REGISTRATION EXAMINATION, NOVEMBER 2012 LICENSED DRAINLAYER QUESTION AND ANSWER BOOKLET. Time allowed THREE hours

Similar documents
REGISTRATION EXAMINATION, november 2015 LICENSED PLUMBER. Time allowed THREE hours

CERTIFYING DRAINLAYER

CERTIFYING DRAINLAYER

REGISTRATION EXAMINATION, JUNE 2013 LICENSED PLUMBER QUESTION AND ANSWER BOOKLET. Time allowed THREE hours

REGISTRATION EXAMINATION, JUNE 2017 CERTIFYING PLUMBER QUESTION AND ANSWER BOOKLET. Time allowed THREE hours

REGISTRATION EXAMINATION, JUNE 2009 DRAINLAYING ANSWER SCHEDULE

CERTIFYING DRAINLAYER

CERTIFYING DRAINLAYER

CRAFTSMAN EXAMINATION, NOVEMBER 2008 PLUMBING ANSWER SCHEDULE

REGISTRATION EXAMINATION, NOVEMBER 2015 LICENSED DRAINLAYER ANSWER SCHEDULE

REGISTRATION EXAMINATION, JUNE 2018 CERTIFYING PLUMBER ANSWER SCHEDULE

Below ground System of pipework required to carry waste fluids from building to disposal site.

Review the section Preparing for work, then complete the following.

Wastewater treatment for single houses. D. O Dowd

WASTEWATER DRAINAGE BYLAW

INYO COUNTY ENVIRONMENTAL HEALTH SERVICES RESIDENTIAL ONSITE SEWAGE TREATMENT AND DISPOSAL GUIDE

SPECIAL SPECIFICATION 3504 Septic Tank System

City of Logan Sanitary Sewer Design Standards

3. Sanitary Plumbing Single Stack System

NZQA Expiring unit standard version 2 Page 1 of 5. Install and maintain water mains and water supply systems and reticulation

G13. Acceptable Solutions and Verification Methods. For New Zealand Building Code Clause G13 Foul Water

Sewer Audit - Design Checklist Gravity sewers, sewage pumping stations and pressure sewers

APPENDIX 5 On Site Sewage Treatment and Disposal 1. Site Requirements

Polysewer Gravity Sewer System SPECIFICATION

SEWER SYSTEM DESIGN GUIDELINES

ON-SITE SEWAGE CONTRACTOR EXAMINATION STUDY GUIDE

SPECIFICATION FOR PIPE CULVERT CONSTRUCTION

Dispute regarding the venting of a branch drain using an air admittance valve to a building at 122 Remuera Road, Auckland

Section 9: Sand Mounds. 9. Sand Mounds

SEPTIC TANK CONSTRUCTION GUIDELINES

Holding tank Interceptor Leaching Leaching bed Leaching bed fill Loading rate Pail privy Percolation time Portable privy Potable Pressurized

March, 2017 Nova Scotia On-site Sewage Disposal Systems Standard revisions effective May 1, Appendix C Falling head permeameter

STANDARD SPECIFICATIONS

RAUPIANO PLUS ACOUSTIC PLUMBING AND DRAINAGE SYSTEM. Product. Scope. Building Regulations. Appraisal No. 809 [2013]

AS/NZS :2015. Plumbing and drainage AS/NZS :2015. Part 2: Sanitary plumbing and drainage. Australian/New Zealand Standard

Compliance Document for New Zealand Building Code Clause G15 Solid Waste

Figure 1 Part site plan showing location of house and drive (drainage not shown)

THIS IS A COURTESY COPY OF THIS RULE. ALL OF THE DEPARTMENT S RULES ARE COMPILED IN TITLE 7 OF THE NEW JERSEY ADMINISTRATIVE CODE.

Approved Document. Drainage and waste disposal. The Building Regulations 2010

On-site domestic wastewater treatment units

PROCEDURE F-6-1 (formerly referenced by 08-02) Procedures to Govern Separation of Sewers and Watermains

The term storage water heater is a defined term used in the Acceptable Solutions and Verification Method for Clause G12 Water Supplies

Drainage and waste disposal

Level 1 Biology, 2012

Wastewater Collection. (Sewer Alternatives)

Assembly and Installation Instructions Grease Separator KLsepa.pop

REQUIRED SEPTIC DRAWINGS


Advanced Enviro-Septic TM Basic Design and Installation Manual

INSTALLING A SEPTIC SYSTEM IN LIVINGSTON COUNTY LIVINGSTON COUNTY PUBLIC HEALTH DEPARTMENT 310 TORRANCE AVENUE PONTIAC, IL /

Septic Tank Guidelines

AS/NZS :2003. Plumbing and drainage AS/NZS :2003. Australian/New Zealand Standard. Part 3: Stormwater drainage

BUILDING INFORMATION BAM /11/13

Household Sewage Treatment System Factsheet Aeration System- Frequently Asked Questions

Trade of Plumbing. Module 2: Domestic Hot and Cold Water Service Unit 13: Below Ground Drainage Phase 2

MINISTERIAL DECISION 5/86 DATED 17TH MAY, 1986 REGULATIONS FOR EXTERNAL BUILDING DRAINAGE

Property is served by unmetered public or private water. Not normally applicable to this item. Page 1 of 5 Supplement to HHE-240 Rev.

The Drainage and Plumbing Regulations 1996.

I. Preconstruction Meeting and Site Preparation Date: Inspector: A. MDE Certified Installer Name

Illustrated Hard Landscape Seminars - Student Notes Copyright 1995 John Heather Rev Curriculum No. GD x 1.25hrs.

Mono County Health Department Construction Guide for Residential and Commercial On-Site Sewage Treatment & Disposal System I.

Consultation on gazetting the competencies required for registration and licensing

For use by Principal Authority. A. Project information Building number, street name Unit number Lot/con.

DRIP EMITTER SYSTEM STUDY GUIDE

ACCESS RISERS & EFFLUENT FILTER

CAPRICORN MUNICIPAL DEVELOPMENT GUIDELINES PRECAST BOX CULVERTS CONSTRUCTION SPECIFICATION

Sustainable, Reliable, Affordable

Klickitat County. On-Site Sewage System. Construction Manual

Design of Sewerage System for Jaffarpur area in Southwest New Delhi

NZQA Expiring unit standard 2117 version 5 Page 1 of 5. Install, test, and maintain water supply backflow prevention devices

AS/NZS :1996 Plumbing and drainage - Part 2.2: Sanitary plumbing and drainage - Acceptable solutions

Commonwealth of Massachusetts Title 5 Official Inspection Form Subsurface Sewage Disposal System Form - Not for Voluntary Assessments

GRAY WATER RECYCLING SYSTEMS

Manufacturing standard

Septic Tanks: The Primary Treatment Device of Conventional Septic Systems

City of Vineland Health Department 640 E. Wood Street, Vineland, NJ (856) (ph.) / (856) (fax)

Pollution Control. A Range of Package Pump Systems for Residential & Commercial Developments. klargester.com

ARCHIVED. Compliance Document for New Zealand Building Code Clause G15 Solid Waste. Prepared by the Department of Building and Housing

Pumper/Service Provider/Septic Technician/Service Technician/Septic Tank Service Provider/Septic Tank Service Technician Need to Know

On-lot System Component Requirements

Drexus Pave Drain. Linear Channel. Water Management. Water Linear Management Drainage Design Guide Drexus Pave Drain Linear Drainage Channel

SECTION 2 - DESIGN STANDARDS FOR GRAVITY SANITARY SEWERS

Environmental Engineering II

Sag Pipe (depressed sewers, or Inverted siphons) Dr. Sataa A. Al-Bayati(10-11)

Commonwealth of Massachusetts Title 5 Official Inspection Form. Subsurface Sewage Disposal System Form - Not for Voluntary Assessments

Module 7: Hydraulic Design of Sewers and Storm Water Drains. Lecture 7: Hydraulic Design of Sewers and Storm Water Drains

Application for a Permit to Construct or Demolish This form is authorized under subsection 8(1.1) of the Building Code Act,1992

Woodford County Health Department 1831 S. Main Street, Eureka, IL Phone: (309) Fax: (309)

Drainage and waste disposal

ACTIVITY: Dewatering Operations AM 12

Planning & Development Services. Septic Smart

C231 Subsoil and Foundation Drains

COSVR639 SQA Unit HL87 04 Install drainage

EARTHSAFE OWNERS MANUAL WASTEWATER TREATMENT SYSTEMS. All information contained within this manual is the property of Eco Water (QLD) Pty Ltd.

Producer Statement. Design: On-Site Effluent Disposal Systems (AS/NZS 1547:2000)

Commonwealth of Massachusetts Title 5 Official Inspection Form Subsurface Sewage Disposal System Form - Not for Voluntary Assessments

Commonwealth of Massachusetts Title 5 Official Inspection Form Subsurface Sewage Disposal System Form - Not for Voluntary Assessments

Skeletank. Rainwater Storage Unit PRODUCT SPECIFICATION SHEET. Product Code: SELH01001

Installation Data for Elliptical Pipes. PD 29 rev E 20/09/05

Private Wells & Septic Systems

Transcription:

Affix label with Candidate Code Number here. If no label, enter candidate Number if known No. 9197 REGISTRATION EXAMINATION, NOVEMBER 2012 LICENSED DRAINLAYER INSTRUCTIONS QUESTION AND ANSWER BOOKLET Time allowed THREE hours Check that the Candidate Code Number on your admission slip is the same as the number on the label at the top of this page. Do not start writing until you are told to do so by the Supervisor. Total marks for this examination: 100. The pass mark for this examination is 60 marks. Write your answers and draw your sketches in this booklet. If you need more paper, use pages 21 25 at the back of this booklet. Clearly write the question number(s) if any of these pages are used. All working in calculations must be shown. Candidates are permitted to use the following in this examination: Drawing instruments, approved calculators, document(s) provided. Publications, Acts, Regulations, Codes of Practice, or Standards other than the ones provided are NOT permitted in the examination room. Check that this booklet has all of 25 pages in the correct order and that none of these pages is blank. YOU MUST HAND THIS BOOKLET TO THE SUPERVISOR AT THE END OF THE EXAMINATION Plumbers, Gasfitters and Drainlayers Board, 2012. All rights reserved. No part of this publication may be reproduced by any means without the prior permission of the Plumbers, Gasfitters and Drainlayers Board.

Candidates that sat this examination in November 2012 were provided with the following documents: New Zealand Building Code clause G13 Foul Water AS/NZS 3500 Part 2: Sanitary plumbing and drainage

SECTION A QUESTION 1 (a) Give THREE ways of changing the direction or gradient of a drain. 1 2 3 (3 marks) (b) Describe the THREE situations when a foul water drain requires ventilating. 1 2 3 (3 marks) (c) The minimum grade cannot be obtained for a foul water drain. Give TWO methods of overcoming this situation. (2 marks) Total 8 marks Licensed Drainlayer 9197, November 2012 1

QUESTION 2 (a) Describe why antibiotics should not be flushed into a septic tank. (b) List FOUR factors that may shorten the life of an effluent field. 1 2 3 4 (2 marks) (c) List TWO devices that can extend the life of an effluent field. 1 2 (2 marks) Total 5 marks Licensed Drainlayer 9197, November 2012 2

QUESTION 3 Complete the table below showing the gradients as a percentage and in mm per m (millimetres per metre). Vented Drain Diameter Ratio (gradient) Gradient in % mm per m DN 150 1 in 60 DN 65 1 in 80 DN 100 1 in 30 DN 300 1 in 120 Total 4 marks QUESTION 4 A trench is to be dug adjacent to the foundation of a building. The trench will be open for longer than 48 hrs. The bottom of the trench will be 450 mm below the underside of the building foundation. (a) State the minimum horizontal separation between the trench and the building foundation. (2 marks) (b) Give a factor which would allow for the minimum separation in (a) to be reduced. Total 3 marks Licensed Drainlayer 9197, November 2012 3

QUESTION 5 Name each device shown in the following diagrams, give a situation where it would be required and state its function. (a) Name Vent Situation Grate Function Outlet (3 marks) (b) Name Gully dish Tight Fitting Covers Situation Outlet Function (3 marks) Licensed Drainlayer 9197, November 2012 4

QUESTION 5 (cont d) (c) Name Situation 1000 mm Function (3 marks) (d) Name Situation 450 mm Function (3 marks) Total 12 marks Licensed Drainlayer 9197, November 2012 5

QUESTION 6 (a) Sketch and label a plan and elevation of an outfall wing-wall. (5 marks) (b) Explain how the velocity of the water at the outfall of a wing-wall could be reduced. Total 6 marks Licensed Drainlayer 9197, November 2012 6

QUESTION 7 The diagram below shows a plan view indicating the position of a drain. E 4 m D A 2.5 m 2 m 5 m C B The drain invert at point A is 400 mm below the datum. The drain has been laid at a gradient of 1 in 80 (1.25%). Complete the following table to show the fall between each change of direction and the depth below the datum for the excavation at points B, C, D and E. Point Fall Depth A 0 mm 400 mm B C D E Total 8 marks Licensed Drainlayer 9197, November 2012 7

QUESTION 8 Give EIGHT situations that require concrete support to be used for a drain. 1 2 3 4 5 6 7 8 Total 4 marks Licensed Drainlayer 9197, November 2012 8

QUESTION 9 (a) Give the meaning of aerobic in relation to on-site sewage treatment systems. (b) Give an advantage of the inclusion of an aeration chamber in an on-site sewage treatment system. (c) Give a disadvantage of the inclusion of an aeration chamber in an on-site sewage treatment system. Total 3 marks Licensed Drainlayer 9197, November 2012 9

QUESTION 10 The sketch below shows a plan view of a surface water system installation. On the page opposite, draw an as-built plan of the sketch using a scale of 1:100 Total 7 marks Licensed Drainlayer 9197, November 2012 10

Licensed Drainlayer 9197, November 2012 11

QUESTION 11 (a) Describe geotextile material (filter cloth), and give a situation where it is required. (2 marks) (b) According to the New Zealand Building Code Clause G13 Foul Water, state the maximum distance permitted between the top of a gully dish and the top of the water seal. (c) Give the reason for the maximum measurement in (b). Total 4 marks Licensed Drainlayer 9197, November 2012 12

QUESTION 12 (a) A 50 m long x 100 mm diameter foul water drain is to be tested for leakage. Complete the tables below by naming TWO types of tests used to ensure the water tightness of the drain, and for each type of test giving the minimum pressure for the test and the minimum time required for the test. Type of test Minimum test pressure Minimum test time Type of test Minimum test pressure Minimum test time (6 marks) (b) Give TWO conditions that can adversely affect the results of a leakage test. 1 2 (2 marks) Total 8 marks Licensed Drainlayer 9197, November 2012 13

QUESTION 13 (a) Name TWO naturally occurring hazardous gases that may be encountered in a trench. 1 2 (b) State why some gases tend to gather in excavations rather than dissipate into the air. (c) Give a method of preventing hazardous gases from gathering in an excavation. (d) If there is a likelihood of air contamination in an excavation, state when the air quality will require testing. Total 4 marks Licensed Drainlayer 9197, November 2012 14

QUESTION 14 (a) List FOUR devices that may be used to ensure a drain that is being laid in a trench has the correct gradient. 1 2 3 4 (2 marks) (b) Complete the table below by giving TWO ways in which the safe condition of an excavation could deteriorate overnight and giving a cause for each. Way Cause (2 marks) Total 4 marks Licensed Drainlayer 9197, November 2012 15

QUESTION 15 Calculate in m 3 the total volume of material required to fill the excavation for the tank shown below. Allow a 20% compaction rate. Formula: Volume of cylinder = 0.7854 D D H 2.1 m Dia 1.7 m 1.6 m 3.5 m 2.8 m Total 5 marks Licensed Drainlayer 9197, November 2012 16

QUESTION 16 Notifiable work requirements need to be considered when planning drainlaying work. List FIVE drainlaying situations when drainlaying work becomes notifiable. 1 2 3 4 5 Total 5 marks Licensed Drainlayer 9197, November 2012 17

SECTION B Answer the following multiple-choice questions by writing your answer (A, B, C, D or E) in the box provided after each one of the questions. Each correct answer in this section of the examination is worth 1 mark. Note that should your choice of answer be unclear in this section of the examination no marks will be awarded for that question. 1. According to AS/NZS 3500 Part 2: Sanitary plumbing and drainage, which of the following shows the normal minimum grade of a 125 mm drain? A 0.12%. B 1.25%. C 1.65%. D 1.50%. E 2.50%. 2. According to AS/NZS 3500 Part 2: Sanitary plumbing and drainage, above what grade are anchor blocks required when a drain is being installed? A 20%. B 25%. C 30%. D 45%. E 60%. 3. According to New Zealand Building Code Clause G13/AS2 Foul Water, what is the maximum distance that a gully dish that discharges into a grease trap should be from the grease trap? A 1 m. B 1.2 m. C 1.8 m. D 2.4 m. E 3 m. Licensed Drainlayer 9197, November 2012 18

4. According to New Zealand Building Code Clause G13/AS2 Foul Water, no access point is required at the junction of a branch drain where it joins to another drain if the branch drain only serves a gully trap, and is less than which of the following lengths? A 2 m. B 2.4 m. C 3 m. D 6 m. E 10 m. 5. According to New Zealand Building Code Clause G13/AS2 Foul Water, an access point is required where a drain exits from within what distance under a building? A 0.6 m. B 1.0 m. C 2.0 m. D 2.4 m. E 3.0 m. 6. According to New Zealand Building Code Clause G13/AS2 Foul Water, the minimum width of a trench for a drain must be no less than the diameter of the pipe plus what measurement? A B C D E 100 mm. 200 mm. 300 mm. 400 mm. 600 mm. Licensed Drainlayer 9197, November 2012 19

7. According to New Zealand Building Code Clause G13/AS2 Foul Water, verifiable levelling devices must be used to ensure uniform gradients of drains laid at gradients in what range? A B C D E 1 in 40 or less. 1 in 60 or less. 1 in 80 or less. 1 in 100 or less. 1 in 120 or less. 8. According to New Zealand Building Code Clause G13/AS2 Foul Water, what is the minimum allowable capacity of a grease trap? A B C D E 80 litres. 100 litres. 140 litres. 180 litres. 200 litres. 9. How may well-pointing make soil unstable? A The soil becomes dry and cracks. B The soil no longer has water to float in. C Fine particles of soil can be pumped out with the water. D The vibration of the pump disturbs the soil. E Forcing the drive pipe into the ground breaks up the soil. 10. Which of the following is NOT classed as PPE? A Earmuffs. B Safety glasses. C High visibility vest. D Head lamp. E Breathing apparatus. Total 10 marks Licensed Drainlayer 9197, November 2012 20

For Examiner s use only Question number Marks Marks 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 Section B Total