Stay-Cable Replacement Design

Similar documents
Hale Boggs Memorial Bridge (I-310 Luling-Destrehan) Stay-Cable Replacement Outside New Orleans, Louisiana. By Michael W. Smart

Stay Cable Replacement of the Luling Bridge Armin Mehrabi Bridge Engineering Solutions

Armin Mehrabi Bridge Engineering Solutions LTRC Seminar Series, Bridge Structures February 20-21, 2008, New Orleans, LA

Cable Stay Replacement and Deck Rehabilitation of I-310 Luling - Hale Boggs Mississippi River Bridge

Cable-Stayed Bridges. PTI Recommendations for Stay Cable Design, Testing and Installation

NDT in Grouted PT Inspection for Bridges

John James Audubon Bridge

Recent Developments in Stay Cable Systems

John James Audubon Bridge. Introduction

Special Considerations for Maintenance of the Sunshine Skyway Bridge

Florida DOT efforts toward improving Post Tension Durability

Post-tensioned Structures Solutions for Repair and Protection

Red Wing Bridge Alternates

Ironton Russell Bridge Project

EVALUATION & REPAIR OF CORROSION DAMAGED ROOF LIFT SLAB WITH WIRE POST-TENSIONING SYSTEM (BUTTON HEADS)

PRESERVING LOUISIANA S INFRASTRUCTURE: US190 MISSISSIPPI RIVER BRIDGE

Ironton Russell Bridge Project

DESIGN OF THE MAIN SPANS OF THE CHONGQING CAIYUANBA BRIDGE

Construction Measurement III SBQ3314. Precast Pre stressed Concrete Works. Dr. Sarajul Fikri Mohamed

Narrow Margin BY KEN SAINDON, SE, PE, AND ALEX WHITNEY, PE

Structural - Engineering Review Checklist

Critical Structures Construction Issues

ABRAHAM LINCOLN BRIDGE

MIDAS Training Series

Design and Construction of the SH58 Ramp A Flyover Bridge over IH70. Gregg A. Reese, PE, CE, Summit Engineering Group, Inc.

Ironton Russell Bridge Project

Gusset Plate Retrofit in Illinois

Ironton Russell Bridge Project

Rehabilitation Design and Construction for the US 190 Mississippi River Bridge Cleaning, Painting, and Repair Project

Specification Changes and Their Effect on Plans. Bridge Construction Issues. BRG VTC April, 2010

SUNSHINE SKYWAY BRIDGE

Post-tensioned Concrete Design PT Installation Guidance

Ironton Russell Bridge Project

Design of Izmir Bay Crossing Bridge

Northeast Bridge Preservation Partnership Meeting

Replacing the Aging US 52 Mississippi River Bridge

The construction technology of Chongqing Chaotianmen Bridge

The Hashemite University Department of Civil Engineering. Dr. Hazim Dwairi. Dr. Hazim Dwairi 1

CAIYUANBA BRIDGE, CHONGQING, CHINA. Man-Chung Tang, Chairman, T.Y. Lin International. Guolei Ren, Vice President, T.Y. Lin International (China)

Seismic Design Criteria of a Cable- Stayed Bridge- An Owner s Perspective

Monitoring of External Prestressing Tendons Construction Process of Jiamusi Highway Prestressed Concrete Bridge during Strengthening in China

Deep Water Drilled Shafts for the Herrington Lake Bridge Replacement Project

ENTRY FORM. DVASE 2016 Excellence in Structural Engineering Awards Program. Structural Rehabilitation of Pier 68S

DESIGN AND LAUNCHING OF A REDUNDANT TRUSS OVER RAILROAD YARD

***************************************************************************************************************

Design & technology characteristics of main bridge of Chaotianmen Yangtze River Bridge

SOME FRP STRENGTHENING PROJECTS IN AUSTRALIA

Modjeski and Masters, Inc. Consulting Engineers 04/18/06 St. Croix River Bridge 3D Analysis Report Introduction

2. Outline of the bridge 3-span continuous deck extradosed bridge Bridge length

SPECIAL SPECIFICATION 4401 Prestressed Ground Anchors

DYWIDAG Multistrand Stay Cable Systems

Teglvaerks Bridge, Copenhagen - Denmark Kjeld Thomsen, Civil Engineer, MSc - CEO ISC Consulting Engineers A/S

INSTALLATION MANUAL FOR MODULAR EXPANSION JOINT (LG SYSTEM)

The Use of Eastern Cottonwood for Stress Laminated Sawn Lumber Bridges in Iowa. Paula Hilbrich Lee Michael Ritter

Ironton Russell Bridge Project

Table of Contents. List of Drawings

Canadian Consulting Engineering Awards 2016 CANADIAN NIAGARA POWER FOREBAY BRIDGE RECONSTRUCTION

client: Centre City Development Corporation, San Diego, Calif.

WCU ALUMNI TOWER MASONRY & ENVELOPE REPAIRS

SR 0136-G10 ABC BRIDGE REPLACEMENT in Eighty Four, PA

Dynamic Characteristics Analysis of Large Self-anchored Suspension Bridge

TECHNICAL SPECIAL PROVISION FOR CONCRETE REPAIRS. Financial Project ID , &

CONSTRUCTION SPECIFICATION FOR FOOTINGS AND PADS FOR ELECTRICAL EQUIPMENT

TCC/SHORE TRANSIT BUS MAINTENANCE FACILITY - PHASE II

I-94/I-69 Interchange Bridge Construction

CONSTRUCTION SPECIFICATION FOR FOOTINGS AND PADS FOR ELECTRICAL EQUIPMENT

HIGH CAPACITY ROCK ANCHORS IMPLEMENTATION OF QA/QC PROGRAMS. JULIO DIAMANTE, P.E.

1. CORROSION OF REINFORCEMENT

ATIS CABLESKIN LONG TERM CORROSION PROTECTION SYSTEM FOR CABLES SHORT DESCRIPTION REFERENCE LIST

Willamette River Transit Bridge. Portland - Milwaukie Light Rail Willamette River Bridge WRBAC

Chapter 8 Anchoring Structures

Griffith University Cable Stayed Pedestrian Bridge

Construction Techniques of The 3 rd Bosphorus Bridge in Istanbul, Turkey

HOAN BRIDGE REHABILITATION

AGENDA AGENDA. Route 15/29 SBL Bridge Superstructure Replacement & Widening. NOVA District. Bridge Views SCOPE. Existing Structure.

OKLAHOMA DEPARTMENT OF TRANSPORTATION SPECIAL PROVISIONS FOR BUY AMERICA

EXHIBIT 2-13-D GERALD DESMOND BRIDGE STAY CABLE SYSTEMS

PUBLIC INFORMATION MEETING June 24, 2015

Requirements for Measuring and Pricing of Structural Concrete

Mondol Fabrics Ltd. Nayapara,kasimpur, Gazipur ( N, E0) 8th March 2014

The Basohli Cable Stayed Bridge, India

US-131 Over the Muskegon River. Corey Rogers, P.E. Bridge Construction Engineer

EXHIBIT 2-13-D GERALD DESMOND BRIDGE STAY CABLE SYSTEMS

Executive Summary RPT-SPE December 21. Old Spences Bridge No Inspection Report

Ironton Russell Bridge Project

Bonner Bridge Replacement Update:

TAB.3 13 Post Tensioning Terminology (PTT)

GROUND ANCHORS. system complying with EN1537

GROUND ANCHORS. system complying with EN1537

I-345 Feasibility Study Public Meeting

3 rd Annual Bridge Seminar Day. New Bridges Over Kentucky Lake. Design of a 550 Basket-handle Network Tied Arch

INSPECTION AND LOAD RATING OF P-T SEGMENTAL BRIDGES. Elias Ajami, PE Illinois Tollway Brett Sauter, PE, SE Ciorba Group

Clinton Street Bridge over the Maumee River. ODOT Project DEF December 2, 2014 Stakeholder s Meeting

12/21/2018 WHAT S NEW SINCE What's New Since SPEC BOOK 2018 SPEC BOOK 2018 SPEC BOOK WHAT S NEW SINCE 2014

SIBLEY POND DESIGN-BUILD BRIDGE REPLACEMENT ROUTE 2 CANAAN/PITTSFIELD, MAINE

REQUESTS FOR ACTION (RFA)

Analysis of the Response Under Live Loads of Two New Cable Stayed Bridges Built in Mexico

Basarab Cable Stayed Bridge in Bucharest

Cast in place concrete parapet and Ministry standard sidewalk railing.

New Pumarejo Bridge over the river Magdalena in Barranquilla. Colombia.

Transcription:

Stay-Cable Replacement Design Mississippi River Bridge Luling, Louisiana Christopher Ligozio CTLGroup Copyright Post-Tensioning Institute all rights reserved. Page 1 of 35

Luling Bridge Copyright Post-Tensioning Institute all rights reserved. Page 2 of 35

Existing Cable System Parallel Wires Socket Filler (optional) Strand or Wire Hi-Am Anchors HDPE Sheathing Button Head Strand or Wire Epoxy-Steel Ball Compound Sheathing Sleeve Grout Filled UV Protection UV Protection Tape PE Pipe Wire Grout Copyright Post-Tensioning Institute all rights reserved. Page 3 of 35

Project Background Cracking/splitting of cable cover pipes Rusting and water leakage in anchorage zones Signs of compromise in cables safety In 2002, LADOTD retained CTLGroup to evalute the condition of the stay cables Copyright Post-Tensioning Institute all rights reserved. Page 4 of 35

Anchorage Inspection Copyright Post-Tensioning Institute all rights reserved. Page 5 of 35

Cable Free Length Inspection Copyright Post-Tensioning Institute all rights reserved. Page 6 of 35

Cable Damage Longitudinal Split in PE PE Damage Copyright Post-Tensioning Institute all rights reserved. Page 7 of 35

Critical Damages PE Damage / Exposed Grout Exposed / Corroded MTE Copyright Post-Tensioning Institute all rights reserved. Page 8 of 35

Inspection Summary 40 out of 72 cables were rated critical Remaining cables had less severe damages Increasing rate of deterioration is evident Timely corrective action was needed Cable replacement selected over repair options based on Life-cycle-cost analysis Copyright Post-Tensioning Institute all rights reserved. Page 9 of 35

Project Scope Assess Current Condition Replacement Cable Design Construction Sequence Design and Structural Analysis Peripheral Design MOT Design Preparation of Construction Documents Cost Estimate Copyright Post-Tensioning Institute all rights reserved. Page 10 of 35

Cable Replacement Design Team Client: LADOTD Prime Consultant: CTLGroup Project Manager: Bridge Engineering Solutions Cable Replacement Design: International Bridge Technologies, Inc. Superstructure Repair Design: TranSystems MOT, Survey & Plans: ABMB Engineers, Inc. Copyright Post-Tensioning Institute all rights reserved. Page 11 of 35

Cable Replacement Objectives Develop a cost effective cable replacement design Minimal engineering by contractors Minimize impact to traffic and MOT requirements Maintain structure capacity for live load, wind force, and construction load effects Monostrand cable system Best available corrosion protection systems Provide for future strand by strand replacement Copyright Post-Tensioning Institute all rights reserved. Page 12 of 35

Cable Replacement Constraints Large spacing of grouped stays Unknown condition of existing stay cables Limited work area, due to MOT constraints Size of replacement cables relative to existing Limited space in anchorage zones. Potential for higher wind loads and wind induced vibration in new cables Copyright Post-Tensioning Institute all rights reserved. Page 13 of 35

Stay Cable Replacement Approach Replace in pairs, Symmetric to tower Use of Temporary Stay Cables Evaluation of anchorage zones to accommodate replacement cables from multiple suppliers Proposed use of Highline to minimize construction space requirements Addition of dampers and cable cross ties for vibration mitigation Copyright Post-Tensioning Institute all rights reserved. Page 14 of 35

Maintenance of Traffic Two traffic lanes maintained during peak traffic times Work Area: 12.25 ft width Copyright Post-Tensioning Institute all rights reserved. Page 15 of 35

Maintenance of Traffic Single lane provided during non-peak traffic Work Area: 12.25 ft width behind barrier Additional 9 ft width adjacent to barrier Copyright Post-Tensioning Institute all rights reserved. Page 16 of 35

Replacement Cable System Parallel strand system Ungrouted Greased and Sheathed Strand PE Sheathing Pipes Equivalent Stiffness Copyright Post-Tensioning Institute all rights reserved. Page 17 of 35

Anchorage Zone Modifications Result of increased Cable Anchorage Sizes Designed to accommodate cables from several suppliers C L Cable LEGEND CL Cable Group Existing Bearing Plate, 13" Ø Hole Existing Cross Beam New Bearing Plate and Chair sized for new Anchorage Ring Nut Existing Anchorage Plate Cap New Anchorage Chair New Cable Copyright Post-Tensioning Institute all rights reserved. Page 18 of 35

Temporary Cables Prevent stress increase in existing cables Allow normal use of the bridge during cable replacement Design provided Copyright Post-Tensioning Institute all rights reserved. Page 19 of 35

Temporary Cables - Saddle Top of Pylon Light weight Geometry Fits all Cable Groups Limited tower strengthening Copyright Post-Tensioning Institute all rights reserved. Page 20 of 35

Temporary Cables - Waler Lower Cross Beam Set from Deck Limit stresses in Cross beam ends Copyright Post-Tensioning Institute all rights reserved. Page 21 of 35

Temporary Support System Provide means of supporting stay cables during removal and installation operations Design developed assuming Highline or cable way to Limits Work zone requirements Schematic Design of Highline Provided Final Design by Contractor Copyright Post-Tensioning Institute all rights reserved. Page 22 of 35

Schematic Highline Design Supported by Saddle at Tower Lower Anchorage tied to Superstructure Copyright Post-Tensioning Institute all rights reserved. Page 23 of 35

Cable Cross Ties Mitigate potential wake galloping Ties between vertical cables Detailed to preserve strand replaceability Copyright Post-Tensioning Institute all rights reserved. Page 24 of 35

Stay Cable Replacement Procedure Copyright Post-Tensioning Institute all rights reserved. Page 25 of 35

Stay Cable Replacement Procedure Copyright Post-Tensioning Institute all rights reserved. Page 26 of 35

Stay Cable Replacement Procedure Copyright Post-Tensioning Institute all rights reserved. Page 27 of 35

Stay Cable Replacement Procedure Copyright Post-Tensioning Institute all rights reserved. Page 28 of 35

Stay Cable Replacement Procedure Copyright Post-Tensioning Institute all rights reserved. Page 29 of 35

Stay Cable Replacement Procedure Copyright Post-Tensioning Institute all rights reserved. Page 30 of 35

Stay Cable Replacement Procedure Copyright Post-Tensioning Institute all rights reserved. Page 31 of 35

Construction Summary LaDOTD Project: 450-37-0022 Engineers Estimate: $34.9 mil Bid Opening: 2/25/2009 Low Bid: $30.5 mil (Kiewitt) Top 3 Bidders: $30.5 to $36.7 mil Copyright Post-Tensioning Institute all rights reserved. Page 32 of 35

Questions Questions? Copyright Post-Tensioning Institute all rights reserved. Page 33 of 35

Copyright Post-Tensioning Institute all rights reserved. Page 34 of 35

Cable Inspection Vehicle Copyright Post-Tensioning Institute all rights reserved. Page 35 of 35