Q&A. (For SOLAS VGM) Q4: How to obtain the VGM? A: 1. Weighing the packed container using calibrated and certified equipment

Similar documents
Safety of Life at Sea Convention (SOLAS) Verified Gross Mass (VGM) ~ Frequently Asked Questions ~ As of 27 th May 2016

Verified Gross Mass (VGM) in HMM Process. 1 st FAQ. Updated on May 31, Customer Advisory. Continue to next page.. 1 of 8

MOL Liner Ltd. Guidelines for Improving Safety and Implementing the SOLAS Container Weight Verification Requirements

1. Principle of Solas + responsibility SOLAS: Safety Of Life At Sea.

SOLAS Verified Gross Mass (VGM) Requirement. Version 2. Check on maerskline.com for the latest version of this document

Implementation guidelines for Solas Amendment on Container Weighing

OCEMA Recommended Best Practice for the Acceptance and Transmission of Verified Gross Mass for U.S. Export Cargoes. June 28, 2016

SOLAS VGM UPDATE. June 22, 2016 Page 1 of 8. organizations involved. 1. IMO is a specialized agency of the United Nations

FAQs - New SOLAS regulation

How to meet the SOLAS Container Weight Verification Requirements

DHL GLOBAL FORWARDING

FAQs - New SOLAS regulation

Verified Gross Mass (VGM) Shippers Guide

Verified Gross Mass (VERMAS)

SOLAS Regulation 2 Verified Gross Mass

SOLAS VGM FAQs Frequently asked questions about the new verified gross mass requirement from the Safety of Life at Sea convention

Transnet IMO, SOLAS VGM Workshop

OVERLOAD. ship instability, personal injury, incorrect vessel stowage supply chain delay, higher operating costs

SOLAS. Verified Gross Mass Shipper Guide. nagel.com

MARITIME AUTHORITY OF JAMAICA. DRAFT Guidelines on the Verification of Gross Mass of a Packed Export Container

VERIFIED GROSS MASS (FACT) S & FAQS

SOLAS Chapter VI / 2. Verified Gross Mass of loaded shipping containers A broker s guide. RSA Marine Risk Management - June 2016

Transnet Port Terminals PRE-ADVISE GUIDE FOR REGISTERED NAVIS CUSTOMERS SOLAS VERIFIED GROSS MASS EDITION JULY 2016

Global CS Team / HMM Updated on February 5, National preparation for Verified Gross Mass in HMM Process

Click to edit Master title style

Manzanillo International Terminal 2016

SOLAS and the VGM. Canadian International Freight Forwarders Association. Montreal May 3 Toronto May 6

Question and Answers

Weight Verification Amendments to SOLAS Chapter VI

COMMENTS. AgTC Position Paper: Safety of Life at Sea (SOLAS) Container Weight Documentation

CONTAINER WEIGHT VERIFICATION AN INTRODUCTION. or put more simply.. where are we now and where do we need to go?

When was the new regulation enforced? Who is affected by the new scheme?

SOLAS Amendment: Container Mass Verification. TPT Durban 3rd June 2016

IMO container weighing rules A first evaluation. Jeroen de Haas Managing Director BMT Surveys

DB Schenker SOLAS VGM Guide. SOLAS VERIFIED GROSS MASS (VGM) Regulation effective 1 July 2016

VERIFIED GROSS MASS (VGM) REQUIREMENTS DURING PSC INSPECTIONS

How to Collaborate with Multiple Parties to Collect the VGM Alan Yip CargoSmart Limited

IMO SOLAS CONTAINER WEIGHT VERIFICATION

Container Weight Verification

South African Maritime Safety Authority

RESOLUTION MSC.380(94) (adopted on 21 November 2014) AMENDMENTS TO THE INTERNATIONAL CONVENTION FOR THE SAFETY OF LIFE AT SEA (SOLAS), 1974, AS

Overview prepared for The VGM Experience Meeting Hamburg, 6 October

South African Maritime Safety Authority

Rohan Masakorala Shippers Academy Colombo Presentation Copyright SAC

IMO DEVELOPMENTS ON MEASURES TO PREVENT THE LOSS OF CONTAINERS

Shipment 1.5. Training Material DAKOSY GE 5.8 Release Date 2018/10. Mattentwiete Hamburg

DRAFT. Accuracy standards for weighing equipment approved by AMSA

New Draft MO42 (Carriage, stowage and securing of cargoes and containers) open for consultation until 30 April 2016

Process of Verified Gross Mass (VGM) Receiving & Reporting at PICT

Rous Head Developments and Mandatory Verified Weighing of Export Containers. CBFCA Conference - May 2016

OEC TERMS & CONDITIONS

Technical Circular. No.: 018/2015 Date: 10 th July 2015

MSC MEDITERRANEAN SHIPPING COMPANY S.A., GENEVA PAGE 1 OF 7

2. Regulation 2 of SOLAS Chapter VI now reads as follows: Existing provisions: Quote

VERIFIED GROSS MASS INDUSTRY FAQS

PD Teesport Update 6th June 2016 Solas Regulations Container Verified Gross Mass (VGM)

Supply Chain Safety Responsibility

PD Teesport Update 6th June 2016 Solas Regulations Container Verified Gross Mass (VGM)

MGN 534 (M+F) MARINE GUIDANCE NOTE

MYMSC A SIMPLE GUIDE

North American Lear Logistics Requirements. Supplier Training

GOVERNMENT GAZETTE No June

e-shipping Portal POWERED BY

Maritime & Logistics Bulletin

ODeX evgm MANUAL. Manual for Electronic Verified Gross Mass

Various SOLAS-related Amendments Contents

A container will not be shipped if the declared VGM is found to be inaccurate.

Container Weight and Container Content

General Shipping Terms and Conditions for Sea Freight

Container Weighing: A guide to the 2016 IMO Shipping Ruling. A Marsden Weighing Group White Paper.

How to Pre-Advise an Export or Outbound Coastal Container using Community Access Portal (CAP)

Verifying Container Weight What, Where and How? Lars Meurling

THE IMPACT OF VGM (VERIFIED GROSS MASS) IMPLEMENTATION AS SOLAS S NEW REGULATION CASE STUDY AT PORT OF TG.PRIOK

Bill Gain Global Lead Trade Facilitation and Border Management

CHALLENGES & LOGISTICS ISSUES REEFER PROTEIN SHIPPERS FACE

Container weight verification:

Customs Concerns for the Motor Carrier and Transportation Intermediary

MSC MEDITERRANEAN SHIPPING COMPANY. Sensitivity: Internal MSC CAMEROON TERMS AND CONDITIONS

BURNING ISSUES FOR OTIs

Lithuanian Maritime Safety Administration: the most important activities and events in

ANNEX 5 DRAFT MSC CIRCULAR DUE DILIGENCE CHECKLIST IN IDENTIFYING PROVIDERS OF CTU-RELATED SERVICES

Applying Software Architecture Concept to Design Single Window for Modifiability

TECC-GH. A Presentation by Times-End C Computers Ltd.

CONTENTS MESSAGE TO THE COMMUNITY:

FAL Convention CONVENTION ON FACILITATION OF INTERNATIONAL MARITIME TRAFFIC, 1965, AS AMENDED Edition. Erratum June 2018

ICHCA Container Weighing Seminar

Logistics Crafted to Fit Your Needs

MSC TANZANIA TERMS AND CONDITIONS

Bill of Lading Manual

한국금융연수원외환전문역 Ⅱ 종자격동영상강의 국제무역규칙 제 4 강신용장통일규칙 (UCP600) 어음 수표법기초

MSC SINGAPORE TERMS AND CONDITIONS

Guideline for Crated and Boxed Cargo

35.00 BL Print original bill of lading at request of other offices BL EXS aangifte BL Preparing certificates BL

PORT OF DAMPIER HANDLING OF GENERAL CARGO, GOODS AND EQUIPMENT PROCEDURE

MSC MEDITERRANEAN SHIPPING COMPANY. Sensitivity: Internal MSC LIBERIA TERMS AND CONDITIONS

MSC BAHRAIN TERMS AND CONDITIONS

Cosmos. Container Messages. Amendments for handling SOLAS Requirements. PSA Antwerp

General Forwarding Instructions

PORT OF MOURILYAN HARBOUR

Shipping Instruction (Draft) INTTRA Guide step-by-step

Transcription:

Q&A (For SOLAS VGM) Q1: What is the request of the new SOLAS? A: SOLAS requires that shipper showing in the bill of loading is responsible for ensuring that the verified gross mass in communicated in the shipping documents sufficiently in advance to be used by the ship s master or his representative and the terminal representative in the preparation of the ship stowage plan. In the absence of the shipper providing the verified gross mass of the packed container, the container should not be loaded on to the ship. Q2: When is the execution time of the new SOLAS? A: On Nov 21, 2014 the IMO s Maritime Safety Committee announced that the new Safety of Life at Sea (SOLAS) will become effective from July 1, 2016. Q3: Who is responsible to submit the VGM in the new SOLAS regulation? A: The shipper showing in the bill of loading or the entity authorized by the shipper is responsible to provide the VGM. Q4: How to obtain the VGM? A: 1. Weighing the packed container using calibrated and certified equipment 2 Weighing all packages and cargo items, including the mass of pallets dunnage and other securing material to be packed in the container and adding the tare mass of the container to the sum of the single masses, using a certified method approved by the competent authority of the State in which packing of the container was completed Q5: Will there be a template to submit VGM? A: Unfortunately not. VGM has to be submitted according to above method (Q4)with the signature of shipper or the person duly authorized by shipper.

Q6: What is the penalty for not complying with the new regulation? A: Please strictly comply with the new regulation, otherwise all the extra cost risk and consequence will be taken by shipper.. Q7: When will Our Company issue a global customer advisory on VGM? A: The first Version is issued on Mar 23, 2016. Q8: When is the cut-off time for submitting VGM to our company? A: The VGM CUT-OFF time should be 24hours prior to the vessel arrival, but every port may adjust the time according to the local process. The VGM CUT-OFF will be displayed on www.coscon.com and your Booking confirmation. Q9: How to submit the VGM? A: You may submit the VGM through following channels: -VERMAS (EDIFACT) message - or via E-SI (but it only be acceptable before VGM CUT-OFF time) - or via our official website - or Mail/ FAX / Hardcopy Below items are mandatory when you submit the VGM: -Booking No. or B/L No.; -Container No.; -Verified Gross Mass (VGM); -Weight Scale (MT/KGS/LBS); -Signature (Responsible Party); -Authorized Person Q10:Who can provide the VGM?

A: Shipper can provide the VGM by own mean, or nominate a third party also. But an authorization in writing has to be given to carrier. Our company does not verify the authorization and all risks arising from VGM information will be borne by the shipper. Q11: What is the process of VGM data transmission? A: The general process of VGM data transmission is Shipper( or nominated 3 rd party) Carrier Terminal If the customer nominates the terminal VGM service, the process should be Terminal Shipper Carrier. Q12: Will our company offer a weighing service? A: Unfortunately not. Currently our company does not have such weighing service. Q13: Would the terminal accept container gate-in without VGM? A: Yes. The VGM must be submitted before VGM CUT-OFF, otherwise this container should not be permitted to load on the vessel. And the shipper will be responsible for all the consequences arising therefrom. Q14: Is VGM mandatory if the GROSS WEIGHT has already been marked on the bill of loading? What is the difference between the Gross weight and VGM A: Yes. No matter the Gross weight provided or not, the VGM is always mandatory. Difference: -Scope of application: The GROSS WEIGHT is applied to trade business such as customs declaration, B/L making etc. VGM is applied to vessel stowage plan according to IMO new SOLAS. -Definition Gross weight means cargo s gross weight. VGM means cargo items, including the mass of pallets dunnage and other securing material to be packed in the container and adding the tare mass of the container to the sum of the single masses.

Q15: Does shipper have to submit VGM with documentation? A: Shipper can provide VGM with document or submit it separately, but it should comply with the VGM CUT-OFF time. In order to avoid the risk of VGM data transmission,other errors and miss loading, it is strongly recommend the shippers to provide the VGM as early as possible. Q16: Will the VGM amendment be acceptable by our company? A: Acceptable. The original date can be updated but all the risks and consequence should be taken by shipper. Q17: How to find the container tare weight? A: All the tare weight can be found on the container. Q18: What is the tolerance of VGM declared by the shipper? A: Shippers have to provide an accurate weight according to the IMO new SOLAS. Q19: How to process the discrepancy between the VGM declared by the shipper and the real weight: A: We will ask the shipper to re-verify the VGM only in exceptional circumstances. If the discrepancy exceeds ±5% or 1 ton (whichever is the smaller), the VGM should be updated accordingly, and all the consequences arising therefrom should be taken by the shipper. Q20:What is the requirement on transshipment units? A: The VGM of transshipment units are also mandatory. Only the full container which has the VGM can be transshipped on the connecting vessel. If the VGM has been submitted at the port of loading, our company will be responsible to relay it to transshipment port.

If you have any question on this new rule, please see our official website or contact our local office. We will keep you updated on developments. Kind regards.