CHAPTER 2B - PHASE I, INITIAL ROADWAY INVESTIGATION & PRELIMINARY FIELD INSPECTION

Similar documents
LOCATION AND DESIGN DIVISION

Table of Contents Local Agency Guidelines Section B August 2011

Page 1D-1 Revised language to link from Project Management Manual to Project Management Online Guide.

ALTERNATIVE PROJECT DELIVERY DIVISION

CHAPTER 3 SCOPE SUMMARY

CHAPTER 13. New January 1, 2013 SUE. Subsurface Utility Engineering. Designation and Location. Chapter Contents

TABLE OF CONTENTS CHAPTER 2D - PLAN DESIGN. SECTION 2D-1 PROJECT REVIEW General... 2D-1

Land Use Regulations Update. Robert W. Hofrichter Assistant Administrator, Maintenance Division December 3, 2008

THE COMMONWEALTH OF MASSACHUSETTS NON-NHS BRIDGE R&R POLICY

Work Breakdown Structure Element Dictionary Preliminary Engineering

LOCATION AND DESIGN DIVISION

5.0 PRELIMINARY ENVIRONMENTAL REVIEW

Chapter DESIGN EXCEPTION PROCESS

EXHIBIT A SCOPE OF SERVICES FOR DISTRICTWIDE CONSULTING ENGINEERNG SERVICES STRUCTURES DESIGN

TRAFFIC ENGINEERING DIVISION

LOCATION AND DESIGN DIVISION

VIRGINIA DEPARTMENT OF TRANSPORTATION Documents Required to be Signed and Sealed

STRUCTURE AND BRIDGE DIVISION

EXHIBIT A SCOPE OF SERVICES FOR. FINANCIAL PROJECT ID(S). Various Projects DISTRICT 2 VARIOUS COUNTIES

Highway / Utility Guide

SCOPE 1.0 General Requirements

100 Design Controls and Exceptions

APPENDIX B. Public Works and Development Engineering Services Division Guidelines for Traffic Impact Studies

Request for Proposals. Hillsdale Pedestrian/Bicyclist Bridge Design

Final Design Guideline

DRAFT SCOPE 1.0 General Requirements

EXHIBIT A SCOPE OF SERVICES FOR FINANCIAL PROJECT ID TRANSPORTATION SYSTEM MANAGEMENT & OPERATIONS (TSM&O) GENERAL CONSULTANT SERVICES

Research Initiatives at TxDOT Related to Utilities and Right of Way

EXHIBIT "A" County Road 54 (Wesley Chapel Boulevard) (from North of Magnolia Boulevard to Oakley Boulevard) Work Order No. C-1640.

Geometric Design: Past, Present, and Future

TRANSPORTATION SYSTEM JURISDICTION AND NUMBERING

Chapter 18. Quality Assurance and Quality Control

Appendix. Sample EA/EIS Scope of Work

Updated Traffic Impact Analysis Regulations Administrative Guidelines

Standard Performance Attributes for Transportation Projects

Design-Builder Peformance Evaluation (DBPE)

Article 16 Traffic Impact Analysis

Review of Construction Costs and Time Schedules for Virginia Highway Projects

LOCATION HYDRAULIC REPORT

Peterborough County Road Safety Audit Guideline Pilot

Chapter 1. General Design Information. Section 1.02 Structure Selection and Geometry. Introduction

LOCATION AND DESIGN DIVISION

I-74 Final Design Request For Proposal

TRAFFIC STUDY GUIDELINES

ROADWAY DESIGN AND CONSTRUCTION STANDARDS

FOR INTERSTATE 81 AND ROUTE 37 INTERCHANGE FREDERICK COUNTY, VIRGINIA MILEPOST 310

100 Introduction Functional Classification Traffic Data Terrain & Locale Design & Legal Speed...

Any discussions or marketing activities related to this specific project.

Exhibit A Mn/DOT Contract No

STRUCTURE AND BRIDGE DIVISION

City of Menifee. Public Works Department. Traffic Impact Analysis Guidelines

SECTION 10 UTILITIES

Project Planning and Development Process

RESOLUTION NO

Attachment No. 1 Council Report Attachment

ADMINISTRATIVE DIRECTIVE #CS-04

I-64 Capacity Improvements Segment III RFQ Information Meeting

Traffic Impact Analysis Guidelines. Town of Queen Creek

Chapter 2 Transportation Element Goals, Objectives and Policies

LOCATION AND DESIGN DIVISION

Interstate 66 Tier 1 Environmental Impact Statement Public Hearing

PARISH OF ASCENSION OFFICE OF PLANNING AND DEVELOPMENT BUILDING DEPARTMENT

Section I - Introduction

NEPA THE NATIONAL ENVIRONMENTAL PROTECTION ACT CEQA THE CALIFORNIA ENVIRONMENTAL QUALITY ACT

Gloucester Parkway Extension RFQ Information Meeting

FEDERAL HIGHWAY ADMINISTRATION RECORD OF DECISION FOR THE LYNNWOOD LINK EXTENSION

1000 Performance Based Project Development (PBPD)

CHAPTER 4 GRADE SEPARATIONS AND INTERCHANGES

Appendix D Functional Classification Criteria and Characteristics, and MnDOT Access Guidance

CHAPTER SURFACE MINING AND RECLAMATION PLAN REGULATIONS

WELCOME IL 47. Community Advisory Group Meeting #5 Waubonsee Community College Wednesday, May 31, 2017

6 93 Corridor TUNNEL CROSS SECTION 42.0' 24.0' WITH 21.0' WITHOUT 1.5' 6.0' 12.0' 12.0' 6.0' 4.0' 0.5' CLEARANCE ENVELOPE (36' W x 16.

I-95 Southbound CD Lanes Rappahannock River Crossing Stafford County/ City of Fredericksburg, Virginia. RFQ Information Meeting - November 9, 2016

ASSIGNMENT OF ACCESS MANAGEMENT CLASSIFICATIONS TO THE STATE HIGHWAY SYSTEM

Appendix D: Functional Classification Criteria and Characteristics, and MnDOT Access Guidance

VDOT Land Use Overview. Brad Shelton, AICP Transportation and Mobility Planning Division June 2015

Arizona Association of County Engineers New Rules for Categorical Exclusions for FHWA Projects

STATEMENT OF PRINCIPLE

SR 50 PD&E Study

Statewide Acceleration Transformation (SWAT)

MEDIAN OPENINGS AND ACCESS MANAGEMENT

DRAFT. SR-60 7 th Avenue Intersection Control Evaluation (ICE) I-605 Corridor Improvement Project (CIP) I-605/SR-60 EA# 3101U0

EXHIBIT A. SCOPE OF SERVICES District-Wide Traffic Operations/Safety Studies (Work Group 6.1)

I-35/I-80/Iowa 141 Interchange IJR and NEPA A Practical Approach to Resolving a Decades-Old Traffic Operations Challenge

Whittier Bridge I-95 Improvement Project Newburyport/Amesbury/Salisbury

REQUEST FOR PROPOSAL (RFP) AS NEEDED ENGINEERING DESIGN SERVICES FOR 2019, 2020 & 2021

EXHIBIT "A" SCOPE OF SERVICES FOR DISTRICT 7 AREAWIDE LIGHTING DATABASE & ASSESSMENT CONTINUING SERVICES FINANCIAL PROJECT NO.

Updated Traffic Impact Analysis Regulations Administrative Guidelines

TRANSPORTATION IMPACT ANALYSISGUIDELINES

PARISH OF ASCENSION OFFICE OF PLANNING AND DEVELOPMENT BUILDING DEPARTMENT

TRAFFIC ENGINEERING DIVISION INSTRUCTIONAL & INFORMATIONAL MEMORANDUM

Preliminary Draft REGIONAL TRANSPORTATION OPERATIONS PLAN. Chapter III

EXISTING ROADWAY CONDITION ASSESSMENT REPORT (ERCAR) SAMPLE OUTLINE

CID (Campus Infrastructure Development) Roadway Improvements Advance Planning/Design Services Code Item 301A

DISTRICT OF NORTH VANCOUVER GUIDELINES FOR THE DEVELOPMENT OF CONSTRUCTION TRAFFIC MANAGEMENT PLANS

Traffic Impact Study Guidelines. City of Guelph

TOWN OF MOORESVILLE TRANSPORTATION IMPACT ANALYSIS PROCEDURES MANUAL TOWN OF MOORESVILLE, NORTH CAROLINA

Draft Noise Abatement Guidelines

VIRGINIA DEPARTMENT OF TRANSPORTATION MATERIALS DIVISION MEMORANDUM. Charles A. Babish, PE State Materials Engineer Approved:

Transcription:

CHAPTER 2B - PHASE I, INITIAL ROADWAY INVESTIGATION & PRELIMINARY FIELD INSPECTION SECTION 2B 1 - GROUND SURVEYS Survey Authorization... 2B-1 Interstate... 2B-1 Principal / Minor Arterial... 2B-1 Urban... 2B-1 Secondary (Arterial-Collector-Local Roads)... 2B-2 Data Required... 2B-2 Complete Surveys... 2B-2 SECTION 2B 2 - COORDINATION WITH OTHER DIVISIONS AND AGENCIES Request For Soils Data... 2B-3 Request For Hydraulic Evaluation... 2B-3 Coordination With Environmental Division... 2B-3 Coordination With Landscape Architect... 2B-3 Coordination With Other State Agencies... 2B-3 Occupiable Space / Buildings On Roadway Projects... 2B-4 Permit Requirements... 2B-4 SECTION 2B 3 - DETERMINATION OF ROADWAY DESIGN Operational / Capacity Analysis... 2B-6 Safety Analysis... 2B-6 Interchange Design... 2B-7 Refining Horizontal Alignment... 2B-7 Refining Vertical Alignment... 2B-8 Permit Determination... 2B-8 Coordination With Other Divisions and Agencies... 2B-8 SECTION 2B 4 - REQUEST FOR ENVIRONMENTAL EVALUATION Request For Appropriate Environmental Document... 2B-9 Data To Be Submitted... 2B-9 SECTION 2B 5 - COST ESTIMATES Determining Preliminary Engineering and Construction Costs... 2B-10 Request For Cost Estimates From Others... 2B-10 Cost Estimates... 2B-10 SECTION 2B 6 - CONSTRUCTABILITY QUALITY REVIEW... 2B-11

SECTION 2B 7 - THE PRELIMINARY FIELD INSPECTION Purpose... 2B-12 Preliminary Field Inspection... 2B-12 Availability of Plans... 2B-12 Items To Be Reviewed... 2B-12 Reviewing The Proposed Method of Development... 2B-13 Preparation of Inspection Report... 2B-13 Incorporating Changes Into Plans... 2B-13 Preparation of Project Cost Estimate and Report... 2B-13 SECTION 2B 8 - VALUE ENGINEERING Value Engineering (VE)... 2B-14

2B-1 CHAPTER 2B - PHASE I, INITIAL ROADWAY INVESTIGATION & PRELIMINARY FIELD INSPECTION SECTION 2B 1 - GROUND SURVEYS SURVEY AUTHORIZATION See PM-100 Scoping Report Surveys are performed in accordance with the current VDOT Survey Manual. The authorization procedure for each roadway classification is described in this section. Above and Underground utilities are to be designated as instructed in VDOT Survey Manual, Chapter 13. INTERSTATE Interstate projects are authorized for survey after Location Approval has been given by the Commonwealth Transportation Board and the Federal Highway Administration and in accordance with tentative construction schedules. PRINCIPAL / MINOR ARTERIAL Principal and Minor Arterial System projects are authorized for surveys in accordance with established construction or planning schedules. Projects with Federal funding for preliminary engineering require prior approval by the Federal Highway Administration. URBAN Urban projects are authorized for survey upon receipt of Form PD-3 from the Urban Program Manager / Project Manager. Projects with Federal funding for preliminary engineering require prior approval by the Federal Highway Administration. Rev. 7/11

2B-2 SECONDARY (ARTERIAL-COLLECTOR-LOCAL ROADS) Secondary project surveys are requested by the District Administrator in accordance with planning schedules, particularly in the Secondary System Contract Advertisement Schedule. DATA REQUIRED In order to assist the survey party in establishing proper horizontal and vertical controls, certain data must accompany the survey authorization. This data should include, but is not limited to: (1) Prints of adjacent projects in the planning or construction stage (2) Existing road plans (3) National Geodetic Survey controls, both horizontal and vertical (4) Prints of the proposed alignment and grade (if available) (5) U.S. Geological Survey topographic quadrangle maps of the area and (6) Photographs of the area (7) Approved PM-100 COMPLETE SURVEYS Projects designed in the Districts: When the field work has been completed by the Survey party, the District Survey Party Engineer transmits the electronic data by memorandum to the District Design Unit for the plotting of horizontal and vertical data. The Central Office shall be notified that the survey is complete. Projects designed in the Central Office, or by Consultants: When the field work has been completed by the Survey Party, the electronic data is to be submitted to the Central Office by memorandum. When the designer receives the survey, it should be checked for utility designations. If none are shown, a request should be made as outlined in VDOT Survey Manual, Chapter 13. Bridge site plans and data sheets will be plotted by the survey party and transmitted to the Central Office by the District Survey Party Engineer, with the exception of Secondary Projects, which are to be sent to the District Structure and Bridge Division. Rev. 1/09

2B-3 SECTION 2B 2 - COORDINATION WITH OTHER DIVISIONS AND AGENCIES REQUEST FOR SOILS DATA Soils data is to be requested on Form LD-252. A copy of the tentative alignment and grades is to accompany this form to the Materials Division. It should be noted that this is a very preliminary soils evaluation and is not to be confused with the more detailed soils report furnished at a later date. REQUEST FOR HYDRAULIC EVALUATION In projecting alternates, consideration must be given to hydrology, hydraulics, and the potential effects a given projection will have on flood prone areas, wetlands, navigable waters and water quality. Consequently, the alternates being considered are to be reviewed by the Hydraulics Section during this stage of project development. COORDINATION WITH ENVIRONMENTAL DIVISION Due to the increased emphasis being placed on the effects of a proposed highway on the environment, it is essential that this Division be contacted in the early stages of development on all projects. A memorandum is to be written stating that preliminary development is underway and requesting their evaluation of the corridors under consideration. A copy of these study corridors is to accompany this memorandum. See Appendix C, Section C-2-NOISE ABATEMENT and Section C-4-WATER RELATED PERMITS for further instructions on coordination with the Environmental Division. COORDINATION WITH LANDSCAPE ARCHITECT See IIM-LD-253 Landscape Architecture Program as well Appendix B(1) (Streetscape and Landscape and Landscape Considerations). * COORDINATION WITH OTHER STATE AGENCIES Project Early Notification will involve all applicable state environmental resource agencies in the early stages of project development. If, however, a project has not been included in the Project Early Notification Process, requests for review with environmental resource agencies such as Historic Landmarks, State Historian, Commission of Game and Inland Fisheries, etc., are to be coordinated through the Environmental Division. Each project has its own individual characteristics and should be reviewed carefully at an early stage to determine if a possible conflict may arise. * Rev. 7/17

2B-4 OCCUPIABLE SPACE / BUILDINGS ON ROADWAY PROJECTS PERMIT REQUIREMENTS POLICY * It should be determined as early as possible in the project development process if the project will involve the construction of a building or other occupiable space, or any work on an existing building or occupiable space. The Project Manager shall contact the Administrative Services Division (ASD), Capital Outlay Section as soon as it is determined that any building or occupiable space will be involved. Any work on a building or occupiable space on a project within the state right of way must comply with the Virginia Uniform Statewide Building Code. The Administrative Services Division (ASD), Capital Outlay Section shall request any required Building Permits from the Bureau of Capital Outlay Management (BCOM). For assistance with permits or document requirements, consult the Administrative Services Division (ASD), Capital Outlay Section. DEFINITIONS Occupiable Space: Building: o A room or enclosed space designed for human occupancy in which individuals congregate for amusement, educational or similar purposes or in which occupants are engaged at labor, and which equipped with means of egress and light and ventilation facilities meeting the requirements of this code. o A combination of materials, whether portable or fixed, having a roof to form a structure for the use or occupancy by persons, or property. * Added 7/16

2B-5 EXAMPLES * These instructions include new construction, renovations, additions, upgrades, replacement of systems, and re-roofing. Some examples include: - Pump Stations - Bus Shelters - Tunnel Portals - Vent Buildings - Communication/Data Shelters - Picnic Shelters - Covered Pedestrian Bridges - Ferry Buildings - Storage Buildings - Inspection/Security/Booths - Toll Booths * Added 7/16

2B-6 SECTION 2B 3 - DETERMINATION OF ROADWAY DESIGN OPERATIONAL / CAPACITY ANALYSIS A review of the volume and types of traffic and the physical characteristics of the roadway that includes capacity analysis or traffic flow simulation and considers potential roadway or traffic control improvement to improve traffic flow through the intersection(s) and along other sections of the roadway. * Traffic Data must now be analyzed in relation to the pre-determined Functional Classification. The basic number of thru lanes required in order for the mainline to operate at a satisfactory level of service shall be determined by capacity analyses. Capacities of connecting and crossing roadways shall also be determined, taking into consideration plans for future improvements to these facilities. Where at-grade intersections are proposed, a capacity analysis shall be made to determine whether or not the intersection will operate at a satisfactory level of service. If the analysis indicates an unsatisfactory service level, an interchange should be considered. When interchanges are proposed or are being considered, a capacity analysis should be utilized to determine the type of interchange required. Peak hour traffic projection to the design year shall be used for all capacity analyses. Reference materials available at this time to assist in capacity analysis include: 1. Highway Capacity Manual 2. Design of Urban Streets 3. Highway Capacity Software SAFETY ANALYSIS A review of crash data and the physical characteristics of the roadway that includes an evaluation of potential engineering countermeasures (physical roadway improvements and/or use of traffic control devices) to reduce the potential for crashes at intersections and along other sections of the roadway. * Rev. 1/12

2B-7 INTERCHANGE DESIGN Because of the wide variety of site conditions, traffic volumes, highway types and interchange layouts, the warrants which justify an interchange may differ at each location. The six major factors to be considered are: 1. Control of access 2. Elimination of bottlenecks or spot congestion 3. Elimination of hazards 4. Site topography 5. Road user benefits 6. Traffic volumes Other than on a freeway, the inability to provide the necessary capacity with an at-grade intersection is a common warrant for an interchange. More detailed warrants and general types of interchanges may be found in Chapter X "Grade Separations and Interchanges" of AASHTO's A Policy on Geometric Design of Highways and Streets. REFINING HORIZONTAL ALIGNMENT Horizontal alignment is to be reviewed for possible revisions due to information received under Section 2B-1- GROUND SURVEY such as: obvious areas of unsuitable material and/or rock, major utility facility relocations and environmental considerations (such as splitting communities, splitting watersheds, conflicts with National or State Forests and Parks, historical property, archaeological sites, recreational areas, sites affected by noise beyond acceptable limits, etc.). The 2009 General Assembly passed Chapter 120 (HB 2577), which amends the Code of Virginia by adding in Article 15 of Chapter 1 of Title 33.2 a section numbered 33.2-276, relating to highway noise abatement. The law provides that, for any highway construction or improvement project that includes, or may include, requirements for the mitigation of traffic noise impacts, VDOT should consider, but is not required to implement, noise reducing design techniques, such as shifting the horizontal alignment away from the noise sensitive receptors. Horizontal alignment must remain within acceptable limits as prescribed in the Geometric Design Standards (See Appendix A, Section A-1and Chapter 2A, Section 2A-6 * ) unless an authorized exception is made by the State Location and Design Engineer and, if applicable, the Federal Highway Administration. * Rev. 1/17

2B-8 REFINING VERTICAL ALIGNMENT Vertical alignment is to be reviewed for possible revisions resulting from data received under Section 2B-1- GROUND SURVEY such as: soil data (compaction factors, etc.) indicating the need to raise or lower grades for earthwork balances, major utility facilities, hydraulic requirements and considerations such as raising grades to obtain adequate cover for drainage structures and vertical clearances for various grade separations. As mentioned above, Chapter 120 of the 2009 Acts of Assembly provides that, for any highway construction or improvement project that includes, or may include the requirements for the mitigation of traffic noise impacts, VDOT should consider, but is not required to implement, noise reducing design, such as placing the roadway in a cut section. Vertical alignment must remain within acceptable limits as prescribed in the Geometric Design Standards (See Appendix A, Section A-1 and Chapter 2A, Section 2A-6 * ) unless an authorized exception is approved by the State Location and Design Engineer and, if applicable, the Federal Highway Administration. Also see IIM-LD-227 for Design Exceptions. PERMIT DETERMINATION The designer shall submit Form LD-252 to the Environmental Engineer with appropriate data. The Environmental Division will review the project and determine what type of water related permits may be required. (See Appendix C, Section C-4-WATER RELATED PERMITS). COORDINATION WITH OTHER DIVISIONS AND AGENCIES After refinements as outlined in this section are made, the electronic files are to be placed in Falcon to allow other divisions and agencies that have been involved up to this point access to the revised plans. For example, furnishing the electronic files allows the Environmental Division to resolve as many problems as possible at this stage (archaeological sites, etc.) and the Local Assistance Division, on applicable projects, to coordinate with city or town representatives. * Rev. 1/17

2B-9 SECTION 2B 4 - REQUEST FOR ENVIRONMENTAL EVALUATION REQUEST FOR APPROPRIATE ENVIRONMENTAL DOCUMENT When preliminary plans are complete, the Environmental Division should be requested (Form LD-252) to prepare an appropriate environmental document. This memorandum should contain a brief description of the corridor or corridors to be presented at the public hearing and the approximate date of the public hearing. Copies of this memorandum should go to the District * Engineer/Administrator, District Construction Engineer and other affected divisions within the Department. This is the point at which an official environmental document is requested. The Environmental Division is involved in environmental evaluations earlier in the location studies (See Section 2A-1-PROJECT INITIATION). DATA TO BE SUBMITTED Electronic files of the corridor/s under consideration and copies of pertinent correspondence for each corridor should accompany the request for the preparation of an environmental document. Costs will be figured after the request, and furnished prior to the completion of the document. In addition, it is desirable that the designer and the Environmental Team leader assigned to the project meet in order to review the data submitted and assure a complete understanding of the various aspects of the project. Contact should also be made with the Policy and Procedure Section to discuss visual aids, statements, brochures and a public involvement program. Traffic data is requested from the Transportation and Mobility Planning Division by Environmental Division. * Rev. 7/15

2B-10 SECTION 2B 5 - COST ESTIMATES DETERMINING PRELIMINARY ENGINEERING AND CONSTRUCTION COSTS At each milestone before Field Inspection (FI) in the project development process, the Project Cost Estimating System (PCES) is to be used to generate an estimate for construction and preliminary engineering. Project cost estimates at Field Inspection Stage should be based on quantities and run through Trns.port, then uploaded to PCES. REQUEST FOR COST ESTIMATES FROM OTHERS Right of way, utility, relocation advisory assistance, and effect on the local tax base estimates and reports are to be requested on PM-104 or by memorandum, depending on the situation. This request is to contain the type access anticipated, a summary of the breakdown required and other information deemed important. Three copies of the proposed method/methods of development are to accompany all requests for R/W information. Request for cost estimates for items such as traffic sign illumination, signals, bridges, etc., required from other divisions, are to be requested on PM-104 or by memorandum. A copy of the proposed method or methods, of development is to accompany this request, if available. The Local Assistance Division makes all contacts with municipalities in urban funded projects. COST ESTIMATES Cost estimates for Preliminary Engineering (PE), Right of Way (R/W) and Construction (Const.) are to be prepared on all plans of development necessary to advance to Preliminary Field Inspection stage. The estimates are to be entered into the PCES system. Rev. 1/09

2B-11 SECTION 2B 6 - CONSTRUCTABILITY QUALITY REVIEW For Project Development Constructability Review Guidelines See Appendix E in the Road Design Manual. Rev. 7/11

2B-12 SECTION 2B 7 - THE PRELIMINARY FIELD INSPECTION PURPOSE Preliminary Field Inspections (where necessary) are held to obtain consensus from the District Offices, Municipalities and other affected agencies and Divisions represented concerning items of major importance such as the location or the method of development, median widths, minimum right of way width, typical section geometrics, horizontal and vertical controls, hydrologic and environmental effects, right of way impacts, sight distances, bridges, utilities, need for bicycle facility, etc. It is not intended that minor items, such as exact pipe locations, exact balance of quantities, turning radii, etc., be reviewed and discussed. PRELIMINARY FIELD INSPECTION After the proposed method of development has been completed the Project Manager, or a representative, is requested to schedule the Preliminary Field Inspection. On Local Assistance Division projects, the Local Assistance Division makes this request, after being advised that preparations for the review have been completed. The Preliminary Field Inspection is to be scheduled far enough in advance to allow for proper distribution and review of the prints. The following notes are to be added to all plan and profile sheets including the title and detail sheets; PRELIMINARY F. I. PLANS and THESE PLANS ARE UNFINISHED AND UNAPPROVED AND ARE NOT TO BE USED FOR ANY TYPE OF CONSTRUCTION OR THE ACQUISITION OF RIGHT OF WAY. AVAILABILITY OF PLANS The availability of plans is to be made in accordance with instructions contained in PM- 105. A notice of the availability of the plans should be made two weeks in advance of the Preliminary Field Inspection. ITEMS TO BE REVIEWED The proposed scheme of development is to be reviewed in its entirety, starting with the typical section. Items listed above, under PURPOSE, should be discussed, in addition to any other significant items relative to the project. Questions, comments, and recommendations from other divisions are to be considered and discussed. Certain items, such as entrance locations on urban projects, may require a separate review at a later date by appropriate personnel. Deleted Information * * Rev. 7/15

2B-13 REVIEWING THE PROPOSED METHOD OF DEVELOPMENT All Preliminary Field Inspections are to be conducted by the Project Manager, or a representative, who may request that the Engineer who prepared the scheme of development make the presentation. On Urban projects, the Project Manager or the Engineer who prepared the method of development and/or a representative from the Local Assistance Division may make the presentation. PREPARATION OF INSPECTION REPORT A report to the Project Manager, or from each discipline involved, is to be written immediately after the Preliminary Field Inspection outlining items discussed. A similar report is generally received from the District * Engineer/Administrator. Those disagreeing with the conclusions reached at the PFI may also file reports outlining their disagreement. INCORPORATING CHANGES INTO PLANS When sufficient time has elapsed to allow those who wish to file a report concerning the Preliminary Field Inspection, the recommendations agreed upon are to be incorporated into the plans. If a difference of opinion exists, the State Location and Design Engineer is to be consulted for a decision. On Urban Projects, the Local Assistance Division Director is to be consulted also. PREPARATION OF PROJECT COST ESTIMATE AND REPORT Construction cost estimates are received from other sections as noted in Section 2B-5- REQUEST FOR COST ESTIMATES FROM OTHERS. Right of Way and Utility Estimates are then added to the construction estimate to complete the estimate of project costs. These costs are placed in the Project Cost Estimating System. * Rev. 7/15

2B-14 SECTION 2B 8 - VALUE ENGINEERING VALUE ENGINEERING (VE) Value Engineering is defined as the systematic application of recognized analysis techniques by a multi-disciplined team that: - Identifies the function of a product or service. - Establishes a worth for that function. - Generates alternatives through the use of creative thinking. - Provides the necessary functions at the lowest overall cost. - Develops recommendations as a result of the job plan followed during a review. Value Engineering is required on any project regardless of highway classification with a total construction cost of more than $5 million. Upon receipt of the Initial Field Review and Scoping Report, the Value Engineering Section of the Construction Division will review and submit the project to the Value Engineering Advisory Committee for their consideration as a VE review candidate. The Value Engineering Section will assemble the required review team and conduct the review in accordance with Project Development Process scheduling. On major/complex projects a second study may be conducted. Prior to the review, the VE coordinator will send a letter to the Project Manager outlining the materials necessary for the review. The Value Engineering Team shall review the project to determine if any significant savings cost avoidance and/or quality improvements can be achieved by providing the required service or necessary function at the lowest overall cost. In all instances, the required service or necessary function will be achieved at the lowest possible life-cycle cost consistent with requirements for performance, maintenance, safety, and aesthetics. The analysis is to be performed promptly by the Team and is to provide the appropriate District Engineer * /Administrator and appropriate Assistant State L&D Engineer, with the team's recommendations. * Rev. 7/15

2B-15 The Chief Engineer will review the Team's recommendations along with those from the District * Engineer/Administrator and the Division Engineer/Administrators and determine the implementation potential of the Value Engineering proposals. The Project Manager will verify that accepted VE recommendations have been incorporated into the project by initialing the accepted recommendation on a copy of the Chief Engineer's Response Letter/Project Summary Information Form and forward it to the VE Regional Coordinator. Any savings should be noted on Form PM-131 (Final Scoping Certification). * Rev. 7/15