Wind Commissioning Guidance

Similar documents
Thermal Commissioning Guidance

Summary note: LCCC Wind Generator Commissioning Test workshop 4 August 2017

NATIONAL ELECTRICITY RULES ELECTRICITY CONNECTION FOR RETAIL CUSTOMERS CHAPTER 5A. Page 615

Further Submissions relating to Capacity Market Pre-Qualification

TSO and DSO Protocol. DSO WFPS Testing

TSO and DSO Protocol. DSO WFPS Testing

GOVERNANCE OF THE COMPLIANCE PROCESS Paper by National Grid

Wind Farm Controllability

BALANCING CODE NO. 1 (BC1)

WP33 CFD Electrical Schematic Obligation

CALL FOR COMBINED HEAT AND POWER (CHP) PROJECTS. Program Guide

Interconnector (UK) Limited

ELECTRICITY INDUSTRY ACT ELECTRICITY INDUSTRY (WHOLESALE ELECTRICITY MARKET) REGULATIONS 2004 WHOLESALE ELECTRICITY MARKET RULES

Consultation on DS3 System Services Contracts for Interim Arrangements. DS3 System Services Implementation Project

Connect and Manage Guidance March 2013

Invitation to Tender for the Global Blockage Effect project for the Carbon Trust s OWA Programme

INFORMATION PACK FOR THE CONNECTION OF GENERATOR PROJECTS

Virtual Reverse Flow: at Interconnection Points. Implementing EU Regulations. Code Modification No. A064. Business Rules. 17 th July Version 3.

Dated: April 16, 2002

New developments in best practice for plant and design-build contracts

EU Gas Balancing Code - Daily Nominations at Interconnection Points (IP)

Invitation to Tender

Union Power Cooperative

ARYAN M.P. POWER GENERATION PVT. LTD.

Regulatory Approach to Maintaining Local Security of Supply in Electricity

CLARIFICATION OF GENERATOR TECHNICAL PERFORMANCE REQUIREMENTS (S5.2.5)

Electricity Market Reform Capacity Market Operational Plan

DRAFT FOR COMMENT. Comments should be sent to by * September 2005 PROPOSED AMENDMENT REPORT

Network Code. on Capacity Allocation Mechanisms

REQUEST FOR PROPOSALS (RFP) - Project for Data Cleaning of Industrial Property Documents of Indonesia

NATIONAL ELECTRICITY MARKET GUIDE TO GENERATOR EXEMPTIONS & CLASSIFICATION OF GENERATING UNITS

De-Energisation Code of Practice

STATEMENT OF CHARGES FOR CONNECTION TO NORTHERN IRELAND ELECTRICITY NETWORKS DISTRIBUTION SYSTEM. Effective from 28 th March 2018 Version 1.

ALLIANCE PIPELINE LIMITED PARTNERSHIP by its General Partner, ALLIANCE PIPELINE LTD. ( Alliance Canada or Alliance )

Semi-Scheduled Generation Dispatch Self-Forecast - Assessment Procedure Consultation. December Final Determination

The Power Potential project Heads of Terms Subject to contract

DELIVERY, SHIPMENTAND HANDLING. Special Requirements per Delivery Terms: Reserved.

National Grid Grain LNG Ltd. Third Party Access Arrangements. Guide for prospective Secondary Capacity customers 2017/18

STATEMENT OF CHARGES FOR CONNECTION TO NORTHERN IRELAND ELECTRICITY NETWORKS DISTRIBUTION SYSTEM. Effective from 1 st October 2017 Version 1.

Introduction of Entry Capacity to Northern Ireland Transitional Arrangements

Draft Modification Report Revision of the Gas Balancing Alert (GBA) Trigger/Safety Monitor Modification Reference Number 0257 Version 1.

SERVICE CONTRACT NOTICE. Improvement of energy sector governance in West Africa

ISSUE CERTIFICATE OF PRACTICAL COMPLETION AND INITIATE HANDOVER TO UNIVERSITY

GSR016: Small and Medium Embedded Generation Assumptions

Capability Policy and Procedure for All School Based Staff. Effective from 1 September 2012 CONTENTS

QP 02 Audit and Certification Procedure

May 1, To: Parties currently registered on Proceeding Distributed Generation Review Proceeding Application A001

RoHS 2 GIGREL (The French Generating Set Association) Draft position FAQ Consultation Submission

Invitation to Tender for the Fibre Optic Cable Protection Assessment (FOPA) project for the Carbon Trust s OWA Programme

277/06 - PRELIMINARY TERRE (P344) IMPLEMENTATION IN ADVANCE OF OFGEM DECISION

LCCC and ESC Supplier Event. 10 May 2017

Project monitor services

SECTION PROJECT CLOSEOUT

IkamvaYouth Study Assistance Policy

Virtual Reverse Flow: at Interconnection Points. Implementing EU Regulations. Code Modification No. A064. Business Rules. Version 2.

A GUIDE TO DATA REQUIREMENTS FOR AUSTRALIAN WIND ENERGY FORECASTING SYSTEM (AWEFS)

Non Registered Embedded Generation Information Pack

SECTION PRODUCT REQUIREMENTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS

MEMORANDUM. Revision of Career Service Rule 13 PAY FOR PERFORMANCE

COMMISSION DELEGATED REGULATION (EU) No /.. of

Market Procedure: Network Control Services

PERFORMANCE IN INITIATING AND DELIVERING CLINICAL RESEARCH INFORMATION SUBMISSION GUIDELINES

Tariffs January 1, 2017

where implicit capacity allocation methods are applied, national regulatory authorities may decide not to apply Articles 8 to 37.

Relevant changes will be made to corresponding sections of OA and RAA.

Attendance Procedure. 1 Scope

ISO RESPONSE TO COMMENTS ON DRAFT RELIABILITY DEMAND RESPONSE PRODUCT TARIFF LANGUAGE

the rules which apply where metered data is missing or not supplied to Network Rail within the prescribed time;

The Electricity (Capacity) Market Rules

Joint TSO/DSO Group Processing Approach Pricing Principles Guidelines

Table of Contents. Project Agreement Schedule 14

PERFORMANCE MANAGEMENT PROCEDURE P17-IK-006

Offshore Wind and Beyond: Holistic Approach and Integrated Solutions for a Sustainable Energy Future

Revised Draft Final Proposal for Participation of Non-Generator Resources in California ISO Ancillary Services Markets

Approved by Trustees on the 7/2/17. Sickness absence management policy and procedure guidance for Headteacher / Principal

Probationary Appointments

GUIDELINE. A Guide to. Testing and Commissioning Guidelines PED/SDQS/MN-TNC(V)1/R/0807(116)

Electricity Supply Agreement

The Voice of the Networks

Town of Whitby Public Works Department

Building Control (Amendment) Regulations MBCA Guidance Document

Implementing Change (Redundancy & Restructures) Policy

SERVICE LEVEL PROCEDURE

DELIVERY, SHIPMENTAND HANDLING

ANGLOGOLD ASHANTI LIMITED Registration No. 1944/017354/06 ( AGA or the Company ) REMUNERATION AND HUMAN RESOURCES COMMITTEE TERMS OF REFERENCE

Performance Improvement Policy

NOIDA METRO RAIL CORPORATION (NMRC) LIMITED

Glenwood School Redundancy Procedure. May Service

Nova Scotia Power System Operator (NSPSO)

WIND/SOLAR FARM VENDOR DISCUSSION

Professional Services Contract (PSC) for Consultants Selection Process for NHS Clients

Casework Technical Support (Social Welfare - Project Management)

Design Build: CCDC

CALIFORNIA INDEPENDENT SYSTEM OPERATOR ANCILLARY SERVICES REQUIREMENTS PROTOCOL

ENGINEERING RECOMMENDATION P2/6 SECURITY OF SUPPLY JULY Energy Networks Association Engineering Directorate

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

Invitation For Expression Of Interest For Providing Project Management Consultancy Services At Vidyasagar Industrial Park at Kharagpur In West Bengal

Issue Paper. Direct Participation of Demand Response Resources in CAISO Electricity Markets. December 22, CAISO JEP / BDC/ JDG 12/22/08, page 1

H. R (a) IN GENERAL. Subchapter I of chapter 1 of title 23, United States Code, is amended by inserting after section 138 the following:

University of Edinburgh. Engineering Services. Guidelines

Transcription:

Wind Commissioning Guidance 80% of Installed Capacity Operational Condition Precedent 2.1 (B) Version 2.0 Issued on 31 October 2017 Applicable to Investment Contracts, CFD Agreement and CFD Standard Terms and Conditions issued in August 2014 and March 2017

Contents 1 Introduction 3 2 Definitions 4 3 Context 5-6 4 Commissioning Evidence 7-8 5 Facility Commissioning Evidence 9 6 Phased Projects 10 Disclaimer This guidance does not and is not intended to supersede or replace the provisions of the CFD. This guidance does not constitute legal or investment advice and should not be relied upon as such. Generators should consult their professional advisors where they require advice, whether legal or otherwise. LCCC further reserves the right to amend this guidance and any associated guidance from time to time. This guidance should not be viewed as in any way restricting LCCC in the nature, type and/or amount of evidence, information and documentation it will require to satisfy itself of the Generator s fulfilment of the Operational Conditions Precedent, nor as to the nature, level and timing of our consideration or reconsideration of the evidence that is provided. LCCC reserves the right at any time to request further or additional evidence, and to review or reconsider the evidence already provided. 2

Section 1: Introduction This document provides generators with guidance on the forms of evidence that the Low Carbon Contracts Company considers acceptable in order to demonstrate that no less than 80% of the Installed Capacity Estimate has been commissioned. 1.1 The Operational Conditions Precedent (OCP) must be fulfilled by the Generator in order for it to be able to issue a Start Date Notice and commence generation that is eligible for CFD payments. It is therefore important that Generators give proper consideration ahead of time to how they intend to evidence that they have fulfilled the OCPs. 1.2 This guidance is intended to assist CFD Generators whose Generation Technology is Onshore Wind or Offshore Wind in considering what evidence they will need to provide to the Low Carbon Contracts Company (LCCC) to demonstrate that they have fulfilled the Operational Condition Precedent 2.1(B) at Schedule 1 (Conditions Precedent) to the Contract for Difference ( CFD ). 1.3 As a general principle, it is LCCC s intention that, insofar as it is possible, a Generator should be able to utilise processes, procedures, documentation, and tests that already form part of its commissioning plan as submissable evidence, providing that these meet the requirements and are in accordance with the Reasonable and Prudent Standard. This guidance is indicative of what would be acceptable to LCCC. If a generator is concerned their project may not be in a position to provide any of the alternatives listed in Section 4 they are encouraged to contact their Commercial Manager as soon as possible. 1.4 LCCC would encourage Generators to engage early in the OCP process. This will enable the parties to discuss the approach; and for LCCC to gain an understanding of the Generators commissioning plan. 1.5 Before the Generator proceeds with the formal submission, we recommend that submissions are made in draft form so that LCCC can comment on the following: any evidence that the Generator is intending to submit with the OCP Notice; and the details of any commissioning programmes / proposed pass-fail criteria / planned tests intended to meet the requirements of OCP 2.1(B). 3

Section 2: Definitions 2.1 The CFD Counterparty is the Low Carbon Contracts Company Ltd. 2.2 Defined terms used in this guidance and not defined herein should be given the meaning provided in the CFD (which is comprised of the CFD Agreement and the CFD Standard Terms and Conditions as published by the Department of Energy and Climate Change on 29 August 2014 1 and in March 2017 2 ). This guidance is also applicable to Investment Contracts. However, Generators with Investment Contracts are advised to review the equivalent clauses. 2.3 Please note that Installed Capacity is determined at the export metering point. This document refers to the Installed Capacity and Final Installed Capacity guidance 3 issued by LCCC which defines Installed Capacity as the capacity of the Facility (expressed in MW) were it to be operated on a continual basis at the maximum capacity possible without causing damage to it (assuming any source of power used by it to generate electricity was available to it without interruption). 1 Department of Energy and Climate Change, Contract for Difference: Standard Terms and Conditions, published in 29 August 2014. 2 Department for Business, Energy & Industrial Strategy, Contracts for Difference: standard terms and conditions, version 2 published in 13 March 2017. 3 Low Carbon Contracts Company, Guidance: Installed Capacity and Final Installed Capacity, published in January 2017. 4

Section 3: Context 3.1 The CFD 4 requires the delivery to the CFD Counterparty of: evidence, in form and content satisfactory to the CFD Counterparty, acting reasonably, that an Installed Capacity of not less than eighty per cent. (80%) of the Installed Capacity Estimate has been Commissioned. 3.2 The CFD defines Commissioned as meaning all of the Commissioning Tests have been successfully completed, followed or passed (as appropriate) in relation to the Facility (or a part of the Facility)... 3.3 The definition of Commissioning Tests as set out in the CFD means: all of the procedures and tests which, in accordance with the Reasonable and Prudent Standard, and in compliance with industry guidelines, practices and standards, are: 1) relevant to generating facilities which are the same as, or similar type to, the Facility (including those which are relevant to the Facility Generation Technology); and 2) required to be completed, followed or passes (as appropriate): (i) in order for a generating facility to generate electricity; or (ii) to demonstrate that a generating facility is fit for commercial operation. 3.4 As a result of the definitions that are relevant to OCP 2.1 (B), two overarching requirements need to be evidenced: 1. that the Facility has been Commissioned meaning that the Commissioning Tests have been completed and it can generate electricity or, is fit for commercial operation; and 2. a capacity of at least 80% of its Installed Capacity Estimate can generate electricity on a continuous basis without causing damage to the Facility. 3.5 To fulfil requirement 1 above, LCCC would expect to see evidence of: A. Turbines commissioned; B. Electrical Balance of Plant (EBoP) commissioned; C. Scada functioning at facility level. To fulfil requirement 2 above, LCCC would expect to see evidence of: D. Sufficient number of turbines commissioned to meet 80% installed capacity threshold; E. Whole facility producing electricity (without damaging facility). Sections 4 and 5 of this document set out specific documents that we have considered acceptable to satisfy the two overarching requirements. We have sought to rely as far as possible on industry standard documents. The table overleaf summarises broadly which main documents as a minimum LCCC considers will satisfy each requirement. 4 At Schedule 1, Part B (Further Conditions Precedent), paragraph 2.1 (B). 5

Requirement to be evidenced (as per section 3.5) A. Turbines commissioned Commissioning Completion Certificates Minimum acceptable evidence to satisfy requirement Electrical List of Functional ION B with Whole Facility Notes losses design Tests 70% thresh- test study & Type for EBoP old lifted Certificates B. EBoP commissioned C. SCADA functioning D. Sufficient number of turbines commissioned E. Facility as a whole able to and producing electricity Either ION B or Whole Facility Test required, not both - see detailed section 4 Either ION B or Whole Facility Test required, not both - see detailed section 4 Generators who consider that their project will not be in a position to provide some of the evidence suggested in Sections 4 and 5 below are encouraged to contact their dedicated LCCC Commercial Manager to discuss as soon as possible. 6

Section 4: Commissioning Evidence 4.1 This section provides further guidance on the form and nature of the evidence LCCC is prepared to accept and would expect to find in an Onshore or Offshore Wind Generator s submission of evidence to demonstrate the capabilities listed under 3.5(A-D): A. Evidence of successful commissioning of the Wind Turbine Generators (WTGs) comprising in aggregate not less than 80% of the Installed Capacity Estimate of the Facility in the form of any of the following, (i) or (ii): (i) Dated, valid Take Over Certificates (TOCs) for each of the WTGs comprising in aggregate not less than 80% of the Installed Capacity Estimate of the Facility (see Section 4.1 D on how to perform the 80% calculation). a) The submission should also include a brief written explanation listing the relevant contractual provisions for issuing the TOCs and any relevant condition precedent, or; (ii) Dated, valid Commissioning Completion Certificates (CCC) for each of the WTGs comprising in aggregate not less than 80% of the Installed Capacity Estimate of the Facility (see Section 4.1 D on how to perform the 80% calculation). a) The submission should also include a brief written explanation listing the relevant pass/fail requirements of the CCC and any relevant condition precedent; b) The submissions should be accompanied by a Directors Certificate certifying the WTGs are ready for commercial operation. LCCC does not require the submission of the snagging list related to the above items. B. Evidence of successful commissioning of the Electrical Balance of Plant (EBOP) system required to export energy of not less than the 80% of the Installed Capacity Estimate of the Facility in the form of any of the following, (i) or (ii): (i) TOCs with respect to each contractor supplying and/or installing part of the EBOP (array cables, offshore substation(s), onshore substation(s), transmission cables(s)). The submission should also include a brief written explanation listing the relevant contractual provisions for issuing the TOCs; or (ii) For the equipment forming the EBOP (array cables, offshore substation(s), onshore substation(s), transmission cable(s)), the Generator is expected to provide: a) A list of the commissioning tests performed on the main components forming the EBOP signed by the Generator / Generator s Engineer. The list should include the type of test performed, date of the test, results of the test in binary fashion (pass/fail) and a summary of any anomalies that occurred during the test. As a minimum, the list should include Factory Acceptance Tests (FATs), Site Acceptance Tests (SATs), Pre-energisation Tests and Energisation Tests for the main components; b) Sign-off letter from the Generator/Generator s Engineer confirming that the commissioning process implemented is in line with good wind industry practice, that nothing material is outstanding and that the commissioning process has been completed successfully. For the avoidance of doubt, LCCC is not requesting the actual test report for each main component in (ii) above. LCCC however retains the right to request the submission of actual test reports if required. LCCC does not require the submission of the snagging list related to the items (i) and (ii) above. 7

C. Evidence of wind farm SCADA functionality. The Generator is required to provide evidence that the commissioned WTGs and the wind farm can be operated and controlled, in the form of: (i) Test on Completion result for the SCADA system. (ii) If (i) above is not available, then the Generator must provide the Interim Operational Notification (ION) B document with the 70% restriction lifted (if applicable to the Facility). (iii) If (ii) above is not applicable to the Facility, then the submission of the whole facility test as set out in 5.3c) of this document will satisfy the SCADA related requirement. D. There are two necessary components to evidence that a sufficient number of turbines have been commissioned to meet the 80% threshold: (i) Type certificate of the WTGs issued by the turbine manufacturer indicating the nameplate capacity 5 of the WTG, with the following information: a) Incorporation of power modes shall be reflected on the type certificate where possible. b) In cases where the incorporation of power modes is not reflected in the type certificate, a side letter from the turbine manufacturer shall be provided specifying exactly what has been installed and addressing the increase in capacity due to the operation of power modes. In cases where no power modes have been installed, the Generator will need to provide a Director s Certificate certifying accordingly. (ii) Electrical Losses calculations performed as part of the Electrical System Design Study ( ESDS ). a) The result of the electrical losses calculation from the design study, expressed as a percentage of 80% of the wind farm Installed Capacity Estimate, will be used to determine the quantity of WTGs that need to have the TOCs or CCCs issued as referred to in point 4.1A above to prove that at least 80% of the Installed Capacity Estimate has been commissioned. Example: if the calculations demonstrate electrical losses of 2%, and if the Installed Capacity Estimate is 100MW, the Generator will need to provide TOCs or CCCs (point 4.1A above) for WTGs totalling at least (100MW x 80% x 2%) + (100MW x 80%) =81.6 MW of nameplate capacity 6. b) The requirements of the electrical losses calculation are the following: c) The electrical losses calculation should estimate the electrical losses within the Facility up to the Transmission Entry Point (between the generating units and the fiscal meter); d) The electrical losses should be expressed as a percentage of the wind farm nameplate capacity and the electrical losses should be calculated corresponding to 80% of the Installed Capacity Estimate; e) The electrical losses calculation should include a description of the methodology followed to estimate the electrical losses and the calculations performed; f) Electrical losses should be estimated based on the as-built parameters of the electrical system. The report/study should include a description of the wind farm electrical design, including main components rating, cables rating and dimensions; and g) If the design assumptions used for the study do not reflect the as-built parameters of the electrical system (i.e. if any changes have been introduced during construction and are not reflected in the study), the Generator should provide an updated version of the Study that reflects the introduced changes. 5,6 Nameplate capacity being equal to the sum of the capacity indicated in the type certificates (taking into account any power modes incorporated) and any other additional capacity noted in any side letters referred to in 4.1D(i)b) of this document. 8

Section 5: Facility Commissioning Evidence 5.1 This section provides further guidance on the form and nature of the evidence LCCC is prepared to accept and would expect to find in an Onshore or Offshore Wind Generator s submission of evidence to demonstrate item 3.5E. Applicability to Phased Projects is clarified in Section 6. 5.2 Facilities connected to the Transmission System should provide an Interim Operational Notification (ION), and if applicable, with the relevant 20% and 70% restrictions (hold-off points) lifted. Offshore wind projects should provide an ION B with the relevant 20% and 70% restrictions (hold-off points) lifted. 5.3 For Facilities connected to the Distribution System, or for Facilities connected to the Transmission System for which the 70% restriction of the ION does not apply, 7 the below are required: a) the G59 test (only for Facilities connected the Distribution System); b) a letter from the respective Distribution Network Operator (DNO) confirming that no connection capacity restrictions apply (only for Facilities connected the distribution system); c) performance of a whole Facility test whereby: (i) The test duration will be 30 consecutive minutes; (ii) The purpose of the test is to demonstrate that the commissioned WTGs and all the associated Facility equipment are effectively operating together (rather than in isolation); (iii) Generators must demonstrate through the provision of relevant SCADA data that: I) The average wind farm availability of the commissioned WTGs during the 30-minute period was not less than 85%; II) For each commissioned WTG that is considered for the test, the average availability during the 30-minute test period was not less than 65%; III) Availability for the purposes of (I) and (II) above should be recorded per WTG through the SCADA system in 5 or 10-min intervals and in binary fashion (i.e. WTG available or not available), independently to the environmental conditions experienced and whether the WTGs actually produce energy or not; IV) All commissioned WTGs under consideration were generating some power for not less than 65% of the test duration (i.e. any time when the wind speed is lower than the cut-in speed of the WTG and therefore the WTG is not producing power will be considered as downtime, even if the WTG is otherwise operational ). Further Requirements for all Facilities 5.4 Facility layout and single line diagram indicating the main equipment (including monitoring equipment) and their location. 5.5 Please note that as part of LCCC s assessment of this OCP, LCCC will require to visit the onshore site 8 with its technical advisor during or, shortly after, commissioning. The scope of the site visit will be to perform a visual inspection of the onshore Facility, including confirming the number of WTGs installed through live CCTV footage if available or through the use of satellite images, to confirm that the required capacity has been commissioned under the CFD. 7 Either because the capacity of the Facility is below the National Grid threshold for such restriction to be required, or because the Facility holds a Phased CFD agreement with the capacity of the Facility belonging to the relevant phase being such that the ION B 70% restriction cannot be lifted without the subsequent phase(s) being commissioned. 8 For Offshore wind projects, though the intention is to limit the visit to the onshore facility, LCCC may also require a visit at the Offshore facility too. Wind Title of Commissioning document hereguidance - 80% of Installed Capacity 9

Section 6: Phased Projects 6.1 The commissioning evidence requirements set out in Sections 4 and 5 of this guidance apply per phase for multiphased projects. 6.2 When a document/test is by industry standard applied to all phases (e.g. ION B), any requirements will be pro-rated according to the MWs of the phase that OCPs are submitted for. 6.3 With regards to apportioned metering phased contracts, the SCADA requirements under 4.1C above will differ. As CFD payments in apportioned metering contracts are based on SCADA data across all phases, reliance on SCADA is critical and therefore commissioning of the SCADA system for each operational WTG belonging to any phase should be fully evidenced. 6.4 Generators with Apportioned Metering contracts are invited to discuss with LCCC at the earliest opportunity how they can meet this requirement. Wind Title of Commissioning document here Guidance - 80% of Installed Capacity 10

Low Carbon Contracts Company Ltd Fleetbank House 2-6 Salisbury Square London EC4Y 8JX lowcarboncontracts.uk e: info@lowcarboncontracts.uk Company registration number: 08818711 Publication date: October 2017