Project Management. Opportunity or Oxymoron? Stacy Munechika, PMP, PMI-ACP. PMI Rochester Chapter Professional Development Day May 2017

Similar documents
SCHEDULE RISK ANALYSIS ESSENTIALS FOR PROJECT SUCCESS

Identify Risks. 3. Emergent Identification: There should be provision to identify risks at any time during the project.

Project vs Operation. Project Constraints. Pankaj Sharma, Pankaj Sharma,

Project Planning & Management. Lecture 11 Project Risk Management

RiskyProject. Project Risk Management Software

Risk Mitigation: Some Good News after the Cost / Schedule Risk Analysis Results

Expert Reference Series of White Papers. Managing Risk An Integrated Approach

Research Presentation RISK INTELLIGENCE: AN INTRODUCTION INTO THE PROJECT AND CONSTRUCTION RISK MANAGEMENT

THE PMP EXAM PREP COURSE

Leveraging Best Practices in Risk Management For Strategic Outcomes. Peter Schmidt Director ESI International

Creating a Risk Intelligent Enterprise: Scenario planning and war-gaming

Facing the Dragon: Data-Driven Risk Management in Small to Midsize Organizations. Sonja Streuber, PMP

Proven Project Risk Management Techniques for Increased Project and Organizational Success

Managing Risk in Agile Development: It Isn t Magic

The Agile PMP Teaching an Old Dog New Tricks

Project Management Professionals

Lecture 2: Project Management, Part 1: Requirements, WBS, Scheduling, and Risk Management. Prof. Shervin Shirmohammadi SITE, University of Ottawa

Integration Knowledge Area

Initiation Group Process. Planning Group Process

PMP Exam Prep Study Group Input-Output-Tools #3a

PMP TRAINING COURSE CONTENT

Deltek Acumen 7/15/16. Learning Objectives. Introduction to Project Risk Analysis. Planning, Risk, Acceleration. The 5 steps. Worked examples Q&A

Knowledge Areas According to the PMBOK edition 5. Chapter 4 - Integration

What Every Manager Needs to Know About Project Management in 2018

Review: Simple schedule risk modelling with Safran Risk

PMP EXAMINATION PREP CHAPTER 6 SCHEDULE MANAGEMENT. PMP Exam Prep

Software Quality Engineering Courses Offered by The Westfall Team

Software Quality Engineering Courses Offered by The Westfall Team

PMP Exam Preparation Workshop. Chapter # 5 Project Scope Management

RISK MANAGEMENT STEPS Lecture 2

BA25-Managing the Agile Product Development Life Cycle

The 9 knowledge Areas and the 42 Processes Based on the PMBoK 4th

The Benefits of the 9m Innovation Model

Project Risk Management

Scenario Planning in Sales & Operations Planning

Stakeholder Management Plan <Project Name>

PMP Exam Preparation Course Project Time Management

Thomson Reuters Enterprise Risk Manager

How to Use an Insight Community to Build and Launch Successful Products

Strategy Analysis. Chapter Study Group Learning Materials

"Charting the Course to Your Success!" Planning and Managing Agile Projects Course Summary

Managing Projects of Chaotic and Unpredictable Behavior

STRATEGIC THINKING, PLANNING & GOAL SETTING

SCENARIO PLANNING IN SALES & OPERATIONS PLANNING

Topics to be covered. Commercial Levers Available to the PM to Manage Agile project delivery

S O Seminar Objective

Project Management Framework with reference to PMBOK (PMI) July 01, 2009

Risk Based Thinking & QMS Risk Management as per ISO

Decision Analysis Making the Big Decisions

For the PMP Exam using PMBOK Guide 5 th Edition. PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc.

Project Risk Management. A DEVELOMENT INSTITUTION s PERSPECTIVE

Aligning Business Architecture with Business Design

Leadership Lessons from Agile and PMI s PM-2. Tim Kloppenborg, PhD, PMP Marcie Lensges, PhD

PRINCESS NOURA UNIVESRSITY. Project Management BUS 302. Reem Al-Qahtani

Understanding and Managing Uncertainty in Schedules

PMI Risk Management Professional (PMI RMP ) Exam Preparation Student Courseware Book

OPM The Missing Link. Jane Betterton, BS,ChE., PMP PMIRGC JaneBetterton.com/ BTSResults.com

OPM The Missing Link

Project Management Basics (Stefan Sobek PMP) Chapter 2: PM in IT-Context

Risk Management How are l l oca i compan es doing today?

Project Time Management

Risk and Opportunity Management - Overview

NYS Forum Project Management Work Group Presents

Course Title: Planning and Managing Agile Projects

Midterm Test Department: Computer Science Instructor: Steve Easterbrook Date and Time: 10:10am, Thursday 1st March, 2012

Continuous Improvement Toolkit. Risk Analysis. Continuous Improvement Toolkit.

Kanban Cadences and Information Flow

M A N A G I N G A M B I G U I T Y A N D U N C E R TA I N T Y

GAHIMSS Chapter. CPHIMS Review Session. Systems Analysis. Stephanie Troncalli, Healthcare IT Strategist Himformatics July 22, 2016

This course will explore how your projects can easily and successfully make the transition to an effective Agile environment.

SESSION 107 Wednesday, November 1, 10:15am - 11:15am Track: People, Culture, and Value

LookingGlass - Project Management Professional Exam Prep (PMP01)

F-PM001 Risk Management Professional Certification

Project Managers Guide to Systems Engineering Measurement for Project Success

Test Management: Leading Your Team To Success 12/10/2011. Test Management: Leading Your Team To Success (extract)

Training and Consulting Programs

Software Project & Risk Management Courses Offered by The Westfall Team

Iasa Engagements enhance Corporate Membership

Five Changes that Project Managers Must Make in an Agile World

Oracle Unified Method (OUM) The OUM Implement Core Workflow The Key to Understanding and Applying OUM. An Oracle White Paper April 2012

Requirement Engineering. L3 The requirement study. Change is constant. Communication problem? People are hard to understand!

Cover Angebot. Agile Innovation Management. How to manage innovation more efficiently and profitably. we show you the way

PMP Exam Preparation Course Project Scope Management

Risk Driver Method Applied to Integrated Cost Schedule Risk Analysis Hulett & Associates, LLC David T. Hulett, Ph.D.

A BRIEF INTRODUCTION TO

L2 The requirement study. Requirement Engineering. Fang Chen

Digitaliseren van risico management


Project Management Professional (PMP) Certification Exam Preparation Program Course Outline with Outcomes

Internal Audit. Providing Assurance Over Project Delivery. Chris Nugent Institute of Internal Audit - 11 March 2014

Sample Exam ISTQB Agile Foundation Questions. Exam Prepared By

nam I BIA Un IVERS ltv OF SCIEnCE AnD TECHnOLOGY

Quantifying Uncertainty in Baseline Projections of CO2 Emissions for South Africa

Information Technology Audit & Cyber Security

Utilizing Design Thinking for Digital Transformation


Project Management Professional (PMP) Exam Prep Course 6 - Project Schedule Management

EXECUTIVE STRATEGIES FOR RISK MANAGEMENT BY STATE DEPARTMENTS OF TRANSPORTATION EXECUTIVE SUMMARY

Project Management Process Groups. PMP Study Group Based on the PMBOK Guide 4 th Edition

All Rights Reserved Best Practices Team, LLC

Transcription:

Project Management Opportunity or Oxymoron? Stacy Munechika, PMP, PMI-ACP PMI Rochester Chapter Professional Development Day May 2017

What makes project outcomes difficult to predict? Survey answers from session attendees in word-cloud format (larger font = more common responses)

The gap in traditional PM? We didn t see that coming! Why didn t we know about that sooner? Why is that end date so hard to predict?

Everyone has a plan, until they get punched in the mouth. - Mike Tyson

Successful delivery of innovative projects is a core business competency Organizations that can delivery innovative & difficult projects have an advantage. Why? Simple projects are too easy to replicate and become commoditized. No long-term competitive advantage. Innovative & difficult projects = more uncertainty Managing uncertainty is key to delivering innovative projects.

Working Definition of Project Uncertainty Project Uncertainty: Gaps in knowledge and awareness that affect our ability to foresee project outcomes. A driver of risk.

Uncertainty Management Uncertainty management is about identifying and managing all the many sources of uncertainty which affects our perceptions of threats and opportunities. Implies exploring the origins of project uncertainty before seeking to manage or compensate for it. Source. Stephen Ward, Chris Chapman, : Transforming project risk management into project uncertainty management International Journal of Project Management, 21, 2003

Embedded Uncertainty in Projects Variability with estimates basis and assumptions Uncertain which outcomes will happen Ambiguous outcomes Information uncertainty Uncertainty in tempo and pace when things will happen Uncertainty in objectives and priorities A byproduct of complexity Source. Stephen Ward, Chris Chapman, : Transforming project risk management into project uncertainty management International Journal of Project Management, 21, 2003

Our Path Forward. Develop a framework for thinking more broadly about project uncertainty and ideas on how to better manage it.

JoHari Window Disclosure/Feedback Model of Self Awareness Known to self Not Known to self Known to others Open Arena Blind Spot Not Known to others Facade Unknown Reference: https://en.wikipedia.org/wiki/johari_window

A Framework for thinking about project uncertainty

Project Team Awareness Unknown Known Awareness & Knowledge Model for Uncertainty Management KNOWLEDGE (known knowns) RISKS (known unknowns) HIDDEN KNOWLEDGE (unknown knowns) UNPREDICTABLE UNCERTAINTY (unknown unknowns) Known Unknown Project Team Knowledge Adapted from: David Cleden, Managing Project Uncertainty, Gower

Quadrant 1: Knowledge (known knowns) You know what to do (or think you know) & plan it out. Compatible with traditional project management methods. Uncertainty is variation around the known (e.g. task duration). Type of Uncertainty Strategies Potential Traps Variation Monitor & Control Monte Carlo simulation Estimation Error & Bias

Cognitive Biases that affect prediction & estimation We have a tendency to be overconfident in our optimistic predictions despite knowing that it took longer in the past. Overconfidence Bias Optimism Bias Planning Fallacy

Planning Fallacy People underestimate the time it will take to complete a future task, despite knowledge that previous tasks have generally taken longer than planned. Roger Buehler

Project Team Awareness Unknown Known Awareness & Knowledge Model for Uncertainty Management KNOWLEDGE (known knowns) RISKS (known unknowns) Quadrant 2 HIDDEN KNOWLEDGE (unknown knowns) UNPREDICTABLE UNCERTAINTY (unknown unknowns) Known Unknown Project Team Knowledge

Quadrant 2: Risks (known unknowns): You know there are some outcomes that have some chance of happening. Risk management involves estimating the probability of occurrence and the impact of the risk should it occur. Risks come from uncertainty, but not all uncertainty can be expressed as risks.

Probability Probability and Impact Matrix 6 Greater than 80% 5 80% Risk A 4 60% 3 40% 2 20% Risk C Risk B 1 Less than 20% 1=Very Low 2=Low 3=Med 4=Med/ High Impact 5=High 6=Very High

Probability Track the level of uncertainty in estimates. Greater than 80% 80% Risk A Risk Probability Impact Likely Optimistic Pessimistic Likely Optimistic Pessimistic 60% 40% A 80% 80% 80% 3 2 5 B 20% 20% 60% 6 6 6 C 20% 20% 40% 2 2 3 20% Risk C Risk B Less than 20% 1=Very Low 2=Low 3=Med 4=Med /High Impact 5=High 6=Very High

Incorporate uncertainty in scenario planning Risk Scenarios Potential Schedule Impact (can use probability vs impact calculation) Optimistic Most Likely Pessimistic Supplier is late with prototype delivery 0 10 days 20 days Sub assembly needs rework 5 20 days 30 days Customer feedback requires redesign 0 15 days 20 days Schedule variation 5 45 days 70 days Aggregated risk scenarios Nominal Schedule Optimistic Most likely Pessimistic Ref: Cledan, Managing Project Uncertainty

Risk Management Tools Requirements management Brainstorming Planning for risk mitigation Critical risk reporting to senior management Quality Control Time-limited action-item lists Prototyping Responsibility assignment Simulation Risk impact assessment Subcontractor management Risk probability assessment Configuration control Reference:, T. Raz, E. Michael, Use and benefit of tools for project risk management International Journal for Project Management, 19, 2001

Which risk management tool do you find most useful? Survey answers from session attendees

Prototyping Responsibility Assignment Simulation Value Contribution of Risk Tools Time-limited action-item lists Quality Control Critical risk reporting to Risk Impact Assessment Subcontractor Management Risk probability assessment Project Performance criteria: Extent /Freq of plan changes Freq. of emergency meetings Agreement in effort estimation Participant satisfaction Customer satisfaction Post-delivery product changes Planning for risk mitigation Brainstorming Configuration control Requirements Management Higher performing project Lower performing project Reference:, T. Raz, E. Michael, Use and benefit of tools for project risk management International Journal for Project Management, 19, 2001

Assumes we can: The Limitations of Traditional Risk Management Methods Conceive the range of outcomes even if we can t predict with certainty which ones will happen. Have the resources and capability to analyze the risks. Produce acceptable estimates for probability and impact. Have the resources to mitigate and track (throughout the project lifecycle). May give us false confidence that all key risks / outcomes have been identified. Stakeholders could react negatively to changes in project situation because risks and outcomes should have been considered.

What if you replace risk with uncertainty?

Project Team Awareness Unknown Known Uncertainty Management Strategy: Increase Awareness KNOWLEDGE (known knowns) RISKS (known unknowns) HIDDEN KNOWLEDGE (unknown knowns) UNPREDICTABLE UNCERTAINTY (unknown unknowns) Quadrant 3 Known Unknown Project Team Knowledge

Quadrant 3: Hidden Knowledge (unknown knowns) The Art of Naming Elephants

Group Dynamics: Risk Workshop vs Risk Interview

Great Questions for Uncovering Hidden Knowledge How might we? And what else? How did we get to our assumptions? What may we be missing? What obstacles can we anticipate if we take this course of action?

Premortem Prospective Hindsight Imagining the event has already happened. 30% Increase in the ability to correctly identify reasons for future outcomes Reference: Gary Klein, Performing a Project Premortem, Harvard Business Review, Sept 2007

Project Team Awareness Unknown Known Uncertainty Management Strategy: Increase Awareness KNOWLEDGE (known knowns) RISKS (known unknowns) HIDDEN KNOWLEDGE (unknown knowns) UNPREDICTABLE UNCERTAINTY (unknown unknowns) Quadrant 4 Known Unknown Project Team Knowledge

Quadrant 4: Unpredictable Uncertainty (Unknown Unknowns) We don t know - we don t know Unk Unk Unpredictable events & Unfathomable outcomes Stuff we didn t bother to find out Black swans and Bolts from the blue

Factors that Increase Unk Unks in Projects

VUCANTO Volatility Complexity Organizational Novelty Uncertainty Pathologies Ambiguity & Culture & Equivocality Technology

Classifying Projects to Evaluate Uncertainty

Project Classification Hard & Soft Framework HARD 0 100 SOFT Clearly defined Physical artifact Only Quantitative No external influences Refinement of single solution Low stakeholder interactions Goal Clarity Deliverable Success Measures External Susceptibility Number of Solutions Stakeholder Interactions Highly Ambiguous Abstract concept (e.g. Organizational Change) Only Qualitative High external influences Exploration of many alternatives High stakeholder participation Reference: Crawford & Pollack, Hard and soft projects: a framework for analysis International Journal of Project Management, 22, 2004

Strategies for project uncertainty Increasing Uncertainty of Objectives and Solutions Monitor & Control Risk countermeasures Plan iteratively Solution searching Buffer management Outcome contingencies Refine targets Parallel paths & multiple explorations Rapid prototyping & fast learning loops

Adapting PM to level of project uncertainty Increasing Uncertainty of Objectives and Solutions Traditional Project Management (e.g. waterfall) Iterative PM Methodologies (e.g. Agile) Extreme PM Methodologies (e.g. Emertxe) Extreme: Project goal is high-level vision. Search for solutions to meet a business value Rapid iteration. Emertxe: Solution in search of business value (R&D)

PM Methodology & Confronting Uncertainty Traditional Project Management (e.g. waterfall) Planned Path Suppress Project Objectives Iterative PM Methodologies (e.g. Agile) Adapt Project Objectives Adapt Project Objectives Extreme PM Methodologies (e.g. Emertxe) Initial Path Reorient Initial Project Objectives New Project Objectives

Be Alert for early warning signs of project uncertainty

Early Warning Signs of Project Failure 20% 100% Early Warning Sign occurs within first 20% of the project

What warning signs indicate high uncertainty or risk of failure? Survey answers from session attendees in word-cloud format (larger font = more common responses)

Dominant Early Warning Signs of Project Failure (Keppelman et al) People-Related 1. Lack of top management support 2. Weak project manager (uh oh) 3. No stakeholder involvement and/or participation 4. Weak commitment of project team 5. Team members lack required knowledge or skills 6. Subject matter experts are overscheduled Reference: Kappelman, McKeeman, Zhang, Early warning signs of IT project failure: the dominant dozen, Information Systems Management, Fall 2006

Dominant Early Warning Signs of Project Failure (Keppelman et al) Process-Related 1. Lack of documented requirements and/or success criteria 2. No change control process (change management) 3. Ineffective schedule planning and/or management 4. Communication breakdown among stakeholders 5. Resources assigned to a higher priority project 6. No business case for the project Reference: Kappelman, McKeeman, Zhang, Early warning signs of IT project failure: the dominant dozen, Information Systems Management, Fall 2006

Predicted Completion Date Track Your Predictions! Establish a process to capture the results of past predictions as a gauge of latent uncertainty Example: Silverberg Chart Checking the predictability of your predictions Yikes! No progress Large schedule slip but with predictable completion Completion Line Predicted = prediction Well behaved project with predictable completion date Date of the Prediction Predicting Project Completion, Eric Silverberg,Research-Technology Management, Vol. 34, No. 3, May/June 1991

In Summary

Project Team Awareness Unknown Known Uncertainty Management Strategies & Tools Be aware of bias in estimates. Manage variation Name the elephant Better Inquiry 1:1 Risk Interviews Premortem KNOWLEDGE (known knowns) HIDDEN KNOWLEDGE (unknown knowns) Known Increase Awareness RISKS (known unknowns) UNPREDICTABLE UNCERTAINTY (unknown unknowns) Unknown Project Team Knowledge Recognize uncertainties in estimates Know limitations of risk management Use Risk Management tools throughout project lifecycle VUCANTO Hard & Soft classification Adapting PM methods to uncertainty profile Early Warning Signs Track predictions

Final thoughts Managing project uncertainty is necessary for difficult projects (the ones your organization should be doing!) Use the Knowledge- Awareness model as a framework for managing project uncertainty. Recognize sources of uncertainty and make it more transparent in the project management lifecycle Strive for an open and alert culture with no elephants in the room and change is not viewed negatively

Thank You! smunechi@gmail.com www.linkedin.com/in/stacymunechika