System Impact Study E001 Moon Lake 230 kv 200 MW Plant

Similar documents
System Impact Study PID MW Plant

Generator Interconnection Affected System Impact Study. Plains & Eastern Clean Line Final Report

PID 276 Feasibility Study Report 4.4MW Distribution Inter-Connection Mermentau Substation

PID275 Feasibility Study Report 9.33 MW Distribution Inter-Connection Valentine Substation

Overview of Control Area / Balancing Authority Functional Requirements Matt Wolf Manager Operations Support May 5, 2010

FACILITIES STUDY GENERATOR INTERCONNECTION STUDY PID 240

Feasibility Study Report

ENTERGY FACILITY CONNECTION REQUIREMENTS March 2007

FILED BEFORE THE CORPORATION COMMISSION OF THE STATE OF OKLAHOMA MA ZOO OF THE REDBUD GENERATING FACILITY AND AUTHORIZING RECOVERY RIDER

P l a n n i n g A s s e s s m e n t S c o p e

I n t e g r a t e d T r a n s m i s s i o n P l a n n i n g N e a r - T e r m S c o p e. June 15, 2016 Engineering

Planning Coordinator and/or Transmission Planner TRANSMISSION SYSTEM PLANNING GUIDELINES

Illinois State Institute for Regulatory Policy Studies Conference

Feasibility Study for the Q MW Solar Project

Southwest Power Pool, Inc. Entergy ENTERGY SPP RTO REGIONAL PLANNING PROCESS MEETING June 16, 2011 NET CONFERENCE AGENDA 1:30 3:00 PM

Platte River Power Authority. Ten-Year Transmission Plan ( )

2. Facility/flowgate limitations and flows at the time the TLR was initiated.

2011 Probabilistic Assessment. 11JAN12 Interregional Coordination

Summary details for SPC TSR # and MH TSR # are shown in Tables ES.1 and ES.2: Service Requested

Generation Interconnection Feasibility Study Report. For. PJM Generation Interconnection Request Queue Position AA1-038

Summary details for SPC TSR # and MH TSR # are shown in Tables ES.1 and ES.2: IFHS MH MW, firm :00:00 CS

TRANSMISSION PLANNING ASSESSMENT METHODOLOGY AND CRITERIA

EIPC Interconnection-wide Webinar and Stakeholder Discussion. November 17, 2015

DUQUESNE LIGHT COMPANY TRANSMISSION PLANNING CRITERIA

CAISO Generator Deliverability Assessment Methodology. On-Peak Deliverability Assessment Methodology (for Resource Adequacy Purposes)

Generation Interconnection System Impact Study Report. For. PJM Generation Interconnection Request Queue Position AA1-038

Feasibility Study Report

East Kentucky Power Cooperative (EKPC) Baseline RTEP Integration Report

MISO South Local Resource Zones (LRZ) Discussion. LOLE Working Group 5/8/2013

Feasibility Study Report

POTOMAC ELECTRIC POWER COMPANY

System Impact Study and Facilities Study Process Manual For Cleco Power LLC

Rochelle Municipal Utilities TRANSMISSION PLANNING CRITERIA. March 21, 2017

Point to Point US to BC, BC to Alberta. and wheel through US to Alberta. System Impact Study

A. Introductions... All. B. Discuss/Approve Minutes of 4/20/2010 ESRPP Meeting... Jody Holland/All. C. SPP Antitrust Guidelines...

Transmission Expansion Advisory Committee. October 11, 2012

Stability Issues in Entergy System

ASSOCIATED NERC STANDARD(S): TPL (referred to as TPL-001 in this document) IMPLEMENTATION: In effect when approved.

AESO System Operating Limits Methodology for the Planning Horizon (R1 FAC-010-AB-2.1)

1.3 Planning Assumptions and Model Development

AESO TRANSMISSION PLANNING CRITERIA BASIS AND ASSUMPTIONS

OHIO VALLEY ELECTRIC CORPORATION

CAISO Generator Deliverability Assessment Methodology. On-Peak Deliverability Assessment Methodology (for Resource Adequacy Purposes)

S P P T P L S t e a d y S t a t e A s s e s s m e n t

DRAFT STUDY PLAN FOR 2018

Interconnection Feasibility Study

SPP REPORT ON MAY 16, 2000 TLR EVENT

2013 SERTP Study Scope Document --DRAFT-- 04/19/2013

Connection Study Requirements

December 20, Amendment to Attachment C to the Southern Companies OATT Docket No. ER14-

FACILITIES STUDY PID224 GENERATOR INTRCONNECTION

SERTP Interactive Training. Interface Analysis

Seasonal Assessments and Modeling of Sub-100 kv Elements (Southwest Outage Recommendations 5, 6, 7 and NERC2) May 7, 2014

SERC. Regional Reliability Plan

Standard TPL Transmission System Planning Performance Requirements

Standard Development Timeline

2016 Probabilistic Assessment. December 5, 2016 Southwest Power Pool

2. Facility/flowgate limitations and flows at the time the TLR was initiated.

Maine Public Service Transmission System Reliability

Standard Development Timeline

Entergy Regional Reliability Coordinators (RC) as of 12/1/2012

Standard MH-TPL Transmission System Planning Performance Requirements

PSE Attachment K Puget Sound Area Transmission Meeting

Eastern Interconnection Planning Collaborative Steady-State Modeling and Load-Flow Working Group

2010 Loss of Load Expectation Report PUBLISHED: 10/01/2010 LATEST REVISION: 10/08/2010

PJM White Paper. Transource Independence Energy Connection Market Efficiency Project

Stakeholder Communication. Inputs, Assumptions, and Preliminary Assessment. Base Model. Needs, Solutions, Sensitivity: Yr 5

Transmission Expansion Advisory Committee. December 15, 2011

Interconnection Feasibility Study

OHIO VALLEY ELECTRIC CORPORATION. Open Planning Meeting. April 4, 2012

Southern Company Services ATCID Version 1.2 Available Transfer Capability Implementation Document (ATCID) ATCID Revision Log

Appendix 1 PRELIMINARY DELIVERABILITY BASELINE ANALYSIS STUDY REPORT

S P P 2016 TPL a n d FA C

NYISO / PJM - Focused Study Reliability Analysis. Northeast Coordinated System Plan IPSAC09 November 06, 2009

Year Assessment Preliminary Study Design

SRRTEP Meeting 2019 Annual Assumptions for Pepco

2010 SERTP. 2 nd Quarter Meeting


AEP Transmission Local Planning Assumptions, Models, and Criteria

Mapping Document for FAC-010-3

Resource and Financial Impact of Clean Line P&E HVDC Delivered Wind Resources for TVA

2012 NCTPC PJM Joint Interregional Reliability Study. PJM Interconnection. Duke Energy Carolinas. Progress Energy Carolinas

NERC Reliability Functional Model

EIPC Scenarios for Analysis in 2014

XXXX. Bremner Trio Small Hydro Project. Interconnection System Impact Study

1999 System Disturbances

PSE&G Assumptions Overview. November 2018

Eastern Interconnection Planning Collaborative. Steady State Modeling and Load Flow Working Group

Audit of the Available Flowgate Capacity Process

Standard Development Timeline

OHIO VALLEY ELECTRIC CORPORATION 2017 TRANSMISSION PLAN. Prepared On OVEC s behalf by: East Transmission Planning American Electric Power

Audit of the Available Flowgate Capacity Process

NORTHERN TIER TRANSMISSION GROUP (NTTG) BIENNIAL TRANSMISSION PLAN. DRAFT SUMMARY REPORT - January 2013

East Kentucky Power Cooperative (EKPC) Transmission System Planning Criteria

April 26, PJM Mr. Mark J. Kuras Senior Lead Engineer NERC and Regional Coordination 2750 Monroe Blvd. Audubon, PA 19403

Black Hills Power, Inc Basin Electric Power Cooperative Powder River Energy Corporation

LONG-RANGE TRANSMISSION PLAN

FACILITIES STUDY TRANSMISSION SERVICE REQUESTS TVA OASIS

Generation Interconnection System Impact Study Report

Transmission Expansion Advisory Committee

Transcription:

System Impact Study E001 Moon Lake 230 kv 200 MW Plant Prepared by: Midcontinent Independent System Operator Independent Coordinator of Transmission 720 City Center Drive Carmel, IN 46032 Rev Issue Date Description of Revision Revised By Project Manager 0 9/10/2013 Posting System Impact Study VG

Contents Executive Summary 3 Energy Resource Interconnection Service 4 1. Introduction 4 2. Short circuit Analysis/Breaker Rating Analysis 4 2.1 Model Information 4 2.2 Short Circuit Analysis 4 2.3 Analysis Results 5 2.4 Problem Resolution 5 3. Load Flow Analysis 5 3.1 Model Information 5 3.2 Load Flow Analyses 5 3.3 Analysis Results 7 Network Resource Interconnection Service 8 4. Introduction 8 5. Analysis 8 5.1 Models 8 5.2 Contingencies and Monitored Elements 8 5.3 Generation used for the transfer 9 5.4 Results 9 6. Required Upgrades for NRIS 10 6.1 Preliminary Estimates of Direct Assignment of Facilities and Network Upgrades 10 7. Interconnection Facilities 10 APPENDIX A: DATA PROVIDED BY CUSTOMER 11 APPENDIX B: PRIOR GENERATION INTERCONNECTION AND TRANSMISSION SERVICE REQUESTS IN STUDY MODELS 18 APPENDIX C: ERIS LOAD FLOW DETAILS OF SCENARIO 1, 2, 3, AND 4 19 APPENDIX D: DETAILS OF SCENARIO 1 2017 23 APPENDIX E: DETAILS OF SCENARIO 2 2017 26 APPENDIX F: DETAILS OF SCENARIO 3 2017 29 APPENDIX G: DETAILS OF SCENARIO 4 2017 32 2

Executive Summary This System Impact Study is the second step of the interconnection process and is based on the E001 request for interconnection on Entergy s transmission system located at the Moon Lake 230 kv substation. The study evaluates connection of 200 MW to the Entergy Transmission System. Requestor for E001 requested ERIS and NRIS. Under ERIS, a load flow analysis was performed. The load flow study was performed on the latest available 2017 Summer Peak Case, using PSS/E and MUST software by Siemens Power Technologies International (Siemens-PTI). The short circuit study was performed on the Entergy system short circuit model using ASPEN software. Under NRIS, the analysis was performed on the 2017-2021 summer and winter models. These models included Entergy s latest Construction Plan upgrades. The proposed in-service date is December 31, 2016. Results of the System Impact Study indicated that under ERIS the additional generation due to E001 generator does not cause an increase in short circuit current such that they exceed the fault interrupting capability of the high voltage circuit breakers within the vicinity of the E001plant with priors and without priors. Therefore, estimated upgrade costs under ERIS with and without prior is $0. See table below. Estimated ERIS Project Planning Upgrade Cost Interconnection Upgrades Planning Estimate for Upgrade* None* --- *The costs of the upgrades are planning estimates only. Cost estimate may change upon the completion of the pending Stability Study. Detailed cost estimates, accelerated costs and solutions for the limiting elements will be provided in the facilities study. Estimated NRIS Project Planning Upgrade Cost NRIS Upgrades Planning Estimate for Upgrade* None --- 3

Energy Resource Interconnection Service 1. Introduction This Energy Resource Interconnection Service (ERIS) is based on a request for 200MW interconnection on Entergy s transmission system at the Moon Lake 230kV substation. The objective of this study is to assess the reliability impact of the new facility on the Entergy transmission system with respect to the steady state and transient stability performance of the system as well as its effects on the system s existing short circuit current capability. It is also intended to determine whether the transmission system meets standards established by NERC Reliability Standards and Entergy s planning guidelines when plant is connected to Entergy s transmission system. If not, transmission improvements will be identified. The System Impact Study process required a load flow analysis to determine if the existing transmission lines are adequate to handle the full output from the plant for simulated transfers to adjacent control areas. A short circuit analysis is performed to determine if the generation would cause the available fault current to surpass the fault duty of existing equipment within the Entergy transmission system. This ERIS System Impact Study was based on information provided by the Customer and assumptions made by Entergy s Transmission Technical System Planning group. All supplied information and assumptions are documented in this report. If the actual equipment installed is different from the supplied information or the assumptions made, the results outlined in this report are subject to change. The load flow results from the ERIS study are for information only. ERIS does not in and of itself convey any transmission service. 2. Short circuit Analysis/Breaker Rating Analysis 2.1 Model Information The short circuit analysis was performed on the Entergy system short circuit model using ASPEN software. This model includes all generators interconnected to the Entergy system or interconnected to an adjacent system and having an impact on this interconnection request, IPP s with signed IOAs, and approved future transmission projects on the Entergy transmission system. 2.2 Short Circuit Analysis The method used to determine if any short circuit problems would be caused by the addition of the E001 generation is as follows: Three-phase and single-phase to ground faults were simulated on the Entergy base case short circuit model and the worst case short circuit level was determined at each station. The E001 generator was then modeled in the base case to generate a revised short circuit model. The base case short circuit results were then compared with the results from the revised model to identify any breakers that were under-rated as a result of additional short circuit contribution from E001 generation. Any breakers identified to be upgraded through this comparison are mandatory upgrades. 4

2.3 Analysis Results The results of the short circuit analysis indicated that the additional generation due to E001 generation caused no increase in short circuit current such that they exceeded the fault interrupting capability of the high voltage circuit breakers within the vicinity of the E001 plant with and without priors. 2.4 Problem Resolution As a result of the short circuit analysis findings, no resolution was required. 3. Load Flow Analysis 3.1 Model Information The load flow analysis was performed based on the projected 2017 summer peak load flow model. Approved future transmission projects in the 2013 ICT Base Plan were used in the models for scenarios three and four. These upgrades can be found on Entergy s OASIS web page at http://www.oatioasis.com/ees/eesdocs/disclaimer.html. The loads were scaled based on the forecasted loads for the year. All firm power transactions between Entergy and its neighboring control areas were modeled for the year 2017 excluding short-term firm transactions on the same transmission interface. An economic dispatch was carried out on Entergy generating units after the scaling of load and modeling of transactions. The E001 generation interconnection point was modeled at the Moon Lake 230kV substation. These associated facilities were then modeled in the case to build a revised case for the load flow analysis. Transfers were simulated between thirteen (13) control areas and Entergy using the requesting generator as the source and adjacent control area as sink. This study considered the following four scenarios: Scenario No. Approved Future Transmission Projects Pending Transmission Service & Study Requests 1 Not Included Not Included 2 Not Included Included 3 Included Not Included 4 Included Included The generator step-up transformers, generators, and interconnecting lines were modeled according to the information provided by the Customer. 3.2 Load Flow Analyses 3.2.1 Load Flow Analysis With the above assumptions implemented, the First Contingency Incremental Transfer Capability (FCITC) values are calculated. The FCITC depends on various factors the system load, generation dispatch, scheduled maintenance of equipment, and the configuration of the interconnected system and the power flows in effect among the interconnected systems. The FCITC is also dependent on previously confirmed firm reservations on the interface. 5

3.2.2 Performance Criteria The criteria for overload violations are as follows: A) With All Lines in Service The MVA flow in any branch should not exceed Rate A (normal rating). B) Under Contingencies The MVA flow through any facility should not exceed Rate A. 3.2.3 Power Factor Consideration / Criteria FERC Order 661A describes the power factor design requirements for wind and solar generation plants. A wind or solar generation facility s reactive power requirements are based on the aggregate of all units that feed into a single point on the transmission system. The Transmission Provider s System Impact Study is needed to demonstrate that a specific power factor requirement is necessary to ensure safety or reliability. Contingencies were taken in Mississippi. All of the bus voltages were monitored in this region. There were no voltage limitations if the study plant is operated in voltage control mode with ± 0.9 power factor as specified by the customer. 6

3.3 Analysis Results Summary of the analysis results are documented in following table for each scenario. Table 3.3 1: Summary of Results for E001 ERIS Load Flow Study Summer Peak Case Used FCITC Available for Scenario 1 FCITC Available for Scenario 2 FCITC Available for Scenario 3 FCITC Available for Scenario 4 Interface Name AECI Associated Electric Cooperative, Inc. 2017 200 200 93 200 AEP-W American Electric Power - West 2017-1059 -885-1113 -939 AMRN Ameren Transmission 2017 200 200 200 200 CLEC CLECO 2017 200 200 200 200 EAI Entergy Arkansas 2017 200 200 200 200 EES Entergy 2017 200 200 200 200 EES SYS Entergy System LOAD Load 2017 200 200 200 200 EMDE Empire District Electric Co 2017 200 200 200 200 EMI Entergy Mississippi 2017 200 200 200 200 LAFA Lafayette Utilities System 2017 200 200 200 200 LAGN Louisiana Generating, LLC 2017 200 200 200 200 LEPA Louisiana Energy & Power Authority 2017-246 -423-187 -364 OKGE Oklahoma Gas & Electric Company 2017 200 200 200 200 SMEPA South Mississippi Electric Power Assoc. 2017-130 -154-131 -156 SOCO Southern Company 2017 200 200 200 200 SPA Southwest Power Administration 2017 68 200 66 200 TVA Tennessee Valley Authority 2017 200 200 200 200 7

Network Resource Interconnection Service 4. Introduction A Network Resource Interconnection Services (NRIS) study was requested to serve 200MW of Entergy network load. The expected in service date for this NRIS generator is January 1, 2017. The tests were performed with only confirmed transmission reservations and existing network generators and with transmission service requests in study mode. Two tests were performed; a deliverability to generation test and a deliverability to load test. The deliverability to generation (DFAX) test ensures that the addition of this generator will not impair the deliverability of existing network resources and units already designated as NRIS while serving network load. The deliverability to load test determines if the tested generator will reduce the import capability level to certain load pockets (Amite South, WOTAB and Western Region) on the Entergy system. A more detailed description for these two tests is described in Appendix E. It is understood that the NRIS status provides the Interconnection Customer with the capability to deliver the output of the Generating Facility into the Transmission System. NRIS in and of itself does not convey any right to deliver electricity to any specific customer or Point of Delivery 5. Analysis 5.1 Models The models used for this analysis are the 2017-2021 summer and winter peak cases developed in 2012. The following modifications were made to the base cases to reflect the latest information available: Non-Firm IPPs within the local region of the study generator were turned off and other non-firm IPPs outside the local area were increased to make up the difference. Confirmed firm transmission reservations were modeled for the year 2017. Approved transmission reliability upgrades for 2013-2016 were included in the base case. These upgrades can be found at Entergy s OASIS web page http://www.oatioasis.com/ees/eesdocs/disclaimer.html under approved future projects. Reference Appendix D. 5.2 Contingencies and Monitored Elements Single contingency analyses on Entergy s transmission facilities (including tie lines) 69kV and above were considered. All transmission facilities on Entergy transmission system above 100kV were monitored. Power Factor Consideration / Criteria FERC Order 661A describes the power factor design requirements for wind and solar generation plants. A wind or solar generation facility s reactive power requirements are based on the aggregate of all units that feed into a single point on the transmission system. The Transmission Provider s System Impact Study is needed to demonstrate that a specific power factor requirement is necessary to ensure safety or reliability. 8

The customer meets the criteria as stated above. 5.3 Generation used for the transfer The Customer s generators were used as the source for the deliverability to generation test. 5.4 Results 5.4.1 Deliverability to Generation (DFAX) Test The deliverability to generation (DFAX) test ensures that the addition of this generator will not impair the deliverability of existing network resources and units already designated as NRIS while serving network load. A more detailed description for these two tests is described in Appendix E. 5.4.2 Constraints Study Case NONE Study Case with Priors NONE 5.4.3 DFAX Study Case Results 5.4.4 DFAX Study Case with Priors Results 5.4.5 Deliverability to Load Test The deliverability to load test determines if the tested generator will reduce the import capability level to certain load pockets (Amite South, WOTAB and Western Region) on the Entergy system. A more detailed description for these two tests is described in Appendix E. A. Amite South: Passed B. WOTAB: Passed C. Western Region: Passed 9

6. Required Upgrades for NRIS 6.1 Preliminary Estimates of Direct Assignment of Facilities and Network Upgrades Limiting Element NONE Planning Estimate for Upgrade* NONE 7. Interconnection Facilities The Interconnection Customer s designated Point of Interconnection (POI) is the Moon Lake 230 kv substation. The estimated cost of interconnection facilities is $1.7 Million. This cost is a planning estimate only. Cost may significantly change based on specific project parameters that are not known at this time. Costs specific to this interconnection will be developed during the Facilities Study. The interconnection customer is responsible for constructing all facilities needed to deliver generation to the POI. 10

APPENDIX A: DATA PROVIDED BY CUSTOMER 11

12

13

14

15

16

17

APPENDIX B: PRIOR GENERATION INTERCONNECTION AND TRANSMISSION SERVICE REQUESTS IN STUDY MODELS Prior Generation Interconnection NRIS requests that were included in this study: PID Substation MW In Service Date NONE Prior transmission service requests that were included in this study: OASIS PSE MW Begin End 77829615 EAGL 150 8/31/2014 8/31/2034 77855178 NRG 51 1/1/2014 1/1/2026 77856582 NRG 20 4/30/2013 4/30/2023 77920125 CCG 35 1/1/2014 1/1/2019 77929413 Entergy Services 4 5/31/2013 5/31/2023 (SPO) 78268667 NRG 1 6/30/2014 6/30/2015 78268668 NRG 103 6/30/2014 6/30/2015 77913381 Quantum Choctaw Power LLC 780 6/1/2017 6/1/2037 18

APPENDIX C: ERIS LOAD FLOW DETAILS OF SCENARIO 1, 2, 3, AND 4 Table 1: Details of Scenario 1 Results (Without Future Projects and Without Pending Transmission Service & Study Request) Limiting Elements Est. Cost AECI AEPW AMRN CLECO EAI EES EESLoad EMDE EMI LAFA LAGN LEPA OKGE SMEPA SOCO SPA TVA Fancy Point - Port Hudson $250,000 230kV ckt 1 X Fancy Point - Port Hudson 230kV ckt 2 $250,000 X Florence - South Jackson 115kV - Supplemental Upgrade FFR Payment 21 International Paper - Mansfield 138kV (CLECO) Other Ownership X International Paper - Wallake 138kV (CLECO) Other Ownership X Jackson Miami - Jackson Monument Street 115kV $2,352,000 X Jackson Miami - Rex Brown-W 115kV $1,478,400 X Philadelphia MS (TVA)- South Philadelphia 161kV Other Ownership X Port Hudson 230/138 transformer 1 $6,560,000 X Port Hudson 230/138 transformer 2 $6,560,000 X Trumann - Trumann West AECC 161kV $5,637,600 X Vacherie - Waterford 230kV $16,551,000 X 19

Table 2: Details of Scenario 2 Results (Without Future Projects and With Pending Transmission Service & Study Request) Limiting Elements Est. Cost AECI AEPW AMRN CLECO EAI EES EESSLoad EMDE EMI LAFA LAGN LEPA OKGE SMEPA SOCO SPA TVA Fancy Point - Port Hudson $250,000 230kV ckt 1 X Fancy Point - Port Hudson $250,000 230kV ckt 2 X Florence - South Jackson 115kV - Supplemental Upgrade FFR Payment 21 Greenwood - Terrebone 115kV $10,170,160 X International Paper - Mansfield 138kV (CLECO) Other Ownership X International Paper - Wallake 138kV (CLECO) Other Ownership X Jackson Miami - Jackson Monument Street 115kV $2,352,000 X Jackson Miami - Rex Brown-W 115kV $1,478,400 X Philadelphia MS (TVA)- South Philadelphia 161kV Other Ownership X Port Hudson 230/138 transformer 1 $6,560,000 X Port Hudson 230/138 transformer 2 $6,560,000 X Vacherie - Waterford 230kV $16,551,000 X 20

Table 3: Details of Scenario 3 Results (With Future Projects and Without Pending Transmission Service & Study Request) Limiting Elements Est. Cost AECI AEPW AMRN CLECO EAI EES EESSLoad EMDE EMI LAFA LAGN LEPA OKGE SMEPA SOCO SPA TVA Fancy Point - Port Hudson $250,000 230kV ckt 1 X Fancy Point - Port Hudson $250,000 230kV ckt 2 X Florence - South Jackson 115kV - Supplemental Upgrade FFR Payment 21 Greenwood - Terrebone 115kV $10,170,160 X International Paper - Mansfield 138kV (CLECO) Other Ownership X International Paper - Wallake 138kV (CLECO) Other Ownership X Jackson Miami - Rex Brown-W 115kV $1,478,400 X Philadelphia MS (TVA)- South Philadelphia 161kV Other Ownership X Port Hudson 230/138 transformer 1 $6,560,000 X Port Hudson 230/138 transformer 2 $6,560,000 X Trumann - Trumann West AECC 161kV $5,637,600 X X Vacherie - Waterford 230kV $16,551,000 X 21

Table 4: Details of Scenario 4 Results (With Future Projects and With Pending Transmission Service & Study Request) Limiting Elements Est. Cost AECI AEPW AMRN CLECO EAI EES EESSLoad EMDE EMI LAFA LAGN LEPA OKGE SMEPA SOCO SPA TVA Brookhaven - Mallalieu (MEPA) Included in 115kV 2013 ICT BP X Fancy Point - Port Hudson 230kV $250,000 ckt 1 X Fancy Point - Port Hudson 230kV ckt 2 $250,000 X Supplemental Upgrade FFR Payment 21 Greenwood - Terrebone 115kV $10,170,160 X International Paper - Mansfield Other 138kV (CLECO) Ownership X International Paper - Wallake 138kV (CLECO) Other Ownership X Jackson Miami - Rex Brown-W 115kV $1,478,400 X Philadelphia MS (TVA)- South Philadelphia 161kV Other Ownership X Port Hudson 230/138 transformer 1 $6,560,000 X Port Hudson 230/138 transformer 2 $6,560,000 X Vacherie - Waterford 230kV $16,551,000 X 22

APPENDIX D: DETAILS OF SCENARIO 1 2017 AECI AEPW International Paper - Wallake 138kV (CLECO) Dolet Hills (CLECO) - S.W. Shreevport 345kV (CLECO) -1059 International Paper - Mansfield 138kV (CLECO) Dolet Hills (CLECO) - S.W. Shreevport 345kV (CLECO) -921 AMRN CLECO EAI EES NONE NONE 27 EESSLoad EMDE 23

EMI LAFA LAGN LEPA Fancy Point - Port Hudson 230kV ckt 1 Fancy Point - Port Hudson 230kV ckt 2-246 Fancy Point - Port Hudson 230kV ckt 2 Fancy Point - Port Hudson 230kV ckt 1-159 Vacherie - Waterford 230kV Raceland - Waterford 230kV 7 Port Hudson 230/138 transformer 1 Port Hudson 230/138 transformer 2 103 Port Hudson 230/138 transformer 2 Port Hudson 230/138 transformer 1 127 OKGE SMEPA Supplemental Upgrade Bogalusa - Adams Creek 500/230kV transformer -130 Supplemental Upgrade Bogalusa - Franklin 500kV -130 Jackson Miami - Rex Brown-W 115kV South Jackson 230/115kV transformer 1-69 Supplemental Upgrade Choctaw MS (TVA) - Clay (TVA) 500kV -61 Supplemental Upgrade South Jackson - Poplar Spring 115kV -14 Supplemental Upgrade Georgetown - Poplar Spring 115kV 9 Supplemental Upgrade Georgetown - Silver Creek 115kV 15 Supplemental Upgrade Angie - Adams Creek 230kV 22 Franklin - Grand Gulf 500kV 25 24

Supplemental Upgrade Supplemental Upgrade Sturgis MS (TVA) - NW Louisville (TVA) 161kV 29 Supplemental Upgrade Ellicott (SOCO) - BarryCC2 (SOCO) 230kV 34 Supplemental Upgrade Base Case 150 Philadelphia MS (TVA) - South Philadelphia 161kV Philadelphia MS (TVA) - Sebastopol (TVA) 161kV 166 Jackson Miami - Jackson Monument Street 115kV South Jackson 230/115kV transformer 1 174 SOCO SPA Trumann - Trumann West AECC 161kV Newport - Newport Industrial 161kV 68 Trumann - Trumann West AECC 161kV Newport AB - Newport Industrial 161kV 102 TVA 25

APPENDIX E: DETAILS OF SCENARIO 2 2017 AECI AEPW International Paper - Wallake 138kV (CLECO) Dolet Hills (CLECO) - S.W. Shreevport 345kV (CLECO) -885 International Paper - Mansfield 138kV (CLECO) Dolet Hills (CLECO) - S.W. Shreevport 345kV (CLECO) -747 AMRN CLECO EAI EES EESSLoad 26

EMDE EMI LAFA LAGN LEPA Fancy Point - Port Hudson 230kV ckt 1 Fancy Point - Port Hudson 230kV ckt 2-423 Fancy Point - Port Hudson 230kV ckt 2 Fancy Point - Port Hudson 230kV ckt 1-335 Vacherie - Waterford 230kV Raceland - Waterford 230kV 6 Port Hudson 230/138 transformer 1 Port Hudson 230/138 transformer 2 39 Port Hudson 230/138 transformer 2 Port Hudson 230/138 transformer 1 63 Greenwood - Terrebone 115kV Bayou Sales (CLECO) - Teche 138kV (CLECO) 186 Greenwood - Terrebone 115kV Bayou Sales (CLECO) - WaxLake 138kV (CLECO) 189 OKGE SMEPA Supplemental Upgrade Bogalusa - Franklin 500kV -154 Supplemental Upgrade Bogalusa - Adams Creek 500/230kV transformer -154 Supplemental Upgrade Choctaw MS (TVA) - Clay (TVA) 500kV -99 27

Jackson Miami - Rex Brown-W 115kV South Jackson 230/115kV transformer 1-83 Supplemental Upgrade South Jackson - Poplar Spring 115kV -37 Supplemental Upgrade Georgetown - Poplar Spring 115kV -13 Supplemental Upgrade Georgetown - Silver Creek 115kV -8 Supplemental Upgrade Angie - Adams Creek 230kV -3 Supplemental Upgrade Franklin - Grand Gulf 500kV 2 Supplemental Upgrade Sturgis MS (TVA) - NW Louisville (TVA) 161kV 6 Supplemental Upgrade Ellicott (SOCO) - BarryCC2 (SOCO) 230kV 12 Supplemental Upgrade Base Case 128 Jackson Miami - Jackson Monument Street 115kV South Jackson 230/115kV transformer 1 160 Philadelphia MS (TVA) - South Philadelphia 161kV Philadelphia MS (TVA) - Sebastopol (TVA) 161kV 171 SOCO SPA TVA 28

APPENDIX F: DETAILS OF SCENARIO 3 2017 AECI Trumann - Trumann West AECC 161kV Newport - Newport Industrial 161kV 93 Trumann - Trumann West AECC 161kV Newport AB - Newport Industrial 161kV 138 AEPW International Paper - Wallake 138kV (CLECO) Dolet Hills (CLECO) - S.W. Shreevport 345kV (CLECO) -1113 International Paper - Mansfield 138kV (CLECO) Dolet Hills (CLECO) - S.W. Shreevport 345kV (CLECO) -971 AMRN CLECO EAI EES EESSLOAD 29

EMDE EMI LAFA LAGN LEPA Fancy Point - Port Hudson 230kV ckt 1 Fancy Point - Port Hudson 230kV ckt 2-187 Fancy Point - Port Hudson 230kV ckt 2 Fancy Point - Port Hudson 230kV ckt 1-97 Vacherie - Waterford 230kV Raceland - Waterford 230kV 8 Port Hudson 230/138 transformer 1 Port Hudson 230/138 transformer 2 121 Port Hudson 230/138 transformer 2 Port Hudson 230/138 transformer 1 143 Greenwood - Terrebone 115kV Bayou Sales (CLECO) - Teche 138kV (CLECO) 186 Greenwood - Terrebone 115kV Bayou Sales (CLECO) - WaxLake 138kV (CLECO) 189 OKGE SMEPA Supplemental Upgrade Bogalusa - Franklin 500kV -131 Supplemental Upgrade Bogalusa - Adams Creek 500/230kV transformer -131 Supplemental Upgrade Choctaw MS (TVA) - Clay (TVA) 500kV -62 30

Supplemental Upgrade South Jackson - Poplar Spring 115kV -17 Supplemental Upgrade Georgetown - Poplar Spring 115kV 7 Supplemental Upgrade Georgetown - Silver Creek 115kV 12 Supplemental Upgrade Angie - Adams Creek 230kV 21 Supplemental Upgrade Franklin - Grand Gulf 500kV 22 Supplemental Upgrade Sturgis MS (TVA) - NW Louisville (TVA) 161kV 25 Supplemental Upgrade Ellicott (SOCO) - BarryCC2 (SOCO) 230kV 32 Jackson Miami - Rex Brown-W 115kV South Jackson 230/115kV transformer 1 80 Supplemental Upgrade Base Case 147 Philadelphia MS (TVA) - South Philadelphia 161kV Philadelphia MS (TVA) - Sebastopol (TVA) 161kV 170 SOCO SPA Trumann - Trumann West AECC 161kV Newport - Newport Industrial 161kV 66 Trumann - Trumann West AECC 161kV Newport AB - Newport Industrial 161kV 98 TVA 31

APPENDIX G: DETAILS OF SCENARIO 4 2017 AECI AEPW International Paper - Wallake 138kV (CLECO) Dolet Hills (CLECO) - S.W. Shreevport 345kV (CLECO) -939 International Paper - Mansfield 138kV (CLECO) Dolet Hills (CLECO) - S.W. Shreevport 345kV (CLECO) -797 AMRN CLECO EAI EES EESSLoad EMDE 32

EMI LAFA LAGN LEPA Fancy Point - Port Hudson 230kV ckt 1 Fancy Point - Port Hudson 230kV ckt 2-364 Fancy Point - Port Hudson 230kV ckt 2 Fancy Point - Port Hudson 230kV ckt 1-274 Vacherie - Waterford 230kV Raceland - Waterford 230kV 6 Port Hudson 230/138 transformer 1 Port Hudson 230/138 transformer 2 58 Port Hudson 230/138 transformer 2 Port Hudson 230/138 transformer 1 79 Greenwood - Terrebone 115kV Bayou Sales (CLECO) - Teche 138kV (CLECO) 186 Greenwood - Terrebone 115kV Bayou Sales (CLECO) - WaxLake 138kV (CLECO) 189 OKGE SMEPA Supplemental Upgrade Bogalusa - Franklin 500kV -156 Supplemental Upgrade Bogalusa - Adams Creek 500/230kV transformer -156 Supplemental Upgrade Choctaw MS (TVA) - Clay (TVA) 500kV -101 Supplemental Upgrade South Jackson - Poplar Spring 115kV -40 Supplemental Upgrade Georgetown - Poplar Spring 115kV -16 Supplemental Upgrade Georgetown - Silver Creek 115kV -10 33

Supplemental Upgrade Angie - Adams Creek 230kV -6 Supplemental Upgrade Franklin - Grand Gulf 500kV 0 Supplemental Upgrade Sturgis MS (TVA) - NW Louisville (TVA) 161kV 3 Supplemental Upgrade Ellicott (SOCO) - BarryCC2 (SOCO) 230kV 9 Jackson Miami - Rex Brown-W 115kV South Jackson 230/115kV transformer 1 64 Supplemental Upgrade Base Case 125 Philadelphia MS (TVA) - South Philadelphia 161kV Philadelphia MS (TVA) - Sebastopol (TVA) 161kV 175 Brookhaven - Mallalieu (MEPA) 115kV Bogalusa - Franklin 500kV 183 Brookhaven - Mallalieu (MEPA) 115kV Bogalusa - Adams Creek 500/230kV transformer 183 SOCO SPA TVA 34