Central Washington University

Similar documents
Marshall Municipal Utilities EXCAVATIONS AND TRENCHING Effective August 1, 2011 Revised August 17, 2017

Excavation Safety Program

WHITMAN COLLEGE TRENCHING AND SHORING PLAN

Date Prepared: Location: Time: Approximate Temperature (degrees F): Weather Conditions: Project Name:

Excavation & Trenching. A Trenching Tragedy

DuPage County Environmental, Safety, Health & Property Loss Control Program Excavation & Trenching Confined Space Procedure

OUTLAW AUTOMATION INC. Safety Management System

Excavation and Trenching

Subpart P. Trenching & Excavating CLIENT SAFETY SERVICES

Two (2) Working Days before you dig, call Underground Service Alert at (811) or 1-(800)

Risk Control at United Fire Group

Excavation and Trenching Safety Program

Title- Excavations Effective Date: 03 Jan 05 Revision-0

Excavation &Trenching

Excavation and Trenching Program. Tampa Electric Company. Energy Supply

Operations: HSE. Ground Disturbance Safe Work Practice (SWP)

To establish the Panama Canal Authority (ACP) occupational safety requirements for excavations.

EXCAVATION AND TRENCHING SAFETY REQUIREMENTS

Excavation and trenching safety

Excavation & Trench Safety 1

TRENCHING AND EXCAVATION

SECTION TRENCH SAFETY PART 1 - GENERAL

MUNICIPALITY PERMIT Issued by the City of Holyoke 63 Canal Street, Holyoke, MA Phone (413) FAX (413)

Excavations. OSHA Office of Training and Education 1

ESSENTIAL SAFETY RESOURCES

OSH INFORMATION MEMORANDUM: 90-X-84. Inspection Procedures for Enforcing the Excavation Standard, Subarticle 7, 1926, Subpart C

Weekly Safety Talks: Excavation & Trenching Application

Trench Safety & Qualified Person Presented by: Mike Ross National Training Director

29 CFR 1926 Construction Subpart P

Purpose of Excavation Training

OKLAHOMA CITY COMMUNITY COLLEGE. Trenching and Excavation Safety Program

Excavations. OSHA (Revised)

Excavation and Trenching 2018 Stand Down. Jim Shelton, CAS Houston North Area Office

!!! Sample Written Program For Your Company!!! Excavation Safety. 29 CFR 1926, Subpart P !!!!! Provided By:

DEPARTMENT OF LICENSING AND REGULATORY AFFAIRS DIRECTOR'S OFFICE CONSTRUCTION SAFETY STANDARDS PART 9. EXCAVATION, TRENCHING, AND SHORING

All employees who perform work which requires the removal of material that exceeds a depth of 1.2 meters (4 feet).

The first line of defense from cave-ins: The Competent Person

Freeport Site Standard

RESOLUTION NO COL Excavation/TrenchingPolicy ADOPTING THE CAYUGA COUNTY EXCAVATION/TRENCHING SAFETY POLICY FOR COUNTY EMPLOYEES.

Trenching and Shoring Safety in Construction Environments. Leaders Guide and Quiz

Trenching and Shoring Guidelines

Field Instruction. All Horizon Power workers who work in and around excavations.

Contents. Before you begin. Introduction: Installing trench support 1. Element 1: Planning and preparing 3

Excavation Safety. May 2007

Safety Meeting Topic #21 Trenches/Excavations

THE UNIVERSITY OF SOUTHERN MAINE (USM) Excavating/Trenching Program

This data sheet discusses problems

Excavation General Awareness Safety Training Presentation Red Willow Production Co.

Trenching & Shoring Safety Course Outline

RISK MANAGEMENT PROCEDURE

OSHA New Confined Space Rule

Excavation & Trenching Study Guide

SECTION CS-2. TRENCH EXCAVATION CONSTRUCTION STANDARDS

SECTION EXCAVATING, BACKFILLING, AND COMPACTION FOR UTILITIES

Trenching. 29 CFR Excavation Requirements. - Controls the trenching and excavation requirements for construction (excluding tunnels)

Excavations. Department of Consumer & Business Services Oregon Occupational Safety & Health Division (OR-OSHA)

SAMPLE PAGES. Construction Safety and Health Program. [Company name]

GROUND DISTURBANCE, TRENCHING, & EXCAVATING SAFE WORK PRACTICE 1.0 PURPOSE

Excavation Safety. Standard Operating Procedures Summary

PRO Ground Disturbance

(c) Presentation of Information. Information is presented in several forms as follows:

CODE OF PRACTICE EXCAVATION

CITY OF WILSON. Public Services Engineering. Backfilling, Compaction, & Patching Policy on Existing Pavements

To Loughborough University Facilities Management (FM) Health and Safety Policy

Excavation Safety 6ES00-2.0

ilkti ...:- WOC LP Standards Section E005 - Excavation kj/0i DOCUMENT NO: WOC-HSE-ST-0001 & EP Department 44, 4R 11. C

TRENCH SAFETY FINAL EXAMINATION

Ground Disturbance or Surface Penetration

Excavation. Function: EHS Number: HAN-EHS-SPI-0278 Page: 1 of 18 Original Effective Date: Reviewed 07/03/18 Effective: Supersedes: 03/17/17

Partner Update MITA. Doug Needham, P.E. Michigan Infrastructure & Transportation Association Vice President of Industry Relations

THE UNIVERSITY OF SOUTHERN MAINE (USM) Excavating/Trenching Program

DIGGING SAFELY. Damage Prevention is a Shared Responsibility. Steve Cleaver Senior Investigator Dig-in Reduction Team (DiRT)

BUILDING A WORLD OF DIFFERENCE. Briefing for Resident Engineers

2. City of Seattle Supplement to the Specification for Road, Bridge and Municipal Construction, most current addition.

TRENCH SAFETY SPECIFICATIONS FOR THE DENTAL DEPOT CITY OF THE COLONY, TEXAS. Prepared for BLUESTONE PARTNERS. Project # 18115

Excavation Safety. Basic

Union County Vocational - Technical Schools Scotch Plains, New Jersey

Electric Service Handbook

CITY OF AUBURN STANDARD SPECIFICATIONS SECTION 13 EXCAVATION AND BACKFILL

SAFETY ORIENTATION FOR EXCAVATION WORKERS

1.01 GENERAL. l.02 PIPELINE TRENCH EXCAVATION PIPELINES AND STRUCTURES REVISION: SECTION 1 PAGE : 1-1

Work involving excavations

Management of Health and Safety Risk Associated with Excavation Cave-in

Excavation and Trenching

Safety Overview. Falls Scaffolding Excavation. Risky Business. But is construction dangerous?

Barricades. Preparer: Owner: Approver: EHS Specialist EHS Team Leader Site Director J. Walker (Electronic Signature on File)

ESSENTIAL STANDARD no.1. Excavations

If a new residence s electrical service is not located within 200 feet of existing

C. Foundation stabilization for pipe and utility structures.

Scaffolding Procedures

SECTION TRENCHING, BACKFILLING, COMPACTION AND GENERAL GRADING

WORKING AT ELEVATED PLACES Working on Roofs

Section 24 Brieser Construction SH&E Manual

TRENCH SAFETY TRAINING

Excavations and Blind Penetrations into Walls & Floors

Instruction Guide APPLICATION OF CIM TO EARTHEN PONDS AND RESERVOIRS (USING CIM SCRIM)

SAFE WORK METHOD STATEMENT

Misan University - College of Engineering Civil Engineering Department

Rockhampton Office Brisbane Office Tarong Site. Barron Gorge Hydro PS Kareeya Hydro PS Mica Creek PS

Section 24 Brieser Construction SH&E Manual

Transcription:

Central Washington University Excavation, Trenching and Shoring Program Plan prepared by: Central Washington University Office of Environmental Health & Safety 400 East University Way Ellensburg, WA 98926 P: 509-963-2252 or 963-2338 F: 509-963-2238 2017 Excavating/Shoring/Trenching) Plan (Rev. 2/2017) Page ii

Table of Contents 1.0 Policy...1 2.0 Definitions...1 3.0 Excavations 4 Feet Deep or Greater...1 4.0 Excavations Less Than 4 Feet...1 5.0 Equipment Procedures...1 5.1 Backhoe...1 5.2 Skid Loader (Bobcat) Operation...2 6.0 Deep Excavations...2 7.0 Storage of Excavated Material...2 8.0 Excavation and Trench Escape Routes...2 9.0 Selection of Shoring, Sloping or Benching System...2 10.0 Sloping System Procedures...2 11.0 Shoring Systems...3 12.0 Surface Encumbrances...3 13.0 Use of Backfilling, Covering or Barriers...3 14.0 Inspections...3 14.1 Unusual Hazardous Conditions...3 14.2 Potential Cave-ins...3 15.0 Underground Utilities...4 15.1 Utility Locating Policy...4 15.2 Contacting Utility Companies...4 15.3 Support and Protection...4 15.4 Signs of Possible Unknown Utility Lines or Pipes...4 16.0 Water Hazards...4 17.0 Walkway and Bridge Requirements...4 18.0 Observers...4 19.0 Top Person (Spotter/Safety Monitor)...4 Appendix A: Utility Locate Form...5 Environmental Health & Safety Page i

1.0 Policy Protecting employees in operations involving excavations or trenching is a very high priority. In order to reduce the hazards associated with excavating and trenching operations, the following specific procedures have been developed (WAC 296-155-650 Thru 664) 2.0 Definitions 2.1 Trenches Trenches are defined as narrow excavations [WAC 296-155-650(26)]. Throughout this plan, all statements referring to excavations also apply to trenches. 2.2 Competent Person One who can identify existing or predictable conditions in the surroundings that are unsanitary, hazardous, or dangerous to employees. They must be knowledgeable in the WAC requirements and have authorization or authority to take prompt corrective measures to eliminate the hazards [WAC 296-155(2)(f)]. 2.3 Benching This refers to the method of protecting employees from excavation caveins by cutting the excavation sides to form one or a series of horizontal levels or steps, usually with vertical or near-vertical surfaces between levels. See WAC 296-155- 66403 figures N-3, N-8, and N-9. 2.4 Utility Locates This refers to the process of identifying the specific location of all utilities before excavating begins (see section 15.0: Underground Utilities). 2.5 Exceptions - Approval from a supervisor is necessary to perform operations or use procedures that differ from the guidelines in the following sections. 3.0 Excavations 4 Feet Deep or Greater Except in solid rock, the sides of trenches and excavations (including embankments) more than 4 feet in depth must be sloped, benched, supported, shored, sheeted or braced in a manner sufficient to protect against hazards associated with the collapse of vertical excavation walls. 4.0 Excavations Less Than 4 Feet Trenches less than 4 feet in depth must be effectively protected when there are indications that hazardous ground movement is possible. 5.0 Equipment Procedures 5.1 Backhoe Operations 5.1.1 Trained Operators Only persons with prior training and experience are permitted to operate a backhoe. Documentation of training and experience will be maintained at the Jongeward Plant Services building office. 5.1.2 Spotter/Safety Monitor A spotter/safety monitor must assist the backhoe operator when digging in areas of potential hazard from electrical or gas utilities or when working in high pedestrian activity areas (also see section 18.0: Observers). 5.1.3 Hard Hats Workers within the caution area, as well as the backhoe operator, must wear an approved hard hat. 5.1.4 Workers Within the Excavation No worker is allowed within the excavation while the end of the backhoe arm is also within the excavation. Workers must exit to a safe location while materials are being positioned Excavation, Trenching and Shoring (Rev. 2/2017) 1 P age

above or lowered into the excavation. While a person is within the excavation, the backhoe arm shall be positioned away from the top edge of the excavation, so that the end of the arm cannot reach the worker, in case of an inadvertent activation. 5.2 Skid Loader (Bobcat) Operations 5.2.1 Trained Operators Only persons with prior training and experience are permitted to operate a skid loader (also referred to as a Bobcat). Documentation of training and experience will be maintained at the Jongeward Plant Services building office. 5.2.2 Caution Area A designated caution perimeter should be maintained around excavations, by using barriers, caution tape and/or signage. The size of the caution perimeter is to be 6 feet greater than (when available) the reach of the skid loader. Observers are to remain outside this perimeter at all times. 5.2.3 Spotter/Safety Monitor A spotter/safety monitor must assist the backhoe operator when digging in areas of potential hazard from electrical or gas utilities or when working in high pedestrian activity areas (also see section 18.0: Observers). 6.0 Deep Excavations Protection systems for use in excavations more than 20 feet in depth must be designed by a registered professional engineer. 7.0 Storage of Excavated Material 7.1 Away From the Edge In excavations or trenches where employees are required to work, excavated or other material will be stored and retained at least 2 feet away from the upper edge. 7.2 Barriers Barriers or other effective retaining devices may be used to prevent excavated or other material from falling or rolling into the excavation or trench. 8.0 Excavation and Trench Escape Routes When employees are required to be in excavations or trenches 4 feet deep or more, an adequate means of exit, such as a ladder or steps, must be provided and located within 25 feet of lateral travel. An earth ramp is acceptable providing all following are met: The stability of the earth is adequate for good footing. The total travel distance does not exceed 25 feet. Adequate shoring or equivalent protection is provided for the entire escape route. 9.0 Selection of Shoring, Sloping or Benching System Whenever excavations are deeper than 4 feet, the use of sloping, benching, or shoring is required to protect the workers. The project supervisor will select the type of system that best suits the soil and work site conditions of each particular excavation. 10.0 Sloping System Procedures 10.1 Slope Faces Employees must not work on the faces of sloped excavations at levels above other employees unless employees at the lower levels are protected from the hazard of falling, rolling, sliding material or equipment. Excavating/Shoring/Trenching Plan (Rev. 2/2017) 2 P age

10.2 Allowable Sloped A maximum slope of 1.5:1 or 34-degrees, will be the standard slope for CWU campus excavating work until further notice. 10.2.1 Actual Slope The actual slope must be less than the maximum allowable slope when there are signs that a cave-in is imminent or might occur as a result of fissures, slumping, bulging, the edge sinking or lowering, or materials separating from the face. In this case the slope should be reduced by a factor of at least ½ horizontal to 1 vertical which would bring the maximum allowable slope to 2:1. The actual slope must be less than the maximum allowable slope whenever there is excess material or equipment next to the excavation or traffic next to the edge. 10.3 Slope Shoring, When Over 3.5 Feet Deep Whenever sloping does not reduce the vertical slides of the excavation to 3.5 feet or less, shoring is required to support the vertical sides. The shoring must extend above the bottom of the slope a minimum of 18-inches to prevent material from sliding or rolling into the trench. 10.4 Other Requirements For more information concerning soil types, soils testing procedures or other related issues and requirements WAC 296-155-657 through 664 in the WISHA Safety Codes Construction Standards Chapter. 11.0 Shoring Systems When sloping or benching is not feasible, then a shoring system meeting the WISHA requirements of WAC 296-155-661 must be provided. The supervisor must be consulted for instructions. 12.0 Surface Encumbrances Trees, boulders, utility poles and other surface encumbrances in the vicinity that might create a hazard during excavating, must be made safe or removed before excavating work begins or continues. 13.0 Use of Backfilling, Covering or Barriers 13.1 Adequate physical barrier protection must be provided at all excavations or trenches. 13.2 All wells, pits, shafts, etc., must be barricaded or covered and clearly identified as a hazard. 13.3 Upon completion of exploration and similar operations, temporary wells, pits, shafts, etc., must be completely backfilled. 14.0 Inspections 14.1 Unusual Hazardous Conditions Daily inspections of excavations, adjacent areas, and protective systems will be made by a designated competent person in situations that might result in a cave-in, failure of protective system, or other hazardous condition. An inspection will be conducted by the competent person before the day s work and throughout the shift as conditions require. Inspections will be made after every rainstorm or other hazard increasing event. 14.2 Potential Cave-ins Excavating/Shoring/Trenching Plan (Rev. 2/2017) 3 P age

Whenever evidence of a situation that could result in a possible cave-in, failure of protective systems or other hazardous conditions is found, exposed employees will be removed from danger until the hazardous conditions have been corrected. 15.0 Underground Utilities Whenever excavation operations approach the location of underground installations, the exact location of the installations shall be determined by a safe and acceptable means [WAC 296-155-655(2)(c)]. 15.1 Utility Locating Policy Utility installations, such as steam lines, electrical power lines, natural gas, sewer, telephone, and water lines, or any other underground installation shall be located prior to opening an excavation. A request for a utility locate will be done on a Utility Locate Form (see sample at the end of this program). Testing shall be performed by a competent person using proper test equipment. After testing has been completed, this form must be filled out, signed and returned to the supervisor who will forward it to the crew, thereby alerting affected employees in writing of utility locations before digging begins. 15.2 Contacting Utility Companies Utility companies must be contacted within established or customary local response times, advised of the proposed work, and asked to locate their underground utility installation prior to the start of actual excavation. This may require a 48 hour lead time. Notification of utility companies may be accomplished by using the Utility Locate Service (1-800-424-5555) or calling each individual utility company. 15.3 Support and Protection While an excavation is open, underground installations will be protected, supported, or removed as necessary to safeguard employees. 15.4 Signs of Possible Unknown Utility Lines or Pipes When digging, use caution if pea gravel, and, concrete, colored plastic tape or other evidence under the surface is discovered that might indicate the location of a utility line. 16.0 Water Hazards Employees should not work in an excavation where water is seeping in unless adequate precautions have been taken to protect employees against the hazards of excess water accumulation. Protective measures may vary with each situation, but could include one or all of the following: Special shoring/support Shield systems to protect from cave-ins Water removal to control the water level or other effective means 17.0 Walkway and Bridge Requirements Where employees or equipment cross over excavations or trenches, walkways or bridges with standard guardrails must be provided. Such walkways or bridges must be designed by competent persons according to accepted safety codes, procedures and practices. 18.0 Observers Employees next to excavations, and not directly involved in the excavation work, will be protected by standard guardrails or equivalent means. 19.0 Top Person (Spotter/Safety Monitor) Excavating/Shoring/Trenching Plan (Rev. 2/2017) 4 P age

No person is allowed to work in a trench over 4 feet in depth unless there is a top person in constant attendance. The top person must be in addition to the equipment operator when the person in the trench is not in constant view of the equipment operator. Excavating/Shoring/Trenching Plan (Rev. 2/2017) 5 P age

Excavating/Shoring/Trenching Plan (Rev. 2/2017) 2 P age