Minimising construction waste through project design

Similar documents
Resource efficiency pursued through design coordination and waste management

Innovative waste management approach achieves exemplary recovery rates

Contractor follows nine-step plan to achieve best practice in construction waste management

Best Practice Construction Waste Procurement: Office Fit-Out of 15 Canada Square, Canary Wharf

Reducing construction waste saves money Bridge Learning Campus, Bristol Contractor: Skanska

Halving Waste to Landfill

Zero waste to landfill: Construction waste collection good practice

PLASTERBOARD SUSTAINABILITY INITIATIVE PSP (UK) 13 November 2012, European Parliament Brussels Presented by: Malcolm Waddell, WRAP UK

A metric for the construction sector. The Net Waste Method testing a new standard for measuring waste neutrality

Scotland s Litter Problem. Quantifying the scale and cost of litter and flytipping

The efficient use of materials in regeneration projects

Railways: Waste less and save money

Construction waste collection good practice: Gloucester Quays

The emphasis should be on the contractor to develop the targets for waste reduction and recovery. What is good practice?

STEEL INSIGHT #10 KEY FRAME COST DRIVERS

Sustainability Best Practice Case Study. Reducing Waste, Reducing Cost. The UK construction industry waste challenge

Defence sector: recycling waste in construction Defence Estates Regional Prime Contract East, Babcock DynCorp

McGrath works in partnership with Hackney Homes

Case Study: Barts Health NHS Trust Food Waste Collection

Reducing and recycling plasterboard waste on a site where space is a constraint

Utilities: Waste less and save money

The Demolition Protocol: Aggregates Resource Efficiency in Demolition and Construction. Volume 3. For Contractors

Assessing the costs and benefits of reducing waste in construction

Design out. Waste Workshop. A guidance document produced by Network Rail in collaboration with:

Grays Waste Management

Costs and benefits of reducing waste in construction. Defence sector new build Woolwich single living accommodation modernisation (SLAM)

The efficient use of materials in regeneration projects

Business Information Pack

Waste management contractors selling the benefits of your Halving Waste to Landfill Commitment to construction clients

Structures concrete. Structures concrete

Assessing the costs and benefits of reducing waste in construction

Reducing Waste in Sainsbury s Supermarket Refits through off site fabrication

Assessing the costs and benefits of reducing waste in construction trade packages

Tool for measuring the recovery rates in CDEW MRFs

Barts Hospital, London

NHSScotland Waste Management Support Programme. Jessica Twemlow Project Manager - NHSScotland Programme of Support

Laying the foundations to double re-use

Designing Out Waste In the Civil Engineering Sector Athens Dioni Spiliopoulou MCIWM Bob Hudson MCIWM

Delivering Sustainability with Prestige: at the BMW PGA Championships

Hickory Building Systems. Overview of Prefabricated Structural System. t ink

Cladd:ISS a strategy for managing cladding interfaces.

Concepts. Products. Service. Harlequin 1, Brentford, London

15/06/ Clippers Quay. Salford Manchester.

Benefits of off site manufacture

2.3.6 Design Development

Scotland s residual waste treatment landscape Dr Paul Moseley Scottish Futures Trust

Summary Guide to Identifying Raw Materials Risks

Suffolk energy-from-waste facility

Offsite Housing The Portfolio Approach. Stephen Wightman. Managing Director SIG Offsite

Material resource efficiency in construction

Environmentally Friendly and Sustainable Development

Halving Waste to Landfill, SEESA

Innovation Construction CIC: B2B Event on MiC

Is off-site construction greener? Bob Francis, Director Modular Systems +

hansen the façade specialist Hansen UnitAl modular system for curtain walls HansenGroup

A blueprint for reducing waste and cutting costs

Buildcorp Contracting is the foundation division of the Buildcorp Group. Established in 1990, Buildcorp Contracting delivers specialist new

Premier Inn, Wilson Street, Middlesbrough, TS1 1AE. Site progress report. February 2017

Offsite modular construction

Reducing construction waste at Sure Start Children s Centres using the EcoCanopy system

Hale Allen Jones The Institution of Structural Engineers East Anglian Branch Award for Structural Excellence Submission

Raploch: urban regeneration

Sustainability and Process Benefits of Modular Construction

Buildcorp Contracting is the foundation division of the Buildcorp Group. Established in 1990, Buildcorp Contracting delivers specialist new

Construction Products Regulations Curtain walling. Stephen Ledbetter, CWCT

Benefits of off site manufacture

Concepts. Products. Service. Providence Tower, London

Raising the Bar for sustainable office design

Achieving effective Waste Minimisation

Scotland s Resource Sector Commitment. Health & Safety Standards. A guide to the resource management sector commitment health & safety

Factsheet no. 2: SEGRO warehouse, Slough, UK

World of Modular Prefabrication in the United Kingdom Bob Mears Head of Sales & Marketing

leading aluminium and composite fenestration solutions innovative window, door and curtain wall systems that bring environments to life

New Main Hospital, Site Park, and Underground Garage Construction Progress Update #16

Non-packaging plastics

Engaging with suppliers on waste prevention

SOUTH LANARKSHIRE COLLEGE LOW CARBON TEACHING BUILDING TECHNICAL CASE STUDY

Trialling the re-use of used EEE from Leeds City Council HWRCs

Waste FY Introduction. 2. Waste. 3. Management Approach

Benefits of the WRAP SWMP Template. Birmingham, 1 April 2008

CASE STUDY. PCI Pharma. Gerteis Roller Compactor for Highly Potent Contained Manufacturing Facility

Construction Strategy: Newtown Secondary School

Pacific Place, the Queensway complex has added a baby brother to the family of office towers, hotels and retail outlets. Three Pacific Place is a

Newton Group CANADACAR SYSTEM. Basic Construction of the CANADACAR System. CANADACAR Module Format

Portcullis House. Project Basics

ACSE AWARDS Large Project Parliament Square, Hobart

WESTERN GRANDSTAND, ADELAIDE OVAL

End of Project Report : Newtown Secondary School

Associate-Membership Examination

Sustainability Performance Report 2nd report: 2012 performance data

KPI. Continuous Improvement Test (CIT) Measurement. To be measured in line with HSE guidance for calculating the Accident Incident Rate (AIR)

Target Zero Waste Home Construction

Construction Waste Management Plan Guidelines. A resource for Western Australian Local Government, Developers, Property Owners and Builders

Façades: Do all-glass buildings make financial sense?

Thesis Proposal. Matthew R Peyton

THE FUTURE OFFSITE CONSTRUCTION & DIGITAL ENGINEERING MATHEW RILEY MANAGING DIRECTOR, RAMBOLL UK

SECTION DEMOUNTABLE WALLS SKY WALLS - STRATUS SYSTEM

FINANCE COMMITTEE EMPLOYMENT OPPORTUNITES IN THE PUBLIC SECTOR SUBMISSION FROM NHS GREATER GLASGOW AND CLYDE

Session 2: A methodology for measuring embodied carbon. Sean Lockie, Director, Faithful and Gould

Small WEEE collections checklist: Third Sector Organisation

Transcription:

Case Study: New South Glasgow Hospitals Minimising construction waste through project design Key facts Applying WRAP s Designing out Waste principles to the project design identified 21 areas of potential waste reduction during the design phase. Use of the WRAP waste forecasting tools has assisted Brookfield Multiplex in identifying and quantifying waste reduction opportunities and associated cost savings. Artist impression of New South Glasgow Hospitals over central park The construction of New South Glasgow Hospitals (NSGH) is one of the NHS s flagship projects. The principal contractor, Brookfield Multiplex, has used tools developed by the Waste and Resources Action Programme (WRAP) to identify potential waste reduction opportunities throughout the design stage of the project. 1 Background The NSGH project in Glasgow is a 575 million capital project and the largest NHS construction project in Scotland. The project involves the construction of a new children s and acute hospital with supporting laboratory facilities that will provide patients in the west of Scotland with outstanding healthcare facilities. The project implemented an innovative on-site sorting system in order to target a landfill diversion rate of 90%.

design for re-use and recovery; design for off-site construction; design for materials optimisation; design for waste-efficient procurement; and design for deconstruction and flexibility. A Designing out Waste workshop held at the project outset by Brookfield Multiplex initially focused on two of the five design principles, as the ability to identify actions in each area is influenced by factors such as the project programme and interface with other design considerations. Artistic impression, aerial view of New South Glasgow Hospitals development from the north Opportunities for off-site and modular construction were explored in every aspect of the design to provide a number of operational advantages including waste reduction. We have since worked closely with our design team and suppliers to establish which options are practicable to implement. Jim Murray Design Manager Brookfield Multiplex Greater Glasgow and Clyde NHS Board specified high standards of environmental and sustainability performance including a BREEAM Excellent rating. This requirement introduced stringent targets for minimising waste generation, which was further supported by Brookfield Multiplex s corporate target to divert 83% of waste from landfill. In order to achieve these targets Brookfield Multiplex approached Zero Waste Scotland for guidance and assistance with the use of the WRAP Designing out Waste Tool and Net Waste Tool. Zero Waste Scotland is the trading name of WRAP in Scotland. Designing out Waste The Designing out Waste Tool has been developed for use by design teams in the pre-design phase of a project. The tool applies a structured approach to the outline project design to identify specific waste minimisation actions that can be implemented throughout the design and construction phase. The identification of waste minimisation actions is achieved in a workshop involving professionals from different design disciplines with each identifying opportunities within their respective elements of the project. The approach focuses on five principles for waste reduction: Opportunities to design for re-use and recovery and for off-site construction on the NSGH project were apparent at the very start of the project whereas other areas, such as design for materials optimisation, required a degree of design work to be undertaken before waste reduction opportunities could be identified. Embedding the five principles as design considerations supported by the iterative use of the tools throughout the design phase ensured that opportunities arising throughout the project were identified and capitalised upon. Design for off-site construction This design principle explores the options for prefabrication and off-site manufacturing in preparation for on-site assembly. The NSGH design team had a major focus on off-site construction with the principle applied across numerous aspects of the design at an early stage. The approach taken by Brookfield Multiplex is reflected in the number of prefabricated components present in the final design including a link bridge connecting buildings and elements associated with the hospital helipad. Widespread use of prefabricated plug and play mechanical and electrical services risers and cable trays are other areas where off-site manufacturing has been maximised, contributing towards an overall reduction in waste. 2

Case Study The adoption of the unitised structural cladding design has brought many benefits to the project including a reduction in waste, and accelerated the fit-out programme by sealing the building earlier than planned. Alan Keeley Construction Director Brookfield Multiplex One of the most visible building components to be manufactured off-site is the glass curtain walling present on the main tower of the hospital. The unitised structural cladding system specified by Brookfield Multiplex will arrive prepared for installation, eliminating the need for contractors to work with materials and therefore removing the potential for waste generation. One of the implementation challenges faced by project architect Nightingale Associates in specifying prefabricated panels was designing to the standard cladding panel sizes, which required adjustments to be made to the setting out of the cladding panels. Another potential waste reduction opportunity identified during the design stage was the off-site fabrication of a number of concrete structures within the building. This included columns, stairways and floor slab end beams building components which might otherwise have been cast on-site, potentially increasing on-site waste generation. The extent of off-site fabrication present within the project design is reflected in the outputs from the initial Designing out Waste workshop. The examples present in the final design and construction highlight where the forecasting tools can add value throughout the design stage and decision-making process. Artistic impression, New South Glasgow Hospitals main entrance Design for materials optimisation This principle promotes the efficient use of construction materials through a design, focusing on material and resource efficiency. Promoting efficiencies through standardisation of components and considering the materials specified in the design can substantially reduce the level of waste generated throughout the construction phase of a project. The main materials optimisation opportunity identified on the design of NSGH was to standardise internal wall dimensions to reduce the number of off-cuts required on dry-lined plasterboard walls. The design team initially considered a standardised room dimension, although the client s need for flexibility, a common challenge to implementing this principle, constrained the opportunity. Unitised cladding panels, fabricated off-site, delivered to site, offloaded and lifted into position on external elevations. 3 To overcome this challenge Brookfield Multiplex s design team worked with the NHS Trust to develop a list of required room types against which standard designs could be produced.

The outputs suggested that actions identified by Brookfield Multiplex could achieve a 6,500-tonne waste saving compared with an industry baseline depending upon the extent of actions implemented in the final project design. Horizontal and vertical, combined mechanical and electrical modules, fabricated off-site. Retaining an element of standardisation enabled Nightingale Associates to introduce standard dimensions that could be replicated throughout the building. In doing so, Brookfield Multiplex was able to design standard dimensions such as sill heights for internal glazing sections, reducing the need for cutting during installation. Identifying specific waste reduction opportunities contributed to a potential reduction in the waste plasterboard arisings in comparison with standard industry practice, which may have required a greater degree of on-site material working. Another area where materials optimisation was promoted was through the setting out of materials within the detailed design. This included the setting out of plasterboard planks in corridor ceilings in a way that eliminated the need for cutting. The layout of flooring tiles in the building atrium involved the specification of different sized tiles within the design to reduce both the overordering of material and the need for cutting during installation. Net Waste: calculating the benefits The Net Waste Tool was used following the Designing out Waste process to quantify the potential waste saving from the identified waste minimisation actions. Specific opportunities identified during the Designing out Waste process were input to enable the impact to be determined against a baseline of standard industry practice. The outputs from the Net Waste Tool were also used to develop a best practice site waste management plan for the project. In addition to generating a forecast of waste volumes, the tool also provided a record of design actions along with an indication of savings that could be achieved upon implementation. The recording and quantification of these decisions taken throughout the project provide Brookfield Multiplex with a basis for project review along with evidencing waste prevention within the project. The Net Waste Tool was also used to estimate the impact of the innovative on-site waste sorting system introduced to the project. This involved Brookfield Multiplex appointing Edinburgh-based Recycling and Data Services Limited to segregate construction waste into individual material streams on-site for direct delivery to material reprocessors. Modelling this approach using the Net Waste Tool identified a diversion rate of over 90% significantly higher than the 75% good practice rate suggested by the tool. Key statistics generated by the Net Waste tool were instrumental in proceeding with both the Designing out Waste actions and the on-site sorting system. Some of the headline savings estimated by the Net Waste Tool included: A 6,500-tonne reduction in construction waste generated throughout the project compared with standard industry practice if all identified actions were to be implemented. An identified potential cost saving in the avoided cost of wasted materials when compared with standard industry practice. A landfill diversion rate of over 90%. The use of the Net Waste Tool also assisted Brookfield Multiplex in identifying its progress against the 10% recycled content target established for the project. 4

Brookfield Multiplex proposes to use the tool on completion of the project to compare target and actual performance and has recently undertaken a project review. Precast concrete columns that have been delivered to site and off loaded ready to be lifted into position. This review has been supported by a supply chain partnership event facilitated by Zero Waste Scotland. The event sought to identify specific waste reduction opportunities around the Designing out Waste principles that can be implemented in partnership with Brookfield Multiplex s supplier and contractors. Suppliers attending the event were asked to identify specific waste reduction actions around which each supplier would be required to implement two actions in their work on the project. The output of this event continues to promote waste minimisation as a design consideration throughout the remainder of the NSGH project. Zero Waste Scotland Ground Floor, Moray House, Forthside Way, Stirling, FK8 1QZ. E-mail: helpline@zerowastescotland.org.uk Helpline freephone 0808 100 2040 www.zerowastescotland.org.uk While steps have been taken to ensure its accuracy, Zero Waste Scotland cannot accept responsibility or be held liable to any person for loss or damage arising out of or in connection with this information being inaccurate, incomplete or misleading. This material is copyrighted. It may be reproduced free of charge subject to the material being accurate and not used in a misleading context. The source of the material must be identified and the copyright status acknowledged. This material must not be used to endorse or used to suggest Zero Waste Scotland s endorsement of a commercial product or service. For more detail, please refer to our Terms & Conditions on our website: www.zerowastescotland.org.uk/terms