October 20, 2017 CAPITAL PROJECT AND PLANNING UPDATE MURDAUGH HALL:

Similar documents
Landscape elements will be completed between now and Spring Break by UCO Contractor should have resolved parking lot lighting issues

Completed. Project. Melbourne High School. Comprehensive Additions and Renovations

Stephen F. Austin State University Board of Regents - Building and Grounds Committee Construction Update July 23, 2018

Grossmont-Cuyamaca Community College District Facilities Construction Update

BOARD OF TRUSTEES OCTOBER 13, 2014

CONSTRUCTION REPORT. Zionsville Community Schools Zionsville, Indiana. October 2014 TSC NO

Auburn University Construction Project Update March 2010

January 1, 2009 March 31, 2009

Program Update. Data and Telecom Cabling-VPA, New Gym, & Physical Science. Physical Science Complex-Roof Replacement

University of North Florida BOARD OF TRUSTEES. CAMPUS PLANNING, DESIGN & CONSTRUCTION CAPITAL PROJECTS UPDATE September 27, 2013

SAMUEL CLEMENS ADDITIONS & RENOVATIONS ( )

Facilities Maintenance & Operations Update. Presidents Executive Cabinet March 6, 2017

SAMUEL CLEMENS ADDITIONS & RENOVATIONS ( )

SAMUEL CLEMENS ADDITIONS & RENOVATIONS ( )

KRISTOPHER J. BRICE Construction Management Faculty Consultant: Dr. Christopher Magent

Program Update. Chino Health Science Parking Lot

SANTA ANA COLLEGE FACILITIES COMMITTEE MEETING OCTOBER 18, 2016

MONTHLY EXECUTIVE UPDATE MARCH 21, Thursday, March 21, 13

LOVEJOY Independent School District

REGISTER OF IOWA STATE UNIVERSITY CAPITAL IMPROVEMENT BUSINESS TRANSACTIONS

Grossmont-Cuyamaca Community College District Facilities Construction Update

PIERCE HALL RENOVATION

Projects Currently in Planning, Design and Construction. April 12, 2017

Request for Proposal for GC/CM Consultant Services Ferndale School District. Secondary High School GC/CM Program. October 19, 2018

CONSTRUCTION UPDATE. April 2017 THIS IS PROGRESS. THIS IS AUBURN.

Facilities Planning & Management

School of Business Project # Overall Project Cost: $26,700, Architect: Urbahn. Scheduled Completion Date: 10/2014.

Instructional Science Facility Phase I

PROJECT COMPLETED. Bayside High School. Comprehensive Additions and Renovations

July 15, 2010 Report No. 11 MONTHLY CONSTRUCTION PROGRESS REPORT METROPOLITAN ENTERTAINMENT & CONVENTION AUTHORITY

Capital Project Recommendations Presented to the Board of Education 9/23/2014

PROJECT # University of South Carolina, Aiken USCA Convocation Center Shed Aiken, South Carolina ADDENDUM NUMBER

SANTA ANA COLLEGE FACILITIES COMMITTEE MEETING APRIL 17, 2018

MOORESTOWN HIGH SCHOOL REFERENDUM PROJECTS

June 10, 2010 Report No. 10 MONTHLY CONSTRUCTION PROGRESS REPORT METROPOLITAN ENTERTAINMENT & CONVENTION AUTHORITY

SAMUEL CLEMENS ADDITIONS & RENOVATIONS ( )

BUCKNELL UNIVERSITY PROCEDURES FOR RENOVATIONS AND NEW CONSTRUCTION

Oconomowoc Area School District Facility Construction Update July 27, 2018

Columbia University School of International + Public Affairs Center on Global Energy Policy Project Construction Logistics.

CONSTRUCTION UPDATE November 2018

January 18, 2010 Report No. 7 MONTHLY CONSTRUCTION PROGRESS REPORT

Merritt Island High School

APPA Chicago August 2015

Auburn University Construction Project April

ACEC/MA 15th Annual State Markets Conference

Renovations & Addition Carroll County, Kentucky BG RTA 1233 CONTRACT DATE: March 24, 2014 CONTRACT FOR: General Construction

PROJECT UPDATES: 1.01 Cox Building Annex - Tony Salcido (3 min)

July 1 September 30, 2008

Facility Improvements

CONSTRUCTION UPDATE JUNE 2015 THIS IS AUBURN.

FACILITIES Summer Projects. September 8, 2015 Board Meeting

Portsmouth Middle School Additional Funding Request

CONSTRUCTION UPDATE. April AUM Projects. Client: Housing and Residence Life Construction Cost: $28 million Completion Date: July 2013

Frost Technical Center

HOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #69 Douthit Hills Student Community, Clemson University Project Joe Jett

Basic renewal/restoration and safety projects

Capital Improvement Program Monthly Status Report

Ohlone Community College District

Oconomowoc Area School District Facility Construction Update June 29, 2018

*Additional Projects were not part of the voter-approved 2006 Bond. They were able to be completed due to savings from other projects.

PROJECT UPDATES. Capital Planning and Space Management Office April 2015

Hinsdale Township High School District 86 Referendum Project Listing April 2, Approved

New Hall High School Project Summary Report to the Board of Education June 3, 2015

Business Affairs Committee Dobo Recovery Update. February 7, 2019

March 24, 2011 Report No. 17 MONTHLY CONSTRUCTION PROGRESS REPORT

Bronx Community College. Five-Year Capital Plan FY through FY

SECTION CONSTRUCTION OPERATIONS AND SITE UTILIZATION PLAN

Health Life Safety Survey and Master Facilities Plan

UNCW Board of Trustees. Facilities Update. October 27, 2016

FY CAPITAL IMPROVEMENT PROGRAM MID-YEAR STATUS REPORT

Suburbia, USA. Image Courtesy of The Whiting-Turner Contracting Company

CORVALLIS SCHOOL DISTRICT Long-Range Facility Master Plan. Community Information Meeting

PHYSICAL RESOURCES COMMITTEE MEETING PROJECT UPDATES FEBRUARY 3, 2016

APSU PROJECT REPORT. Client. Athletics REMAINING BUDGET STATUS. Client. Athletics

Annual Report to the CITIZENS GENERAL OBLIGATION BOND OVERSIGHT COMMITTEE. January 2011

Andover Schools Facilities Update

Cultural Facilities: Capital Needs Inventory and Priorities. Arts, Culture and Libraries Committee October 17, 2016

MARCH 23 FACILITIES MASTER PLANNING AND OVERSIGHT COMMITTEE Included Materials

Invitation to Bid. RLS Construction Group requests your firm to submit a quotation on the following project:


Derby Hall. Herrick Archives Number 025 A. IDENTIFICATION & LOCATION

University of North Florida BOARD OF TRUSTEES. CAMPUS PLANNING, DESIGN & CONSTRUCTION CAPITAL PROJECTS UPDATE January 18, 2011

JMU Capital Projects SWaM Outreach Event Presentations

Long Term School Funding Program Measure M Component: Citizen s Oversight Committee Report

Jackson Miracle Building Plan Outreach Roundtable. February 14, 2017

Planned Procurement Opportunities Report. August 2017

Planned Procurement Opportunities Report. August 2017

PROJECT UPDATE August 28, 2014

State College Area School District Memorial Field Phase 2 Update

LANSDOWNE HIGH SCHOOL RENOVATION PRELIMINARY DESIGN PRESENTATION. The Board of Education of Baltimore County Verletta White, Interim Superintendent

PROPOSITION R Citizen s Bond Oversight Committee

Planned Procurement Opportunities Report. September 2017

North Allegheny School District

MONTHLY PROGRESS REPORT

HOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #77 Douthit Hills Student Community, Clemson University Project Joe Jett

Semi-Annual Report. January 1, 2012 June 30, 2012

Orange Education Center Project Update. Board of Trustees Meeting February 25, 2019

Boynton High School & Blackford Site

October 1, 2008 December 31, 2008

Facilities Services Newsletter Summer 2012

Transcription:

October 20, 2017 CAPITAL PROJECT AND PLANNING UPDATE MURDAUGH HALL: Final pay applications and change orders in progress, still in discussion with AH Received final Change Order and Close out documents Oct. 18 th from AH and FSB Will go to the January 2018 RUSO for final project close-out +- $117K withheld from AH contract. Smaller projects continue by Alpha and Housing DINING FACILITY: Start Date: Jan. 2018 Completion: Fall 2019 Size: TBD Total Project Budget: $19,000,000 Contractor: Lingo Construction (CMR) Architect: ADG Architects Client/ADG/Lingo/AES (Team) bi- weekly meetings continue, next is Nov. 1 st ADG/Lingo presented scope revisions, size, and costs at Team meeting October 18 th Planning of kitchen/food services area is on-going to tighten up the space, program, equipment list and costs Project schedule will be revised when scope and costs are finalized but occupancy and operations will likely be pushed to October/November 2019 Discussion to not begin construction until after NCUR April 4-7, 2018 due to heavy use of HFH to allow for construction on site for late April, 2018 PERFORMING ARTS CENTER: Start Date: TBD Completion: TBD Size: TBD Total Project Budget: TBD Contractor: TBD Architect: City of Edmond with Hornbeek Blatt Steering Committee met twice this past week to review the Consultant Team s feasibility assessment. The team found that there is a need for a 600 to 1000 seat facility. o A 250 seat theater and school of Music is included in both scenarios. Discussions were centered around: o The building program, both shared and dedicated spaces o Potential sites o Business plan 11/28 Presentation to UCO Cabinet: 8:00am 9:30am 1

CAMPUS MASTER PLAN: Start Date: Dec. 2015 Completion: October 2017 Size: NA Total Project Budget: $250,000 Architects: Rees Associates Met with Provost Barthell and Assoc. Provost Simmons (Oct 2) Met with Kevin F (Oct 3) to update and review status Meeting with President (Nov 1 st at 2 pm) Public meetings scheduled mid-november Final meeting to present to UPC (Nov. 10, 2017) 3 campus maps essentially will define proposals for campus growth to include: o Projects completed and or under construction o Project in planning with proposed next identified projects and; o Potential projects as defined in the Capital Master Plan (Legislative Long Range Planning Commission report) Final report completion December 2017 for potential January 26, 2018 RUSO SOUTH CENTRAL PLANT: Start Date: Jul. 2016 Completion: Early Fall 2017 Size: 6,500 sq ft Total Project Budget: $18,500,000 Contractor: Timberlake Construction & Johnson Controls Engineer: Robert Piland (JCI holds contract) Three major components: (Work for all three is currently underway) $3M building to house the plant equipment - start date: 11/15/16 completion: Fall 17 Work is complete. (excluding minor details to be provided by JCI) $12M chiller plant equipment and controls - start date: 2/24/17 completion: Fall 17 Installation work inside the plant is substantially complete. Testing, balancing, and automation of the system will continue until end of the year. Site repair work and sodding are underway. $3.5M underground piping - Clean-up is scheduled to be complete by Nov. 15 th Final connections to Health & Phys. Ed. Building and Math and Computer Science are underway and will be complete no later than Dec. 31 Mitchell Hall Theater connection to take place spring of 2018. NOTE: Remaining Balance of funds will be directed towards the addition of a Central Plant connection north of Ayers, for use by: New Dining Facility, Hamilton Field House, New North Hamilton Annex, & Wantland Stadium. 2

STEM TEACHING & RESEARCH CENTER: Start Date: Jan. 2017 Completion: Fall 2018 Size: 55,000 sq ft Total Project Budget: $24,000,000 Contractor: Lippert Brothers Architect: Elliott + Associates Structural Steel work complete. Mechanical, Electrical, Plumbing, Roofing, Framing, and Masonry work are all underway. AV/IT, Furniture, and Electronic Door Access meetings are on-going. (procurement will occur Spring Semester) Prior to Thanksgiving, Lippert will provide updated schedule. Overall the project is on schedule to meet substantial completion date. LIBERAL ARTS ADDITION: (KT/TD) Start Date: Fall 2017 Completion: Summer 2019 Size: 55,000 sqft Total Project Budget: $18,350,000 Contractor: Lippert Brothers Architect: Beck Design 100% review documents to AEE/AHJ on Oct. 23 rd Project to advertise for bid Oct. 26 th Bid opening Nov. 16 th Site Mobilization, Thanksgiving break Ground breaking ceremony Nov. 29 th Open for classes Fall of 2019 Numerous trees will be relocated to south side of Business over Thanksgiving break. SPORTS PERFORMANCE CENTER: (KT/RH) Start Date: Apr. 2017 Completion: Fall 2018 Size: 41,000 sq ft Total Project Budget: $14,000,000 Precast concrete panels installation and structural steel work are underway. AV/IT, and Electronic Door Access meetings are on-going as well. (procurement will occur Spring Semester) Studio Architecture is developing options for furniture and equipment; will work with Athletic Department and A&E Services to determine preferred selections. Project is on schedule to meet or beat contractual completion date of 08.24.18 Move in to follow, approx. 4-6 weeks. 3

NORTH HAMILTON ANNEX: Start Date: Summer 2018 Completion: Fall 2019 Size: 26,000 sqft Total Project Budget: $10,500,000 Design work underway JE Dunn provided schedule: o 03/20/18 100% Bid documents o 03/23/18 04/31/18 Bid and Contract o 05/01/18 to 06/29/18 Building Demo o 07/09/18 Construction Start o Fall 19 Construction Complete TEMPORARY WRESTLING/ HITTING FACILITY Start Date: Summer 2017 Completion: Spring 2018 Size: 8,000 sqft Total Project Budget: TBD JE Dunn provided schedule: o 09/15/17 100% Bid documents o Bids received 10.17.17 o 11/01/17 Construction Start o Spring 18 Construction Complete BASEBALL FACILITY Start Date: Fall 2017 End Date: Spring 2018 Total project budget: $2,500,000 Updated cost proposal for phase one expected back from vendor early next week. Phase one work will include new field turf playing surface and outfield wall system. The work is expected to be complete by early spring for the upcoming season. Phase two to include dugouts, press box and locker room. Work to begin early summer. 4

TRANSPORTATION AND PARKING: Start Date: Jan. 17 Completion: August 20, 2017 and Late July 2018 Size: NA Total Project Budget TBE Contractor: TBD Architect/Engineer: Dewberry Design/Wallace Engineering Lot 10 Reconfiguration, LOT 14, 15 (Visitor and Event Parking) o Dewberry will begin design modifications for Lot 10 in early Oct. 2017 for completion January 2018 o Renovations may be done summer 2018 and summer 2019 pending extent of changes o New request from T&P for an engineered review of existing Parking Lot conditions to begin for integration into Parking Committee HFH SEATING REPAIRS Start Date: Spring 2018 End Date: Summer 2018 Total Cost: $200,000 Received quotes from Hussey and Irwin seating vendors to replace North/South seats. Existing units in good condition will be used to replace damaged seats at East/West. HOH GREENHOUSE FABRICATION Start Date: Fall 2017 End Date: Fall 2017 Total Cost: $45,000 New electrical and plumbing services to the building were installed last week. The existing fence was removed and reinstalled last week as required. New concrete foundations for the greenhouse are being poured this week. 5