Tavua to Volivoli- Stage 3, 5 (Pole 50 to Pole 93)

Similar documents
Supply to Rancho De Viti Investments Corporation at Maranitawa - Ba (Scheme No. G52/07)

Supply to Navala Village - Ba (Scheme No. BA 11/13)

TENDER NO MR 117/2016 PROJECT: SUPPLY TO KAMINIELI VOLAU AT TACI VILLAGE, REWA SCHEME: NU08/15

TENDER NO MR197/2015 PROJECT: SUPPLY TO DINESH CHND & 10 OTHERS DAKU LABASA SCHEME: LAB 13/13

TENDER NO MR183/2015 PROJECT: SUPPLY TO VODAFONE, DIGICEL & FEA TOWERS DREKETI LABASA SCHEME: LAB G53/14

TENDER NO MR184/2018 PROJECT: ELECTRICITY SUPPLY TO VUNISEA VILLAGE, DREKETI SCHEME: LAB02-17

PROJECT: NEW 11kV FEEDER FROM RARAWAI 33/11kV SUBSTATION TO YALALEVU INDUSTRIAL AREA AS PER SCHEME NO. SR38/14

PROJECT: SUPPLY TO BERRY ROAD APARTMENT - SUVA SCHEME: G43-13

PROJECT: NASRUP SECTION 1B UNDERGROUND RELOCATION STAGE 4 FROM CH SCHEME: C (FROM WAQADRA SUB TO NATALY JUNCTION)

PROJECT: INCREASE DEMAND FOR UNIVERSITY OF FIJI- KULA STREET SAMABULA SCHEME: G115-15

PROJECT: RELOCATION OF FEA ASSETS NEW VATUWAQA BRIDGE TRENCHING WORK SUVA SCHEME: C21/14

PROJECT: SUPPLY TO STATE FORESHORE SUB- DIVISION, VIRIA, VATUWAQA PART A.2: UNDERGROUND LV CABLING WORKS STAGE 1 & 2 SCHEME: G74-15

TENDER DOCUMENT MR 52/2015. Installation of 33kV Underground Power Cables

BIDDING DOCUMENT. TENDER No. MR 79/2017 PREFERRED CONTRACTOR - TRENCHING WORKS FOR UNDERGROUND CABLES IN THE CENTRAL DIVISION

MR 303/2017. SURVEY OF 11kV SUBMARINE POWER CABLE ROUTE FROM MALAU JETTY IN VANUA LEVU TO MALI ISLAND AND FROM MALI TO VOROVORO ISLAND IN MACUATA

Tender Number: MR 19/2017

Supply & Installation of new Air Conditioning Units at various FEA Sites Fiji Wide

SECTION -2 QUALIFICATION INFORMATION, FORMS OF BID AND CONTRACT

Monasavu Dam Access Roads Upgrade

Tender for Concrete Driveway Reinstatement Works at Denarau Business Park - Nadi

Tender for the Supply of Fine Sand for 33kV Cabling Works in Suva

Managing PTC Creo Parametric Data with PTC Windchill PDMLink 11.0

Tender Number: MR 141/2016

Fiji Electricity Authority Transmission Unit 2 Marlow Street, Suva

Tender Document MR 359/2017. Supply of 2 x 20ft Container with build-in storage shelving. Fiji Electricity Authority Generation 15-Dec-17

SENIOR COMMUNICATIONS OPERATOR, 1467

Tender Document. MR 145/ Construct New Lube Oil Containment Bund at Labasa Power Station. Fiji Electricity Authority Generation 02-Jun-17

Business Administration of PTC Windchill 11.0

Introduction. There are two primary schools of thought in developing an audit approach:

Web Portal: Submit A Locate Request

Naiyala Repeater Site Civil Works

The PTC Windchill PDMLink 11.1 MCAD Data Management Process for PTC Creo Parametric

Maintenance and Refurbishment Works of Quarters Two (2) at FEA s National Control Center, Vuda. Tender Number: MR 334/2017

Continuous Improvement Policy

Tender for Sale of Obsolete and Scrap items

Carry out Maintenance on Two (2) X 132kV/33kV Power Transformers at FEA Cunningham Rd Substation

PRESS STATEMENT BY HON. MINISTER FOR LANDS & NATURAL RESOURCES ON ENQUIRY REPORT ON MULTIPLE FATALITY ACCIDENT AT NEWMONT AHAFO MILL EXPANSION (A.M.

Energy Fiji Limited Transmission Unit 2 Marlow Street, Suva

TOWN OF LABRADOR CITY FORM OF TENDER TLC SUPPLY & INSTALLATION OF CONCRETE FLOOR

INDEPENDENT ELECTRICAL CONTRACTORS SAFETY PROGRAM AWARENESS & RETENTION KIT

SINGLE STAGE TWO ENVELOPE SYSTEM

Reform Update- Dealing with Construction Permits India (Both Delhi and Mumbai)

MR 113/2015. Request for Quotation for EIA Study for proposed Momi Bay 33/11kV Zone Substation and Nawai 33kV Switching Station Projects

AGENDA PRE-CONSTRUCTION MEETING

Finance Manager Corporate & UK Full-time, Permanent appointment Oxford, UK

National Maintenance Agreement Features

During the discussions, the Committee finalized the following additional TOR for further study:

HEALTH, SAFETY AND ENVIRONMENT MANAGEMENT SYSTEM MANUAL

Section - III Evaluation and Qualification Criteria

Request for Proposal Corrigendum 02. Selection of Service Provider for User Acceptance Test (UAT) & Automation Testing

MR 24/2015. Date: 12/02/15. Tender Name: Preferred Supplier for Supply of. Standard Overalls and Live Line Overalls

Article II Definitions Section 200 Interpretation II Definitions II-1

Fiji Electricity Authority. Tender Document for Supply of Printer (with. Scanner, Copier, A3, A4 and Colour) (Tender #: MR-139/2016)

SAN MATEO COUNTY FAIR REQUEST FOR PROPOSALS ADVERTISING, MARKETING & PUBLIC RELATION SERVICES RFP #

MANUAL OF ENVIRONEMT LAWS INPAKSITAN

Workflow Administration of PTC Windchill 11.1

PRE-QUALIFICATION OF HARDWARE AND ELECTRICAL ITEMS SUPPLIERS FOR YEAR PRE-QUALIFICATION DOCUMENT

NetSuite SuiteFoundation Sample Test: March 2018

Appendix 3. POLICY & PROCEDURE No

SPPL RFQ Ref No.: REPLACEMENT OF BALL FLOAT VALVE FOR WATER TRANSFER TANK AT SINGAPORE POOLS BUILDING

SUBCONTRACTOR SAFETY, HEALTH, AND ENVIRONMENTAL MINIMUM PERFORMANCE STANDARD (MPS)

MORSES CLUB PLC ( MCL or the Company ) REMUNERATION and CORPORATE SOCIAL RESPONSIBILITY COMMITTEE ( RemCo or the Committee ) TERMS OF REFERENCE

How To Standard Costing

I. Introduction/Welcome to MAPP

ELDORADO GOLD CORPORATION BOARD OF DIRECTORS TERMS OF REFERENCE

POLICY FOR SELECTING VENDORS OF NON-CONSTRUCTION PURCHASING CONTRACTS, PROFESSIONAL SERVICES AND DELEGATION OF IMPLEMENTATION AUTHORITY

Office of the President of Brazil Office of the Chief of Staff Office of the Deputy Chief for Legal Matters LAW No DATED AUGUST 5, 2003

LEED Reference Guide for Green Building Operations and Maintenance For the Operations and Maintenance of Commercial and Institutional Buildings 2009

RFQ Drainage Ditching and Culvert Replacement

Corporate Policy and Procedure

J&P OMAN COMPANY ORGANISATION P.110 PROCEDURE. Page: 1 of 16. Document Title: Issue Date: 13/04/2014. Revision Date: 06/06/2016 Revision No.

FIJI ELECTRICITY AUTHORITY TENDER DOCUMENT. Addendum # 1 TENDER NUMBER: MR283/2017. TENDER NAME: 33kV Underground Cable Installation Works

Tender for Supply of Smart UPS - 3kVA and/or R19 42RU Rack Complete

PUBLIC AND PRIVATE IMPROVEMENTS CODE OF THE TOWNSHIP OF UPPER ST. CLAIR

COAA EPCM CONTRACT PHILOSOPHY. COAA EPCM Contract Committee

AGRICULTURAL PRODUCE MARKETING COMMITTEE

NOTICE FOR SELECTION OF ARCHITECT FOR ALTERATION / ADDITIONAL CONSTRUCTION WORK ON THE EXISITING BUILDING OF BHUBANESWAR CHAPTER OF ICSI

ADDENDUM NO. 2. Penny Owens, Assistant Purchasing Agent, City of Knoxville

INSTRUCTIONS TO BIDDERS

TENDER SPECIFICATION

NetSuite ERP Consultant Sample Test: April 2018

NetSuite Financial User Sample Test: April 2018

MR 73/2018 TENDER FOR SUPPLY OF ELECTRIC ARC FLASH PROTECTIVE CLOTHING FIJI ELECTRICITY AUTHORITY

CITY OF TORONTO. BY-LAW No (OMB)

SCOPE OF WORK FOR ELECTRICAL WORK

ENERGY FIJI LIMITED TENDER DOCUMENT MR11/2019

NetSuite ERP Consultant Sample Test: March 2019

TENDER DOCUMENT FOR REPLACEMENT OF THE EXISTING PASSENGER LIFT WITH 10 PERSONS CAPACITY AT HOLKAR STADIUM, INDORE.

FIJI ELECTRICITY AUTHORITY

DEMOLITION BID. BID OPENING November 20, 2018, 8:00pm. Village of Germantown 306 Prairie St. Germantown, IL 62245

ADDENDUM 1. Repair and Maintenance of Landfill Gas Chiller System. Return date: Bid must be received no later than 2:00 PM, Monday, June 25, 2018

Position Description: Site Supervisor Reports to: Site Manager/Project Manager

REQUEST FOR PROPOSAL. Construction Management Services Not at Risk

FLORIDA DEPARTMENT OF TRANSPORTATION

PONDICHERRY UNIVERSITY SCHOOL OF LIFE SCIENCES DEPARTMENT OF BIOCHEMISTRY & MOLECULAR BIOLOGY (R.V.NAGAR, KALAPET, PUDUCHERRY

UNIVERSITY OF KENTUCKY Memorial Hall/College of Law Expansion and Renovation UK Project No

for selection of Architect for above mentioned work. The scope of the work of the Architect shall be as under:

New Balance Athletic Shoe, Inc.

NOTICE INVITING TENDER (NIT)

Gasparilla Island Bridge Authority REQUEST FOR PROPOSALS TOLL COLLECTION SYSTEM

Transcription:

Construction of 33kV Double Circuit Tavua to Volivoli- Stage 3, 5 (Pole 50 to Pole 93) TENDER NO: MR19/2015 33kV DOUBLE CIRCUIT-TAVUA TO VOLIVOLI Page 1

Bidder s Name: Bidder s Address: Bidder s Telephone Numbers: Bidder s Email Address (Optional): Fiji Electricity Authority is seeking proposals from FEA Trained and Certified Contractors to carry out 33kV Power Line Construction for the 33kV Double Circuit- Tavua to Volivoli -Pole 50 to Pole 93. This will require a total of 45, 17m wooden power poles with a total length of 3.71km, 33kV Neon O/H double line to be strung. 1.0 Notes: 1. Bidders are to submit a breakdown of prices (unit rates) together with total included in this tender document. By providing this information the FEA does not take liability of the actual conditions in field. The bidders / contractors shall verify the actual conditions and the geographic terrain during the site visits. The bidders shall self-evaluate the realities in the field and submit firm prices. No variations shall be entertained. 2. Safety plan to be included in the tender bid 3. Lineman, cable jointer and Trainee/Line worker Certificate to be included in the tender bid 4. Safety report for the year 2014 shall be submitted with the tender 5. A list of Power Line Construction projects completed for FEA shall be submitted with the tender 6. Certification of equipment to be included in the bid 7. Vegetation Management Training certificate shall be submitted with the tender 8. Please pay specific attention to Clause xii under PART 6.1, Contractor Requirements: Lineman Contractor shall ensure that the project has one Certified Lineman and 3 Registered Trainee Line Workers/ Linemen working on the project on a full time basis. Records of these personnel shall be submitted with the tender bid. Contractors unable to submit positive proof that they meet this key requirement shall not be considered 33kV DOUBLE CIRCUIT-TAVUA TO VOLIVOLI Page 2

9. Please pay specific attention to Clause xxv under PART 6.1, Contractor Requirements: Transportation of material The Contractor shall transport all materials from FEA Navutu Stores to work site 2.0 Site Inspection Dates: 1. Site Visits for the 33kV Double Circuit-Tavua to Volivoli shall be held from 9am till 1pm on Wednesday 18 th February 2015. Interested Bidders are to report to Unit Leader Distribution Western in FEA s Navutu Depot, Lautoka. Name: Saimone Rogoimuri Cell Phone:9992419 2. The site visit requirements for this tender are compulsory and attendance shall be recorded 3. Interested bidders shall provide their own Transport and shall not ride in FEA vehicles 3.0 Lodgement of Tenders in sealed envelopes marked It is mandatory for Bidder s to submit two (2) hard copies of the tender bids in sealed envelope shall be deposited in the tender box located at the Supply Chain Office at the FEA Head Office, 2 Marlow Street, Suva, Fiji. Courier charges for delivery of Tender Documents must be paid by the bidders. This tender closes at 4:00pm, on Wednesday 25 th February 2015. Each tender shall be sealed in an envelope with: The envelope bearing only the following marking: Tender- MR 19/2015 33kV Double Circuit-Tavua to Volivoli The Secretary, Tender Committee Fiji Electricity Authority Supply Chain Office Private Mail Bag, Suva It must also indicate the name and address of the tenderer on the reverse of the envelope. All late tenders, unmarked Envelopes and envelopes without bidder s name and address on the reverse of the envelope will not be accepted. For further information or clarification please contact our Supply Chain Office on phone (+679) 3224360 or (+679) 9991587. 33kV DOUBLE CIRCUIT-TAVUA TO VOLIVOLI Page 3

4.0 First Schedule 4.1 Special Conditions of the Contract The work shall comprise of the Construction and installation of 33kV power poles as per attached drawing # A1-03-N57-005 Please enter unit rates and lump-sum prices in the table below. The total Contract sum for the work shall be $ VIP Power Line Construction- 33KV Double Tavua Volivoli Pole 50 to Pole 93 UNIT RATES: Item No. Description Quantity Unit Rate Total Section C: Kings Road Tavua to Rabulu (Refer to drawing # A1-03-N57-005, Sheet 5 to 9) Pole 50 to Pole 93 1 Excavate foundation holes for new wooden power poles to a depth of 3m, install new Wooden Power Pole [17m] complete with dressing and stringing of conductor as per drawing 45 2 Install ground stay 1 LUMP SUM COSTS: Item No. 1 Material Transport Cost Transportation of materials from FEA Navutu Depot to Site Total Item No. Vegetation Management Total 1 Vegetation Management as per actual condition on site 33kV DOUBLE CIRCUIT-TAVUA TO VOLIVOLI Page 4

The total number of 17m poles to be erected as per drawing is 45 poles. However, the exact number depending on the pace at which the Contractor progresses and also as per site conditions. This shall also apply to the accessories and materials to be used for the required poles. Power Pole replacement or upgrading of existing poles shall be carried out under FEA power shutdown and a Permit to Work. The power shutdown shall be customarily from 8.30am to 4.00pm All work on existing power lines to be upgraded or diverted will be carried out by FEA including final connections 4.2 Work Schedule (a) Latest date for commencement of the works: (b) Date of completion of Section C: (g) Date of practical completion of the works: (h) Date for final completion of the works: 7 days from issue of LPO 5 weeks from issue of LPO 5 weeks from issue of LPO 5 weeks from issue of LPO 4.3 Supervision of Contract For the purpose of supervising the contract on behalf of the Authority, references in the General Conditions to the Authority shall include the Unit Leader Distribution Western or his designated officer. The Project Manager shall be the Unit Leader Distribution Western, the Project Engineer shall be the Construction, Operations & Maintenance Engineer Western, and the Project Supervisor shall be the Construction Coordinator Western. 4.4 Insurance (Refer to Clause 14) (a) Contractor's risk $500,000 (b) Public Liability $500,000 (c) Worker's Compensation $250,000 The contractor shall indemnify FEA against any claims for liability, injuries, losses, damages etc that may arise during the execution of the works. 4.5 Liquidated and Ascertained damages (Refer to Clause 20): The liquidated and ascertained damages shall be $200 per day 33kV DOUBLE CIRCUIT-TAVUA TO VOLIVOLI Page 5

4.6 Defects Liability Period (Refer to Clause 21): The defects liability period shall be 6 months 4.7 Retention Fund (Refer to Clause 24) (a) Limit of retention fund: (b) Nature of retention fund: (c) Release of retention fund: 10% of contract sum cash Subject to no pending defect, and as per FEA Finance Policy. 5.0 Second Schedule 5.1 Specifications for the Construction of 33kV Double Circuit-Tavua to Volivoli-Pole 50 to Pole 93 5.1.1 General This specification covers the Construction of 33kV Power Lines for the Supply to Momi Bay Resort- Nadi as per attached Drawing # A1-03-N57-005 under conditions of Contract attached herein. 5.1.2 Scope of Work Work involved in this contract is broadly classified into seven parts: i. Scarfing of the 17m power pole to be carried out at Navutu Depot and transported to Site ii. Transportation of line hardware from Navutu Depot to Site after instruction from FEA iii. Excavate foundation holes for new 17m power poles to a depth of 3m at marked locations iv. Installation of 17m poles complete with dressing v. Stringing of conductors vi. Stay erection- ground and fly stay as specified vii. Vegetation clearing where required- this shall involve clearing of vegetation within 30m either side of the power line pole 33kV DOUBLE CIRCUIT-TAVUA TO VOLIVOLI Page 6

6.0 Third Schedule 6.1 Contractor Requirements i. Tender Bid Contractor shall submit a firm bid clearly listing unit costs for all items as per required and stated. Vegetation clearing and Transportation costs shall be submitted as a lump sum. ii. iii. iv. Site Visit Contractor shall participate in a site visit which is compulsory. Bids from tenderers who do not participate in the site visit shall be disqualified. Standards All construction work shall be in compliance with FEA Standard Overhead Line Design & Construction Manual. Safety Plan The tender bid shall include a Safety Plan that will be evaluated by the FEA s HSE Unit. Tender bids with incomplete, unacceptable, or without a Safety Plan will not be considered for award. v. Safety Record Tender bid shall include a brief report on Safety performance over the last two years. The report shall include all incidents and accidents. vi. Sub-contracting Subcontracting shall not be permitted, except where this is specifically presented in the tender bid, and only upon approval by FEA. Subcontractors shall be required to fulfil all requirements as if they were the contractor. vii. Scope of works - Work involved in this contract is broadly classified into seven phases, and progress payments shall be processed accordingly. a. Scarfing of the 17m power pole to be carried out at Navutu Depot and transported to Site b. Transportation of materials from Navutu Depot to Site after instruction from FEA c. Excavate foundation holes for new 17m power poles to a depth of 3m at marked locations d. Installation of 17m poles complete with dressing e. Stringing of conductors f. Stay erection- ground and fly stay as specified g. Vegetation clearing where required- this shall involve clearing of vegetation within 30m either side of the power line pole 33kV DOUBLE CIRCUIT-TAVUA TO VOLIVOLI Page 7

viii. ix. Contact - Contractor shall have a valid postal address, Office phone/fax/e-mail contact. The Principal shall be available by mobile phone at any time. Work Program - Contractor shall submit a work programme before starting of project. This shall be part of the contract. Work shall commence within seven (7) days after receiving an official FEA Local Purchase Order. x. Training Contractor shall ensure his employees have attended FEA Safety Manual Training and Pole Top Rescue Training at least once in the past 6 months, and records of this shall be submitted with the tender bid. In the event that the training has not been carried out, the Contractor shall ensure these training are carried PRIOR to induction for new project. Copies of training records and valid certificates shall be provided with the tender. Bids without these documents will be disqualified xi. Ground condition Contractors are to note that sub-soil comprises soapstone and could contain other services like Telecom Fiji Ltd, Water & Sewerage, etc. xii. xiii. xiv. Lineman Contractor shall ensure that the project has one certified lineman and 3 registered Trainee Line Workers/ Linemen working on the project on a full time basis. Records of these personnel shall be submitted with the tender bid. Invoicing Contractor shall submit details of work completed to allow prompt approval of invoice. Safety Induction - A Safety induction must be conducted before start of power line construction work. Contractor shall ensure that all employees who work on the project attend the Safety Induction. All contractor employees are to present a valid company ID card clearly showing a current photo, employee name, employee date of birth and employee job description. xv. Instruction to Commence Work - Contractor shall NOT commence work on site unless an Instruction to Commence Work has been received from the Project Manager. xvi. Signboards - One signboard (6 X 4 ) must be erected at the start of the works and one at the end of the works clearly stating : 33kV DOUBLE CIRCUIT-TAVUA TO VOLIVOLI Page 8

DANGER PROJECT: POWERLINE CONSTRUCTION [Description of project] CONTRACTOR: POWER LINE CONSTRUCTION WORK xvii. xviii. xix. Accident Reporting All accidents and incidents shall be reported immediately to FEA using approved forms available in the FEA Safety Plan Template, or equivalent. Project Updates - Contractor shall meet with FEA Project Manager, Project Engineer and Project Supervisor on a weekly basis to discuss project progress and bottlenecks. These meetings shall be minuted for records, and circulated to the appropriate stakeholders. xx. xxi. Vegetation clearing Vegetation clearing shall be in accordance with FEA Vegetation Management Policy. Vegetation, which at a mature height will exceed 2m in height and will be within falling distance from the FEA lines are to be removed. Vegetation debris shall be disposed off neatly at a location agreed to by FEA. No debris shall be left by the roadside, or blocking drains. Tidiness The Contractor shall maintain the worksite in a neat and tidy condition. xxii. Consent for Vegetation clearing no vegetation shall be cleared unless specific instruction to do so has been received from the Project Supervisor. Notwithstanding this, the contractor shall inform the tree owner that he is required to clear the tree, and shall obtain the owner s confirmation that he has given FEA his consent to remove the tree, prior to proceeding with cutting the tree. xxiii. Fires No fires are to be lit at jobsites for the purpose of clearing vegetation or vegetation debris. xxiv. Village Protocols the contractor shall comply with protocols involved in working on land owned by Indigenous Fijians to ensure smooth work progress. 33kV DOUBLE CIRCUIT-TAVUA TO VOLIVOLI Page 9

xxv. xxvi. Transportation of material The Contractor shall transport all materials from FEA Navutu Store to work site, EXCEPT concrete poles Security - Contractor shall be responsible for the safekeeping of all materials at work site, and will be required to pay for damage and/or loss. xxvii. xxviii. Damage to property The Contractor shall ensure that there is no damage to roadways, footpaths, drains, water-courses, properties and other services. The Contractor shall make good to the satisfaction to the owner any damage caused by the contractor. Portable signboards - Portable signboards must be placed at 50m intervals. xxix. xxx. Traffic and Pedestrian Control The Contractor shall ensure that there is minimum disruption to the flow of traffic and pedestrian. FEA procedures on Traffic Control and Pedestrian Control shall be diligently exercised. Worksite protection - Bollards/cone must be placed at 10m intervals. xxxi. Barricades - Open trench/pole-hole is to be barricaded on a full time basis by the Contractor. xxxii. Jobsite Safety Assessment - Contractor to carry out Jobsite Safety Assessment daily, and as and when required, and submit these to FEA on a weekly basis. xxxiii. Contractor HSE Compliance - Contractor shall comply with FEA/Contractor HSE Manual at all times. xxxiv. Credit of surplus material The contractor shall transport and credit all unused materials to FEA Stores. xxxv. Defects Rectification The contractor shall rectify all defects within seven (7) days as per contract. xxxvi. xxxvii. Project completion The contractor shall complete work on time as per contract. Project progress If the Contractor fails to proceed with the works with reasonable diligence or suspends the works or refuses to comply with the reasonable direction from FEA by reason of which the works are materially affected and any such default continues for a period of seven (7) days after the issue of written notice, FEA may itself call any other person to complete the works at the Contractor s risk and expense. 33kV DOUBLE CIRCUIT-TAVUA TO VOLIVOLI Page 10

xxxviii. xxxix. Safe Work Procedure Training - Contractor must have completed Distribution Safe Work Procedure training. FEA/Contractor HSE Manual - Contractor shall comply with FEA/Contractor HSE Manual at all times 6.2 FEA Requirements i. FEA Project Supervisor shall obtain Road/footpath opening permits ii. iii. iv. FEA Project Engineer shall obtain clearance from Municipal Council, Telecom Fiji Ltd, Water Supply Department, and Sewerage Department FEA s HSE Unit shall vet Safety Plan submitted by Contractor and approve after queries clarified by Contractor FEA Project Engineer shall ensure that any FEA underground mains on the jobsite is clearly located, marked and identified to the Contractor v. FEA Project Engineer shall submit to the Project Manager all necessary approval documentation from Municipal Council, Fiji Roads Authority, Telecom Fiji Ltd, Water Supply Department and Sewerage Department. Upon receipt of these approvals, and the approved Safety Plan, the Project Manager shall issue an Instruction to Commence Work to the Contractor vi. vii. FEA Project Supervisor and Project Engineer shall carry out regular site inspections to ensure compliance with HSE requirements, and submit Safety Visit Reports of the visit FEA Project Supervisor and Project Engineer shall issue Non-Conformance Report if required, and follow up for verification of implementation of Action Items arising out of the Non- Conformance Report. 33kV DOUBLE CIRCUIT-TAVUA TO VOLIVOLI Page 11

6.3 Payment Schedule Payment shall be made as per payment schedule: Phase Description Percentage payment 1 Material Transportation to worksite 15% 2 Vegetation Clearing 5% 3 Excavation of new poles, pole scarfing, pole dressing, erection, stays, ABS 50% 4 Conductor Stringing 15% 5 Transformer installation complete 5% 6 Retention 10% to be released after 6 months pending zero defects. 33kV DOUBLE CIRCUIT-TAVUA TO VOLIVOLI Page 12