Remediation of the Former Gasworks, High Wycombe, UK

Similar documents
Greenwich Mohawk Brownfield

From Wasteland to Green Parkland The West Melbourne Gasworks

Resource efficient remediation

SOIL AND GROUNDWATER REMEDIATION IN IRAQ

On-Site Remediation Approach for a Former Petrochemical Plant

In Situ, Low Temperature Thermal Remediation of LNAPL with Pesticides and Other Recalcitrant Compounds

ENVIRONMENTAL CONSULTANCY

Brownfield Regeneration. Cork Docklands Challenges

IXPER 70C Calcium Peroxide CASE STUDY

SOIL REMEDIATION OF A FORMER POWER PLANT SITE IN TULITA, NORTHWEST TERRITORIES

Executive Summary. ES.1 Objectives and Scope

South London Energy from Waste, Beddington Lane Initial Contaminated Land Assessment, July 2011

VertaseFLI. The UK experience and its applicability to the Irish market. Presented by Dr Chris Piddington

Clyde Street Remediation Project The Project Location

EXTRACT. MONITOR. CONTROL.

Final Report - Annex Report on the validation of the technique using a multi criteria analysis VOPAK-EXPERO3 - LIFE09/ENV/B/000407

Self-Sustaining Treatment for Active Remediation (STAR): Overview and Applications of the Technology

Remediation Plan. for. Creek County Landfill Site. E/2 SE NW 28-18N-12E Creek County, OK

Guy Lavoie, C.E.T. Project Director

Presenters' Contact Information

THERMAL REMEDIATION OF A CLOSED GASOLINE SERVICE STATION PRESENTATION AND DISCUSSION LED BY: GLEN VALLANCE PROJECT MANAGER, CGRS

Financial Sustainability Can Ports Be Green in a Recession? John D. Pauling, P.E., BCEE

Tighes Hill Remediation Project Update

Lessons Learned During In Situ Chemical Oxidation - Failure & Success?

Variation of NEPM Schedule B1

Creamer Environmental. Containment, Caps & Liners. 12 Old Bridge Road C ed ar Grov e, N e w Jer s e y

SUSTAINABLE REMEDIATION & BROWNFIELD RE-DEVELOPMENT Former industrial site in St. Laurent, Montreal, Qc

In Situ Treatment of Contaminated Soil and Groundwater: Lessons Learned from the Field

Surfactant Enhanced Remediation Of Petroleum and Chlorinated Contaminated Sites. Bud Ivey Ivey International

Performance of the Groundwater Containment System at the Former Canada Creosote Site. Tom Jacklin, M.Eng., P.Eng.

Assessment of Impacts from Groundwater Control Projects

Monitored natural attenuation (MNA) as a long-term management technique for contaminated sites

Embedding Sustainability in Contaminated Site Management

ETHICALCHEM BACKGROUND

S-ISCO REMEDIATION OF COAL TAR

This chapter assesses the likely impact of the proposed power plant in relation to ground conditions and potential contamination.

APRIL 2011 The Avenue

Management & Remediation of Sites in the Petroleum Industry:

Design Considerations for Large Diameter Auger Soil Mixing with Steam and Zero- Valent Iron for Remediation of Chlorinated VOCs

Groundwater and Fluid Filled Cables

Scottish Contaminated Land Forum 8 th September 2011

ORIN. Remediation Technologies. ORIN Remediation Technologies. Chemical Treatments. By: Larry Kinsman

27 Land and groundwater contamination

INTRODUCTION. 1 Proposed Plan for the Former Lee Field Naval Air Station Landfill Area 2 Site

Greenwich Mohawk Brownfield

Rethink remediation. Soil and groundwater treatment

Asbestos: Strategies for the identification and remediation of asbestos-contaminated materials

The influence of large scale inhomogeneities on a construction dewatering system in chalk Dr Toby Roberts. CTRL Thames Tunnel

ISOTEC Case Study No. 67 ISCO TREATMENT PROGRAM: IMPACTED GROUNDWATER TREATMENT UTILIZING ACTIVATED SODIUM PERSULFATE

Case Study Using the Decision Analysis Process to Select a Remediation Strategy for an Upstream Oil and Gas Facility

SR (Sustained Release) ISCO Reagent CASE STUDY

IMPLEMENTATION AND SYSTEM OPERATION

SOIL VAPOUR BASED RISK ASSESSMENT. Overview and Analysis of Cost for Soil Vapour Based Assessment vs. Direct Remediation

Surfactant Enhanced Remediation Technologies and Case Studies. Dan Socci EthicalChem. SMART Remediation Ottawa, ON February 4, 2016

Proposed Plan Closed Sanitary Landfill

Remediating Complex Sites. East land Quality Forum. By Steve Edgar. VertaseFLI BRISTOL SHEFFIELD HERTFORD MANCHESTER

Eden Remediation Services Kenneth Summerour, P.G.

Permeable Reactive Barriers for Petroleum Hydrocarbons

Assessment and Restoration of the BP Llandarcy Refinery Landfill Martin Chapple, URS Corporation Ltd., Bristol, UK

NYSDEC Public Meeting September 12, 2013 Brooklyn Navy Yard, Building 92

Quanta Resources Superfund Site: Yesterday & Today

Characterization and Remediation of Diesel in a Fractured Rock Aquifer with a Nutrient-Flushing System

In Situ Chemical Oxidation (ISCO) Delivery Mechanisms & Injection Strategies

SCHEDULE 3.1 DETAILED CONSTRUCTION PLAN Part B: Narrative Area B

Stabilisation/Solidification of Manufactured Gas Plant Wastes: Selected Case Histories Part 3

UK National Nuclear Laboratory Environmental Remediation

CRT CRT. Carus Remediation Technologies. Simplified Science. Carus Remediation Technologies. Carus Remediation Technologies

Manufactured Gas Plant Site Management - Program 50

Advancing the Science of In Situ Groundwater Remediation Petroleum Hydrocarbon Remediation Technologies

Thermal Remediation Services, Inc.

Field-proven remediation technologies for the most challenging sites.

2010 Symposium ~ IMWA 2010 ~ Mid-Conference Excursion 5 Belinda Campbell, David Forrester. Sydney Tar Ponds and Collieries

Sustainable remediation in New Zealand

Methodology for Identifying the Area of Concern Around a Property Potentially Impacted by Vapor Migration from Nearby Contaminated Sources

Bench- and Pilot-Scale Treatability Testing of ISCO and Surfactant Enhanced Biodegradation of Long Chain Petroleum Hydrocarbons

DECISION DOCUMENT. Kent Avenue Station Site Voluntary Cleanup Program Brooklyn, Kings County Site No. V00732 October 2013

Sustainable and Innovative Remediation of the Remote and Historic Hay Camp Abattoir and Warden Station Wood Buffalo National Park

Nevada Environmental Response Trust Site Fact Sheet

Quanta Resources Site

MISSOURI DEPARTMENT OF NATURAL RESOURCES. Monitored Natural Attenuation of Groundwater Contamination at Voluntary Cleanup Program Sites

COMMUNITY BRIEFING PAPER BOTANY GROUNDWATER PROJECT

Co-operation Canada Netherlands. Groundwater and soil management

IN-SITU CHEMICAL OXIDATION REMEDIATION PROGRAM INTERIM REPORT PHASE 2B

Site Profiles - View. General Information. Contaminants: Site Hydrology:

CAPABILITY STATEMENT

IPEC Conference San Antonio, TX November 13, 2013 Glenn Nicholas Iosue

BUILDING A FRESH FUTURE FOR CONTAMINATED SITES

Site Background December 2005

Thorpe Marsh CCGT Power Station ENVIRONMENTAL STATEMENT SUPPLEMENTARY INFORMATION

Residual LNAPL Remediation Using BOS 200 at Budget Rental Car Site in Louisville, Kentucky USA

PermeOx. Plus. Enhanced Aerobic Biodegradation

BREAKTHROUGH TREATMENT FOR PFAS. CASE STUDY: First Demonstrated In Situ Treatment Solution For PFOA/PFOS At Former Industrial Site

D2 Project Environmental Remediation Briefing August 21, 2018

Solidification/Stabilization

DESIGNING DRAINS AND SEWERS FOR BROWNFIELD SITES. Guidance Notes

Groundwater Risk Assessment

Prepared by Ken Summerour, P.G.

Numerical Groundwater Model for the Kaweah Delta Water Conservation District

Cottonmount Landfill Stable Non Reactive (SNR) Asbestos Cell. Volume 2 NON TECHNICAL SUMMARY. December 2012 SLR Ref:

Manufactured Gas Plant Site Remediation - Program 50

Transcription:

Remediation of the Former Gasworks, High Wycombe, UK Apr-4-06 MGP Symposium, Reading UK, April 2006 Presented By Stuart Arch Apr-4-06 4/4/06 WPREpresentation1.ppt 1 Site Setting Contents of Presentation Remediation Strategy Development Stakeholder Involvement Site Characterisation and Risk Assessment Remediation Feasibility Remediation Design and Implementation 2 4/4/06 WPREpresentation1.ppt 1

1969 Aerial Photograph Current Site Boundary Pann Mill PWS River Wye 3 4/4/06 Historical Site Layout Plan 4 4/4/06 WPREpresentation1.ppt 2

Gasworks Journal 5 4/4/06 2001 Aerial Photograph Current Site Boundary GH6 GH5 6 4/4/06 WPREpresentation1.ppt 3

Strategy Development First Investigation 1997 2002 to 2003 2003 to 2004 We are now here 7 4/4/06 2006/07 Remediation Goals Mitigate the risks posed to the River Wye and Public Water Supply wells. Mitigate potential environmental liability associated with potentially mobile NAPL in the subsurface. Ensure that following remediation the site is suitable for its ongoing use. Achieve the goals above without unacceptable short-term impact. 8 4/4/06 WPREpresentation1.ppt 4

Remediation Criteria Considered: Short term risk to the environment. Destabilising a currently manageable situation Remediation Criteria have been developed based on: Site Specific Conceptual Models of Risk Groundwater Modelling Human Health Risk Assessment (CLEA) Assessment of Potentially Mobile Hydrocarbons 9 4/4/06 Stakeholder Involvement National Grid Landowner/problem holder Thames Water Utilities Ltd Provides public water supply Environment Agency Groundwater and surface water protection Remediation process licensing Other environmental protection obligations Wycombe District Council Contaminated land risks to human health Planning Permission for remediation Noise, dust, traffic and other public protection aspects 10 4/4/06 WPREpresentation1.ppt 5

Stakeholder Involvement First discussions with external stakeholders following initial investigation. Shared site data. Agreed the Remediation Strategy Development plan. Regular liaison following completion of each phase of the strategy development. Agreed specific remediation goals and detailed design. Open invitation for stakeholders to visit site. Regular progress reports. 11 4/4/06 Site Investigation 12 4/4/06 WPREpresentation1.ppt 6

Conceptual Model 13 4/4/06 NOT TO SCALE Groundwater Risk Assessment 14 4/4/06 MODFLOW and MT3DMS Deterministic Simulations Calibrated Well, however, Concerns about being over or under conservative Probabilistic Simulations Additional Information about likelihood of exceedance Additional confidence for Stakeholders Contaminants of Concern Naphthalene Benzene Xylenes Phenols Ammonium WPREpresentation1.ppt 7

Groundwater Risk Assessment 15 4/4/06 Groundwater Risk Assessment 16 4/4/06 WPREpresentation1.ppt 8

Human Health Risk Assessment UK Contaminated Land Exposure Assessment (CLEA) methodology Current and potential future uses were considered Chemicals of Concern were identified and associated remediation criteria calculated Remediation / Development measures were proposed 17 4/4/06 Remediation Criteria 18 4/4/06 WPREpresentation1.ppt 9

Contaminant Source Areas 19 4/4/06 Remediation Feasibility Study We considered Remediation Approaches to: Manage the Receptors e.g., restrict future site use or treat abstracted groundwater) Break pathway (e.g., Permeable Reactive Barriers) Remove/Treat the Sources Three Treatment Train Options Proposed Similar Approaches i.e., source removal and treatment Amount of residual contamination likely was inversely proportional to risk of creating impact during implementation High-Medium-Low Costs 20 4/4/06 WPREpresentation1.ppt 10

Cost Benefit Analysis This was not just a financial (costs) assessment Monetised Benefits included: Value of aquifer improvement Reduction in Haulage impact to environment Improvement in surrounding property value Assessment considered who benefited Remediation Option 1 gave benefit to society and landowner Partial excavation and ex-situ treatment of sources, in-situ treatment of residual, minimise disposal Remediation Option 3 mainly benefited society Removal of buried tar tanks and contaminants above water table only and long term monitoring/attenuation 21 4/4/06 Cost Benefit Analysis 22 4/4/06 WPREpresentation1.ppt 11

Cost Benefit Analysis 23 4/4/06 Implementation of Remediation A Two Stage Remediation Strategy Phase I (2005) - Enabling and Ex-Situ Remediation Diversion of Services Demolition of Buildings and Retaining Walls Installation of cofferdam containment and pumping system Soil Washing of Gravels Bioremediation of flinty clay and chalk Water Treatment Environmental Monitoring and Validation 24 4/4/06 WPREpresentation1.ppt 12

Cofferdams to Enable Excavation 25 4/4/06 Soil Washing in Action 26 4/4/06 WPREpresentation1.ppt 13

Soil Washing Performance 27 4/4/06 Bioremediation Underway 28 4/4/06 WPREpresentation1.ppt 14

Bioremediation Performance High Wycombe Gasworks - Bioremediation Cells 12000 10000 Total Petroleum Hydrocarbons C6-C40 (mg/kg) 8000 6000 4000 2000 0 A1 A2 A3 A4 A5 B1 B2 B3 B4 B5 Biopile Cells Oct-05 Jan-06 29 4/4/06 Implementation of Remediation 30 4/4/06 WPREpresentation1.ppt 15

Implementation of Remediation Currently reviewing results of Phase 1. Groundwater quality changes. Pilot studies using sodium permanganate and Fenton s Reagent have been undertaken. Updating groundwater modelling based on findings during Phase 1. Phase 2 - Proposed In-situ Remediation Extraction of remaining NAPL in the southern half of site using HVE or similar Injection of Permanganate (south end of site) Injection of Fenton s Reagent into gravels (north end of site) Ongoing groundwater monitoring potentially MNA 31 4/4/06 Acknowledgements Client: National Grid Property Holdings Ltd. Engineer: WorleyParsons Komex Ltd. Planning Supervisor: RSK ENSR Shear Ltd. Cost Consultant: Davis Langdon LLP Principal Contractor: Morrison Construction Services Ltd. Specialist Remediation Subcontractors: DEC NV Soil Washing Biogenie Ltd Bioremediation QDS Ltd. - Groundwater treatment 32 4/4/06 WPREpresentation1.ppt 16