Addendum 1.0. For Lagrange Library Specification 1.0. Technology Consultants Fort Wayne, Indiana

Similar documents
1. Telecommunications mounting elements. 2. Backboards. 3. Telecommunications equipment racks and cabinets. 4. Grounding.

A. Basket Cable Tray: A fabricated structure consisting of wire mesh bottom and side rails.

COMMUNICATIONS CABLING SECTION COMMUNICATIONS CABLING PART 1 - GENERAL

TABLE OF CONTENTS DIVISION 27 - COMMUNICATIONS

The following sections are included in Division 27: Section : Underground Ducts and Raceways for Communication SysteMS 283

A. Basket Cable Tray: A fabricated structure consisting of wire mesh bottom and side rails.

DTW Works Master Specification Version 2006 Issued 2006/08/01 Section Data System Page 1 of 7

Request for Proposal

1 data PIC location (with 2 ports) typically asf for multiple staff members

Document No Issue Date: May 15, 2012

c. Army Reserve Design Process Submittal Requirements (DPSR) d. USARC G-2/6 IT Design Criteria Updates, 26 March 2013 ( ENCLOSURE 1)

PHYSICAL FACILITIES Consultant s Handbook Division 27 COMMUNICATIONS 0000 COMMUNICATIONS

UNIVERSITY OF ALABAMA AT BIRMINGHAM DEPARTMENT OF FACILITIES PLANNING. NAME: Communications Equipment Room ORIGINAL DATE:

Communications Page 1 of 9

Warranties. What You Need To Know To Ensure Performance For Your Telecommunications Cabling System

The University of Texas at Austin September 30, 2011

COMMUNICATIONS EQUIPMENT ROOM FITTINGS

SECTION HORIZONTAL CABLING

ADDENDUM No. 2 Request for Proposals (RFP) 19RFP033 Structured Network Cabling

SECTION COMMUNICATIONS EQUIPMENT ROOM FITTINGS

Police/Emergency Service Center PSGP Grant #2007-GB-T CN

c. Army Reserve Design Process Submittal Requirements (DPSR) d. USARC G-2/6 IT Design Criteria Updates, 17 October 2013 ( ENCLOSURE 1)

RESEARCH AND TECHNOLOGY BUILDING RENOVATION MAY 18, 2009 SECTION COMMUNICATIONS

OREGON UNIVERSITY SYSTEM STANDARD PUBLIC IMPROVEMENT CONTRACT BID FORM. FROM: Name of Contractor

Standards and Procedures Security Room Construction/Renovations At University of North Carolina Wilmington

TELECOMMUNICATIONS ROOMS. Table of Contents PART 1 GENERAL 2 A. LOCATION: 2 B. SIZE 2 C. STRUCTURAL 3 D. ENVIRONMENTAL 3 E. ELECTRICAL AND LIGHTING 3

Portland State University OIT Networking & Telecommunications Services

Telecommunications Standards A. PERFORMANCE REQUIREMENTS

OKLAHOMA STATE UNIVERSITY - BUILDING DESIGN STANDARDS

DENVER PUBLIC SCHOOLS STRUCTURED CABLING DESIGN SPECIFICATIONS REVISED

SECTION COMMON WORK RESULTS FOR COMMUNICATIONS PART 1 - GENERAL 1.1 RELATED DOCUMENTS

TELECOMMUNICATIONS DESIGN AND CONSTRUCTION GUIDELINES

Compass 5 Partners, LLC Addendum Number Two

We will require two copies each of your lump sum proposals, vendor qualification questionnaire and your bid bond documents.

DIVISION 27 COMMUNICATIONS COMMUNICATIONS GENERAL. Part 1 - General. Record Version

SECTION TELECOMMUNICATIONS SYSTEMS

FORM FOOTWALL. FORM FOOTWALL (floating) (floating) Installation Manual

INSTALLATION MANUAL. FOOTWALL/SINKWALL (floor mount)

Pre-installation checklist. 3. Project manager has read specifications, and specs to be on-site during work.

SECTION HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS

RSU 14 - WINDHAM RAYMOND SCHOOL DISTRICT OFFICE OF THE ASSISTANT SUPERINTENDENT

E0.3. Telco. Specifications No Scale 12/3/2014 ADDENDUM #4. Table 1.1

DIVISION 27 COMMUNICATIONS COMMUNICATIONS GENERAL. Part 1 - General. Record Version

A. Drawings and general provisions of the Contract, including General Conditions and Division 1 Specification sections, apply to work of this Section.

OPS WIFI UPGRADE REQUEST FOR PROPOSAL: ADDENDUM - 1

February 5, Proposals must be received on or before March 5, Proposals received after this date will be disqualified.

SECTION COMMON WORK RESULTS FOR COMMUNICATIONS

C o u n t y o f F a i r f a x, V i r g i n i a

CAMPUS NEW CONSTRUCTION & MODERNIZATION

UNIVERSITY OF CHICAGO

SECTION COMMON WORK RESULTS FOR COMMUNICATIONS

Third Party Design, Construction and Operations on FIU Campuses

UBC Technical Guidelines Section Edition Audio-Video Infrastructure Page 1 of 5

C.I.C.S. WRIGHTWOOD SCHOOL CHICAGO CHARTER SCHOOL FOUNDATION TECHNOLOGY UPGRADES STRUCTURED CABLING SPECIFICATIONS SC0-01

SECTION COMMUNICATIONS OPTICAL FIBER OSP CABLING

HASTINGS AREA SCHOOL SYSTEMS HASTINGS, MICHIGAN

UNLV Campus Wiring Specification September 15, 2016

ADDENDUM NO. 2 Page 1 of 13

September 23, 2016 ADDENDUM #2

Central Mississippi Regional Library System Notice to Bidders Cabling Switches E Rate Registration with USAC

SPITZER CONFERENCE CENTER BRIEFING SUITE REFRESH Addendum #2 02/22/2018 LCCC POJECT NO. SPBSR-17 BPA PROJECT NO

BANK OF INDIA. TENDER DOCUMENT PART B (Financial Bid) Last Date of submission of Tenders: BOQ

Essex County College - West Essex Campus Addition And Renovations dlb # / 11-14

NYULMC AMBULATORY CARE CENTER FIT-OUT PHASE 1 Perkins & Will Architects PC 222 E 41st ST, NYC Project: Issued for GMP March 15, 2017

.1 This Section includes equipment, materials, labour and services to provide telephone and data distribution systems including, but not limited to:

PHYSICAL FACILITIES Consultant s Handbook Specifications Division 27 Communication 0528 Pathways. Page 1 of 6

Dayton Metropolitan Housing Authority Rosemont/Hoch Electrical Upgrades

SECTION PATHWAYS FOR COMMUNICATIONS SYSTEMS

DIVISION 27: COMMUNICATIONS AND TECHNOLOGY DESIGN STANDARDS TABLE OF CONTENTS

FORM HEADWALL. FORM HEADWALL (floating) (floating) Installation Manual

SECTION TELECOMMUNICATIONS GENERAL REQUIREMENTS

Request for Proposals Phone System Maintenance Agreement

INDEX. Page SECTION 1.0: SCOPE Toronto Hydro Requirements Ontario Electrical Safety Code 1 SECTION 2.0: PURPOSE 1

1.0 GENERAL 1.1 DOCUMENTS

FORM HEADWALL. FORM HEADWALL (floor mount) (floor mount) Installation Manual

It is acceptable to place all required information in the main element (such as D5010) and delete the sub-elements provided in this template.

Telecommunication Spaces


UMass Amherst Information Technology. Design and Construction Guidelines

FREQUENTLY ASKED QUESTIONS

ADDENDUM NO. 2. November 8, For: Wawona Hotel Heating Replacement CIF 5013

SEISMIC PROTECTION SYSTEMS Bracing Products for Racks & Cabinets

ADDENDUM NO. 5. April 9, 2014

ENDOALPHA Audio/Video Peripheral (AVP) Facility Requirements Planning Guide

APPENDIX D INFORMATION TECHNOLOGIES DESIGN GUIDELINES (TAMPA CAMPUS)

Issue for Bid January 25, 2010 SECTION A - COMMUNICATIONS COPPER HORIZONTAL CABLING

RESPONSE: No. Original Bid due date and time will remain.

ADDENDUM 2 I. QUESTIONS AND ANSWERS. TE1031: Outside Plant Dark Fiber Optic Infrastructure Construction

SECTION GROUNDING

Project No. # PART 1 - GENERAL. Guide Specification. University Pullman. be all- MS Word Tracking. section. that the. requirements of the

Telecommunications Design Guidelines University of Alberta Cabling Standards (version 2.1)

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017

SECTION (Master Template Final-05) ELECTRICAL BOXES. A. Provide boxes for electrical equipment and wiring devices as follows:

SECTION CLIMBING WALLS

LOS RIOS COMMUNITY COLLEGE DISTRICT 1919 Spanos Court, Sacramento, CA Phone (916) FAX (916) Purchasing Department

University of Florida Telecommunication Standards JANUARY 2010

FIXED CEILING COLUMN. Installation Manual FIXED CEILING COLUMN

VILLAGE OF MARATHON CITY MARATHON COUNTY WISCONSIN

The University of Texas at Austin September 30, 2011

SECTION GENERAL ELECTRICAL REQUIREMENTS PART 1- GENERAL

Transcription:

Addendum 1.0 For Lagrange Library Specification 1.0 Technology Consultants Fort Wayne, Indiana TECHNICAL SPECIFICATIONS FOR TELECOMMUNICATION DISTRIBUTION FACILITIES AND INSTALLATION PROCEDURES For Lagrange Library (File Name: O:\itsstu\TC\LaGrange Library\Lagrange Library_Addendum1.0.doc) March 29 th, 2011 All technical questions should be addressed to: Larry Temenoff, RCDD/OSP/WD/TPM Technology Consultants, LLC 4415 W Wallen Rd. Fort Wayne, IN 46818 (260) 625-2400

Telecommunications Consultants, LLC Addendum 1.0 1.) Change 1.0 GENERAL SPECIFICATIONS AND OVERVIEW Bidding Requirements: The Contractor completing installation shall have been in business for at least five years, not necessarily under the same name. The Contractor completing the installation shall be experienced in voice and data installation. The Contractor shall supply names and telephone numbers of contacts for their past four projects to be used as references. The Contractor shall have on staff a Building Industry Consulting Service International (BICSI) Registered Communications Distribution Designers (RCDD) or BICSI Technician. The RCDD or Technician will be the Project Manager and shall approve construction design, drawing, and upon completion of installation, certify compliance with the standards and installation practices as specified by Technology Consultants, LLC. For the bidding process, the Project Manager must submit a signed and/or stamped Bill of Materials (BOM) consisting of supplies and materials (excluding material and labor cost) with the bid. If the Project Manager is a BICSI Technician signatures will be sufficient on the BOM. The BOM should be adequate to establish if all necessary materials and supplies have been included in the bid. The Project Manager who signs the BOM shall be the same Project Manager throughout the project with the exception of written consent from the owner. A manpower schedule and a project time line will also be required within the bid package to verify that the contractor will be able to complete the project on time. A per-unit drop cost for the addition or deduction of drops must be submitted with the original quote. This rate is good for all additional drops until testing has been completed. Bidding Requirements: The Contractor completing installation shall have been in business for at least five years, not necessarily under the same name. The Contractor completing the installation shall be experienced in voice and data installation. The Contractor shall supply names and telephone numbers of contacts for their past four projects to be used as references. The Contractor shall have on staff a Building Industry Consulting Service International (BICSI) Registered Communications Distribution Designers (RCDD). The RCDD or Technician will be the Project Manager and shall approve construction design, drawing, and upon completion of installation, certify compliance with the standards and installation practices as specified by Technology Consultants, LLC. For the bidding process, the Project Manager must submit a signed and/or stamped Bill of Materials (BOM) consisting of supplies and materials (excluding material and labor cost) with the bid. The BOM should be adequate to establish if all necessary materials and supplies have been included in the bid. The Project Manager who stamps the BOM shall be the same Project Manager throughout the project with the exception of written consent from the owner. A manpower schedule and a project time line will also be required within the bid package to verify that the contractor will be able to complete the project on time. A per-unit drop cost for the addition or deduction of drops must be submitted with the original quote. This 2

Telecommunications Consultants, LLC rate is good for all additional drops until testing has been completed. 2.) Change 1.0 GENERAL SPECIFICATIONS AND OVERVIEW General Installation Requirements: After the successful contractor has been selected, two packets of all pre-construction submittals must be presented by the Project Manager. Both cover sheets shall have the Project Manager s name (printed legibly) and signature, as well as stamped and initialed (if an RCDD). The RCDD stamp and initials or BICSI Technician s signature, are required for all pages following the cover sheet. A copy of the RCDD or BICSI certification certificate must be included in the bid. Also, each vendor specification sheet (submittals) shall be stamped and initialed by the RCDD, or signed by the BICSI Technician. The same Project Manager must oversee the project from the time of winning the bid until the entire project is completed. In the case of a catastrophic situation, both parties must agree on a Project Manager substitution. Each vendor specification sheet (submittals) shall be initialed by the Project Manager. General Installation Requirements: After the successful contractor has been selected, two packets of all pre-construction submittals must be presented by the Project Manager. Both cover sheets shall have the Project Manager s name (printed legibly) and signature, as well as stamped and initialed (if an RCDD). The RCDD stamp and initials or BICSI Technician s signature, are required for all pages following the cover sheet. A copy of the RCDD BICSI certification certificate must be included in the bid. Also, each vendor specification sheet (submittals) shall be stamped and initialed by the RCDD, or signed by the BICSI Technician. The same Project Manager must oversee the project from the time of winning the bid until the entire project is completed. In the case of a catastrophic situation, both parties must agree on a Project Manager substitution. Each vendor specification sheet (submittals) shall be initialed by the Project Manager. 3.) Change 4.02 EQUIPMENT BAYS 1. The TR must have one A-C grade 5' x 4' x 3/4" plywood backboard mounted by screw to the north wall of the TR and one A-C grade 3' x 4' x 3/4" plywood backboard mounted to the east wall. The plywood backboard must be of good quality and have no knots. The plywood backboard must be painted on all sides with two (2) coats of fire-retardant paint (International Fire Resistant Systems, Inc. part no.: FF88). The plywood backboard should be mounted 24" above the finished floor with the 4' dimension vertical. All screw heads and scuffs due to construction shall be touched up with the fire-retardant paint. 3

Telecommunications Consultants, LLC 1. The TR must have A-C grade 5' x 4' x 3/4" plywood backboard mounted by screw to all walls of the TR. The plywood backboard must be of good quality and have no knots. The plywood backboard must be painted on all sides with two (2) coats of fire-retardant paint (International Fire Resistant Systems, Inc. part no.: FF88). The plywood backboard should be mounted 24" above the finished floor with the 4' dimension vertical. All screw heads and scuffs due to construction shall be touched up with the fire-retardant paint. 4.) Change 6.0 FACILITIES DESCRIPTION 6.10 Data/voice station wiring from the TR to a communications outlet will consist of CommScope part no.: 6ECMP or Berktek equivalent (ivory or white). The four (4) pairs of unshielded wires will be terminated at each end on an ivory GIGA channel mini-jack RJ45 receptacle (Hubbell part no.: HXJ6OW or Panduit equivalent) using TIA/EIA 568B-A standards and labeled. 6.10 Data/voice station wiring from the TR to a communications outlet will consist of CommScope part no.: 6ECMP, Berktek part no.: 10167312, or General Cable part no.: 7131931 (ivory or white). The four (4) pairs of unshielded wires will be terminated at each end on an ivory GIGA channel mini-jack RJ45 receptacle (Hubbell part no.: HXJ6OW or Panduit equivalent) using TIA/EIA 568B-A standards and labeled. 5.) Change TR Layout Drawings sent out for bidding. See attached drawing for update. End of Addendum 1.0 (Attachments Follow) 4

Re: Project LaGrange 001 11 (LaGrange Library) Date: March 28, 2011 Questions from Pre Bid Meeting, 3 28 2011 1. How firm is the completion date of May 4, 2011? Response: Some leeway could be arranged but no more than one week 2. Who can be the project manager for this project? Response: Because of the complexity of this building, an RCDD will be required for the project management. 3. How many walls need to have painted backer board installed? Response: All four (4) walls should have 4x8 plywood installed with FF88 paint covering both sides. 4. How many four post cabinets are required? Response: Two (2) four post cabinets Part # GL720E 2436 Series with stated options. No 2 posts racks are required 5. Where is the phone demarcation point Response: In the MC at the 110 Block 6. Where are the cables terminated? Response: In the 4 post cabinet using 48 port patch panels or a hybrid patch panel 7. Will there need to be a ladder rack installed in the MC? Response: A ladder rack will need to be installed by the TelCom contractor and should be either B Line or Monosystems. 8. How is the spine wire manager to be mounted? The TelCom contractor will have to install and secure to the existing furniture with an 18 cable loop 9. What manufacturer s jacks will be permitted to be installed in the power and data modules? Response: Hubbell or Panduit Category 6 and keystone form factor is recommended 10. What type of receptacles will be allowed for the access points? Response: When possible use the existing junction boxes provided for this function. If a J Box is not present, a biscuit above the ceiling may be permitted.

11. What cable vendors are allowed on this project? Response: The three vendors allowed are: Berktek, Commscope, General Cable, all category 6E Plenum only 12. How are cables in the floor boxes mounted? Response: Where terminating in existing floor boxes, there should be an interface plate installed by others. It is the TelCom contractor s responsibility to interface with the mounting bracket in the floor box. It is recommended to use a keystone form factor. 13. What if there is a long lead interface hardware item; what should be done? Response: A temporary solution should be implemented so testing can be completed by the target date. 14. Will there be any need for flooded cable in basement floor boxes? Response: No, normal cable should be sufficient; this is a sub floor installation. 15. Where will all of the station cables be terminated? Response: In the MC; there is no IC in this building 16. Can the 4 conduits between floors be modified so that the cable runs can be shortened? Response: Yes, the 4 conduits are dedicated solely to telecommunications cabling; However, there should be no sharp edges and the use of plastic bushings is required 17. What are the orange dots in the J Boxes? Response: These boxes are dedicated for telecommunications. If these boxes are not used, they should be blanked. Larry Temenoff, RCDD/OSP/WD/TPM Technology Consultants, LLC