SECTION 3 STAKING REQUIREMENTS

Similar documents
SECTION CONSTRUCTION SERVICES

CONSTRUCTION SURVEY. Construction survey includes personnel, equipment, and supplies required for, but not limited to, the following:

CITY OF BENICIA IMPROVEMENT PLAN REVIEW CHECKLIST

CHAPTER 5 WATER SYSTEM DESIGN STANDARDS

CONSTRUCTION STAKING GUIDELINES

STREET IMPROVEMENTS (Refer to Title 18, chapter entitled "STREETS" of the Layton Municipal Code.)

This is only a general checklist; please refer to the CVWD Development Design Manual (DDM) for all requirements and regulations.

SECTION 12 STANDARDS FOR CONSTRUCTION PLANS AND SPECIFICATIONS

SECTION VI POTABLE WATER, RECYCLED WATER, AND SANITARY SEWER SYSTEM FACILITY CONSTRUCTION

CITY OF MELISSA MANUAL FOR THE DESIGN OF WATER AND SANITARY SEWER LINES

CONSTRUCTION PLAN REVIEW CHECKLIST FOR PRIVATE DEVELOPMENT

APPENDIX B STANDARD CONSTRUCTION DRAWING NOTES

UNIFORM STANDARD DRAWINGS CLARK COUNTY AREA, NEVADA YEAR 2015 REVISIONS

T a b l e o f C o n t e n t s

COUNTY OF YUBA DEPARTMENT OF PUBLIC WORKS IMPROVEMENT STANDARDS

A.1 WATER SYSTEM PLAN SUBMITTAL PROCEDURES AND GENERAL REQUIREMENTS

SECTION GENERAL EXCAVATION

CITY OF HILSHIRE VILLAGE SWIMMING POOL PLAN SUBMITTAL CHECK LIST ADDRESS: DATE:

CITY OF LA MARQUE, TEXAS CHAPTER 3 WATER SYSTEM DESIGN CRITERIA

2. City of Seattle Supplement to the Specification for Road, Bridge and Municipal Construction, most current addition.

CITY OF ASTORIA PUBLIC WORKS ENGINEERING DIVISION ENGINEERING DESIGN STANDARDS FOR IN-FILL DEVELOPMENT

SPECIFICATIONS FOR STREET CONSTRUCTION WITHIN THE TOWN OF PLAINVILLE

Table of Contents. Section 11,010 - Construction Survey Section Includes Description of Work Submittals 1. 1.

CHAPTER 12 INSTALLATION OF UTILITIES AND OTHER SYSTEMS TABLE OF CONTENTS

LOT GRADING. LOT GRADING REQUIREMENTS The following lot grading requirements came into effect on May 1, 2007:

Index. Composition and Order of Plan Set. Utility Plan... 5

GRADING & DRAINAGE PERMIT SOIL EROSION AND SEDIMENTATION CONTROL PERMIT PROGRAM OVERVIEW

[Type text] Heber Light & Power. Developers & Excavators. Electrical Service Requirements Manual

PUBLIC WORKS DEPARTMENT GENERAL NOTES

SECTION 4 - DESIGN STANDARDS FOR WATER DISTRIBUTION FACILITIES

Alaska Department of Transportation and Public Facilities. Alaska Construction Surveying Requirements (US Customary Units)

GENERAL NOTES ROADWAY CONSTRUCTION RD0001-1A ISSUED:2017 REVISED: --

SECTION CURB, COMBINATION CURB AND GUTTER, AND MONOLITHIC MEDIAN. 1. Bituminous concrete pavement; Section

SECTION CURB RAMPS AND OTHER MINOR CONCRETE FACILITIES. Part 1 - General Work Included Related Requirements...

Chapter 3: Permit Procedures and Requirements

Department of Building and Zoning Approaches and Sidewalks for ONE AND TWO FAMILY CONSTRUCTION

PUBLIC INFRASTRUCTURE DESIGN STANDARDS

CITY OF PANAMA CITY BEACH Utilities Administration & Engineering Offices 116 South Arnold Road Panama City Beach, FL 32413

20 North Main Alpine, UT (Phone) (Fax) SITE PLAN

UNIFORM DESIGN AND CONSTRUCTION STANDARDS FOR EXTENDING WATER DISTRIBUTION SYSTEMS SECTION 2 DESIGN STANDARDS

CITY OF MERIDIAN LAND DEVELOPMENT SERVICES SUBDIVISION PLAN REVIEW CHECK LIST

UNIVERSITY SERVICES ANNEX James Madison University Harrisonburg, Virginia State Project Code: Architect s Project Number:

WASHOE COUNTY COMMUNITY SERVICES DEPARTMENT GRAVITY SEWER COLLECTION DESIGN STANDARDS

TABLE OF CONTENTS PART III MINIMUM DESIGN STANDARDS Section 115 WATER DISTRIBUTION SYSTEM GENERAL SIZING LINES 115.

UTILITIES CHECKLIST CITY OF CHESAPEAKE DEPARTMENT OF PUBLIC WORKS SUBDIVISION NAME: A/C & TAX MAP PARCEL NOS (13 DIGITS) DEVELOPER:

WASHOE COUNTY DEPARTMENT OF WATER RESOURCES GRAVITY SEWER COLLECTION DESIGN STANDARDS

ZONING CLEARANCE PLAN REVIEW CHECKLIST. Based on the Revised Town of Carefree Zoning Ordinance

York County Engineering Department Roadway Inspection Requirements

Ivins City Standard Specifications for Design and Construction Part 2 Engineering and Design Standards

SECTION CS-2. TRENCH EXCAVATION CONSTRUCTION STANDARDS

PART II. - SPECIFICATIONS AND DESIGN STANDARDS TO CITY OF HEWITT, TEXAS SUBDIVISION ORDINANCE FOR PUBLIC WORKS CONSTRUCTION [TEXT]

TENTATIVE SUBDIVISION MAP FOR THE LOT MERGER & RE-SUBDIVISION OF A VERTICAL SUBDIVISION & CONDOMINIUM MAP

Americans with Disabilities Act (ADA) Surveys

FOOTHILLS SOLAR PARK AND SUBSTATION

York County Engineering Department Roadway Inspection Requirements

In general, the City will not approve a development which cannot be served by extensions to the City s wastewater collection system.

Range Point Monuments

DESIGN STANDARDS SECTION DS 7 STREET LIGHTING

Division IV Section 4100 Measurement and Payment PUBLIC WORKS DEPARTMENT

CONCRETE CURB AND GUTTER

YOU MUST HAVE YOUR PROPERTY STAKES LOCATED AND EXPOSED BEFORE A PERMIT WILL BE ISSUED

TOWN OF MANCHESTER PLANNING AND ZONING COMMISSION Subdivision Application Minimum Submission Requirements

Guidelines for Design of Potable Water Distribution Facilities In New Developments

Contact the Jurisdictional Engineer for materials allowed by each jurisdiction.

CURRENT NORTH LAS VEGAS ADDENDA

LAKEHAVEN WATER & SEWER DISTRICT - WATER PLAN REVIEW CHECKLIST

FENCES YOU MUST HAVE YOUR PROPERTY STAKES LOCATED AND EXPOSED BEFORE A PERMIT WILL BE ISSUED

TABLE OF CONTENTS CHAPTER SECTION SUBJECT PAGE

PALM BEACH COUNTY THOROUGHFARE ROAD DESIGN PROCEDURES

Chapter 7. Street Drainage. 7.0 Introduction. 7.1 Function of Streets in the Drainage System. 7.2 Street Classification

FENCE PERMIT APPLICATION

CHECKLIST FOR STREETS, INLETS, AND STORM SEWER DESIGN

Appendix 3. POLICY & PROCEDURE No

SECTION MINOR CONCRETE

ITEM 481 MONOLITHIC REINFORCED CONCRETE BOX SEWERS

N.J.A.C. 19: This file includes all Regulations adopted and published through the New Jersey Register, Vol. 50 No. 1, January 2, 2018

Section 7 Roadway GENERAL REQUIREMENTS I. TYPICAL SECTION...7-1

PLANS. All plans shall be submitted on 24 x 36 sheets

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS

CUYAHOGA COUNTY DEPARTMENT OF PUBLIC WORKS CUYAHOGA COUNTY ENGINEER TOWNSHIP SUBDIVISION STREET DESIGN STANDARDS AND IMPROVEMENT PLAN REQUIREMENTS

SECTION UNCLASSIFIED EXCAVATION AND GRADING

CITY OF ANAHEIM SEWER DESIGN MANUAL

COUNTY OF ALBEMARLE. Community Development Department 401 McIntire Road, Room 227 Charlottesville, Virginia (434)

CHAPTER 70 PUBLIC WORKS DEPARTMENT DEVELOPMENT STANDARDS ARTICLE 70 BASIC PROVISIONS

Zoning Permits 11-1 ZONING PERMITS

DESIGN CRITERIA AND STANDARD DRAWINGS FOR WATER AND SEWER FACILITIES

EXCAVATION WORK IN PUBLIC RIGHT-OF-WAY GENERAL NOTES

Intro. ADA Operations Contact Info

PART II - SURVEYING AND GRADING CRITERIA

SECTION 14 EMBANKMENT

SUBDIVISION CHECKLIST. Subdivision Name. Prior To Review. Preliminary plan approved by Planning Commission / Council as required.

PART V - STORM DRAIN DESIGN CRITERIA

PART V - STORM DRAIN DESIGN CRITERIA

# 17 ) UN DESERT GREEN FARMS SPECIAL USE PERMIT EXTENSION OF TIME PUBLIC HEARING

ENGINEERING REVIEW CHECKLIST City of Mount Clemens

Fence and Wall Guidelines

CITY OF MEQUON. STANDARD SPECIFICATIONS for LAND DEVELOPMENT ENGINEERING. Tenth Edition October 2015

IFB B Attachment 3 Page 112-1

CHANCEFORD TOWNSHIP, YORK COUNTY, PENNSYLVANIA ORDINANCE NO

THE ANTICIPATED SEQUENCE OF EVENTS ARE AS FOLLOWS, BUT THE CONTRACTOR IS RESPONSIBLE FOR ALL MEANS AND METHODS

Transcription:

3.01 TOPIC INDEX SECTION 3 STAKING REQUIREMENTS 3.01 INDEX 3.02 PURPOSE 3.03 GENERAL 3.04 STAKING PROCEDURE 3.05 TMWA / DEVELOPER COORDINATION 3.06 WATER STAKING DETAILS 3.07 DEVELOPER RESPONSIBILITIES 3.08 EXAMPLES OF STAKE LETTERING 3.09 SUBDIVISION PUBLIC UTILITY EASEMENT STAKING AND DETEMINATION OF PUE, RIGHT OF WAY AND LOT CORNERS 3.02 PURPOSE The purpose of this Standard is to provide guidelines for the inspector to determine the correct location of utility installations, in single-family, multiple resident, and commercial areas. (The type and location of survey stakes is ultimately the responsibility of the developer, contractor and surveyor to determine). It is the responsibility of the construction contractor to build improvements in the correct horizontal and vertical location relative to the approved plan. As-built surveys can be performed to insure the improvements are in the correct plan locations. 3.03 GENERAL Utility staking is contingent upon the completion of the following by the developer: A. Clearing and cutting streets, sidewalks, and utility easements (if in public R/W), to sub-grade. Subgrade for street construction may be staked along the centerline of the proposed road. Cut-Fill grades on the stakes are usually given to subgrade and written as SG on the lath above the stake. Centerline is abbreviated CL. The detail for the road section (elevation difference from subgrade to finished grade FG may be determined by looking at the civil detail for the road. B. Establishment of lot corners or an offset for protection and finished street, curb, and sidewalk grades where required. A preliminary wooden stake is typically placed at the lot corners so the contractor will be able to accurately place utility boxes and stub-outs. The lath above the stake will usually be written with the adjoining lot number such as LOTS 35/36 SECTION 3 - STAKING REQUIREMENTS 3-1

3.04 STAKING PROCEDURE The developer is to provide and maintain the staking in the following order. 3.04.01 Sub-grade Stakes These indicate the offset and grade cut or fill at the following locations as appropriate: A. Property corners (none on apartments and townhouses). B. Lot pad corners (none on apartments and townhouses). C. Building corners (none on lot sale developments). D. Other locations as required. Sub-grade stakes are generally correct to within 0.2' which is sufficient precision to stake sub-grade. However, care must be exercised when staking a utility location in that a greater degree of precision may be necessary. 3.04.02 Finish Grade Stakes It is the developer s responsibility to see that finish grade is staked, in all areas back of sidewalk, where there will be utility installations. If the finish grade is not provided, the minimum depth of cover over any pipe shall be sixty (60) inches. Trench depth in the unstaked area will take into account the minimum pipe bedding in details 10L-6 and 10L-7 in addition to the minimum pipe cover described above. 3.04.03 Curb and Gutter Stakes The proposed road and sidewalks as well as the curb and gutter are typically defined by these stakes. These stakes are usually set on five to ten foot offsets behind the face of curb. These stakes indicate the offset and grade cut or fill, normally to top of curb. They are set with greater precision and are generally correct to within 0.02'. The writing on the lath (3 to 4 stake above the stake in the ground) will usually have a number at the top indicating the offset from the stake to the proposed feature and the letters TFC which mean Top Face of Curb. Curb and Gutter stakes may also be set to Flowline (FL) of the gutter or Top Back of Curb (TBC). The location of the street right of way line can usually be determined from the curb and gutter stakes by use of the road improvement standards of the Cities of Reno and Sparks and Washoe County as shown in the table below. For instance with a 60 foot wide right of way within the City of Reno it is 4.5 feet from the back edge of the sidewalk to the right of way line. If the curb and gutter stakes SECTION 3 - STAKING REQUIREMENTS 3-2

area to the top face of curb it will be nine feet from the face of curb to the right of way (4 foot wide sidewalk plus 6 inch wide curb plus the 4.5 foot per the City Standard previously mentioned). To take this one step further if the survey stake is set on a ten foot offset to top face of curb the right of way line will be one foot (toward the curb) from the survey stake. Of course the Public Utility Easement line can be determined by measuring it s width from the right of way line after it has been located. Curb and Gutter stakes are usually set at stations no more than 50 feet apart along tangents and 25 foot intervals along curves. At curb returns (the intersection of curbs from two streets) the BC or PC (Begin Curve or Point of Curvature) and EC or PT (End Curve or Point of Tangency) stake is set along with at least one stake for a point along the curb return such as the ½ Delta (midpoint) of the curve. 3.04.04 Final Lot Corners These are not normally staked until all construction is complete and are of little use in determining the location of underground utilities. 3.05 TMWA / DEVELOPER COORDINATION When approaching the task of providing utilities for a proposed development, the following is normally required. A. TMWA personnel reviews information with the developer. B. Developer reviews plans with TMWA designer at pre-construction meeting. C. The developer provides the staking and grading necessary for utility installation. D. TMWA personnel and developer agents review plans at the project site. E. Check standard street improvements and compare with project plans. F. Before staking, the developer shall confirm the location of property corners to ensure that they conform to the proper established street R/W widths. 3.06 WATER STAKING DETAILS 3.06.01 Offset Distance An offset distance, from C/L of trench, shall be selected which will ensure the protection of stakes during trenching. The stakes are typically placed at a minimum offset of 10 feet from any valve, tee or change in direction of the pipe., normally, SECTION 3 - STAKING REQUIREMENTS 3-3

3.06.02 Interval are placed adjacent to the developer s curb and gutter stakes which provides an adequate offset. Stakes will be placed at or near the property corners or at 50' intervals. However, the interval may have to be decreased to 25' or less on curves or where the site conditions otherwise dictate. 3.06.03 Stake Lettering Given below are some examples of typical stake information necessary for utility installation. A. Distance to centerline of gas trench C/L Gas 10' or 10 with a circle around it and CL GAS B. Distance to centerline of water trench C/L Wtr. 10' or 10 with a circle around it and CL WATER. Note: Cut/Fill grades to waterlines are sometimes given to the TOP of the proposed pipe. 3.07 DEVELOPER RESPONSIBILITIES 3.07.01 Maintenance and Adjustments: The developer is responsible for maintenance of all stakes and adjustments, if necessary, of all boxes and pads to proper grade. 3..07.02 EXAMPLES OF STAKE LETTERING SECTION 3 - STAKING REQUIREMENTS 3-4

3.07.03 SUBDIVISION PUBLIC UTILITY EASEMENT STAKING The location and geometry of the street Right of Way, Public Utility Easements and Lot corners can be seen on the Subdivision Final Map. These are recorded maps that can be downloaded from the Washoe County Assessor s Web site by going to Mapping and then selecting Tract Maps. You will need to know the Tract Map Number for the Subdivision which may be shown on the Subdivision Improvement Plans. A. Applicant to furnish property line chisel mark on curb B. Front PUE to be 7.5, side lot PUE to be 5 and others as required C. Offset stakes 10 to 15 by Applicant SECTION 3 - STAKING REQUIREMENTS 3-5