GO RAIL NIAGARA SERVICE EXTENSION

Similar documents
Niagara Region Transportation Master Plan Road Network Strategy Technical Paper

REGIONAL EXPRESS RAIL (RER)

Executive Summary i Regional Transportation Plan March 2018

Niagara Region Transportation Master Plan Niagara-Hamilton Trade Corridor Technical Paper

Niagara s Transportation Strategy 1. Introduction:

HAMILTON B LINE LRT EVALUATION OF PHASING SCENARIOS TECHNICAL REPORT

Findings to Date UBC LINE RAPID TRANSIT ALTERNATIVES ANALYSIS 1. UBC Line Rapid Transit Alternatives Analysis Findings to Date

407 TRANSITWAY WEST OF HURONTARIO STREET TO EAST OF HIGHWAY 400 MINISTRY OF TRANSPORTATION - CENTRAL REGION

Parking and Multi-Modal Station Access. Jennifer Niece Metrolinx, Sr. Advisor, Sustainability Toronto, Ontario

Public Information Centre #1. March 2010

TRANSPORTATION DEMAND FORECASTING INFORMATION SESSION

MEMORANDUM. Executive Summary. Recommendation. Background

407 TRANSITWAY - KENNEDY ROAD TO BROCK ROAD MINISTRY OF TRANSPORTATION - CENTRAL REGION

DRAFT. GTHA Fare Integration Draft Preliminary Business Case. Draft Report for Discussion September 2017

Niagara Region Transportation Master Plan Goods Movement Technical Paper

CITY OF VAUGHAN EXTRACT FROM COUNCIL MEETING MINUTES OF APRIL 11, 2018

Technical Report: GO Expansion RER New Stations Business Case Analysis

EXECUTIVE SUMMARY ORGANIZATION OF REPORT

Transit Service Guidelines

Service Business Plan

2040 Transportation Policy Plan Conversion to Performance Based Planning Basis. 25 th Annual CTS Transportation Research Conference May 21, 2014

EXECUTIVE SUMMARY 1. OVERVIEW OF TRANSPORTATION PROBLEMS AND OPPORTUNITIES

2001 GTA CORDON COUNT TRANSPORTATION TRENDS McCormick Rankin Corporation. Prepared on behalf of:

Ottawa Transportation Master Plan 2013

QEW Garden City Skyway Niagara Street to Glendale Avenue Risk and Value Engineering Support Major Infrastructure Decisions

Re: EX16.1 Attachment 2 GO Regional Express Rail 10-YEAR PROGRAM: City Of Toronto New Stations Analysis

Draft Regional Transportation Plan Comments

What is the Transportation Policy Plan (TPP)?

The Regional Municipality of Halton. Chair and Members of the Planning and Public Works Committee. Mitch Zamojc, P. Eng., Commissioner, Public Works

4. IDENTIFICATION OF SPECIFIC TRANSPORTATION PROBLEMS WITHIN THE STUDY AREA

Alternatives Analysis, New Starts

Greater Golden Horseshoe Transportation Plan

Recommendation: Oppose the Ministry of Transportation s preferred alternative for

Transit Investment Direction and Plan Introduction. Transportation Advisory Board TPP Workshop August 16, 2017

ALBION FLATS DEVELOPMENT EXISTING TRAFFIC CONDITIONS AND POTENTIAL IMPACTS

SOUTHWEST LRT (METRO GREEN LINE EXTENSION)

3. STATION SPACING AND SITING GUIDELINES

REGIONAL EXPRESS RAIL UPDATE

Service Development. Committee of the Whole April 3, 2019 Adam Harrington, Director of Service Development 1

2010 Minnesota Comprehensive Statewide Freight and Passenger Rail Plan. Minnesota Department of Transportation

Increasing Ridership and Efficient Passenger Transit

2004 FEASIBILITY STUDY UPDATE

Chapter 11 ECONOMIC ANALYSIS

THE REGIONAL MUNICIPALITY OF YORK

3. SYSTEM ANALYSIS Future (2031) AADT and SADT Estimates

RER New Stations Initial Business Case BRESLAU STATION. Kitchener Corridor. July Draft

Niagara Region Transportation Master Plan Transit Strategy Technical Paper

Welcome. Background. Transportation Master Plan Study Stages. How We GO. At tonight s session, you can expect the following:

Business Case Guidance. Draft March 2018

US & USRC Track Capacity Study Train Capacity Analysis Present to Maximum Capacity and Beyond

ABSTRACT Introduction Problem Formulation Review of International Best Practices

Planning and Development Services Committee. Local and Regional Partnerships Niagara GO Mobility Hub Study Memorandum of Understanding

3.6 GROUND TRANSPORTATION

Table of Contents. YRT/Viva at a Glance 17 Our Commitment 18

Los Angeles County Congestion Reduction Demonstration Project

Benefit Cost Analysis Narrative

Breakfast with the Experts PURCHASING MADE #GYBPurchasing. RIC Centre is a member of

TAC Sustainable Urban Transportation Award (SUTA) High Occupancy Toll (HOT) Lanes Pilot Project

THAT, on recommendation of the Audit, Finance and Risk Management Committee, the Board pass the following resolution:

Transit Investment Direction and Plan Introduction. Transportation Advisory Board October 18, 2017

Metrolinx wishes to acknowledge the invaluable contribution of IBI Group to the preparation of this backgrounder.

MONITORING IMPLEMENTATION AND PERFORMANCE

2030 Transportation Policy Plan SUMMARY PRESENTATION. Land Use Advisory Committee November 15, 2012

Contents i Contents Page 1 A New Transportation Plan Community Involvement Goals and Objectives... 11

Chapter 4. Recommendations

TECHNICAL REPORT 2001 GTA CORDON COUNT TRANSPORTATION TRENDS Prepared on behalf of:

IPSWICH NORTHERN ROUTES STUDY. Stage 1 Progress

Future Build Alternative Traffic Forecasts and Level of Service Analysis

Caltrain Rapid Rail Plan

407 TRANSITWAY. Planning & Preliminary Design

Cambourne to Cambridge Better Bus Journeys: Strategic Outline Business Case Economic Case City Deal Partners. 28 September 2016

Markham Centre Transportation Study Update

Re: EX16.1. Developing Toronto's Transit Network Plan to Attachment 6

UK Road Pricing Feasibility Study: Modelling the Impacts Elizabeth Cox 1 UK

Section 11: Transportation Strategies Toolbox

Chapter 1 Introduction

Region of Waterloo. Rapid Transit Initiative. Preliminary Preferred Option May 12, 2009

The Big Move: Next wave of projects and funding new infrastructure.

Factor Potential Effects Mitigation Measures

Workshop #3 Needs Assessment. Ministry of Transportation IBI Group March 27, 2014

Rail Freight and Passenger

Transit Project Assessment Process

CITY OF OSHAWA ITMP THE CORPORATION OF THE CITY OF OSHAWA INTEGRATED TRANSPORTATION MASTER PLAN

PROPOSED. Relief Line Project Assessment. Terms of Reference: Phases 1A-4 A NEW RELIEF LINE IN TORONTO

CTA Blue Line Forest Park Branch Feasibility/Vision Study: Transit Ridership Forecasting Analysis Technical Memorandum Submitted By

Northern Illinois Commuter Transportation Initiative (NICTI) Locally Preferred Alternative Briefing Paper

Regional Transitway Guidelines

Appendix E Technical Description of the Modeling Framework

This document has been developed to provide context to the Board as part of the strategic planning process. Regional development and travel trends

The Economic and Societal Impact of Hampton Roads Transit: Investment Scenarios

1/ The 2008 Wheel-Trans Operating Budget (summarized in Appendix A) as described in this report and the following accompanying reports:

APPENDIX 2 GO Regional Express Rail 10-Year Program: New Stations Analysis. Board of Directors Report June 28, 2016

1 GO TRANSIT TEN-YEAR CAPITAL PROGRAM

APPENDIX F1 Legislative Context

GO Transit Georgetown South Corridor Service Expansion and Airport Transportation Link between Lester B. Pearson Airport and Union Station

An Overview of Transportation Issues in the NY Metro Area July 26, 2010

APPENDIX B - GLOSSARY FEBRUARY 2017

Fishermans Bend Integrated Transport Plan Peer Review John Kiriakidis, GTA Consultants 28/03/2018

Travel Demand Forecasting User Guide

Appendix A: Project Planning and Development A-1 White Paper on Transit and the Tappan Zee Hudson River Crossing Project

Transcription:

Business Case: Finch Avenue West Rapid Transit GO RAIL NIAGARA SERVICE EXTENSION INITIAL BUSINESS CASE Date: November, 2014 NOVEMBER 2015 Page 1

TABLE OF CONTENTS 1.0 Executive Summary...p.5 2.0 Introduction....p.6 3.0 Problem Statement and Options. p.7 4.0 Strategic Case.p.8 5.0 Financial Case........p.9 6.0 Economic Case.....p.10 7.0. Deliverability and Operations Case......p.11 8.0 Conclusion and Next Steps.. p.12 Page 2

Glossary of Terms Appraisal Analysis of a program, investment or intervention that has not yet been implemented and focuses on estimated or forecasted evidence. Benefits Case Analyses (BCA) Business Case Cost Benefit Analysis Economic Case Reports produced by Metrolinx between 2008 and 2012 focusing on select economic impacts and financial costs of major proposed Metrolinx transit projects. BCAs have subsequently been replaced by the new Business Case framework. A collection of a suite of evidence on the potential strategic, economic, financial, deliverability and operational impacts of a proposed program, intervention or investment to inform decision-making throughout the project lifecycle. Metrolinx Business Cases are an enhancement and replacement of Metrolinx s former Benefits Case Analyses reports. A form of evaluation that focuses on comparing certain economic impacts (generally benefits) to the cost of an investment. Cost Benefit Analysis is used in the Economic section of Metrolinx s Business Case framework and was also used to inform previous Benefits Case Analyses. One component of the Metrolinx Business Case that examines or reviews the impacts of proposed investments or interventions. Economic impacts include transportation user benefits (journey time impacts, road decongestion impacts, safety/accident reductions, etc.), environmental impacts (changes in emissions levels, vibration, etc.), social and community impacts (the distribution of benefits among populations, severance/isolation impacts, etc.), wider economic benefits (agglomeration/productivity impacts, etc.) and public funding impacts (property tax revenues, etc.). The Economic Case generally includes a costbenefit ratio. Economics is a branch of science that studies the production, distribution and consumption of goods and services. Financial Case Delivery and Operations Case Strategic Case One component of the Metrolinx Business Case that examines the lifecycle costs and revenues of proposed investments or interventions. One component of a Metrolinx Business Case that examines the impacts of proposed investments or interventions on operations, the delivery of the proposal, potential risks, procurement and related commercial or management issues. One component of a Metrolinx business case that examines the alignment of proposed programs, investments or interventions with Metrolinx strategic plans and goals. It involves the presentation of transportation planning information, including traffic forecasts, related travel patterns, drivers and interdependencies. Page 3

Acronyms BCR Benefit cost ratio LRT BRT ALM MAE NPV PV Light Rail Transit Bus Rapid Transit Automated Light Metro Multiple Account Evaluation Net Present Value Present Value RTP Regional Transportation Plan, The Big Move, 2008 SOV TTS VKT Single Occupant Vehicle Transportation Tomorrow Survey Vehicle Kilometres Travelled Page 4

1 EXECUTIVE SUMMARY This Initial Business Case report provides a summary of the strategic, financial and economic performance of the proposal to provide weekday commuter GO rail expansion into the Niagara Region. Substantial additional work will be required to refine estimates and optimize the investment associated with this potential investment. One option has been assessed: two peak period, peak direction GO trains running inbound from Niagara Falls to Confederation station in Hamilton for interchange to Toronto in the AM, and outbound from Confederation to Niagara Falls in the PM using the CN corridor. Trains would also stop at Grimsby and St. Catharines. Grimsby, St. Catharines and Niagara Falls would require upgrades. Additional options involving direct train service to Toronto would impose significant reliability concerns on the existing Lakeshore West service due to the at-grade Welland Canal crossing and have not been tested at this time. The report finds that the costs exceed benefits by a significant margin, with a substantial operating subsidy requirement forecast. Alternative service concepts, including those proposed by Niagara Region, have been examined in the past and have resulted in similar findings. Transit market growth is a function of the relative attractiveness of transit when compared with alternatives. This is largely perceived by users to relate to the quality of a journey and is typically measured in terms of cost, speed, comfort and convenience. Solutions that combine to create a greater competitive advantage for rail (and which may not be solely be limited to the specification of the rail service) should be considered. A pre-requisite for the operation of regular weekday GO rail service to Niagara is a robust and deliverable operational solution that eliminates the reliability concerns associated with the Welland Canal crossing. Further work to support the development of sustainable transportation links between the Niagara region and the Greater Toronto and Hamilton Area (GTHA) is anticipated. Such work should include consideration of innovative solutions that could drive efficient delivery and/or market growth in order to address value for money considerations. Table 1: Summary Table Indicator Option 1 ($M) Nominal Capital Costs (Total) $166 Nominal Annual Operating Costs (2031) $15.5 Nominal Annual Revenue (2031) $4.4 Operating Cost Recovery Ratio (2031) 0.29 Total Costs (PV, 2015 $) $412 Benefits (PV, 2015 $) $168 Net Benefits (PV, 2015 $) ($244) Benefit Cost Ratio 0.41 Page 5

2.0 INTRODUCTION The Niagara Region is set to experience population growth in the next 20 years, although at a slower rate than the rest of Ontario. Figure 1: Population Growth, Niagara Region and Ontario (Source: Ontario Ministry of Finance) GO rail Lakeshore West services currently operate between Union Station, Hamilton GO Centre station and West Harbour station (formerly James St North station). Weekend summer service operates beyond Hamilton to Niagara. The extension contemplated in this business case makes use of the CN corridor from Hamilton to Niagara currently used by GO Transit to provide seasonal GO rail service to Niagara Falls, with trains terminating at Stoney Creek Confederation station. The planned new GO Train stations are described as follows: Niagara Falls station: This station would be located near the existing VIA Rail station in the City of Niagara Falls. This location is served by local transit services and the arterial road network. St Catharines West station: This station would be located at or near the site of the existing VIA Rail station on the west side of St Catharines. Local bus service would be available on St Catharines Transit routes 3 and 15. Road access would be from St Paul Street West (Niagara Region Road 81). Grimsby station: This station would be located adjacent to Casablanca Boulevard and near the existing GO Transit bus terminal. The location has access to and from the QEW via the Casablanca interchange. Page 6

3.0 PROBLEM STATEMENT AND OPTIONS Problem Statement How can transit service be developed in the Niagara - Hamilton corridor to best meet the short, medium and long term transportation needs of the local communities? Context There are currently about 20,000 daily person trips in each direction on the Niagara - Hamilton - Toronto corridor that are Niagara based, with 60% terminating in Hamilton and 10% in Toronto. Approximately half of these trips occur in the AM peak period (0600-0900). The dominant mode is auto with transit currently accounting for approximately 125 trips per AM weekday peak period (from Niagara towards Toronto) on GO Bus Route 12 that operates between Niagara and Burlington with intermediate stops in St Catharines, Grimsby and Stoney Creek and with timed transfers at Burlington GO station for Toronto-bound service. Travel demand on the corridor is forecast to increase by approximately 30% in the next 25 years and this will create additional congestion on the QEW and potentially limit economic growth. Options Do Minimum: Lakeshore West Line is a well-established GO rail corridor. It provides rail service to Hamilton, Burlington, Oakville, and south Mississauga into Toronto with connecting GO Transit bus and local transit services at all stations. This line currently has peak period services only between Hamilton and Toronto Union. This line has all day weekday and weekend GO train services between Toronto Union Station and Burlington (Aldershot station) with train-meet buses connecting west to the Hamilton GO Centre. Test Option: Two morning and two evening peak direction trains, for a total of four train trips per day. This service will connect Niagara with the GTHA using the CN track at Confederation station. At Confederation, passengers can transfer onto the existing Lakeshore West Line (with no impact to the latter), for travel further east into Union Station and beyond. Further options that could be tested in future iterations of this business case may include: Bus connection from Burlington, rerouted within Niagara to reach tourist areas All day low frequency Niagara Shuttles rail service concept Use of alternative rail alignments and/or rail rolling stocks Page 7

4.0 STRATEGIC CASE The core metric that has been used to measure strategic effectiveness of the GO rail service in the Niagara peninsula is ridership. The ridership forecasts used in this business case are derived from a business case put forward by Niagara Region in April 2015 for GO rail service between Niagara and the GTHA 1. Although GO rail service proposed would have marginal or no travel time improvement over today s GO bus service and would face reliability challenges due to the Welland Canal crossing, the Niagara Region forecasts assume significant future year deterioration in the performance of the highway network. It is on this best case scenario that the evaluation contained in this business case has been undertaken. Table 2: AM Peak Period Boardings 2021 Boardings Niagara Falls 50 St. Catharines 120 Grimsby 230 Total 390 2031 Boardings Niagara Falls 100 St. Catharines 230 Grimsby 460 Total 780 Figure 2: Stations served by proposed service Confederation Grimsby St. Catharines Niagara Falls 1 Niagara GO Rail: A Case for Weekday GO Train Service between Niagara and the GTHA, April 2015 Page 8

5.0 FINANCIAL CASE The financial case seeks to understand the investment costs and the ongoing operating costs throughout the whole life of the asset. The capital and operating cost estimates along with revenue estimates have been assembled for an assumed 60 year asset life and are presented in Table 3. Table 3: Financial Information Nominal Dollars Option 1 ($M) Capital Cost (Total)* $166 Annual Incremental Operating Costs (2031) $15.5 Annual Incremental Revenue (2031) $4.4 Operating Cost Ratio (2031) 0.29 *Costs include inflation. In real terms, the capital costs are $160M. The analysis suggests that the Niagara peak period service does not provide a positive financial case and operating cost recovery ratio. Operating costs are assessed based on detailed understanding of the unit rate of operating costs for diesel GO rail service. The operating cost recovery ratio of 0.29 is lower than the 2014-15 GO rail system average of approximately 0.76, meaning that this will result in an overall decrease in the operating cost recovery of GO service. Capital costs of $160 million are estimated to be required for station upgrades and other infrastructure necessary for the provision of services described. It is assumed that there is no additional rolling stock costs associated with the option under consideration. These are preliminary estimates that require further development and confirmation. In particular, the capital cost estimate is sensitive to a variety of assumptions and work is underway to better understand the range of estimates under alternative costing assumptions. It is expected that the central estimate is likely to increase once this work is completed. In addition, the capital cost estimate presented is a lowend estimate because no capital infrastructure renewal or maintenance costs have been calculated to date, and these costs are therefore not included in these figures. Page 9

6.0 ECONOMIC CASE The economic case measures, quantifies and monetises transport impacts (benefits) and seeks to compare those benefits with costs to understand relative performance and value-for-money of each investment option. Table 4: Economic Information 2015 $ Value Option 1 ($M) Total Costs (PV) Benefits (PV) Net Benefits (PV) BCR $412 $168 -$244 0.41 In summary, the analysis suggests that the Niagara Peninsula peak period service does not provide value for money in economic terms, with costs outweighing the benefits of the proposed service. Travel time savings were estimated based on the expected change in travel time between current travel and future travel between Niagara Region and the GTHA. Current GO bus travel times between Niagara Falls and Burlington (GO Bus Route 12) suggest congestion on the QEW in peak periods is typically not an issue. As a result, travellers from Niagara to east of Burlington may not experience travel time savings. For travellers headed to Hamilton, some travel time savings may occur, in part due to the current bus route. This business case assumes 1 30 of travel time savings for existing GO bus users. However, sensitivity tests of 10 minutes travel time savings were tested and found to have a marginal impact on performance (i.e., BCR remains <0.5). The majority of benefits stems from reduced auto operating costs and road congestion. However, as this project is proposed for outside the GTHA, estimated road congestion reduction impacts may not be accurate. Reliability impacts resulting from the Welland Canal may result in missed connections to Lakeshore West service at Confederation station. These impacts have not been considered and would further lower project performance. Page 10

7.0 DELIVERABILITY AND OPERATIONS CASE The deliverability and operating evidence focuses on key project implementation risks and any construction and on-going operating impacts that may result from investment options. To date, no formal agreement has been reached with the St Lawrence Seaway Management Corporation (SLSMC) to operate regular train service across the Welland Canal. Until an agreement is reached setting out an operational solution to the Welland Canal crossing that involves the co-ordination of rail and seaway movements, there is a risk of recurrent delay to the proposed service of up to 20 to 30 minutes or more, 12 to 16 times per month. This delay would reduce the reliability of the current service provided to Niagara GO bus users. The current Niagara Seasonal Rail Service provides a snapshot of the risk associated with the Welland Canal. During the 2014 season, 27 train trips 12% of the 225 total train trips encountered a service disruption resulting from shipping traffic through the Welland Canal, causing an 18-minute delay to the train service on average. Overall on-time performance on the Niagara service, accounting for all service disruptions including those at the Welland Canal, was 63%. In comparison, on-time performance was at 95% on the entire GO network in 2014. As noted in the financial section of this business case, the cost estimate for capital works are preliminary estimates (for example, does not include renewal and/or maintenance of capital assets). In addition, it does not include any new grade separations or train layover facilities. More work is currently underway with CN to undertake a capacity study. The results of this study will inform an update to the business case in terms of providing a more detailed assessment of the infrastructure required to accommodate additional service. Page 11

8.0 CONCLUSION AND NEXT STEPS The overall business case for GO rail investment in the Niagara peninsula is low. Both short and long term prospects for GO rail investments are constrained by the Welland Canal vertical lift bridge. This is of particular importance as GO RER proposals are developed, and the potential to create knock on impacts across the network increase. Such impacts could disrupt many more passenger journeys than just those affected on the Niagara Peninsula if through service from Niagara to the Lakeshore West corridor is contemplated in the future. Page 12