h Installation Manual

Similar documents
h GRP Pipe Systems Transportation, Installation & Maintenance

DUCTILE IRON PIPES AND FITTINGS DETAILED PRODUCTS SPECIFICATIONS

TABLE OF CONTENTS

Saudi Vitrified Clay Pipe Co.

Installation Instructions for Circular Trench Pipes (DN300 DN1200) PD 46 rev D October 2013

HEKAPLAST. PE-HD twin wall cable ducts and cable protection pipes for underground installation. Corrugated and Twin Wall Pipes of Plastics

San Antonio Water System Standard Specifications for Construction ITEM NO. 848 SANITARY SEWERS

VALLECITOS WATER DISTRICT SECTION POLYVINYL CHLORIDE (PVC) PRESSURE PIPE

SPECIFICATION FOR REINFORCED SOIL WALL

Althon slot channels Althon

Precast Concrete Trench Drain Systems INSTALLATION INSTRUCTIONS

Technical Data Sheet NEC/GRAN/95:01

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS

PVC Fittings & Laterals for Solid-Wall PVC Sewer Pipe

1993 SPECIFICATIONS CSJ SPECIAL SPECIFICATION ITEM 4110 CONCRETE ENCASED DUCT BANK

freestone eco Prestige & quality DIY vertical wall Large blocks - 10/m 2 Smooth surface finish No concrete footings

SECTION DUCTILE IRON FITTINGS. A. This section includes materials, installation, and testing of ductile iron fittings 48 inches and smaller.

Installation Data for Elliptical Pipes. PD 29 rev E 20/09/05

TCC/SHORE TRANSIT BUS MAINTENANCE FACILITY - PHASE II

DISTRIBUTED BY EMPIRE INFRASTRUCTURE PTY LTD

Reinforced concrete slot channel

Handling and Installation Instructions

A. Product Data: For surface pathways, wireways and fittings, floor boxes, hinged-cover enclosures, and cabinets.

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS

STRAIL level crossing systems & STRAILastic track damping systems

CORRUGATED DRAINAGE PIPES FOR DRAINING UNDERGROUND AND SURFACE RUNOFF WATER 01 / 2017 CATALOGUE

Top Performance Pipes for Toughest Conditions

CONNECTION TO INSPECTION CHAMBERS PRAKTO

ASSEMBLY AND OPERATING MANUAL LTW SLIDE RAIL SYSTEM - Type FP

Tasman Retaining Wall System

San Antonio Water System Standard Specifications for Construction ITEM NO. 813 WATER SERVICE FOR FIRELINES

SECTION SANITARY UTILITY SEWERAGE PIPING

INDEX FOR SPECIFICATIONS FOR REMOVING CULVERTS AND PLACING CULVERTS SCOPE... 1

SECTION STORM DRAINAGE

ITEM 460 REINFORCED CONCRETE PIPE Description. This Item shall govern for the furnishing of reinforced concrete pipe.

Multi-Gard PVC Assembly/ Field Cuts

Assembly and Installation Instructions Grease Separator KLsepa.pop


***************************************************************************************************************

Retaining Wall System

Section 2 Specification 2.18 Concrete and/or Corrugated Steel Storm Sewer TABLE OF CONTENTS

Perfect Manhole Installation Manual May 2012 Rev 8 Perfect Manhole System Precast concrete manholes with load bearing elastomeric joints

innostrail - installation instructions Subject to technical changes / January 2010 STRAIL level crossing systems & STRAILastic track damping systems

PVC pressure pipe (grey)

INDEX FOR SPECIFICATIONS FOR JACKING CULVERTS THROUGH EMBANKMENTS SCOPE... 2

UNDERGROUND UTILITY CONTRACTORS GENERAL TRADE KNOWLEDGE EXAMINATION CONTENT INFORMATION

Strengthened Soil Wall Construction Manual

ITEM NO SLIPLINING SANITARY SEWERS

SECTION A1 EXCAVATION AND BACKFILL GENERAL

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS

SECTION EXCAVATION AND BACKFILL FOR UTILITIES AND STRUCTURES

This section includes materials and installation of ductile-iron pipe and fittings for potable and recycled water systems.

San Antonio Water System Standard Specifications for Construction ITEM NO. 812 WATER MAIN INSTALLATION

Tasman Retaining Wall System

SECTION UTILITY POLYETHYLENE CONTAINMENT PIPE SYSTEMS

Innovation in Joint Restraint Systems for PVC Pressure Pipe and Fittings. Clean & Safe Drinking Water Workshop. Wednesday, March 25, 2015

ITEM D-701 PIPE FOR STORM DRAINS AND CULVERTS

UPONOR INFRASTRUCTURE. Uponor Gravity Sewer Systems 47

DOUBLE SLIDE RAIL INSTALLATION METHOD. Double Slide Rail August

STRAIL - installation instructions. Subject to technical changes / December STRAIL level crossing systems & STRAILastic track damping systems

Chapter 10. Pipeline Installation

Installation and maintenance instructions for GRAF rainwater storage tank, Carat-S series

GROUNDtrax GROUNDGRIDZ

ASSEMBLY AND OPERATING MANUAL LTW SLIDE RAIL SYSTEM - Type PV

for potable water supply

R-Group Finland Oy. RTA, RWTL and RWTS Lifting anchors Design instructions

FREESTONE ECOTM. Retaining Wall SystemTM. No one knows Blocks and Pavers better

SECTION TRENCHING, BACKFILLING, COMPACTION AND GENERAL GRADING

Employment Intensive Infrastructure Program (EIIP) in Lebanon ANNEX 2

INSTALLATION AND BURIAL OF GRP PIPES MANUAL

CONCRETE PIPES CONCRETE PIPES FACTORY. Since Concrete. Slabs (Cover) for Cable. Trench Jacking. Jacking Pipes. Non & Reinforced. without.

NOVEMBER 2016 GRANDWALL. retaining walls installation guide

NEMO TANK INSTALLATION GUIDE INSTALLATION INSTRUCTIONS FOR THE NEMO TANK STAGE

TS 803 DUCTS DUCT INSTALLATION, PROTECTION AND MARKING WITHIN A TRENCH OPEN TRENCH DUCT INSTALLATION PROFILE

UNIVERSITY OF MISSOURI Hydronic Energy Distribution 2016 Q1

Single-skin, externally reinforced, brick tank. Instructions for manufacture

Installation Guide for Precast Concrete Culverts

CONSTRUCTION SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS AND BOX SEWERS IN OPEN CUT

SECTION FACILITY SANITARY SEWERS

FOX METRO WATER RECLAMATION DISTRICT MANHOLE / SEWER PIPE MATERIALS AND INSTALLATION SPECIFICATIONS MATERIALS 1. PIPE & FITTINGS

Special Provision No. 421F01 April 2006

JUST THE FACTS CONCRETE PIPE VS. HDPE

Customer Requirements Conduit Installations, High Voltage

BRANZ FACTS RESILIENT NON-STRUCTURAL ELEMENTS SEISMICALLY RESILIENT NON-STRUCTURAL ELEMENTS # 3. Restraint systems

ASSEMBLY AND OPERATING MANUAL LTW SHORING BOXES VB 100

SECTION PIPE INSTALLATION

Section 3 Fusible PVC Pipe Connections

Summary. Mini KKP - Assembly and operating manuel Pile guide box. Montage. Implementation. Accessories. Technical data

SPECIFICATION FOR PIPE CULVERT CONSTRUCTION

Bio-Sand Filtration Filter Construction Guidelines

Building Construction

This type of masonry shall consist of brick laid in full beds of cement mortar.

50.20 Drainage Structure Design

Multicell. Vikimatic MultiCell Conduit Systems MULTICELL

SECTION UNDERGROUND ELECTRICAL CONSTRUCTION

PRODUCTION OF POLYETHYLENE AND POLYPROPYLENE PIPES POLYPROPYLENE SEWAGE PIPES PPHM HIGH PERFORMANCE PIPES.

LANDSCAPE RETAINING WALLS

R-Group Finland Oy. REA Lifting Inserts Technical Manual According to Eurocodes, EU Machinery directive 2006/42/EC and VDI/BV-BS 6205 CE Approved

RPA Plate Lifting Inserts Technical Manual

CAPRICORN MUNICIPAL DEVELOPMENT GUIDELINES PRECAST BOX CULVERTS CONSTRUCTION SPECIFICATION

Transcription:

h Installation Manual

1 General Information The installation of HOBAS GRP Pipes is subject to applicable standards and guidelines such as EN 1610 and ISO/ TS 10465-1. Correct installation always requires individual calculations and comprehensive planning by certified engineers. In addition to all applicable standards and guidelines, engineers shall at all times consider all relevant conditions of the individual installation and operating situation of a certain project. All figures and recommendations included in this manual or provided by HOBAS are basic information regarding HOBAS Pipe Systems and do not represent a commitment with respect to individual projects. 2 Health and Safety Legal and local provisions as well as safety and accident prevention regulations must be observed and complied with at all times. 3 Support HOBAS offers different types of customized support based on individual service agreements. For further information please feel free to contact our HOBAS Experts. 4 Transport At the factory, all pipes are loaded to suit the means of transport (rail, truck, or ship). To economically transport pipes of different diameters, smaller diameter pipes may be nested inside larger ones. The loading of the pipes is performed with a forklift or crane, preferably using a coil boom. Pipes must be lifted individually with lifting slings or similar (do not use hooks!). On a level surface suitable rolls may be used as an alternative. 5 Storage It is recommended to stack pipes on a level surface to evenly distribute the load. Mechanical damage and soiling of the joint surfaces must be avoided. If required, wooden beams and wedges can be used.

6 Buried Pipelines The system stiffness is an important aspect of buried installations and determined by the pipe and soil stiffness. The pipeline must be carefully bedded as the soil around the pipe has a supporting function. 6.1 Pipe Trench The minimum trench depth depends on the loads that are applied on the pipeline (traffic load, thrust load from bends, etc.). In any case, it is necessary to choose an installation depth below the frost line. HOBAS Specialists offer assistance in calculating the installation depth for individual applications. The minimum trench width should be calculated according to EN 1610. Requirements of ISO/TS 10465-1 can also be used if applicable. 1. Installation of single pipe in trench according to EN 1610: Table 1: Minimum Trench Width (de + x) Diameter [mm] Supported trench [m] Unsupported trench [m] b > 60 b 60 200 de + 0.40 de + 0.40 > 200 to 350 de + 0.50 de + 0.50 de + 0.40 > 350 to 700 de + 0.70 de + 0.70 de + 0.40 > 700 to 1200 de + 0.85 de + 0.85 de + 0.40 > 1200 de + 1.00 de + 1.00 de + 0.40 For the values de + x, the minimum working space between the x pipe and the trench wall or support equals 2. de... external diameter [m] b... angle of unsupported trench side measured to the horizontal [ ] 2. Installation of two pipes in trench; minimum trench width: de 0.5 m + de 1 + 1 de + 2 + de 2 + 0.5 m 2 2 3. Use of sheet piles during trench excavation; minimum trench width: de + 2.0 m or 3 de (the larger value is applicable)

1 b 6 2 3 5 7 4 10 8 9 1 Surface 6 Pipe bedding 2 Main backfill 7 Trench depth 3 Initial backfill 8 Trench width at pipe bedding 4 Depth of embedment 9 Trench width at pipe crown 5 Sidefill 10 Trench bottom 6.2 Soil Quality Both the native soil and the bedding material must have a sufficient load-bearing capacity. If the load capacity of the excavated material is insufficient, it must be substituted by suitable bedding material (see 6.3. Trench Bottom and 6.4. Bedding and Backfilling). Table 2: Deformation Modulus E B (N/mm 2 ) and Degree of Compaction D Pr (%) Soil Types (acc. to ATV 127) D Pr = 85 90 92 95 97 100 Group 1: Non-cohesive soil (e.g. gravel) Group 2: Slightly cohesive soil (e.g. sand) Group 3: Cohesive mixed soil (e.g. sand/clay mixture) Group 4: Cohesive soil (e.g. clay) 2 6 9 16 23 40 1.2 3 4 8 11 20 0.8 2 3 5 8 14 0.6 1.5 2 4 6 10

Table 3: Possible Cover Height (H) and Max. Allowable Initial Deformation (Def) SN 2500 SN 5000 SN 10000 Soil Types (acc. to ATV 127) H [m] Def H [m] Def H [m] Def Group 1: Non-cohesive soil (e.g. gravel) Group 2: Slightly cohesive soil (e.g. sand) Group 3: Cohesive mixed soil (e.g. sand/clay mixture) Group 4: Cohesive soil (e.g. clay) 4 < 4 % 8 < 4 % 12 < 4 % 3 < 4 % 5 < 4 % 7 < 4 % - - 4 < 3.4 % 6 < 3.5 % - - - - 4 < 3 % All figures shown above are non-binding examples. Each installation must be carried out on the basis of expert calculations and instructions. 6.3 Trench Bottom The trench bottom must be prepared in accordance with the required slope and installation depth of the pipe. The trench soil should not be loosened. If the soil is still loosened, suitable material must be added and evenly compacted. Any excavated material unsuitable for bedding the pipe and backfilling the trench should be stored separately. 6.4 Bedding and Backfilling With respect to the structural analysis of the installation, special attention has to be paid to the compaction of the bedding material. The thickness of the pipe bedding must be at least 15 cm or 0,1 x DN after compaction. With soft or unstable soils additional 15 cm of the soil should be replaced with e.g. soil type group 1 or 2. The pipe bedding must be tamped (e.g. with hand tamper or small pneumatic air tamper) and the entire length of the pipe must lie flat on the soil with the exception of the bell holes for the couplings. To ensure that the pipe sits flat on the base, bell holes measuring approximately three times the width of the coupling must be provided in the pipe joint area. Once the pipeline is bedded, the bell

Bell Hole holes must be backfilled with material of a comparable or higher degree of compaction. The bedding serves to apply a lateral soil pressure which relieves pressure on the pipeline. The bedding material must be inserted on both sides of the pipeline and backfilled up to a height of 30 cm above the top of the pipe. The material must be compacted on both sides simultaneously in order to prevent the pipeline from being displaced in any direction. If the soil is saturated with ground water or if aquifers are present, the material used for bedding and backfilling must be free of fines. In the sidefill and initial backfill zones the use of light vibro-tampers (max. service weight 30 kg) or light vibratory plates (max. service weight 100 kg) of an appropriate compaction depth is recommended. The following requirements apply regarding the bedding material: Perfectly compactable and sufficiently load-bearing, non-cohesive material If the material is compacted to a proctor compaction of 92 %, the minimum rigidity must be 3 N/mm 2 Depending on the diameter range, the below listed grain sizes should be used as bedding material: DN 400 8-16 mm DN 500 16-32 mm

Vibro-tamper, medium Service weight approx. 30 kg to compact the sidefill and initial backfill zone Service weight approx. 60 kg to compact the main backfill zone 0.3 m above the pipe crown The trench shall be refilled and backfilled in 30 cm layers. Each layer has to be compacted separately. The pipes must be stable and proper compaction achieved. The removal of sheet piles may have an effect on the pipe support. Therefore, sheet piles should be removed carefully and backfilling should be closely supervised. In the backfill zone between 0.3 and 1.0 m above the top of the main pipe the material can be compacted with a medium vibro-tamper (max. service weight 60 kg) or vibratory plate (max. service weight 500 kg). Heavy compaction equipment may be used beyond the 1 m mark above the top of the pipe. An underground warning tape should be provided. During the construction phase, major load transitions (use of e.g. heavy construction machinery or vehicles) should be avoided. 6.5 Pipe Handling Depending on the conditions on site, pipes up to DN 500 can be lowered into the trench manually. If a lifting gear is necessary, we recommend the use of lifting slings. Never attach hooks or chains as pipe ends may be damaged.

6.6 Pipe Jointing The pipes are delivered with one coupling mounted onto one pipe end. All parts of the pipe both its inner and outer surface must be cleaned and checked before the pipes are connected. The sealing elements of the couplings must be clean. A lubricant must be applied to the pipe ends and sealing elements (use only the lubricant supplied). Depending on the pipe dimensions, there are several possibilities to join the pipes: With a lever: With an appropriate pushing force: With an installation aid: E Group Worldwide HOBAS manufactures and markets HOBAS GRP Pipe Systems. The HOBAS Network includes HOBAS Production Facilities and Sales Organizations throughout the world. E Engineering GmbH Pischeldorfer Strasse 128 9020 Klagenfurt Austria T +43.463.48 24 24 F +43.463.48 21 21 info@hobas.com www.hobas.com Published: 11/2014 All rights reserved. No part of this document may be reproduced or utilized in any form or by any means without our prior written permission. All information in the document is correct at the time of going to press. However, we reserve the right to make changes without notice, in particular to technical data. The data given is not binding and must therefore be checked in each individual case and revised as appropriate.

Various coupling types are available to join HOBAS Pipes. HOBAS Technicians will help determine the optimal coupling. Standard Couplings: FW Coupling/FWC (GRP coupling, EPDM/NBR gasket seal) DC Coupling (GRP coupling, EPDM gasket) Special Couplings: Restrained Pressure Pipe Joints (GRP coupling, locking element, EPDM/NBR gasket seal) Assembly Coupling, e.g. by Straub (stainless steel coupling, EPDM/NBR gasket) Adapter Coupling (GRP coupling, EPDM gasket) Sleeve Coupling, e.g. by FlexSeal (EPDM gasket) Masonry Coupling (GRP coupling) 6.7 Curved Installation Depending on the pipe diameter, HOBAS Couplings can accommodate the following degrees of angular deflection: Table 4: Angular Deflection Depending on the Pipe Diameter Diameter [mm] Maximum Allowable Deflection < 600 3 600 to < 1000 2 1000 to < 1900 1 1900 0.5 Depending on the internal pressure and the angular deflection, it may be necessary to add suitable thrust blocks (concrete supports). a 6.8 Shored Trenches If the trench needs to be shored, the shores must be installed step by step as the trench is filled or compacted in layers. Trench subsidence influences the build-up of load above the pipes and should be avoided. When the shoring is removed, it is important to make sure the compacted backfill material ends flush with the native soil at the trench wall.

6.9 Pipe Length Adjustment On Site A circular saw can be used to cut HOBAS Pipes to length on site. After chamfering the trimmed end of the pipe, the coupling can be mounted using lubricant. No further finishing is required (no turning or similar). 6.10 Installation of Fittings Fittings are joined similarly to standard pipes (e.g. with a cable pull). If elbows with a large angle are installed, suitable installation aids may be required to properly direct the force necessary for the jointing process. HOBAS can supply such installation aids. The incorporation of elbows, branches, reducers, or similar fittings produces thrust forces. The amount depends on the shape and the internal pressure. These forces must be directed into the soil by utilizing thrust blocks or suitable compaction of the backfill material. The forces can also be directed into the soil by friction between pipe and soil. Locked joints are necessary in this case. Thrust Blocks Tee: Bend: Reducer:

Calculation of the thrust force: RN N N a de N = P de² π 40 RN = N a a = 2 sin a 2 P... Test pressure [bar] de... External diameter [mm] N... Internal force [kn] RN... Resulting thrust force [kn] a... Factor for calculating the thrust force [-] a... Angular deflection [ ] When calculating the thrust force, the test pressure of the system should be taken into consideration. 7 Concrete Casing All HOBAS Pipe Types are suitable for concrete casing. The pipes shall be laid according to 6.1 to 6.10 and then secured against buoying upwards using round steel bows (at least three per 6-m pipe). Plastic putty shall be used to prevent cement slurry from entering the gap in DC couplings. Then the concrete can be cast layer by layer and has to be well compacted levelled. Do not use timber supports. 8 Above Ground Installation The design of the pipeline supports should correspond to the HOBAS Recommendations. The pipe supports should be placed at a distance of maximum 3 m. In most cases, a supporting angle of 120 and a cradle width of 20 cm will suffice. When designing the supports, the longitudinal and lateral forces must be taken into consideration.

Length A DN DN 1 A 1 B A-A 5 B 2 3 4 1 Supports 2 Pipe 3 Coupling 4 Rubber strips 5 Fixation 9 Pressure Test A pressure test may be performed on properly bedded pipelines only. Before applying pressure, the line must be filled entirely with water. The test pressure should be max. 1.5 times the nominal pressure of the pipe or the nominal pressure + 5 bar. The lower of these two pressure values is applicable. The max. duration of the pressure test is recommended to be 1 hour. The end caps must be carefully secured so they can withstand the forces. 10 Other Installation Methods HOBAS Pipes can be installed by various methods, e.g. open cut, above ground, under water, relining, and jacking. Ask our HOBAS Technicians for further information or visit the HOBAS Website. HOBAS. Make things happen. www.hobas.com