DESIGN AND CONSTRUCTION OF DERRY ROAD AND CANADIAN NATIONAL RAIL GRADE SEPARATION

Similar documents
Plessis Road Twinning and Grade Separation at CN Redditt Subdivision: Design Challenges and Innovative Solutions

SR 0136-G10 ABC BRIDGE REPLACEMENT in Eighty Four, PA

The Chief Estimator Software. Item Cost Summary Bridge & Overpass Projects

SINGLE STEEL BOX GIRDER BRIDGES FOR THE TERMINAL DEVELOPMENT PROJECT AT TORONTO PEARSON INTERNATIONAL AIRPORT. Srdjan Brasic, M.Sc., P.Eng.

ARGENTINE CONNECTION BRIDGE TRIPLE TRACK CROSSING. Kansas City Terminal Railway Company

Grade Separation Systems. Single-Span Rail Bridge Construction Procedure. An innovation from art engineering inc.

RESILIENT INFRASTRUCTURE June 1 4, 2016

Design and Construction of the SH58 Ramp A Flyover Bridge over IH70. Gregg A. Reese, PE, CE, Summit Engineering Group, Inc.

Geotechnical Challenges During the Construction of Denison Road East Railway Grade Separation

Conceptual Design Report

DESIGN OF CAMPBELL ROAD OVERPASS IN KELOWNA. Yulin Gao, M.A.Sc., P.Eng., SNC-Lavalin Inc. Samson Chan, M.Eng., P. Eng., SNC-Lavalin Inc.

DESIGN OF TEMPLETON OVERPASS FOR THE CANADA LINE. Yulin Gao, M.A.Sc., P.Eng., SNC-Lavalin Inc. Samson Chan, M.Eng.,P.Eng., SNC-Lavain Inc.

ESTABLISHING A SOLID FOUNDATION FOR NEW BRIDGE CONSTRUCTION REPLACEMENT OF BRIDGE OVER THE SOUTH CANADIAN RIVER NEAR PURCELL, OKLAHOMA

NORFOLK SOUTHERN CORPORATION UNDERPASS GRADE SEPARATION DESIGN CRITERIA

SEGMENTAL CONTRUCTION IN THE INNER CITY: THE BQE CONNECTOR RAMP TO WILLIAMSBURG BRIDGE

Sweet Creek Road Retaining Wall Replacement. Mapleton, OR

Review of Plans and Specs from a Constructability Perspective

STRUCTURE SELECTION REPORT

Ironton Russell Bridge Project

MINNESOTA HISTORIC PROPERTY RECORD PART I. PROPERTY IDENTIFICATION AND GENERAL INFORMATION

Railway Bridge: Design and Detailing for Construction

Chapter 1. General Design Information. Section 1.02 Structure Selection and Geometry. Introduction

Cast in place concrete parapet and Ministry standard sidewalk railing.

Ironton Russell Bridge Project

MILTON-MADISON BRIDGE REPLACEMENT

Ironton Russell Bridge Project

PUBLIC INFORMATION MEETING June 24, 2015

Constructability Guidelines

MISENER DAM. Site Number LYNN STREET, PORT DOVER km N of Highway 6

VT 14 East Montpelier Bridge Project Informational Meeting. February 22, 2017

Kicking Horse Cantilever Structure. Bruce Hamersley, P.Eng., Klohn Crippen Berger Ltd. Keith Mitchell, P.Eng., Klohn Crippen Berger Ltd.

ASCE STRUCTURAL ENGINEERING CONFERENCE. Ames Iowa

Folsom Lake Crossing by Hans Strandgaard, Alex Harrison, Jeff Aldrich, and Jeff Thomure, CH2M HILL

Ironton Russell Bridge Project

TRUNK SEWER RELOCATIONS AT 900 ALBERT STREET SERVICING, CONSTRUCTABILITY AND MAINTENANCE REPORT

Ironton Russell Bridge Project

Ironton Russell Bridge Project

EXECUTIVE SUMMARY. Figure 1 - Rail Deck Park Study Area. Executive Summary Rail Deck Park Engineering & Costing Study Report Page 1 of 10

Highway Bridge Structure Components

Ironton Russell Bridge Project

BUILDING THE MERSEY GATEWAY a step by step guide

DESIGN OF ROAD OVERBRIDGES

RESILIENT INFRASTRUCTURE June 1 4, 2016

Presented by: Taya Retterer BRG Webinar July 30, 2012

Dundas Street Crossing of Sixteen Mile Creek A Field Spliced, Post-tensioned Precast Concrete Girder Bridge

Rehabilitation of Masonry Piers at Nipigon, Ontario

UPDATED 04 OCT 07. Following are sample questionnaires to be used to collect information from owners of affected facilities.

CNR Milton Mobility Hub Environmental Impact Statement (EIS) EXPERT REPORT ON GEOTECHNICAL ASPECTS

I-74 over the Mississippi River

ACHD Bridge and Culvert Policy DRAFT

Final Estimates Level 2

Safe, innovative, quality construction since Riding on the Strength

Save time. Save money. Specify a fast, economical Vist-A-Wall MSE. fast and easy to install. They adapt well to curves, angles and

Pattullo Bridge Replacement Project. Cost Report

Well Road Project Accelerated Bridge Construction Using Self-Propelled Modular Transporters (SPMT s) By: Mark Bucci, P.E.

TYPICAL SECTIONS TYPICAL NO. 1 (MAINLINE) STA TO STA STA TO STA

COUNTY ENGINEERS ASSOCIATION OF MARYLAND SPRING 2016 CONFERENCE. Conference Center at the Maritime Institute Anne Arundel County, Maryland

Jane Addams Memorial Tollway (I 90) Fox River Bridge Traffic Needs Drive Innovative Solutions

ACCELERATED BRIDGE CONSTRUCTION IN NEW ZEALAND THE DESIGN PROCEDURE

CHAIR AND MEMBERS CIVIC WORKS COMMITTEE MEETING ON APRIL 24, 2017

Misan University - College of Engineering Civil Engineering Department

3.6 Construction Methods

Design Challenges and Construction Benefits of Precast Segmental Rail Bridges

Trenchless Crossing of a Failure Prone Watermain in Poor Soil Conditions

7 Bridges in 74 Days. NC 12 Detour

Strathcona County Functional Planning Study Highway 15:06 From Range Road 220 to Highway 830 A P P E N D I X G BRIDGE ASSESSMENT E00311A

Draft. Not Yet Approved SECTION 10.1 GENERAL SCOPE DEFINITIONS

NORFOLK SOUTHERN RAILWAY COMPANY FILES: BR & BR

ABRAHAM LINCOLN BRIDGE

SOUTH MEDFORD INTERCHANGE BRIDGES

UNDERWATER BRIDGE INSPECTION REPORT DISTRICT 6 - RICE COUNTY

Welcome and thank you for spending time with us today to talk about the 75 th Street Corridor Improvement Project.

SPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006

Canadian Consulting Engineering Awards 2016 CANADIAN NIAGARA POWER FOREBAY BRIDGE RECONSTRUCTION

The New Incremental Launching Construction Technology of Jiubao Bridge Long-span Hybrid Arch-girder Structure

DESIGN OF THE MAIN SPANS OF THE CHONGQING CAIYUANBA BRIDGE

PHASING CONSIDERATIONS FOR BRIDGES

B R I D G E O F F I C E

Introduction.» Demolition Concepts» Concept Design» Final Design» Construction» Health Monitoring

A New At the port columbus

Bridge Construction. Nick Haltvick North Region Bridge Construction Engineer May 17, Bridge Office mndot.gov/bridge/construction.

B R I D G E O F F I C E

MOSLEY STREET URBANIZATION TH

Lesner Bridge Replacement

PAN PAC PULPMILL TREATMENT TANK

6 Preliminary Assessment of Construction Method and Constructability Issues

Automated Machine Guidance

Modeling and Design of Bridge Super Structure and Sub Structure

1.02 RELATED WORK: Refer to the following sections for related work: Section 4000-Concrete Materials and Methods

Pueblo's New 4th street

PRECAST CONCRETE GIRDER ERECTION

FRST 557 Lecture 7b Cross Drainage Structures: Culverts and Bridges

Alberta Bridge Inventory STANDARD BRIDGE & CULVERT COMPONENTS. Standard Bridges. Typical Bridge Components. In Alberta there are about 13,300 bridges.

Design of Izmir Bay Crossing Bridge

LRFD Bridge Design Manual Changes

2016 STRUCTURE INSPECTION APPRAISAL REPORT. Prepared For: THE CORPORATION OF THE TOWNSHIP OF AMARANTH COUNTY OF DUFFERIN

CONSTRUCTION SPECIFICATION FOR TRENCHING, BACKFILLING, AND COMPACTING

List of Our Completed Projects:

7. Draw an equipment set up for the production of a beam by post tensioning. 10. What are the common concrete structures which are produced by

Progressive Erection Applied to Box Girder with Strutted Wing Slab

Transcription:

DESIGN AND CONSTRUCTION OF DERRY ROAD AND CANADIAN NATIONAL RAIL GRADE SEPARATION Vireak Hinh, P.Eng. R.V. Anderson Associates Ltd., Toronto, Canada Jennifer Trimble Region of Halton, Oakville, Canada Paper prepared for presentation at the Structures Session of 2015 Annual Conference & Exhibition of the Transportation Association of Canada Charlottetown, PEI

ABSTRACT The Derry Road (Regional Road 7) grade separation was identified as part of the 2006 Class Environmental Assessment for Derry Road Transportation corridor conducted by the Regional Municipality of Halton. The report was initiated out of Halton s 2004 Transportation Master Plan and recommended an underpass at the Canadian National Railway Crossing of Derry Road between Scott Boulevard and Bronte Street in Milton, Ontario. Derry Road is an arterial road running across Halton Region from the City of Hamilton boarder to Halton s boundary with Peel Region, crossing through both the City of Burlington and the Town of Milton. The underpass was identified to satisfy east-west capacity requirements, to reduce delays and improve safety for cyclists, pedestrians and vehicular traffic. The crossing consists of CN right-of-way passing through a densely populated area. R.V. Anderson Associates Limited was retained by Halton Region as the Prime Consultant to design and construction management for grade separation capable of carrying two tracks across a four span railroad bridge. New Alliance is the General Contractor. The project included a number of unique challenges requiring innovative solutions for lane configurations and detours to maintain traffic flow and address safety for workers and pedestrians. Project features include a 4200 cubic meter precast storm detention tank buried under Derry Road, a fully computerized pumping station and two oil-grit separators to address debris and pollutants from stormwater runoff. In tandem with the bridge construction, Derry Road has been lowered by approximately seven meters and accommodates four lanes of traffic. The construction of the underpass was accelerated from 2018 to 2013 to accommodate the rapid growth in Milton. Construction is expected to be completed by summer of 2015.

1 INTRODUCTION Derry Road (Regional Road 7) is an east-west major arterial road within the Regional Municipality of the Region of Halton, bisecting Halton, from the City of Hamilton limit to Peel Region boundary. The Derry Road/CN Rail Grade Separation was identified as part of the 2006 Environmental Study Report (ESR) completed for the Derry Road corridor. The report recommended that Derry Road be reconstructed from 2 to 4 lanes including a grade separation at the CN Rail crossing. The work was completed in two contracts with the road widening and detour commencing in 2009 and the underpass in 2013. The ESR confirmed the existing at-grade crossing at the CN Rail line would not be able to accommodate the anticipated travel demand projected for 2021. An underpass was identified as the preferred solution. Project features include a 4200 cubic meter precast storm detention tank buried under Derry Road, a fully computerized pumping station and two oil-grit separators to address debris and pollutants from stormwater runoff. The project also required a secant retaining wall system to maintain an existing Milton Hydro transfer station. In tandem with the bridge construction, Derry Road has been lowered by approximately seven meters. Photo 1: Grade Separation looking westbound

2 DESIGN SUMMARY 2.1 Bridge Substructure Before excavating to road sub-grade, augured caissons and piers were constructed at grade level just below pier cap elevation. This approach allowed for cost savings and avoided deep excavation and expensive shoring system. The caissons extend down and installed into sound bedrock. A total of 34 caissons were installed in rock sockets to support the bridge structure. Each abutment is built with connecting wingwalls for ground stability near the tracks. The substructure design comprised a large diameter caisson which transitioned into a smaller diameter pier to increase spacing between the columns while maintaining strength of the system. Forming the size change between pier and caisson became a major challenge and required careful planning and attention to detail. The Contractor used an innovative double steel casing technique which allowed them to achieve the design requirement. Figure 1: Bridge Elevation 2.2 Bridge Superstructure After the bridge substructure was completed, the deck was formed by falsework shoring system which extended approximately 2 meters above grade. Constructing the deck in a shallow excavated area was the preferred solution to avoid expensive excavation costs. The deck slab is 1.5 meters thick and spans over 3 piers. Once the bridge deck was formed and reinforcements were in place, it was ready for 680 cubic meters of concrete. The continuous pour took place over an 8 hour window which required careful coordination and staging.

All bridge bearings of the piers and abutments are spherical bronze bearings, which provide excellent corrosion resistance and full freedom of rotation in all directions. These bearings weigh approximately 1900 kilograms each. Sliding plates in the bearings also allow for longitudinal expansion and contraction of the bridge deck. The bearings are self-lubricating and outfitted with bird screens to prevent corrosion from feces accumulation. Photo 2: Continuous Concrete Deck Pour 2.3 Stormwater Detention Tank The lower elevation of the new road at the underpass will result in surface runoff collecting and ponding underneath the bridge if adequate drainage is not provided. The stormwater detention system is used to detain surplus water during storm events and then allow it to drain during periods of lower flow. Figure 2: Typical cross section of precast storm detention tank

The amount of water to be detained during a 50-year storm is 4200 cubic meters. To accommodate this large volume of water, a storm tank 10.5 m wide by 120 m long with varying height was designed. Rail traffic was continuous through all stages of excavation and tank construction. The stormwater detention tank consists of a V-shaped cast in place concrete channel with upstand walls on either side and then topped with 66-1.8 m wide precast concrete arches spanning across the walls. After being completed, the tank was buried beneath engineered backfill before the road was constructed on top. 2.4 Pumping Station Photo 3: Installation of precast detention tank To pump out the storm water from the detention tank, it was necessary to add a pumping station at the grade separation. A 3.0 m diameter precast maintenance shaft approximately 15 m deep was constructed to house three submersible pumps. Whenever the tank is full of water, the pumps are turned on automatically and a forcemain carries the water to a nearby manhole. 3 CONSTRUCTION CHALLENGES 3.1 Railway Requirements Before track diversion could take place, a railway protection wall was constructed to support the existing CN freight operation. The track protection comprised of steel pile and lagging which were tied back with inclined grouted anchors. Track settlement and pile deflection points were installed to monitor and measure movements of the wall during construction. CN Rail freight operations were required to remain uninterrupted throughout construction. In order to maintain rail operations, a detour track was constructed to the east of the existing track and utilized until the new CN Bridge was completed.

Careful coordination between Contractor and CN flagging contributed to an integral role for the success of the switchover. 3.2 Traffic Requirements The nature of the construction, with limited space for equipment and materials required a series of road closures that resulted in an enhanced communication strategy with the community. Halton used a wide variety of communication tools from social media to traditional print and on site Police services, to help the motorists and residents navigate the road closures. A detour road was constructed to maintain traffic around the construction zone. 3.3 Site Constraints The underpass is located in a fully developed section of Milton. The project includes 1.3km of Derry Road between Scott Boulevard and Bronte Street and is bordered by Milton District Hospital and Milton Fire Department Headquarters (Station #3). Approximately 30,000 vehicles travel on Derry Road every day. There are a number of existing and proposed utilities within the Derry Road right-of-way. Existing Milton Hydro transfer station is located in the northwest quadrant of the CN Rail crossing Derry Road. Hydro One transmission lines with Bell Canada plant are located on a pole line southwest and north boulevard of the CN Rail Crossing. Road protection wall at the southwest corner was installed to allow the staging for the excavation. 3.4 Settlement Monitoring The grade separation is located in close proximity to many different residential and commercial properties. In combination with high volumes of dewatering, there was risk of settlement damage to adjacent properties without proper project controls. Adding to the risk was the fact that the railroad tracks were also not allowed to settle. Careful monitoring was performed to ensure settlements were avoided. A detailed survey of the surrounding properties was undertaken. Particular care was taken to look out for existing cracks. Total stations were used throughout construction to survey track positioning and possible shoring wall deflection.

4 CONCLUSION The Derry Road grade separation successfully overcame a number of significant engineering and coordination challenges to provide improved traffic and pedestrian flow to the surrounding neighbourhood. Cooperation between the General Contractor, CN, Town of Milton, Region of Halton and local property owners contributed to overcoming many challenges. The project is on track to be completed by the end of summer 2015.