DSA Inspectors Arcadia USD Arcadia HS Campus Enrichment Inspection Report Apr 2014 Architect DSA Application No. A03-111889 33 Narcissa Drive, Rancho Palos Verdes, CA 90275 (626) 786-4331 Info@KnowlandInc.com
This form shall be completed by the Project Inspector, in accordance with California Code of Regulations, Title 24, Part 1, Section 4-337and submitted to the DSA. School District/Owner: Arcadia Unified School District DSA File #: 19 - H32 Project Name/School: Arcadia High School Campus Enrichment DSA App. #: 03-111889 From: Kenneth Burr DSA Project Inspector Certification #: Cert 5654, Class 1 Building #(s) (As identified on the plans): C, D, E, F, G, H, K, O, P, W, and Rally Court (site) Report #: 43 Page 1 of 2 Date of Report: 5/5/2014 DSA 152 Card #(s): N/A REPORTING PERIOD DATES From: 4/1/14 To: 4/15/14 Construction project is estimated to be 78 % complete at this time. (List above all building numbers and inspection card numbers for which this report applies.) PROVIDE THE FOLLOWING INFORMATION FOR THE REPORTING TIME PERIOD: (Continues on Page 2) STATUS OF CONSTRUCTION WORK: Bldg B Electrical and plumbing rough in has begun Bldg P (East Portion - Cafeteria) Demo and abatement is ongoing Bldg O oranamental fencing is being installed Bldg U framing, electrical, HVAC and Plumbing is ongoing Site-work site utilities are ongoing, Main walkway canopy north half is complete OUTSTANDING DEVIATION NOTICES: (List Notice Numbers used on forms DSA 154.) Notice issued for storefront window system being installed without approval from DSA on the deferred approval RESOLVED DEVIATION NOTICES: (List the Notice Numbers used on forms DSA 154.). Issued 03/21/13 Page 1 of 2 DIVISION OF THE STATE ARCHITECT DEPARTMENT OF GENERAL SERVICES STATE OF CALIFORNIA
DSA 155 PROJECT INSPECTOR SEMI-MONTHLY REPORT Issued 03/21/13 Report #: 43 Page 2 of 2 Date of Report: 5/5/2014 DSA App. #: 03-111889 PROVIDE THE FOLLOWING INFORMATION FOR THE REPORTING TIME PERIOD (Continued from Page 1) QUESTIONS OR UNUSUAL CONDITIONS: (List any questions or unusual conditions encountered.) PROBLEMS OR NON-COMPLYING CONDITIONS: (List any problems or non-complying conditions and how they were resolved.) [1] All Addenda are approved [2] Storefront Deferred Approval Submittal not DSA-Approved. A/E review comments returned to GC and sub-contractor 4.18.13. INSTRUCTIONS RECEIVED FROM THE ARCHITECT OR REGISTERED ENGINEER: (List any.). OFFICIAL SITE VISITORS: (List any and whom they represent. May include, architects, registered engineers, school district representatives, DSA field representative, etc.). Weekly Owner/Architect/Contractor meetings. Owner s Rep and Architect in attendance. Submit completed form electronically to the DSA Regional Office with construction oversight authority for the project: DSA OAKLAND oakfielddoc@dgs.ca.gov DSA SACRAMENTO sacfielddoc@dgs.ca.gov DSA LOS ANGELES lafielddoc@dgs.ca.gov DSA SAN DIEGO sdfielddoc@dgs.ca.gov Issued 03/21/13 Page 2 of 2 DIVISION OF THE STATE ARCHITECT DEPARTMENT OF GENERAL SERVICES STATE OF CALIFORNIA
This form shall be completed by the Project Inspector, in accordance with California Code of Regulations, Title 24, Part 1, Section 4-337and submitted to the DSA. School District/Owner: Arcadia Unified School District DSA File #: 19 - H32 Project Name/School: Arcadia High School Campus Enrichment DSA App. #: 03-111889 From: Kenneth Burr DSA Project Inspector Certification #: Cert 5654, Class 1 Building #(s) (As identified on the plans): C, D, E, F, G, H, K, O, P, W, and Rally Court (site) Report #: 44 Page 1 of 2 Date of Report: 4/18/2014 DSA 152 Card #(s): N/A REPORTING PERIOD DATES From: 4/16/14 To: 4/30/14 Construction project is estimated to be 78 % complete at this time. (List above all building numbers and inspection card numbers for which this report applies.) PROVIDE THE FOLLOWING INFORMATION FOR THE REPORTING TIME PERIOD: (Continues on Page 2) STATUS OF CONSTRUCTION WORK: Bldg B Electrical and plumbing rough in has begun Bldg P (East Portion - Cafeteria) Demo and abatement is ongoing Bldg O oranamental fencing is being installed Bldg U framing, electrical, HVAC and Plumbing is ongoing Site-work site utilities are ongoing, Main walkway canopy north half is complete OUTSTANDING DEVIATION NOTICES: (List Notice Numbers used on forms DSA 154.) Notice issued for storefront window system being installed without approval from DSA on the deferred approval RESOLVED DEVIATION NOTICES: (List the Notice Numbers used on forms DSA 154.). Issued 03/21/13 Page 1 of 2 DIVISION OF THE STATE ARCHITECT DEPARTMENT OF GENERAL SERVICES STATE OF CALIFORNIA
DSA 155 PROJECT INSPECTOR SEMI-MONTHLY REPORT Issued 03/21/13 Report #: 44 Page 2 of 2 Date of Report: 4/18/2014 DSA App. #: 03-111889 PROVIDE THE FOLLOWING INFORMATION FOR THE REPORTING TIME PERIOD (Continued from Page 1) QUESTIONS OR UNUSUAL CONDITIONS: (List any questions or unusual conditions encountered.) PROBLEMS OR NON-COMPLYING CONDITIONS: (List any problems or non-complying conditions and how they were resolved.) [1] All Addenda are approved [2] Storefront Deferred Approval Submittal not DSA-Approved. A/E review comments returned to GC and sub-contractor 4.18.13. INSTRUCTIONS RECEIVED FROM THE ARCHITECT OR REGISTERED ENGINEER: (List any.). OFFICIAL SITE VISITORS: (List any and whom they represent. May include, architects, registered engineers, school district representatives, DSA field representative, etc.). Weekly Owner/Architect/Contractor meetings. Owner s Rep and Architect in attendance. Submit completed form electronically to the DSA Regional Office with construction oversight authority for the project: DSA OAKLAND oakfielddoc@dgs.ca.gov DSA SACRAMENTO sacfielddoc@dgs.ca.gov DSA LOS ANGELES lafielddoc@dgs.ca.gov DSA SAN DIEGO sdfielddoc@dgs.ca.gov Issued 03/21/13 Page 2 of 2 DIVISION OF THE STATE ARCHITECT DEPARTMENT OF GENERAL SERVICES STATE OF CALIFORNIA
Arcadia High School Week of April 04, 2014 Top right termite damage to header in the cafeteria Top left Ductwork delivery to the library Bottom Right laying out for circle soffit Bottom left framing block for circle soffit
Arcadia high School Week of April 11, 2014 Top Right duct being installed in the library Top Left framing the circle soffit Bottom Right framing the circle soffit Bottom Left trenching for the storm drain at the library
Arcadia High School Week of April 18, 2014 Top Right waste and vent lines in the restrooms by student store Top Left site demo south side of J Bottom Right circle soffit framing in the library Bottom Left restroom walls in the library
Arcadia High School Week of April 30, 2014 Top Right site water valves south side of J Top Left water valves and gas linne under storm drain Bottom Right ductwork installed with flexes attached Bottom Left circle soffit framing with recessed lighting
Campus Enrichment Project Daniel Alberico Phone: none DSA #4269 Fax: none Cell: (818) 402-7163 Email: Danielalberico@att.net April 1, 2014 Overcast, 65 Project: Arcadia High School-Campus Enrichment A#03-111-889 File No. 19-H32 180 Campus Dr, Arcadia, Ca 91007 Construction Manager: Building Companies Nino and Moore Building Companies D: 7-Carpenters on framing crew at the library installing steel beams for the Hvac roof units, forming for bathroom curbs and epoxing allrthread bolts. 2- Miller Demolition workers at building P continue demolition at the restrooms in building P and start demolition of shear wall on west side of building. 2-Murry company Plumbers continue roof drain installation. 3- Insulation workers installing wall insulation at building B. 4- TSI steel workers installing steel beams at roof for Hvac units. SPECIAL INSPECTION: Nino and Moore Steel Inspector on site at building U repair to existing beams Per RFI #83. MEETINGS: none none : DSA field Engineer-Natu Patel on site and issued Field Note #9 and jobwalk. KNOWLAND CONSTRUCTION SERVICES 2181 E. FOOTHILL BOULEVARD, SUITE 203, PASADENA, CA 91107
Campus Enrichment Project Daniel Alberico Phone: none DSA #4269 Fax: none Cell: (818) 402-7163 Email: Danielalberico@att.net April 2, 2014 Clear, 65 Project: Arcadia High School-Campus Enrichment A#03-111-889 File No. 19-H32 180 Campus Dr, Arcadia, Ca 91007 Construction Manager: Building Companies Nino and Moore Building Companies D: 5-Carpenters on framing crew at the library installing roof blocking, misc, forming for bathroom curbs. 2- Miller Demolition workers continue demolition of building U masonry screen wall on the north-west corner of building. 2-Murry company Plumbers installing gas line, and roof drain strubs on the north side of building U. 3- Drywall workers start installing drywall at building P. 4- TSI steel workers installing steel beams at roof for Hvac units. SPECIAL INSPECTION: none MEETINGS: none none : none KNOWLAND CONSTRUCTION SERVICES 2181 E. FOOTHILL BOULEVARD, SUITE 203, PASADENA, CA 91107
Campus Enrichment Project Daniel Alberico Phone: none DSA #4269 Fax: none Cell: (818) 402-7163 Email: Danielalberico@att.net April 3, 2014 Clear, 65 Project: Arcadia High School-Campus Enrichment A#03-111-889 File No. 19-H32 180 Campus Dr, Arcadia, Ca 91007 Construction Manager: Building Companies Nino and Moore Building Companies D: 5-Carpenters on framing crew at the library installing roof blocking, misc, forming for bathroom curbs, rebar. 2- Miller Demolition workers completed demolition of building U masonry screen wall on the north-west corner of building. 2-Murry company Plumbers installing gas line, and roof drain strubs on the north side of building U. 3- Drywall workers continue installing drywall at building P. 4- TSI steel workers installing steel beams at roof for Hvac units. SPECIAL INSPECTION: none MEETINGS: none none : none KNOWLAND CONSTRUCTION SERVICES 2181 E. FOOTHILL BOULEVARD, SUITE 203, PASADENA, CA 91107
Campus Enrichment Project Daniel Alberico Phone: none DSA #4269 Fax: none Cell: (818) 402-7163 Email: Danielalberico@att.net April 4, 2014 Clear, 65 Project: Arcadia High School-Campus Enrichment A#03-111-889 File No. 19-H32 180 Campus Dr, Arcadia, Ca 91007 Construction Manager: Building Companies Nino and Moore Building Companies D: 5-Carpenters on framing crew at the library installing soffits, misc, forming for bathroom curbs, rebar. 2- Miller Demolition workers removing demolition of building U masonry screen wall on the north-west corner of building. 2-Murry company Plumbers installing roof drain lines at building U. 3- Drywall workers continue installing drywall at building P. 4- TSI steel workers installing steel beams at roof for Hvac units. SPECIAL INSPECTION: none MEETINGS: none none : none KNOWLAND CONSTRUCTION SERVICES 2181 E. FOOTHILL BOULEVARD, SUITE 203, PASADENA, CA 91107
Date: 4/7/2014 6 Framers framing soffits and wall sin building U 7 Electrical roughing in conduits in building B and conduits in the walls at U 3 Plumbers roughing in waste and vent lines in the student store 5 Demo demoing walls in the cafeteria
Date: 4/8/2014 6 Framers framing soffits and wall sin building U 7 Electrical roughing in conduits in building B and conduits in the walls at U 3 Plumbers roughing in waste and vent lines in the student store 5 Demo demoing walls in the cafeteria 4 Painters painting canopy east side of the finger buildings
Date: 4/9/2014 6 Framers framing soffits and wall sin building U 7 Electrical roughing in conduits in building B and conduits in the walls at U 3 Plumbers roughing in waste and vent lines in the student store 5 Demo demoing walls in the cafeteria 4 Painters painting canopy east side of the finger buildings 3 SS erecting the supports on the underside of library roof for hvac supports
Date: 4/10/2014 6 Framers framing soffits and wall sin building U 5 Plumbers roughing in waste and vent lines in the student store 5 Demo demoing walls in the cafeteria 4 Painters painting canopy east side of the finger buildings 2 Glazers installing blackout windows in the finger buildings
Date: 4/11/2014 5 Framers framing soffits and wall sin building U 5 Demo demoing walls in the cafeteria 4 Painters painting canopy east side of the finger buildings
Date: 4/14/2014 5 Framers framing soffits and walls in building U 5 Demo demoing walls in the cafeteria 4 Painters painting canopy east side of the finger buildings 1 Lather placing expanded metal in plaster patch areas 3 Plumbers waste and vent in the student store, welding gas line for U 6 Electrical conduits and boxes rough in the library
Date: 4/15/2014 5 Framers framing soffits and walls in building U 4 Demo demoing walls in the cafeteria 4 Painters painting canopy east side of the finger buildings 1 Lather placing expanded metal in plaster patch areas 4 Plumbers waste and vent in the student store, welding gas line for U 8 Electrical conduits and boxes rough in the library 2 HVAC setting controls on the rooftop units
Date: 4/16/2014 5 Framers framing soffits and walls in building U 2 Concrete floating bottoms of windows in U to level the aluminum frames 4 Painters painting canopy east side of the finger buildings 4 Plumbers waste and vent in the student store, welding gas line for U
Date: 4/17/2014 5 Framers framing soffits and walls in building U 2 Concrete floating bottoms of windows in U to level the aluminum frames 4 Plumbers waste and vent in the student store, welding gas line for U
Date: 4/17/2014 5 Framers framing soffits and walls in building U 3 Concrete floating bottoms of windows in U to level the aluminum frames
Date: 4/21/2014 4 Graders grading the restroom and the student store 4 SS erecting the equipment screen on the roof of the library 6 Framers framing soffits, walls and window infills in the library 3 Utility trenching for gas and water on the south side of building J 7 Electrical roughing in conduits in the library and trenching and placing conduits under slab in P
Date: 4/22/2014 4 Graders grading the restroom and the student store 3 SS erecting the equipment screen on the roof of the library 7 Framers framing soffits, walls and window infills in the library 3 Utility trenching for gas and water on the south side of building J 7 Electrical roughing in conduits in the library and trenching and placing conduits under slab in P 5 Paint painting classrooms in building B
Date: 4/23/2014 4 Graders grading the restroom and the student store 3 SS erecting the equipment screen on the roof of the library 9 Framers framing soffits, walls and window infills in the library 3 Utility trenching for gas and water on the south side of building J 8 Electrical roughing in conduits in the library and trenching and placing conduits under slab in P 5 Paint painting classrooms in building B
Date: 4/24/2014 4 SS erecting the equipment screen on the roof of the library 9 Framers framing soffits, walls and window infills in the library 8 Electrical roughing in conduits in the library and trenching and placing conduits under slab in P
Date: 4/25/2014 4 SS erecting the equipment screen on the roof of the library 9 Framers framing soffits, walls and window infills in the library
Date: 4/28/2014 4 SS erecting the equipment screen on the roof of the library 6 Framers framing soffits, walls and window infills in the library 4 Demo sealing columns in the library with exposed mastic 3 Plumbers sewer and water tie in at student store 5 Electrical rough in at U and P
Date: 4/29/2014 4 SS erecting the equipment screen on the roof of the library 6 Framers framing soffits, walls and window infills in the library 4 Demo sealing columns in the library with exposed mastic 3 Plumbers sewer and water tie in at student store 5 Electrical rough in at U and P
Date: 4/30/2014 4 SS erecting the equipment screen on the roof of the library 6 Framers framing soffits, walls and window infills in the library 4 Demo sealing columns in the library with exposed mastic 4 Plaster scrath coat at the patches and breezeway in building B 5 Electrical rough in at U and P