems and Data Strategy Data Architect Support Services RFQ Released July 7, 2016 Responses Due July 29, 2016

New Business & Open Discussion Facilitator: Robert (Budd) Kneip, Chair

Next Meeting August 24, 2016 Time and Location TBD

Contact Information FloridaPALM@myfloridacfo.com myfloridacfo.com/floridapalm