SYSTEM DEVELOPMENT EXTENSIVE RURAL ELECTRIFICATION PROGRAMS - EGYPT CASE

Similar documents
International Symposium on Solar Physics and Solar Eclipses (SPSE) 2006 R. Ramelli, O. M. Shalabiea, I. Saleh, and J.O. Stenflo, eds.

Distribution Network Planning for Mumbai

POWER INDABA CONFERENCE

ADDRESS BY MINISTER FOR ENERGY, DR. JOE OTENG-ADJEI

BANGLADESH: DISTRIBUTION SYSTEM UPGRADE AND EXPANSION PROJECT

COST ANALYSIS OF RENEWABLE ENERGY FOR POWER SUPPLY FOR REMOTE AREA IN YEMEN : A CASE STUDY FOR SOCOTRA ISLAND

STANDARD DRAWINGS. September 2013 UPDATED FEBRUARY 2016

Green+ ELECTRICITY AUTHORITY OF CYPRUS. NER 300 European Program 2 nd call of proposals Zero Energy Mountains of Cyprus. Green

Additional Information on Project Components

Optimum Design and Evaluation of Hybrid Solar/Wind/Diesel Power System for Masirah Island

Action Fiche for EGYPT

POWER SECTOR IN SOUTH SUDAN

The women in our village want solar panels so their children can study at night.

Power Systems 2 ELE3015. Lecture 1: Transmission Lines

Transmission Systems of the Future: Trends, Challenges and innovative Solutions

North of Scotland Future Energy Scenarios. August ssen-transmission.co.uk

2 FINDING OF THE POTENTIAL SITES

A SUBSTATION CONCEPT FOR CHANGEABLE LOAD CONDITIONS

SUMMARY OF DISTRIBUTION BUSINESS

Renewable Energy Contribution to Energy Independency in Palestine. Eng. Emad Khader July 2016

RENEWABLE ENERGY SYSTEMS WIND ENERGY (1) Prof. Ibrahim El-mohr Prof. Ahmed Anas. Lec. 5

Ministry of Infrastructure The Republic of Rwanda AFRICA ENERGY FORUM JW MARRIOTT HOTEL, DUBAI 9 th JUNE, 2015

SECTOR ASSESSMENT (SUMMARY): ENERGY (ELECTRICITY TRANSMISSION AND DISTRIBUTION)

Energy from the Desert

Embedded microgrids within the InterFlex project

SCALING-UP RENEWABLE ENERGY PROGRAM (SREP) COUNTRY INVESTMENT PLAN KENYA

research works are to be continued to define the potential

Construction of overhead lines in environmentally sensitive areas

THE DISTRIBUTION SYSTEM SECURITY AND PLANNING STANDARDS. Asset Management & Regulation, ESB Networks

SECTOR ASSESSMENT (SUMMARY): ENERGY

Current & future grid infrastructure. Lewis Dale Regulatory Strategy Manager

RENEWABLE ENERGY SYSTEMS HYBRID ENERGY SYSTEMS APPLICATIONS

Electric Power Systems An Overview. Y. Baghzouz Professor of Electrical Engineering University of Nevada, Las Vegas

Renewable Energy & Energy Efficiency in Egypt

Electric Power Systems An Overview. Y. Baghzouz Professor of Electrical Engineering University of Nevada, Las Vegas

Dynamic Analysis of Transmission Tower

MIEL I Hydroelectric Power Plant

Tigran MELKONYAN Head of Foreign Relations Department Ministry of Energy and Natural Resources of RA November, 2014 Bangkok, THAILAND

The ambitious rural electrification programs initiated by the State are major and structuring vehicles of socioeconomic

ELECTRICITY SECTOR 1

The Ultimate Goal of the Ministry of Energy

Total Transmission Cost Estimate for the Maximum Reserve Capacity Price for 2018/19

The Brightness and Township Electrification Program in China. Prof. Ma Shenghong Beijing Jikedian Renewable Energy Development Center June.

POWER SYSTEMS RENEWABLE ENERGY SUSTAINABLE ENERGY

The Energy Service of the Ministry of Commerce, Industry and Tourism has the overall responsibility of Energy in Cyprus and specifically for:

EPS. Organization Chart. Civil Sector Head. Steel Structures Dept. Manager. Supervision Dept. Manager. Concrete structures Dept.

Operational optimisation of generation, transmission and distribution Human resource development Training of utility staff and management

BRIGHTER SOLUTIONS FOR GREEN ENERGY KEYNOTE SPEECH BY:

Planning A Strategic Tool to Power System Management

National Energy Policy 1995

A new map for urban development in Egypt, depending on mega projects of renewable energy

RURAL ELECTRIFICATION AGENCY OF NIGERIA

sustainable Energy Deployment in Egypt

Feasibility of Wind Power Technology Schemes in St. Martin s Island of Bangladesh

Ergon Energy Corporation Limited 12 November 2009

Ergon Energy Corporation Limited 4 June 2010

Renewable energy: Investing in Africa

Kenya: Some Facts. Services, Industry, Mining. electricity inadequate (35% of households). Target is universal access of electricity l

UNIFIED REGIONAL PLANNING OF ELECTRICITY AND GAS DISTRIBUTION NETWORK WITH GIS ORIENTED PLANNING SOFTWARE

Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. Report No.

Design and Simulation of Micro-Power System of Renewables

Big Thunder Wind Park

Jawaharlal Nehru National Solar Mission

The Future of Renewable Energy in Libya

Session IV: Access to Electricity Services in Rural Areas

Electric Power Systems An Overview

Electrical Network Design, Engineering & Construction

Smart Grid Development in Taiwan

Lebanese National Renewable Energy Grid Code

The Distribution System Security and Planning Standards

Information Document Protection System Information ID# R

Contents. 1 Introduction Background Aim of this document The Network in Dumfries and Galloway Asset Replacement...

15 TH ANNUAL EAST AFRICAN POWER INDUSTRY CONVENTION

Ing. Andrew T Barfour, FGhIE,FID Director/Project Coordinator GEDAP Ministry of Energy & Petroleum GHANA

Energy Storage for micro- and minigrids in urban and rural Africa. Maxine Ghavi, Group SVP, Program Director Microgrid, ABB

JICA s Cooperation for Electricity Sector in Jordan

A Proper Design of Wind Turbine Grounding Systems under Lightning

Developing Infrastructure in Bihar

CIGRE STRATEGY Prelude to next Century

Ex-Ante Evaluation (for Japanese ODA Loan)

BASIC CONCEPTS. Yahia Baghzouz Electrical & Computer Engineering Department

Introduction to Substation Design TADP 542

THE RENEWABLE ENERGY IN LIBYA: PRESENT DIFFICULTIES AND REMEDIES

End-to-end electrical solutions for the biggest challenges involved with connecting wind energy to the grid. Solutions for Wind Energy Integration

The Ghana Experience in Funding Rural/Renewable Energy Through Levies on Fossil Fuels and Electricity

MoEW Energy Sector Strategy LCRP

Projection of the Future Electricity Demands ( ) for Rajasthan, India and a Sustainable Development Energy Model for Developing States

DRAFT. GUIDELINES FOR Usage of AIR INSULATED SUBSTATION (AIS) or GAS INSULATED SUBSTATION(GIS)

HORNS REV 1 OFFSHORE WIND FARM

GOVERNMENT OF THE ARAB REPUBLIC OF EGYPT

Rural Electrification by Renewable Energy in Cambodia

Ontario ENGINEERING STANDARD SPECIFICATION 1/10 REV. ELECTRICAL DISTRIBUTION HIGH VOLTAGE SUBSTATION GROUNDING AND BONDING. Approved by.

MAXIMIZING. Making Use of Existing Roofs

Towards a sustainable Romanian energy sector: Roadmap to RES in 2030 Deloitte Romania, June 2018

Getting Smart Answers! Kevin W. Chiu. Siemens AG

Kintyre Hunterston Link. The upgrade of grid access in Kintyre

Modelo de regulação do setor elétrico na Inglaterra. Paul Whittaker Diretor de Regulação da National Grid

A Fundamental Utility Restoration and Evolution Using GIS. City / Code: Beirut ArcView and other developed applications

RÍO AMOYÁ - LA ESPERANZA Hydroelectric Power Plant

9001:2008 7, 1, 2018 II. RENEWABLE ENERGY AND SUSTAINABLE DEVELOPMENT STRATEGY

Transcription:

SYSTEM DEVELOPMENT EXTENSIVE RURAL ELECTRIFICATION PROGRAMS - EGYPT CASE ENG. EL DESOUKI M. ALI ENG. AHMED HASSAN ENG. LAILA MOHY RURAL ELECTRIFICATION AUTHORITY MINISTRY OF ELECTRICITY & ENERGY Egyptian rural society represents over half of its total population. Since 1970, rural society had not experienced any progress either in social or economical fields. As it is well known that electricity plays the main role in a country progress. In 1971 it was decided to start a limited program for electrification the rural areas. In early 1990s, the Egyptian Government has given priority to implement fullscale rural electrification program to cover the whole country. In fact, this project is not limited to electrify villages and attachments but also extends to play an active role in supplying electricity to different national projects (land reclamation, new residential cities, industrial zones, etc.) to serve the continuous development of the society as a whole. This calls for extending thousands of kilometers of medium and low voltage lines, constructing of hundreds of distribution panels and transformer points and erecting high voltage networks up to 66 Kv. Challenges has started to face decision-makers for design and planning of such distribution systems which have required new modern and effective software programs. Rural Electrification Authority s top management decided to modernize its work procedures to have a proper design and reducing the time it takes to design the new electrical network and develop and rehabilitate the existing one. Latest Electricite de France (EDF) software programs and knowhow have been introduced within the framework of French - Egyptian cooperation to perform such complex planning and design. Now, immense change is achieved having significant influences on the way electric systems are planned and designed. On the other hand, because there are still limited communities scattered very far from the unified electric networks, where it is very costly to extend the grid to such communities. The Egyptian Government has launched a program to apply new and renewable energy technologies. Technical feasibility studies are carried out to supply electricity to such various remote and desert areas. Rural Electrification project is considered a success project since about 98% of rural inhabitants in Egypt are now enjoying electricity and passing through dynamic changes with better style of life. As illustrated, Egypt is one of the world achievers and certainly the lead country among the developing countries in that field. A quick look at the electrical distribution map of Egypt realize that design and planning of the distribution of electrical networks are performed now in a manner that will assure the continuity and reliability of the power supply, and in the meantime reducing the distribution system losses and costs.

SYSTEM DEVELOPMENT EXTENSIVE RURAL ELECTRIFICATION PROGRAMS - EGYPT CASE ENG. EL DESOUKI M. ALI ENG. AHMED HASSAN ENG. LAILA MOHY RURAL ELECTRIFICATION AUTHORITY - MINISTRY OF ELECTRICITY & ENERGY 1- INTRODUCTION This paper presents the topic of implementation of the extensive rural electrification programs in Egypt. It demonstrates how Egypt, like many other countries in the developing world, is seeking to provide better living standards to the people specifically in rural zones throughout the accelerated economical and social development plans. This project through out its long history was considered to be a top priority and treated with a sense of utmost urgency to curtail the wide gap between urban and rural inhabitants. A strategy has been established to reach rural areas, remote and isolated zones allover the country that can be supplied with electrical energy, either by the conventional way or by using new and renewable energy sources. This calls for extending thousands of kilometers of medium and low voltage overhead transmission lines and constructing hundreds of transformer points. Challenges facing decision-makers for design and planning of distribution systems have required new modern and effective software programs. So, Rural Electrification Authority s top management decided to modernize its work procedures. Latest Electricite de France (EDF) software and knowhow programs have been introduced to perform such complex studies and in the mean time to ensure reliability of power supply. Egypt has made rural electrification a priority and, as a result, close to 8 million dwellers now have access to electricity. This figure includes about 36.3 million (out of 37.3 million) people who were provided with access to electricity in the 29-year period from 1971 to 2000. 2- RURAL ELECTRIFICATION PROJECT HISTORY Before the start of the project, most of rural inhabitants were essentially dependent on traditional fuels such as kerosene, biomass, dung cake, etc. The electrification of the rural areas was very limited, it represent only 5% of total number of towns and main villages. In 1970, having enough installed electrical power and extended networks covering most of the country, the Egyptian Government realized that supplying electricity to rural areas is the gateway for the sustainable development for such areas and to achieve real development for transferring rural society from a primitive consumption community into a productive civilized one. It was agreed to give full attention to initiate a national project for electrification to cover such areas. Implementing such sizable project was so costly for private sector or any non-governmental bodies to afford. Accordingly, the Egyptian Government decided to launch that project. In 1971, the Rural Electrification Authority (REA) has been established to take over this responsibility. REA has been charged with following tasks: 1) Implementing all works related to rural electrification projects, its development and enforcement of the existing distribution networks, all including substations and overhead transmission lines of low, medium and high voltage up to 66 Kv. 2) Performing all electrical connections to supply loads from 0.5 Mw and more for governmental projects, authorities and similars in cities, villages, and land reclamation areas. 3) Planning and studies in the field of REA s activities. At the start of the project the total population of Egypt were about 27.5 Million inhabitants over 17.5 Million of them were living in rural areas and the rate of population growth was 2.8 %. 2-1 Planning and Technical Studies Several studies were conducted covering different alternatives of electricity policies based on economic variables. The studies have been carried out using technical assistance of other countries that have experience in this field. It was decided to focus first on those areas with high-density population, high economic growth potential and lowest cost. The target of the project was to finalize the electrification of 3500 villages and 119 towns in 10 years. In 1971, load demand was estimated at 5 Watts/Capita but ten years later that value had to be increased to 40 Watts/Capita. The necessary equipment for the job was estimated to be: Π24 substations 66,33/11 Kv of total installed capacity about 500 MVA together with 500 Kms overhead transmission lines 66 & 33 Kv. ΠComplete transformer substations 11/ 0.4 Kv

(pole mounted/kiosks) of total installed capacity of 1500 MVA. Construction of the medium and low voltage overhead transmission lines. The following set of criteria and parameters were adopted as basis in planning the electrical networks of the rural areas: Œ Operating medium voltage to be 11 Kv, 3- ph scheme and the low voltage 380/220 V, 3- ph, 4- wire system. Œ The system should be solidly earthed. Œ The rural loads are considered as third class category. Œ Single circuit, radial system is the general configuration. Œ Single circuit, ring system configuration using devices for connecting and disconnecting to ensure continuity of supply for some specific loads in urban areas. Œ Using local manufactured equipment as much as possible. Œ Voltages drop at the end user not to exceed ± 7.5 %. During the implementation of the project, several obstacles had hindered and delayed the implementation of the project according to its schedule such as: shortage of capital investment, rapid increase of the cost of equipment, rehabilitation of the old existing electrical networks, high increase of growth rate of rural inhabitants and consequently high increase of load demand. 2-2 New Technology Transfer As a result of the increased consumption in the electrified villages and towns, it was decided to raise the average load demand to be 150 watts/capita in rural areas and to be 300 Watts/Capita in urban areas. In the field of planning high voltage networks. Quintet program is used to fulfill: load forecast, power flow, load balance, short circuit current and feasibility studies. Figure (1&3) show flow chart for operation in planning of high voltage networks and an output of Quintet Program. Data Impute INGRES Database QUINTET Demar Quasar Economical study Excel Short Circuit Calculations Courcirc Power Flow & Voltage Drop Calculations Eurostag Power Loss Calculations Fig. (1): Flow Chart for Operation in Planning of High Voltage Networks (Quintet Program) The following tasks are performed for planning high voltage networks: Œ Technical and economical studies for planning electrical networks. Œ Layout general strategy for the electrical networks. Œ Technical and economical studies for supplying electricity for agricultural & industrial projects etc. 2-3 System Design In order to achieve this big leap it was necessary to modernize the work procedures. Latest software programs have been introduced within the framework of French-Egyptian cooperation to ensure reliability of power supply, reducing the distribution system losses and determining the best feeding points. Economical studies have been carried out for the future expansions, low voltage drop, minimum losses and optimum transformer capacities. A Geographic Information System has been developed providing a reliable tool to record and update the electrical network technical data on geographic maps. This system allows now easy retrieval of any technical data required for design and planning. As an example: (2) In the field of designing high voltage transmission lines. The following programs are used: Œ JOVE for designing the longitudinal sections and distribution of towers, calculations of mechanical loads and determining the tension and sagging tables. Œ SAFI program for designing the towers and steel structure. Œ TRANS for calculating the mechanical loads on towers and designing foundations of different types of towers and soil.

Fig. (3) Power Diagram as an Example of Quintet Outputs Figure (2) shows an output of JOVE program. In the field of designing of transformer substations 66/11(22) Kv: : The following programs are used: ΠTRANS for designing steel structure and foundation. ΠSAFI for structural designing tasks for concrete and metal buildings. ΠDifferent programs which are home made to design the ground networks and lighting arrestors and short circuit calculations. In the field of planning medium voltage networks. The following programs are now in operation: ΠPRAO for technical and economical studies. Existing Network On Geographical Maps Civil Maps Input Proposed Network On Geographical Maps ARCVIEW Load Forecast Calculations EXCEL DBASE BASIX Wiring Diagram for Existing Network ORACLE Existing Electrical Network PRAO Fig. (4): Flow Chart for Operation of BASIX PRAO & ARCVIEW PROGRAMS Proposed Electrical Network ΠBASIX database preparation. ΠARCVIEW for mapping up the existing and future networks geographically. Figure (4) shows flow chart for operation of BASIX, PRAO & ARCVIEW programs. The following tasks are performed in that regard: ΠPlanning medium voltage networks of 207 towns, technically and economically. ΠTen years master plan for each network. ΠTime table to implement the required networks according to technical and economical studies. ΠDevelopment of electrical networks annually on geographical maps. Figure (5) shows master plan for the network of a town in Delta Zone in the year 2010. In the field of design of medium voltage lines. Camelia program is now used to design medium voltage overhead transmission lines. The following tasks are performed:: ΠStudying loading new substations and relieving loads on the existing one ΠPreparing electrical and mechanical calculations for transmission lines. ΠDesigning of different types of 11 & 22 Kv poles. ΠDesign concrete foundation of towers. In the field of planning of low voltage networks. LV PLAN program is now used to fulfill this task. The following studies can be performed: ΠDesign of overhead transmission lines networks and its routes. ΠSpecifying types of insulators, cross section and transformer capacities. Figure (6) shows an output of LV plan program.

Fig.(5): Master Plan of a Town in Delta in the Year 2010 2-4 Project Achievements 2-5 Investments By the year 2000, the following tasks have been achieved: 1st) In the field of high voltage networks, 315 Substations 66,33/11Kv and 66/22Kv with total capacity of 9000 MVA together with 4550 Kms cables and overhead transmission lines 66,33 Kv. B) In the field of medium and low voltage networks, the following have been constructed to reinforce and rehabilitate towns electrical networks: Π369 Distribution points 11 & 22 Kv. Π8591 Kiosks 11 (22) / 0.4 Kv. Π26500 Kms of medium and low voltage cables and overhead transmission lines. C) In the field of electrification, the following have been executed: ΠElectrification of 36010 main villages and attachments. ΠEnforcement and rehabilitation the electrical networks for previously electrified main villages and refurbishment of obsolete electrical networks. The rural electrification program was implemented and financed through state budget, in addition to soft loan and grant agreements in the framework of mutual economical cooperation with international donors. The total investment for implementing all the previous achievements is amounted to 8500 Million L.E. (one US$ is currently equal to 3.9 L.E). 3- FUTURE PLANS The Ministry of Electricity and Energy has set a strategy covering the period up to the year 2017. Within this strategy, REA has to meet the growing demand of electric energy all over the rural zones, by executing the following tasks annually: ΠImplementation of 7 S/Sts 66/11 (22) Kv and the necessary overhead transmission lines & under ground cables. ΠRehabilitation of the distribution networks of 213 towns. ΠFinalize electrification of the remaining small residential communities (wherever possible). ΠContinuous rehabilitation of the pre-electrified villages of about 300 rehabilitating process and 530 replacement of obsolete villages networks. 4- SUPPLYING ELECTRICITY TO OTHER PROJECTS Fig. (6): Low Voltage Networks of an Attachment REA scope is not limited to electrification of villages and attachments but also has the role of

supplying electricity to different projects to serve the continuous development of the society. REA is performing technical studies, design and implementing the required electrical network by using the above mentioned programs for the following projects: - 4-1 Land Reclamation: In the frame of the Egyptian Government strategy to invade and reclaim the desert targeting 1347000 Feddans, over 440 000 Feddans have been supplied with electricity by the end of 2000. It is planned to supply 12000 Feddans by electricity annually. 4-2 New Residential Cities: In order to meet vertical and horizontal expansion of inhabitants, 32 new cities and residential areas have been planned to be built and of course supplied with all necessary services including electricity. Up till now, fourteen residential cities have been supplied with electricity. Eighteen substations 66/22(11) Kv have been constructed with total capacity of 1245 MVA. Other four complete substations with total capacity of 470 MVA are now under construction. 4-3 Industrial Zones: Matching up with the State s Policy in developing local industry, industrial zones have planned to encourage new industrial projects and create job opportunities. Concentrated programs are adopted to implement the electrical infrastructure to supply 50 industrial zones with electricity nationwide. By the end of 2000, ten substations 66/ (11) 22 Kv have been constructed with total capacity of 485 MVA to supply electricity for fourteen industrial Zones. Nine substations are now under construction with total capacity of 525 MVA. renewable energy to meet the needs of these communities. The Egyptian Government has launched a program to apply new and renewable energy technologies. In that direction, technoeconomic studies has been carried out to identify the optimum choice to electrify these communities for residential purposes (e.g. Lighting units, pumping water, small local industries and small clinics for healthcare). Various pilot projects have been implemented using hybrid systems of Wind/Diesel and photovoltiac (PV) techniques. As example the following projects has been executed so far: ΠRemote village of forty houses in wadi al- Natroun in the western desert was supplied with electricity through PV technology. ΠA group of remote villages located on the northwest coast were supplied with electricity, using hybrid 25 kw diesel/windmills. Further projects are planned to be executed in the near future. 6- CONCLUSION The Egyptian Rural Electrification Program, which began in 1971, has increased the required number of electrified main villages and attachments from 3500 to 35650 villages making over 98% of inhabitants are having access to electricity. Providing rural inhabitants with electricity have offered them a better style of life and opened up new horizons for investments resulting in transferring them from a primitive consuming community to a civilized productive one. This project took a long time, over industrious efforts and substantial amounts of money along the past three decades. 5- APPLICATION OF RENEWABLE ENERGY RESOURCES TO SUPPLY REMOTE RURAL AREAS WITH ELECTRICITY: Since there are still limited communities scattered in the western desert, Sinai, coastal areas of Red and Mediterranean Sea, located very far from the unified electric network, it is very costly to extend the grid to such small and very far communities. So, it was decided to promote the utilization of