Chapter 18. Materials Requirements Planning

Similar documents
Materials Requirements Planning

History IE 376 PRODUCTION INFORMATION SYSTEMS. Course Notes Lecture #2.A Material Requirements Planning

Material Resources Planning

The Planning Hierarchy

Material Requirements Planning (MRP) and ERP 14. Outline

Net Requirements Plan. The logic of net requirements. MRP Planning Sheet. Gross Requirements Schedule

Material Requirements Planning (MRP), chap 15

Chapter 12. Enterprise Resource Planning

Chapter 6 RESOURCE PLANNING SYSTEMS. Prepared by Mark A. Jacobs, PhD

7/14/2010. Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall.

Materials and Resource Requirements Planning

A typical manufacturing plant

Oman College of Management and Technology

Resources Planning. Introduction

Enterprise Resource Planning

Note 8: Materials Requirements Planning

PRODUCTION SCHEDULING PART-A

MATERIAL AND CAPACITY REQUIREMENTS PLANNING (MRP AND CRP) Part -1. Dr. Mahmoud Abbas Mahmoud Al-Naimi Assistant Professor

PLANNING FOR PRODUCTION

What can Visual Planner do for you Rick Worley TriMin Systems April 2016

MORE MATERIAL REQUIREMENT PLANNING

Notes for Production and Operations Management- I

MANUFACTURING SYSTEMS MATERIAL REQUIREMENTS PLANNING

University of Puerto Rico Mayagüez Campus Industrial Engineering Department

Manajemen Persediaan. MRP Lot For Lot. Modul ke: Fakultas FEB. Program Studi Manajemen

INTEGRATED. Reservations, Tracking, and Action Messages. Microsoft Dynamics NAV 5.0. Technical White Paper

Manish Naik Senior Consultant Enterprise Solutions Infosys Technologies Ltd.

Time to Shipment MRP Guide DBA Software Inc.

R12 Inventory Attribute Controls

Chapter 6 Resource Planning Systems

IV/IV B.Tech (Mech. Engg.) 7th sem, Regular Exam, Nov Sub: OPERATIONS MANAGEMENT [14ME705/A] Scheme of valuation cum Solution set

MPR Sample Test. CPIM(Certified In Production & Inventory Management) - 1 -

MANUFACTURING RESOURCE PLANNING AND ENTERPRISE RESOURCE PLANNING SYSTEMS: AN OVERVIEW

Yuji Yamamoto PPU411. Today s topic. What is MPS and MRP Developing MPS How to make MRP Enterprise Resource Planning Kanban system

MASTER PRODUCTION SCHEDULE (MPS)

MATERIAL REQUIREMENT PLANNING

What s New in Dynamics NAV 2013: Manufacturing. May 22, 2014

SAP Certified Application Associate - Production - Planning & Manufacturing with SAP ERP 6.0 EHP6

Infor ERP LN 6.1 Enterprise Planning. User's Guide for Order Planning

Introduction. Introduction. Introduction LEARNING OBJECTIVES LEARNING OBJECTIVES

9. What are the activities within the scope of production planning? 1. Aggregate production planning

CRC Press Taylor &. Francis Croup Boca Raton London New York CRC Press is an imprint of the Taylor & Francis Group, an Informa business

THE USE OF SPREADSHEETS TO TEACH MASTER PRODUCTION SCHEDULE (MPS) AND MATERIALS REQUIREMENTS PLANNING (MRP)

SAP Business One. A Single System to Streamline Your Entire Business


Sage 200 Manufacturing Datasheet

APICS PRINCIPLES OF OPERATIONS MANAGEMENT TOPIC OUTLINE CONCEPTS AND APPLICATIONS

Introductory Exercise: Aggregate Planning

ANYTIME 500 ENHANCED MRP

Part IV Methods for Dependent Demand

Supply Planning in Microsoft

CP-81 The best waze to get to destination MRP! Paul Whiteman Lexell Blue Susan Pucciano Lexell Blue

AUTOSIMPLY. Manufacturing Order. Features. About AutoSimply

Infor LN Enterprise Planning User Guide for Order Planning

Bill of material. A bill of material (BOM) represents the structural links between finished products, intermediate items, components and raw materials

Supply Chain. Planning. Answer Essential Questions. For Your Business Quickly and Easily

SAP Material Master A Practical Guide. Matthew Johnson

What is ERP? Source: Wikipedia

TU-E2020 ADVANCED OPERATIONS MANAGEMENT. Master Production Scheduling Material Requirements Planning

Reading Sample. Response and Supply Planning with SAP IBP Contents. Index. The Authors

Breakdown. Learn the implications of the breakdown field in Item Master Data

Introduction Manufacturing Data Management

Oracle Value Chain Planning

AVANTUS TRAINING PTE LTD

Inventory Replenishment

Manufacturing Functionlity in Microsoft Dynamics GP. Gain complete control over your inventory, production and orders.

How much money can you add to the bottom line with good inventory management?

Al-Qadisiya Journal For Engineering Sciences Vol. 4 No. 3 Year 2011

Microsoft Dynamics GP. Manufacturing Core Functions

Manufacturing Efficiency Guide DBA Software Inc.

LFL. KEYWORDS: Lot sizing techniques, Material requirements planning.

Production Management and Scheduling

CUSTOMER INTRODUCTION

There are three options available for coping with variations in demand:

Foreword 7. 1 Production planning Planning approaches Planning strategies Definition of the example 17

Last Updated March 13, IndustriOS Software, Inc.

Replenishment Orders. Version 8.4. RMS/Present. Master Production Schedule. Material Requirements Plan. Work Order/ FPO Maintenance

Infor ERP LN 6.1. User's Guide for Unit Effectivity

Epicor Planning and Scheduling. Planning at peak performance to maximize business profitability.

GBI - Introductory Course 6/11/2015

What is MRP (I, II, III) 1. MRP-I

Purchasing Guide DBA Software Inc.

SALES Course Assignment VERSION 18

Management Tool based on MRP and Lot-sizing A case study for comparing different cases

Subbu Ramakrishnan. Manufacturing Finance with SAP. ERP Financials. Bonn Boston

Bill of Material Functionality

Functional Area Systems Production / Operation Systems

Mid-Term Examination. Suggested Solution to ECLT 5940 Supply Chain Management. Time: 7:00 9:45 PM

Manufacturing & Supply Chain Enhancements

NorthClark Computing, Inc. Part Number Search Query User Guide

UNIT II PRODUCTION PLANNING AND CONTROL AND COMPUTERISED PROCESS PLANNING

1. MRP Module. 2. Record. 2.1 Material Requirement Planning

02/10/2016. Functional Area Systems Production / Operation Systems. Examples: Functional Area Info Systems. Functional Area Information Systems

Resource Portal for Management Sciences Students, Teachers and Business Professionals. Visit

Hybrid Manufacturing Methods

Custom Manufacturing Guide DBA Software Inc.

Oracle Capacity. User's Guide Release Part No. E

BAAN IV. BaanSync Scheduler 6.0 Interface User Manual

Upgrading to R12 (12.1.3) from 11i ( ) SCM. - Abhai Tripathi, Fujitsu America. Fujitsu America.

Requirements Planning Implementation Guide Release 9.2

Transcription:

1 Chapter 18 Materials Requirements Planning

Material Requirements Planning 2 Materials requirements planning (MRP) is a means for determining the number of parts, components, and materials needed to produce a product MRP provides time scheduling information specifying when each of the materials, parts, and components should be ordered or produced Dependent demand drives MRP MRP is a software system

Example of MRP Logic and Product Structure Tree 3 Given the product structure tree for A and the lead time and demand information below, provide a materials requirements plan that defines the number of units of each component and when they will be needed Product Structure Tree for Assembly A A B(4) C(2) Lead Times A 1 day B 2 days C 1 day D 3 days E 4 days F 1 day D(2) E(1) D(3) F(2) Total Unit Demand Day 10 50 A Day 8 20 B (Spares) Day 6 15 D (Spares)

4 First, the number of units of A are scheduled backwards to allow for their lead time. So, in the materials requirement plan below, we have to place an order for 50 units of A on the 9 th day to receive them on day 10. Day: 1 2 3 4 5 6 7 8 9 10 A Required 50 Order Placement 50 LT = 1 day

Next, we need to start scheduling the components that make up A. In the case of component B we need 4 B s for each A. Since we need 50 A s, that means 200 B s. And again, we back the schedule up for the necessary 2 days of lead time. 5 D a y : 1 2 3 4 5 6 7 8 9 10 A R e q u ire d 50 O rd e r P la c e m e n t 50 B R e q u ire d 20 200 O rd e r P la c e m e n t 20 200 LT = 2 Spares A 4x50=200 B(4) C(2) D(2) E(1) D(3) F(2)

Finally, repeating the process for all components, we have the final materials requirements plan: Day: 1 2 3 4 5 6 7 8 9 10 A Required 50 LT=1 Order Placement 50 B Required 20 200 LT=2 Order Placement 20 200 C Required 100 LT=1 Order Placement 100 D Required 55 400 300 LT=3 Order Placement 55 400 300 E Required 20 200 LT=4 Order Placement 20 200 F Required 200 LT=1 Order Placement 200 Lead Times A B C D E F 1 day 2 days 1 day 3 days 4 days 1 day Total Unit Demand Day 10 50 A Day 8 20 B (Spares) Day 6 15 D (Spares) D(2) B(4) E(1) A D(3) C(2) F(2) Part D: Day 6 40 + 15 spares 6

7 Master Production Scheduling (MPS) Time-phased plan specifying how many and when the firm plans to build each end item Aggregate Plan (Product Groups) MPS (Specific End Items)

Types of Time Fences 8 Frozen No schedule changes allowed within this window Moderately Firm Specific changes allowed within product groups as long as parts are available Flexible Significant variation allowed as long as overall capacity requirements remain at the same levels

Example of Time Fences 9 Frozen Moderately Firm Flexible Capacity Firm Customer Orders Forecast and available capacity 8 15 Weeks 26

Material Requirements Planning System 10 Based on a master production schedule, a material requirements planning system: Creates schedules identifying the specific parts and materials required to produce end items Determines exact unit numbers needed Determines the dates when orders for those materials should be released, based on lead times

Engineering design changes Bill of material file Firm orders from known customers Primary reports Planned order schedule for inventory and production control Aggregate product plan Master production Schedule (MPS) Material planning (MRP computer program) Forecasts of demand from random customers Secondary reports Inventory transactions Inventory record file Exception reports Planning reports Reports for performance control 11

Bill of Materials (BOM) File A Complete Product Description 12 Materials Parts Components Production sequence Modular BOM Subassemblies Super BOM Fractional options

13 Inventory Records File Each inventory item carried as a separate file Status according to time buckets Pegging Identify each parent item that created demand

Primary MRP Reports 14 Planned orders to be released at a future time Order release notices to execute the planned orders Changes in due dates of open orders due to rescheduling Cancellations or suspensions of open orders due to cancellation or suspension of orders on the master production schedule Inventory status data

15 Secondary MRP Reports Planning reports, for example, forecasting inventory requirements over a period of time Performance reports used to determine agreement between actual and programmed usage and costs Exception reports used to point out serious discrepancies, such as late or overdue orders

16 Additional MRP Scheduling Terminology Gross Requirements Scheduled receipts Projected available balance Net requirements Planned order receipt Planned order release

17 MRP Calculations Projected available balance t = Projected available - Gross Requirements + Scheduled balance t receipts t t-1 + Planned order - Safety stock receipts t

18

19

20

Closed Loop MRP 21 Production Planning Master Production Scheduling Material Requirements Planning Capacity Requirements Planning No Feedback Realistic? Yes Execute: Capacity Plans Material Plans Feedback

MRP Example 22 A(2) C(3) X C(2) B(1) D(5) Item On-Hand Lead Time (Weeks) X 50 2 A 75 3 B 25 1 C 10 2 D 20 2 Requirements include 95 units (80 firm orders and 15 forecast) of X in week 10

23 A(2) X It takes 2 A s for each X Day: 1 2 3 4 5 6 7 8 9 10 X Gross requirements 95 Proj. avail. balance 50 50 50 50 50 50 50 50 50 0 On- Net requirements 45 hand Planned order receipt 45 50 Planner order release 45 A Gross requirements 90 LT=3 Scheduled receipts Proj. avail. balance 75 75 75 75 75 75 75 0 On- Net requirements 15 hand Planned order receipt 15 75 Planner order release 15 B Gross requirements 45 LT=1 Scheduled receipts Proj. avail. balance 25 25 25 25 25 25 25 0 On- Net requirements 20 hand Planned order receipt 20 25 Planner order release 20 C Gross requirements 45 40 Proj. avail. balance 10 10 10 10 0 On- Net requirements 35 40 hand Planned order receipt 35 40 10 Planner order release 35 40 D Gross requirements 100 Proj. avail. balance 20 20 20 20 20 20 0 On- Net requirements 80 hand Planned order receipt 80 20 Planner order release 80

24 A(2) X It takes 1 B for each X B(1) Day: 1 2 3 4 5 6 7 8 9 10 X Gross requirements 95 Proj. avail. balance 50 50 50 50 50 50 50 50 50 0 On- Net requirements 45 hand Planned order receipt 45 50 Planner order release 45 A Gross requirements 90 LT=3 Scheduled receipts Proj. avail. balance 75 75 75 75 75 75 75 0 On- Net requirements 15 hand Planned order receipt 15 75 Planner order release 15 B Gross requirements 45 LT=1 Scheduled receipts Proj. avail. balance 25 25 25 25 25 25 25 0 On- Net requirements 20 hand Planned order receipt 20 25 Planner order release 20 C Gross requirements 45 40 Proj. avail. balance 10 10 10 10 0 On- Net requirements 35 40 hand Planned order receipt 35 40 10 Planner order release 35 40 D Gross requirements 100 Proj. avail. balance 20 20 20 20 20 20 0 On- Net requirements 80 hand Planned order receipt 80 20 Planner order release 80

25 A(2) C(3) X It takes 3 C s for each A B(1) Day: 1 2 3 4 5 6 7 8 9 10 X Gross requirements 95 Proj. avail. balance 50 50 50 50 50 50 50 50 50 0 On- Net requirements 45 hand Planned order receipt 45 50 Planner order release 45 A Gross requirements 90 LT=3 Scheduled receipts Proj. avail. balance 75 75 75 75 75 75 75 0 On- Net requirements 15 hand Planned order receipt 15 75 Planner order release 15 B Gross requirements 45 LT=1 Scheduled receipts Proj. avail. balance 25 25 25 25 25 25 25 0 On- Net requirements 20 hand Planned order receipt 20 25 Planner order release 20 C Gross requirements 45 40 Proj. avail. balance 10 10 10 10 0 On- Net requirements 35 40 hand Planned order receipt 35 40 10 Planner order release 35 40 D Gross requirements 100 Proj. avail. balance 20 20 20 20 20 20 0 On- Net requirements 80 hand Planned order receipt 80 20 Planner order release 80

26 A(2) C(3) X C(2) B(1) It takes 2 C s for each B Day: 1 2 3 4 5 6 7 8 9 10 X Gross requirements 95 Proj. avail. balance 50 50 50 50 50 50 50 50 50 0 On- Net requirements 45 hand Planned order receipt 45 50 Planner order release 45 A Gross requirements 90 LT=3 Scheduled receipts Proj. avail. balance 75 75 75 75 75 75 75 0 On- Net requirements 15 hand Planned order receipt 15 75 Planner order release 15 B Gross requirements 45 LT=1 Scheduled receipts Proj. avail. balance 25 25 25 25 25 25 25 0 On- Net requirements 20 hand Planned order receipt 20 25 Planner order release 20 C Gross requirements 45 40 Proj. avail. balance 10 10 10 10 0 On- Net requirements 35 40 hand Planned order receipt 35 40 10 Planner order release 35 40 D Gross requirements 100 Proj. avail. balance 20 20 20 20 20 20 0 On- Net requirements 80 hand Planned order receipt 80 20 Planner order release 80

27 A(2) C(3) X C(2) B(1) It takes 5 D s for each B D(5) Day: 1 2 3 4 5 6 7 8 9 10 X Gross requirements 95 Proj. avail. balance 50 50 50 50 50 50 50 50 50 0 On- Net requirements 45 hand Planned order receipt 45 50 Planner order release 45 A Gross requirements 90 LT=3 Scheduled receipts Proj. avail. balance 75 75 75 75 75 75 75 0 On- Net requirements 15 hand Planned order receipt 15 75 Planner order release 15 B Gross requirements 45 LT=1 Scheduled receipts Proj. avail. balance 25 25 25 25 25 25 25 0 On- Net requirements 20 hand Planned order receipt 20 25 Planner order release 20 C Gross requirements 45 40 Proj. avail. balance 10 10 10 10 0 On- Net requirements 35 40 hand Planned order receipt 35 40 10 Planner order release 35 40 D Gross requirements 100 Proj. avail. balance 20 20 20 20 20 20 0 On- Net requirements 80 hand Planned order receipt 80 20 Planner order release 80

28 Lot Sizing in MRP Programs Lot-for-lot (L4L) Economic order quantity (EOQ) Least total cost (LTC) Least unit cost (LUC) Which one to use? The one that is least costly!