GC s Subcontractor QA/QC Plan Sample

Similar documents
Essentials QA/QC Plan Sample for Ericsson Qualifications

Oil and Gas Contractor QA/QC Plan Sample Selected pages (not a complete plan)

Essentials QA/QC Plan Sample

Inspection Forms Available by Division Sections

Fire Protection Contractor QA/QC Plan Sample

Communications Contractor QA/QC Plan Sample

Selected pages (not a complete plan)

Flooring Contractor QA/QC Plan Sample Selected pages (not a complete plan)

Utility Construction Contractor QA/QC Plan Sample Selected pages (not a complete plan)

ADDENDUM 2 - JULY 14, 2015

TABLE OF CONTENTS Public Safety Building

DESIGN & CONSTRUCTION GUIDELINES

Earthworks QA/QC Plan Sample

Excavation QA/QC Manual Sample

DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT

SERIES 0 BIDDING REQUIREMENTS AND CONTRACT FORMS

Invitation to Bid. RLS Construction Group requests your firm to submit a quotation on the following project:

DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT

Asphalt Paving Essentials QA/QC Plan Sample

Franklin Hall Renovation TABLE OF Document Indiana University Bloomington

PAULDING COLLEGE & CAREER ACADEMY

Table of Contents. Division 2 Site Work Site Preparation Site Demolition Tree Protection Excavation, Trenching, and Backfilling for Utilities

Division 00 Procurement and Contracting Requirements

Landscape Services QA/QC Manual Sample Selected pages (not a complete plan)

Janitorial Essentials QA/QC Plan Sample

Watercrest - Sand Hill - Columbia, SC TABLE OF CONTENTS PROCUREMENT AND CONTRACTING REQUIREMENTS

TABLE OF CONTENTS. (Δ = Rev 06/08)

TABLE OF CONTENTS. (Δ = Rev 11/15) Update #7

TABLE OF CONTENTS. (Δ = Rev 04/17) Update #8

CSO / BSU NW2 NORTH RESIDENTIAL NEIGHBORHOOD PHASE #2 VOLUME 1 PROCUREMENT AND CONTRACTING DOCUMENTS GROUP

DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT

PROCUREMENT AND CONTRACTING DOCUMENTS GROUP

DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT

Schedule of Values Cruise Terminal 2 Expansion

DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT

VOLUME 4 DIVISION SPECIFICATIONS

FTA-DOT QA/QC Plan Sample Selected pages (not a complete plan)

Janitorial QA/QC Manual Sample

FRANKLIN VILLAGE APARTMENTS Building I Franklin Street Morristown, NJ Block: 3901 Lots: 4,5,6

Project Manual Index of Specifications Shenandoah Schools Concession Building

PROJECT MANUAL FOR: HUMPHREYS CO. SHERRILL BUILDING RENOVATIONS: NEW URGENT CARE CLINIC & EXTENSION SERVICE OFFICE

TABLE OF CONTENTS Updated 1/2014 SECTION TITLE DATE

Appendix J - Custom Uniformat for EDU Migration

LEVEL TWO NUMBERS AND TITLES. Introductory Information. Bidding Requirements. Contracting Requirements. Facilities and Spaces. Systems and Assemblies

APPLICATION AND CERTIFICATE FOR PAYMENT

KU West Campus LEEP II High Bay Facility Project # , A (c)

CM ASSIGNMENT OF TEMPORARY FACILITIES see included IU Project Site Requirements

TABLE OF CONTENTS DIVISION 1 GENERAL REQUIREMENTS

DOT-FHWA QA/QC Plan Sample Selected pages (not a complete plan)

Selected pages (not a complete plan)

G703 Continuation Sheet Minimum Schedule of Values Please use the breakdown listed below when submitting your billing for the project

ADDENDUM NO. 2 Consisting of 3 pages and Attachments

CAMPUS STANDARDS HANDBOOK

Montgomery County Public Schools Facilities Guide DIVISION 0 - CONDITIONS OF THE CONTRACT

1.5 Other than persons listed above, number of full-time office employees: 1.6 Number of full-time, permanent field employees:

Texas Tech University Health Sciences Campus - MSBII Supplemental Bid Instructions March 3, 2017

Inspection requests submitted by 2:30pm will be scheduled for the following business day unless otherwise requested.

Northwestern Facilities

4.1.3 Project Manual

Prequalification Form

Building Permit Application

FACILITY COMPONENTS - MIDDLE SCHOOL

Kimberly School District New Elementary School

INSPECTION TIMING CHECKLIST FOR RESIDENTIAL FRAME BUILDING PRIOR TO INSPECTION REQUEST

DIVISION 26 RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS PART 1 - GENERAL RELATED DOCUMENTS

Janitorial Essentials QA/QC Plan Sample

Work Performed Please see the attached list of Construction Codes and mark all that your company typically performs

City Of Mendota Construction Procedures

APPLICATION FOR CONTRACTOR REGISTRATION AND RENEWAL OF REGISTRATION INSTRUCTIONS AND CHECKLIST

J~e~~r Senior Director of Construction Services Facilities Design and Construction UNIVERSITY OF CALIFORNIA, SAN DIEGO.

RIVERSIDE CHURCH OF CHRIST. Lafayette, LA

* Cost Code# * Description * Division 1100 Summary 1 - General Requirements 1200 Price and Payment Procedures 1 - General Requirements 1300

ADDENDUM NO Refer to Specifications Section Alternates. Clarifications to alternate descriptions are as follows:

CONSTRUCTION COST BREAKDOWN THIS IS FORM CCB

BILL NO. 1 GENERAL ITEMS. Item No. Description Lump Sum Prices Excluding HST

Project Manual for the TCU ADDITION AND MEDICAL IMAGING RENOVATION. Lincoln, Nebraska. ESA Project No

City of Westerville Guide to Commercial Inspections

FACILITY COMPONENTS - ELEMENTARY SCHOOL

Introduction... 07/17 Table of Contents... 07/17 Administrative Requirements... 07/14

DOCUMENT B. 2. The low bidder shall submit this Expanded Subcontractors Listing to the Owner within 24 hours after the bid opening.

Training Certification Categories

B. RESIDENTIAL MASTER PLUMBER $ $ $

Project #1139 Budget #82. $ Budgeted $ Billed to Date $ Paid to Date $ Due 210, , , ,158.50

State of Ohio Ohio School Facilities Commission TABLE OF CONTENTS

PROJECT MANUAL PROJECT LABOR AGREEMENT

Nassau County Building Department

FACILITY COMPONENTS - ELEMENTARY SCHOOL

FIRESTOPPING & SMOKE SEALS

2016 CDM Smith All Rights Reserved July 2016 SECTION MULTIPLE CONTRACT SUMMARY

Building Systems and Design Elements included in SliDeRulE

Received by:* Date Received:* Zoning Approval:* Date:* PERMIT#:* *ZONING: *SETBACKS: FRONT ft/ SIDE ft/ REAR ft *FLOOD ZONE:

TABLE OF CONTENTS VOLUME 1. DIVISION 00 - INTRODUCTORY INFORMATION, BIDDING REQUIREMENTS, CONTRACT FORMS & CONDITIONS OF THE CONTRACT Pages

Item # 1: Attached are the revised Table of Contents and Specifications added: Section Cabinets and Vanities

JULY 11, 2017 SECTION MARRIOTT MIDTOWN DUAL BRAND BULLETIN NO. 4 AC/MOXY SECTION BULLETIN NO. 4

SECTION B. Index of Contents of Section C

SECTION : OPERATION & MAINTENANCE MANUALS

Town of Milton Halton Paramedic Services Station No. 17 and Milton Fire Station No. 5 Tender No and

BIDDING SHEET CHECKLIST--SUBCONTRACTORS AND SUPPLIERS SUBCONTRACTOR/ PHONE DATES SUPPLIER NAME: CALLED BID. Sample

Simcoe County District School Board. 5yr Condition Assessment 2006/07 to 2010/11. Hillcrest PS (Barrie), 9205

Essentials Pipe Fabrication Quality Plan Sample Selected pages not a complete plan

Transcription:

GC s Subcontractor QA/QC Plan Sample Include your Subcontractors in your Project Quality Control Plan Show your clients your seamless approach to controlling subcontractor quality on their project Contact: Ed Caldeira 410-451-8006 Pat [Pick the date]

PROJECT-SPECIFIC SUBCONTRACTOR QUALITY PLAN TABLE OF CONTENTS Background Information... 4 Project Name... 4 Project Number... 4 Location of Project Work... 4 Subcontractor Scope of Work... 4 Project.Quality Policies... 5 [Insert Subcontractor Company Name] Project Qualty Policy... 5 Policy for Compliance with [GC_CompanyName] Quality Assurance/Quality Control Plan Requirements 6 Project QC Personnel... 9 Project QC Job Position Assignments... 9 Duties, Responsibilities, and Authority of QC Personnel... 9 Employee Qualifications... 10 Project Quality Coordination and Communication... 14 Submittals... 17 Qualification of Subcontractors and Suppliers... 20 Testing Plan... 22 Work Task Quality Inspections... 24 Control of Punch Items and Nonconformances... 28 Quality Assurance Surveillance... 30 Appendix... 32 Selected Pages Page 3 GC s Subcontractor Project-specific Quality Plan Copyright

PROJECT QUALITY POLICIES [INSERT SUBCONTRACTOR COMPANY NAME] PROJECT QUALTY POLICY Our objective is to safely deliver 100 percent complete construction work that meet all contract and [GC_CompanyName] Quality Assurance/Quality Control Plan the first time, every time. Our commitment to quality means: Compliance with [GC_CompanyName] Quality Assurance/Quality Control Plan. Compliance for fully implementing and complying with all provisions of this Subcontractor QC Plan. Our quality standards meet or exceed all applicable regulations, codes, industry standards, and manufacturer specifications as well as with our customers contract and individual. We ensure that only knowledgeable, capable, and qualified employees carry out the planning, execution, and control of our work. We stand behind our work. We conduct a series of quality inspections for each work task: before work begins, at first article completion, while work is in process, and at completion. We inspect all materials before use. Should problems be found, we prevent them from cover-up, inadvertent use, and then quickly correct them. We are always improving. We make systematic improvements to remove quality risks and enhance quality performance. We abide by the [GC_CompanyName] Subcontractor Quality Control Policy Requirements (see Appendix) We conduct our work with dignity and respect for the customer, our subcontractor partners, and ourselves. [Insert Subcontractor Company Name] Officer Signature / Title / Date Selected Pages Page 5 GC s Subcontractor Project-specific Quality Plan Copyright

[GC_CompanyName] Point Of Contact List Version April 30, 2012 Project ID Project Name Preparer Date [ProjectNumber] [ProjectName] [ProjectManagerName] Type of List: Company Customer Suppliers/Subcontractors Company Name and Position Contact Responsibilities Phone Contact Numbers Email Selected Pages Page 15 GC s Subcontractor Project-specific Quality Plan Copyright

PROJECT QUALITY COORDINATION AND COMMUNICATION [Insert Subcontractor Company Name] has regular, planned communications with customers, subcontractors, and suppliers to coordinate quality expectations, priorities, activities, and improvements. Throughout the project, [Insert Subcontractor Company Name] holds preparatory meetings prior to the start of upcoming milestones, tasks, or phases of work. These meetings are attended by key company, subcontractor personnel responsible for carrying out, supervising, or inspecting the work, and interested customer representatives. We review quality, coordinate quality inspections and hold points. In the process, we listen to each stakeholder to understand their concerns for critical details. We add the critical details to inspection checklists. We also train production personnel on these details in weekly and toolbox talk meetings. [Insert Subcontractor Company Name] weekly team toolbox meetings deploy findings of the preparatory meeting to field personnel. The venue is used to train personnel on technical, reinforce critical details for heightened awareness, and institute improvements to work methods. It is also a forum for team communications and coordination. Selected Pages Page 14 GC s Subcontractor Project-specific Quality Plan Copyright

[GC_CompanyName] Subcontractor Quality Control Policy Requirements This Contract is an unclassified Contract. The Subcontractor is to execute all Work per the plans and specifications. The Subcontractor shall complete the Work in accordance with the Contract Documents, including all labor, materials, equipment, services and other items required to complete such Work. The Work of this Contract is defined by the Contract Documents, and requires the entire and complete performance of the Work described therein, and those things which Subcontractor through his business and professional experience has cause to know are reasonably inferable for a complete and satisfactory job. Without limiting any other of the Contract Documents, all Work shall be performed in full compliance with the contract, contract technical specifications, contract drawings, and approved contract submittals. Without limiting any other of the Contract Documents, all Work shall be performed in a professional and workmanlike manner in full compliance with the [GC_CompanyName] Quality System. The intent of the Contract Documents is to include all items necessary for the proper execution and completion of the Work. The Contract Documents are complementary, and what is required by any one shall be as binding as if required by all. Work not specifically covered in the Contract Documents will nonetheless be required if it is consistent therewith and is reasonably inferable there from as being necessary to produce the intended results. Should conflicts occur in the Contract Documents, the Subcontractor shall request interpretation from [GC_CompanyName] before proceeding with the Work. If the Subcontractor fails to make such a request, no excuse will thereafter be entertained for failure to carry out the Work in a satisfactory manner. This project is to be constructed in accordance with governmental regulations including federal regulations; state regulations; state building codes; state, county, city, and township addenda to state building codes; work details and specifications in architectural drawings approved by Government regulatory authorities. Any deviations must be approved in writing by [GC_CompanyName] and the relevant Government agency. Should a conflict between the Contract Documents and the governmental regulations arise, then the governmental regulations shall supersede and take precedent over the Contract Documents. Subcontractor shall have timely access to all relevant governmental regulations while completing Work at the project site. Selected Pages The project is to be constructed in accordance with relevant industry standards. Any deviations must be approved in writing by [GC_CompanyName]. Should a conflict between the Contract Documents and the relevant industry standards arise, then the industry standards shall supersede and take precedent over the Contract Documents. Subcontractor shall have timely access to all relevant industry standards while completing Work at the project site. Should a conflict between the Contract Documents and the plans/specifications arise, then the plans and specifications shall supersede and take precedent over the Contract Documents. [GC_CompanyName] reserves the right to take responsibility for the completion of any single item or task included in the Subcontractor s Scope of Work and defined in the Contract Documents. Page 33 GC s Subcontractor Project-specific Quality Plan Copyright

Inspection Forms Available by Division Sections CONCRETE THERMAL AND MOISTURE PROTECTION Cast Decks and Underlayment Concrete Finishing Concrete Forming Concrete Reinforcing Grouting Precast Concrete Structural Concrete MASONRY Concrete Form Masonry Units Concrete Unit Masonry Exterior Stone Cladding Maintenance of Masonry Manufactured Brick Masonry METALS Metal Decking Metal Railings Metal Stairs Structural Steel Framing WOOD/PLASTICS/AND COMPOSITES Architectural Wood Casework Exterior Finish Carpentry Interior Finish Carpentry Sheathing Wood Decking Wood Framing Applied Fireproofing Blanket Insulation Board Insulation Dampproofing and Waterproofing Exterior Insulation and Finish Systems Firestopping Flashing and Sheet Metal Joint Protection Membrane Roofing Thermal and Moisture Protection-Roof Accessories Thermal and Moisture Protection-Roof and Deck Insulation Thermal and Moisture Protection-Roof Panels 07.41.00 Roof Tiles Roofing and Siding Panels Sheet Metal Roofing Shingles and Shakes Siding Wall Panels Weather Barriers

OPENINGS PLUMBING Door Hardware Electric Domestic Water Heaters Doors and Frames Facility Potable-Water Storage Tanks Glazing 08.80.00 Facility Sanitary Sewerage Louvers and Vents Facility Storm Drainage Unit Skylights Facility Water Distribution Windows Fuel-Fired Domestic Water Heaters FINISHES Plumbing Fixtures Plumbing Insulation Access Flooring Acoustic Treatment HVAC Acoustical Ceilings Air Outlets and Inlets Backing Boards and Underlayments Air Terminal Units Carpeting Breechings//Chimneys// and Stacks Masonry Flooring Central Cooling Equipment Painting and Coating Commissioning ofhvac Plaster and Gypsum Board Cooling Towers Resilient Flooring Facility Fuel-Oil Piping Stone Facing Facility Fuel-Storage Tanks Terrazzo Flooring Facility Natural-Gas Piping Textured Ceilings Furnaces Tiling Heating Boilers Wall Coverings HVAC Air Cleaning Devices Wood Flooring HVAC Ducts and Casings HVAC Fans FIRE SUPPRESSION HVAC Insulation HVAC Piping and Pumps Suppression Water-Service Piping Fire Pumps Fire-Suppression Sprinkler Systems Fire-Suppression Standpipes Fire-Suppression Water Storage HVAC Water Treatment Indoor Central-Station Air-Handling Units Instrumentation and Control for HVAC Refrigerant Piping Testing// Adjusting// and Balancing for HVAC

Concrete-Concrete Finishing 03.35.00 Sep2011 Project: Phase: Contract#: Organization: 9101 Field Operations Crew: Compliance Verification o Compliance with initial job-ready o Compliance with material inspection and tests o Compliance with work in process first article inspection o Compliance with work in process inspection o Compliance with Task completion inspection o Compliance with inspection and test plan o Compliance with safety policies and procedures Reported Nonconformances and incomplete items: FTQ 2TQ Heightened Awareness Checkpoints Concrete Finishing Schedule reviewed with ENGINEER/ARCHITECT prior to Concrete Placement 1030 No damage to coated reinforcing exposed during patching activities 1031 Adequate water is present to wet finishing equipment and prevent smearing of the finish 1032 Color admixture evenly distributed throughout concrete mix (no streaking or color variations) 1033 Surface Grooves orientated to direct water off of the slab 1034 Adequate form release agent has been applied to concrete stamps 1035 Finished surfaces are free of pin holes// spalling// and other surface irregularities 1036 Finishing is smooth and ready to receive surface treatment (carpet// tile// etc.) 1037 Concrete sealer applied to surfaces free of dust and standing water 1038 Site runoff is directed away from placed concrete until properly finished and cured 1039 FTQ Scores and Completion Sign-off Field Mgmt.-Superintendent Inspection 91.45.01 Quality On-Time Safety Sign and date*: Cell # / ID #:: Signed: Date: Task has been has been verified complete and in compliance with contract drawings and specifications except for non-conformances and incomplete items reported above. Field Mgmt.-QA Inspection 91.45.02 Quality Sign and date*: Cell # / ID #:: Signed: Date: Task has been has been verified complete and in compliance with contract drawings and specifications except for non-conformances and incomplete items reported above. Quality Score On-Time Score Safety Score 5 = 100% NO problems 5 = On Time 5 = 100% NO problems 4 = 1 minor problems 4 = Late 4 = 1 minor problem 3 = Hotspot or 2-3 minor 3 = Late by 1 day 3 = Hotspot or 2-3 minor 2 = 6+ or major problems 2 = Late by 2 days 2= 4+ or major problem 1 = Excessive problems 1 = Late more than 2 days 1= Injury Copyright 2011 First Time Quality

ELECTRICAL Conduit for Electrical Systems Electrical and Cathodic Protection Enclosed Bus Assemblies Exterior Lighting Grounding and Bonding for Electrical Systems Identification for Electrical Systems Interior Lighting COMMUNICATIONS Low-Voltage Circuit Protective Devices Low-Voltage Controllers Low-Voltage Electrical Power Conductors and Cables (<600V) Low-Voltage Electrical Service Entrance Low-Voltage Switchgear Low-Voltage Transformers Raceway and Boxes for Electrical Systems Switchboards and Panelboards Audio-Video Communications Cable Trays for Communications Systems Communications Backbone Cabling Communications Equipment Room Fittings Data Communications Structured Cabling Voice Communications ELECTRONIC SAFETY AND SECURITY EARTHWORK Commissioning of Electronic Safety and Security Conductors and Cables for Electronic Safety and Security Electronic Access Control and Intrusion Detection Electronic Surveillance Fire Detection and Alarm Mass Notification Systems Pathways for Electronic Safety and Security Bored Piles Caissons Clearing and Grubbing Driven Piles Excavating and Fill Grading EXTERIOR IMPROVEMENTS Base Courses Curbs// Gutters// Sidewalks// and Driveways Fences and Gates Flexible Paving Irrigation Planting Retaining Walls Rigid Paving

Electrical-Grounding and Bonding for Electrical Systems 26.05.26 Feb2012 Project: Phase: Contract#: Vendor: 9101 Field Operations Crew: Compliance Verification o Compliance with initial job-ready o Compliance with material inspection and tests o Compliance with work in process first article inspection o Compliance with work in process inspection o Compliance with Task completion inspection o Compliance with inspection and test plan o Compliance with safety policies and procedures Reported Nonconformances and incomplete items: FTQ 2TQ Heightened Awareness Checkpoints Connections tight and free of corrosion// paint// and other non-conductive materials 1633 Anti-oxidant paste applied to connection junctions 1634 Shielding grounded across splices and connections 1635 Ground cabling entering/exiting buildings are sealed and waterproofed 1636 Metal conduits// boxes// panels// etc. bonded to Grounding System 1637 Ground rods not located in rock or stone fill 1638 Wiring secured to prevent movement and chafe 1639 Multi-strand wire or strap connectors utilized on movable connections 1640 Ground system tested for continuity 1641 FTQ Scores and Completion Sign-off Field Mgmt.-Superintendent Inspection 91.45.01 Quality On-Time Safety Sign and date*: Cell # / ID #:: Signed: Date: Task has been has been verified complete and in compliance with contract drawings and specifications except for non-conformances and incomplete items reported above. Field Mgmt.-QA Inspection 91.45.02 Quality Sign and date*: Cell # / ID #:: Signed: Date: Task has been has been verified complete and in compliance with contract drawings and specifications except for non-conformances and incomplete items reported above. Quality Score On-Time Score Safety Score 5 = 100% NO problems 5 = On Time 5 = 100% NO problems 4 = 1 minor problems 4 = Late 4 = 1 minor problem 3 = Hotspot or 2-3 minor 3 = Late by 1 day 3 = Hotspot or 2-3 minor 2 = 6+ or major problems 2 = Late by 2 days 2= 4+ or major problem 1 = Excessive problems 1 = Late more than 2 days 1= Injury Copyright 2011 First Time Quality

UTILITIES Culverts Public Water Utility Distribution Piping Sanitary Utility Sewerage Force Mains Sanitary Utility Sewerage Piping Storm Drainage Structures Storm Utility Water Drains Subdrainage Water Utility Distribution Equipment

Utilities-Sanitary Utility Sewerage Force Mains 33.34.00 Feb2012 Project: Phase: Contract#: Vendor: 9101 Field Operations Crew: Compliance Verification o Compliance with initial job-ready o Compliance with material inspection and tests o Compliance with work in process first article inspection o Compliance with work in process inspection o Compliance with Task completion inspection o Compliance with inspection and test plan o Compliance with safety policies and procedures Reported Nonconformances and incomplete items: FTQ 2TQ Heightened Awareness Checkpoints Piping has sufficient cover for anticipated traffic 2147 Piping bury below frost line for lines containing standing sewage 2148 Proper separation between water and sewer lines maintained (10' horizontal// 18 vertical with water on top) 2149 Mechanically restrained joints tight and secure 2150 Push-on joints fully inserted 2151 Thrust blocking and anchors in contact with piping and firmly attached 2152 Fittings and accessories compatible (material// pressure rating// connection type) with the piping utilized 2153 Protective coating/wrap is intact// uniform// and free of damage 2154 Indicator tape or tracer wire installed above piping 2155 Piping pressure tested and free of leaks 2156 FTQ Scores and Completion Sign-off Field Mgmt.-Superintendent Inspection 91.45.01 Quality On-Time Safety Sign and date*: Cell # / ID #:: Signed: Date: Task has been has been verified complete and in compliance with contract drawings and specifications except for non-conformances and incomplete items reported above. Field Mgmt.-QA Inspection 91.45.02 Quality Sign and date*: Cell # / ID #:: Signed: Date: Task has been has been verified complete and in compliance with contract drawings and specifications except for non-conformances and incomplete items reported above. Quality Score On-Time Score Safety Score 5 = 100% NO problems 5 = On Time 5 = 100% NO problems 4 = 1 minor problems 4 = Late 4 = 1 minor problem 3 = Hotspot or 2-3 minor 3 = Late by 1 day 3 = Hotspot or 2-3 minor 2 = 6+ or major problems 2 = Late by 2 days 2= 4+ or major problem 1 = Excessive problems 1 = Late more than 2 days 1= Injury Copyright 2011 First Time Quality

For More Information: Contact: Ed Caldeira 410 451 8006 www.firsttimequality.com EdC@FirstTimeQuality.com For More Information, contact: Ed Caldeira Caldeira Quality, LLC First Time Quality 410 451 8006 www.firsttimequality.com EdC@FirstTimeQuality.com