GBR Fundamentals. Past Practices and Lessons Learned. Seminar on Geotechnical Baseline Reports. October 5, 2013

Similar documents
MANAGING UNDERGROUND RISKS: GEOTECHNICAL BASELINE REPORTS

MANAGING UNDERGROUND RISKS: GEOTECHNICAL BASELINE REPORTS

Geotechnical baseline reports

Contracts and Risk. Building blocks for success. Miami, November 14 th, 2016

GEOTECHNICAL BASELINE REPORTS APPLYING THE GUIDELINES TO MICROTUNNELING


G&P GEOTECHNICS SDN BHD CHECKLIST FOR EARTHWORKS (ROCK EXCAVATION AND ROCK SLOPE STRENGTHENING WORKS) WORK INSTRUCTIONS FOR ENGINEERS KYW.

4.5 GEOTECHNICAL, SUBSURFACE, AND SEISMIC HAZARDS

Developed countries require a modern infrastructure Roads Railways Power Communications Water Wastewater

RISK MANAGEMENT. Harald Wagner PhD, PE

Soil Improvement by Compaction Grouting

Construction Management

SHAFT CONSTRUCTION SECANT PILE

2008 Underground Construction Technology International Conference & Exhibition, Cobb County Galleria Center, Atlanta, GA - January

April 7, Webster Street Sub-Surface Stormwater Storage System Bid No Bid Date: 4/13/17 ADDENDUM NO 1

Is It Time for Design-Build?

Prof. Eng. Daniele PEILA

BRADSHAW CONSTRUCTION CORPORATION

Compaction and Jet Grouting

Problems Realized with Contractor-Proposed Pilot Tube Auger Boring

CHALLENGING SITES & HYDRO TUNNELLING CHOICE OF TECHNOLOGIES AND CONTRACT IMPLICATIONS

CONDUCTED FOR: PREPARED FOR: 5 May 2016 YPC Project No. 16GY146

CC1602 Microtunneling

SPECIFICATION FOR JET GROUTING

Supervision of tunnelling constructions and software used for their evaluation

Experts in tunneling with Tunnel Boring Machines

Winnipeg. ~~brt?ce /he ~,y.,f. Cockburn and Calrossie Combined Sewer Relief Works C Trunk Sewer Geotechnical Baseline Report 1-INAL- REV 1

Report of Exploratory Test Pits

IMPORTANCE OF RELIABLE GEOTECHNICAL INVESTIGATION FOR SAFE AND ECONOMICAL FOUNDATION DESIGN OF CIVIL STRUCTURES

What Every APPA Member Needs To Know About Construction Contracts

Concepts for handling changing muck properties caused by TBM excavation

Optimization of Supports in a Road Tunnel through Conglomerate during Construction

Preliminary Concepts for Soil-Bentonite Cutoff Wall Topock Compressor Station, Needles, California

8Re: Northern Access 2016 Project. Ischua Creek Crossing (MP 62.4) Analysis of Feasibility and Risks of Direct Pipe Installation

EJCDC Contract Documents for America s Infrastructure Buy online at

Logistics of Limited Space Urban Tunnelling at Singapore s Mega Metro

EJCDC Contract Documents for America s Infrastructure Buy online at

Risk Evolution from Planning to Construction on the LA Metro Crenshaw/LAX Light Rail Transit Project

STATE UNIVERSITY CONSTRUCTION FUND

HDD Training. Mitigation. Mark Miller, PE Jon Robison, PE

SECTION DRILLED CONCRETE PIERS AND SHAFTS

TBM Selection and Specification

Construction Family of Documents

The new Standard DWA-A 125E. Pipe jacking and related techniques. published in German and English by

SEMINARI MAGGIO Management of Geotechnical Risks

Slurry MTBM in Alluvial Soils and 25k Rock Chris L. Windley, P.E. McKim & Creed Inc. Stephen D. Leitch, P.E. Hazen and Sawyer, P.C. Joshua P.

EJCDC Contract Documents for America s Infrastructure Buy online at the ACEC Business Resource Center

Geotechnical Investigations Water Main Construction

TRENCHLESS SOLUTIONS FOR SEWER NETWORKS AND SEA OUTFALLS.

WARNING DO NOT BID ON THIS PROJECT

Project Owners, especially in the public sector, are. Design-Build and Public-Private Partnerships: Risk Allocation of Subsurface Conditions

King County Uses Trenchless Methods to Construct a Large Siphon Under Seattle s Ship Canal

FIDIC PROCUREMENT OPTIONS, Clause 3 and Clause 20

August 15, 2006 (Revised) July 3, 2006 Project No A

U.S. Army Corps of Engineers Jacksonville District Sediment Quality Control/Quality Assurance Plan For Maintenance Dredging with Beach Placement

Working Group 14 Mechanized Tunnelling Working Group 19 Conventional Tunnelling

REHABILITATION OF THE LANGETENTAL FLOOD DIVERSION TUNNEL

CONDUCTED FOR: PREPARED FOR: 18 October 2010 YPC Project No. 10GY133

Contracting and Project Delivery Options

DIFFICULT GROUND SOLUTIONS:

Design Challenges for Paradise Whitney Interceptor, Project 669, Las Vegas, Nevada

SEATTLE S BRIGHTWATER UNDERGROUND CONVEYANCE SYSTEM TUNNELING & UNDERGROUND CONSTRUCTION

PILE CAPACITY REDUCTION OF JACK-IN PILES WITH EMPTY PREBORED HOLE AT META-SEDIMENTARY FORMATION IN PENINSULAR MALAYSIA

POSTER PAPER PROCEEDINGS

TERMS OF REFERENCE PROJECT EDINBURGH ROAD FROM SPEEDVALE AVENUE TO LONDON ROAD

Wastewater Capital Projects Management Standard Construction Specification

CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING

COPYRIGHTED MATERIAL. Contents PART ONE: THEORY...1. Preface to the Third Edition xiii. About the Authors xv. Acknowledgements xvii

SEMINAR. Introduction to Continuous Flight Auger (CFA) piling Thursday 21/8/2013. Facilitator: Martin Larisch

Soil conditioning for EPB tunnelling in choesionless soil, clay and rock masses and backfilling in shield tunnelling

PROJECT INFORMATION. 1.1 Site Location. October 4, Jerry Schwab/President 315 Aden Ave., Suite 26 Glendale, CA 91203

Crossrail and our international tunnelling expertise

INDEX FOR SPECIFICATIONS FOR JACKING CULVERTS THROUGH EMBANKMENTS SCOPE... 2

Occupational Health & Safety Risk Management in Tunnel Works. Donald R Lamont C.Eng.,FICE. Animateur ITA WG5 - Health & Safety in Works

CONSTRUCTION SPECIFICATION FOR EXCAVATING AND BACKFILLING - STRUCTURES

Ardaman & Associates, Inc. Geotechnical, Environmental and Materials Consultants

VTA s BART Silicon Valley Phase II Extension

Ask the right questions

CHAPTER 32 - WELL ABANDONMENT ORDINANCE OF DUBUQUE COUNTY, IOWA. Adopted September 5, Part 1 Introduction...2

Small Diameter Rock TBM Tunneling in Baltimore

ORAL PAPER PROCEEDINGS

Subsurface Investigations PDCA Professor s Driven Pile Institute. Loren R. Anderson Utah State University June 25, 2015

SITE INVESTIGATION Validation and Interpretation of data

SEDIMENT QUALITY CONTROL/QUALITY ASSURANCE PLAN FOR BEACH RESTORATION OR NOURISHMENT USING AN OFFSHORE BORROW AREA. [FDEP Permit No.

Contracting Methods and Risk Management

GEOTECHNICAL INVESTIGATION PROPOSED OUTFALL LOCATION CITY OF MORGAN S POINT DRAINAGE HARRIS COUNTY, TEXAS REPORT NO

New developments in best practice for plant and design-build contracts

Shield TBM risk model based on Bayesian networks applicable in design stage

Tunnel Boring Machine Optimization

Misan University - College of Engineering Civil Engineering Department

2013 ASCE Agenda. Microtunneling in Difficult Ground Craig Camp. Microtunneling Characteristics (NASTT) Akkerman MTBM Introduced 1995

CIVIL and STRUCTURAL ENGINEERING PROFESSIONAL SERVICES NWCE- 8VTDJX. with the option to extend for up to a further 24 months. USER GUIDE Version 2

Korean Risk Management Practices : a Contractor s Perspective

TBM experiences from the Koralm railway tunnel (Austria) and re-use of TBM muck. Gerhard HARER

Behavior of Surrounding Soil during Construction and Its Countermeasures Using Pipe Jacking Method in Deep Strata

Fundamentals of Construction Contract & Contractual Risks: Design Risks

THE ROLE OF CERN IN THE LARGE CONSTRUCTION CONTRACTS FOR LHC CIVIL WORKS

Technology. Trenchless. Planning, Equipment, and Methods. Mohammad Najafi. Mc Gravu Hill

REPORT OF GEOTECHNICAL EXPLORATION AND ENGINEERING ANALYSIS

Transcription:

GBR Fundamentals Past Practices and Lessons Learned Seminar on Geotechnical Baseline Reports October 5, 2013 Association of Geotechnical and Geoenvironmental Specialists Randall J. Essex, P.E. Executive Vice President Hatch Mott MacDonald

Topics Historic Perspective GBR Fundamentals Risk Sharing Philosophy Physical vs Behavioral Baselines Lessons Learned Future Developments

Historic Perspective The U.S. enjoys more lawyers per capita than anywhere else in the world 1970s DC Subway Claims were litigated in a Board of Contract Appeals process Solution: Improve US Contracting Practices to keep the lawyers out of our business

Historic Perspective (cont d) Underground Technology Research Council (ASCE) publication: Avoiding and Resolving Disputes in Underground Construction (1989) Differing Site Conditions Clause (Contractual) Geotechnical Interpretive Report Escrow Bid Documentation Disputes Review Board

Historic Perspective (cont d) Contractual context is for North America Must adapt to accommodate different conditions of contract and legal norms

GBR Fundamentals Tunneling Facts of Life What is a GBR? How is it used?

8 Underground Facts of Life Tunnel projects are linear and can extend for kms Subsurface conditions can vary significantly across the site Subsurface conditions influence means, methods, and construction cost Underground surprises = commercial risk Contractors do not accept risk, they price risk Owners want the lowest cost of construction for their projects It s better to anticipate a risk event than be surprised Contracts that anticipate risks will result in lower cost and fewer claims

8 Underground Facts of Life We prepare a Geotechnical Baseline Report to Tunnel projects are linear and can extend for miles Underground surprises = commercial risk It s better to anticipate a risk event than be surprised Subsurface conditions can vary significantly across the site Contractors do not accept risk, they price risk Contracts that anticipate risks will result in lower cost and fewer claims Subsurface conditions influence means, methods, and construction cost Describe anticipated subsurface conditions during construction Describe how those conditions will influence construction Owners want the lowest cost of construction for their projects Describe how those conditions have influenced the design Identify key risks on the project Describe who carries the risks for conditions within and beyond the baselines

A GBR Is A Contract Document A set of contractual assumptions regarding the anticipated subsurface conditions An aid to administering the Differing Site Conditions clause under the contract A guidance document for bidding the project A risk allocation document to help manage the construction

A GBR is Not Based only on geotechnical data also reflects local construction experience and data gaps A warranty that the baseline conditions will be encountered Mother Nature is inherently variable and impossible to predict precisely A mechanism for pushing all risks to the Contractor

Risk Sharing Philosophy Surface vs Subsurface Projects Risk Shedding vs Risk Sharing Goals: Fairer basis for contracting Help avoid and resolve disputes Keep the lawyers out of our business

Surface vs. Subsurface Construction Surface Works Complicated construction Simple constraints Can work-around delays Underground Repetitive construction Complicated constraints Linear = Limited Critical Path No work-arounds Risks and consequences are different

Joint Code of Practice for Risk Management of Tunnel Works in the UK (2003) The 1990s 2000s Several spectacular UK tunnel failures Insurance losses following 9/11 attack Insurers needed to reduce their risk exposure Two driving principles Risk Registers Reference Conditions (a.k.a. Baselines)

Joint Code of Practice for Management of Tunnel Works in the UK (2003) Section 7 - Project Development Design Studies By the end of the Project Development Stage, the Client shall prepare (or have prepared on his behalf) ground reference conditions or geotechnical baseline conditions 1. Such Ground Reference Conditions or Geotechnical Baseline Conditions may not necessarily be those that have been assumed and adopted for the development of a preferred project option or options in terms of project outline designs or detailed designs as appropriate. They shall, however, be issued to tenderers as integral and formative information provided at time of tender on which tenders should be based (see Section 8). The Client shall take responsibility for the Ground Reference Conditions or Geotechnical Baseline Conditions so issued which shall form the basis for comparison with ground conditions encountered. The nature and form of the Ground Reference Conditions or Geotechnical Baseline Conditions shall be sufficiently detailed to obviate any argument as to matters of fact on which the tender was to be based and also provide the baseline against which encountered conditions can be reliably assessed. 1 See Geotechnical Baseline Reports for Underground Construction Guidelines and Practices published by the America Society of Civil Engineers, 1997

A Code of Practice for Risk Management of Tunnel Works (2006) International Insurers Group 2006 Modification of 2003 document Same objectives

Risk Shedding vs. Risk Sharing Risk Sharing: Owner ultimately owns the ground Risks allocated to contractor for: Specified range of anticipated conditions Means and methods consistent with anticipated conditions Workmanship Cost / Schedule Performance

Baseline Philosophy Physical and behavioral baselines Baselines should be a reasonable extension of the available information Assume the baseline is a line in the sand Within the baselines Beyond the baselines Contractor s Risk Owner s Risk Can set provisional sums for potential conditions outside baseline

Baseline Philosophy (cont d) The GBR should be brief 30-50 pages max The Owner should be involved with the setting of the baselines understanding the consequences of where the baselines are set

Physical vs Behavioral Baselines Physical baselines properties and strength characteristics - independent of construction means and methods Behavioral baselines How the ground responds to excavation processes

Physical Baselines - Soils Clays, silts, sands and gravels Strength, c/φ (for K A face pressure calcs), unit weight, water content, grain size, Atterberg limits Abrasivity, stickiness potential Permeability (horizontal and vertical) Cobbles, boulders, obstructions Groundwater levels, artesian conditions Contaminated ground and groundwater

Physical Baselines - Rocks Rock types - Sedimentary, Igneous, Metamorphic Strength - UCS, BTS, Point load, Punch penetration Mineralogy - Grain size, shape, interlock Boreability: DRI, CLI, Cerchar Abrasivity Stickiness potential (claystones) Rock Mass Defects - Joints, fractures, shears, weathering, alteration Permeability, Gas, Contamination

Physical Baselines Baseline Representations Characteristics of ground types across project Percentage of ground types to be encountered At shaft locations By tunnel reach Ground conditions Mixtures of different strata Interlayered systems Soil over rock Soil mixtures Rock mixtures Conditions beyond excavation limits

Physical Baseline Representations Item Poor Better Best Geologic Profile None No stratum boundaries Stratum boundaries Profile Information Data None Stick logs Soil logs with strength, plastic limits, water contents Rock logs with Recover, RQD, geophysics Tabulated results Tabulated results with min, max, and average values Histogram representation of data sets, showing min, max, baseline values, and data set signature

Behavioral Baselines How the ground will respond to the excavation process Open shield tunneling Close face / pressurized face NATM Tunnelman s classification (firm, raveling, running, flowing, squeezing) Atmospheric behavior still useful for pressurized face assessments Pressurized face tunneling: responses of soil types to different soil conditioning agents and dosages

Valuable Information for Pressurized Face Tunneling Cohesive soils Consistency Index Function of LL, PL, and W C Granular soils response to different foam dosage rates

Cohesive Soils: Consistency Index (Stickiness, Clogging) Ball, Young, Isaacson, Champa, Gause (2009). Research in Soil Conditioning for EPB Tunneling through Difficult Soils. Rapid Excavation and Tunneling Conference Thewes and Burger (2004) Clogging risks for TBM drives in clay. Tunnels & Tunnelling International, pp.28-31. June.

Granular Soils Slump Tests Different conditioners Foam Injection Ratios High Density Limestone Slurry Bentonite Polymer Ball, Young, Isaacson, Champa, Gause (2009). Research in Soil Conditioning for EPB Tunneling through Difficult Soils. Rapid Excavation and Tunneling Conference

Approach for D-B Contracts Same philosophy Owner owns the ground Risks should/can be shared Three-step development process Step 1 - GBR for Bidding (GBR-B) Addresses relevant physical conditions Specify/preclude certain means/methods Provides gaps for DB teams to explain Design approaches and bases Construction approaches and bases Anticipated ground behavior consistent with approaches

Approach for D-B Contracts (cont d) Step 2 GBR for Construction (GBR-C) Blanks filled in States behavioral issues key to design and construction means / methods Step 3 - Owner review Review baseline statements for reasonableness Resolve baseline terms and bid items Discussions with more than one bidder Accepted GBR is basis for Contract

Lessons Learned: Terms Avoid use of ambiguous words, such as could, may, or might if it might be encountered, Contractor can assume that it won t Avoid qualitative words high groundwater table frequent occurrence of boulders occasional joints short stand-up time Use quantitative terms where possible that can be measured and verified in the field

Lessons Learned: Data vs Baselines Baselines should be consistent with the data, if representative What if data is not representative insufficient borings insufficient testing non-representative database uncertainty in between the borings Previous experience In this case, baselines can over-ride the data

Lessons Learned: Fit within Contract GBR must fit with other Contract Documents Best to finalize following design completion Key link: measurement and payment provisions Reference, do not repeat or paraphrase, other Contract Documents GBR can serve as a roadmap to the Project Identify constraints and latitudes

Compatibility Check Page-Turning Consistency Check 3 C s Clear Concise Consistent General Conditions GDR Contract Drawings GBR Technical Specifications Payment Provisions

Additional Reading ASCE Guidelines Publication Reflects 30 years of practice Several industry feedback forums North America s views on GBR preparation and use ASCE Book Dept.,ISBN 13: 978-0-7844-0930-5 Amazon.com

PPP A Growing Challenge From ground risk perspective, PPP is no different than designbuild But PPP schemes are forcing us back to the You bid it, you build it ways of the 1970s We need to educate the financiers and concessionaires

Future Developments 2010 ITA World Tunnel Congress in Vancouver Dedicated 4 hours to Ground Reference Condition Reports ITA Contracting Practices Working Group will issue a GBRs guidance document for international use Conclusion: GRRs (or GBRs) serve a critical role, and are being used with increasing frequency around the world

Future Developments (cont d) GBRs are being used in Switzerland, New Zealand, Chile, Hong Kong, Singapore, Australia, the UK, and Japan Are they well written? Yes and No. ASCE Gold Book was recently translated into Japanese for application in Japan ASCE Gold Book will be translated into German Increased focus on understanding influence of different soil conditioning agents on tunnel spoil behavior how to baseline / should we baseline?

Future Developments (cont d) Abrasion-related wear is becoming the Achilles heal of pressurized face tunneling projects How to baseline or allocate risks associated with planned and unplanned interventions? Most critical for large diameter TBM projects

Summary Underground construction is unique Tunneling projects are becoming increasingly risky dependent upon successful application of sophisticated tunneling equipment Different contracting strategies are warranted GBR approach works Consistent with UK and Int l Joint Code Recommendations re Ground Reference Conditions Write reasonable baselines and enforce them Better to benefit from others lessons learned than your own

GBR Fundamentals Past Practices and Lessons Learned Seminar on Geotechnical Baseline Reports October 5, 2013 Thank You! randy.essex@hatchmott.com Tampa, Florida +1-240-361-3001