ECONOMICS COURSE. Preconstruction Operations

Similar documents
APPENDIX D CONSTRUCTION PHASE CRITERIA

ADMINISTRATIVE DIRECTIVE #CS-04

REQUEST FOR PROPOSALS. Construction Manager CM Services Pre-Construction and Construction Services

BID PROPOSAL CITY OF HOMESTEAD, FLORIDA WWTP INFLUENT PUMP STATION

G , Request for Proposal Land Survey

REQUEST FOR PROPOSAL. Construction Management Services Not at Risk

REQUEST FOR PROPOSALS OREGON CITY ANNEX FIBER OPTIC ENGINEERING & INSTALLATION. Date Due: Friday, September 8, Time Due: 4:00 p.m.

Subject: Statement of Qualifications for Public Safety Building Design

DRAFT Proposal to Provide Public Works Observation Services for the City of Calabasas Overlay Project

The construction phase, of course, is the execution of the work as required by the contract documents when the building is finally built.

Document B252TM 2007

[JURISDICTION] S AMENDMENTS TO AIA DOCUMENT B , STANDARD FORM OF ARCHITECT S SERVICES: DESIGN AND CONTRACT ADMINISTRATION

A , Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum

A.1 WATER SYSTEM PLAN SUBMITTAL PROCEDURES AND GENERAL REQUIREMENTS

The Home Depot U.S.A., Inc. Instructions to Bidders

Commencement of Works vs commencement of Works Program (FIDIC Rainbow Conditions of Contracts)

Addendum #1. Beaver Dam Creek Trail & Pedestrian Bridge Phase 1 Town of Damascus, Virginia VDOT # EN , PE101, C501 UPC #51977

SAN ANTONIO WATER SYSTEM PRE-CONSTRUCTION MINUTES

VAE VIEW ELEMENTARY WINDOW REPLACEMENT West 1600 North Layton, UT Specifications. Construction Documents

REQUEST FOR QUALIFICATIONS CONSTRUCTION MANAGEMENT at RISK SERVICES FOR THE BECKER COUNTY JAIL DETROIT LAKES, MN

Chapter 2 Parties to the Contract

STATEMENTS OF QUALIFICATIONS ARE DUE NO LATER THAN 5:00 P.M. FRIDAY, JUNE 23, 2017

REQUEST FOR PROPOSAL ARCHITECTURAL & ENGINEERING SERVICES OTTAWA COUNTY ROAD COMMISSION COOPERSVILLE AREA MAINTENANCE COMPLEX

PROJECT MANUAL for Phantom Canyon Tunnel Repair Project. Location On Fremont County Road miles North of Intersection US Highway 50 with FCR 67

ANNEXURE A SCOPE OF WORK FOR PROFESSIONAL SERVICES: RESTORATION OF NON PAREILLE BUILDINGS. Principal Agent and Professional Architectural Services

CITY OF LA MARQUE CHAPTER 7. Construction, Inspection, Approval and Acceptance Procedures for Public Infrastructure

ATTACHMENT D SCOPE OF SERVICES

A62 UT PRE-CONSTRUCTION MEETING AGENDA

WEST YELLOWSTONE SIEGEL LEARNING CENTER REQUEST FOR QUALIFICATIONS / PROPOSALS FOR CONSTRUCTION MANAGER AT RISK (CM-AR) SERVICES

GENERAL REQUIREMENTS

Document B Standard Form of Agreement Between Owner and Architect, Construction Manager as Adviser Edition

SECTION QUALITY CONTROL

REQUEST FOR QUALIFICATIONS

MARYLAND STADIUM AUTHORITY

Chapter 1, Introduction

A62 PRE-CONSTRUCTION MEETING AGENDA

SAN FRANCISCO PUBLIC UTILITIES COMMISSION INFRASTRUCTURE CONSTRUCTION MANAGEMENT PROCEDURES

CONSTRUCTION MANAGEMENT. By GREEN PLANET SERVICES Lesley Padayachee Cell:

Document B101 TM. Standard Form of Agreement Between Owner and Architect

Highway / Utility Guide

REQUEST FOR QUALIFICATIONS STATEMENT (RFQ) CONSTRUCTION MANAGEMENT AT RISK SERVICES FOR THE GREENWOOD HIGH SCHOOL GYMNASIUM GREENWOOD, SOUTH CAROLINA

Attachment 1 Architectural Services

RFQ. Request for Qualifications Phase One. Renovation of City Owned Homes CITY OF BEREA, OHIO. Mayor Cyril Kleem

DUKE UNIVERSITY CONSTRUCTION STANDARDS

1/24/2014. Schedules Schedule of Values Submittals Payment Applications Requests for Information Change Order Requests Change Orders

ADDENDUM #1 Construction Support Services for the Water Treatment Plant Project PW

Architectural Design and Build Process. A Client Guide

REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES NOT AT RISK FOR THE. St. Charles County Ambulance District

MASTERSPEC TECHNICAL SPECIFICATIONS DIVISION 01 GENERAL REQUIREMENTS

Pre-Construction Conference Discussion Guide

Construction Administration Process

SECTION PRODUCT REQUIREMENTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS

How do FIDIC contracts work

Public Works Audit Preliminary Findings: Temporary Inmate Housing & City Hall Elevator Overhaul

SECTION CONTRACTOR QUALITY CONTROL

Learn best practices with regard to contract administration and management; Identify the various phases of contract administration; Gain practical

REQUEST FOR PROPOSALS FOR PROFESSIONAL ENGINEERING SERVICES

AMERICAN INSTITUTE OF ARCHITECTS (AIA) DOCUMENT SUMMARY

Professional Practice 544

MARYLAND STADIUM AUTHORITY

Chapter 4 State Requirements for Educational Facilities Section 4.1

Section I - Introduction

VILLAGE OF VERNON HILLS REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGER AT RISK SERVICES. Part I: Proposal Information

CONTROL OF WORK 1.02 AUTHORITY AND DUTIES OF THE ENGINEER S AUTHORIZED REPRESENTATIVE

REQUEST FOR PROPOSALS PROFESSIONAL SERVICES FOR THE ROOF AND HVAC REPLACEMENT PROJECT PW1320

Baysinger Design Group, Inc West DeYoung Street, Suite 100B Marion, Illinois Ph Fax

Kirk W Buffington, CPFIM, CPPO, C.P.M.,

Chapter 6, Construction

1997 Part 2. Document B141. Standard Form of Architect's Services: Design and Contract Administration TABLE OF ARTICLES

PUBLIC CONTRACT CODE SECTION

MANDATORY PRE-BID MEETING FLORIDA KEYS AQUEDUCT AUTHORITY

Request for Proposal Design Build Services Kiel High School Athletic Field Improvements

TRIAD ENGINEERING CONSULTANTS, INC.

MONTGOMERY STREET. Construction Manager at Risk (CMAR) Services

UNIVERSITY OF KENTUCKY Memorial Hall/College of Law Expansion and Renovation UK Project No

COMMERCIAL MANAGEMENT. Construction Law Competencies

C. The Joint Utility Committee regularly meets on the 2 nd Wednesday of each month at 9 A.M. unless otherwise rescheduled.

TOWN OF WINTER PARK REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGER / GENERAL CONTRACTOR

San Antonio Water System Standard Specifications for Construction

COUNTY OF SAN JOAQUIN

POST-CONSTRUCTION REVIEW

ATTACHMENT W.2 GENERAL SPECIFICATIONS

Florida Cleanroom Systems

SECTION 1.0 PROJECT REVIEW AND ACCEPTANCE PROCESS

REQUEST FOR QUALIFICATIONS

TABLE OF CONTENTS I. PARTIES TO THE CONSTRUCTION PROJECT...1 A. OWNER...1 B. ARCHITECT...1 C. INSPECTING ARCHITECT...1 D. CONTRACTOR...

REQUEST FOR QUALIFICATIONS DELTONA MIDDLE 250 ENTERPRISE ROAD DELTONA, FLORIDA REPLACEMENT SCHOOL PROJECT NO

YOUR TRANSPORTATION CO.

BIDDING INFORMATION FOR HOLLY HILL ADMINISTRATION COMPLEX RENOVATION AND ADDITION. for the COUNTY OF ORANGEBURG. Project Number: FY

PUBLIC WORKS COMMISSION 2018 STREET EXCAVATION PERMIT PROCEDURE

REQUEST FOR PROPOSAL: Construction Management at Risk Services Hamilton International Air Cargo Logistics Facility. RFP Components

STATEMENT of WORK Survey Storage Shed 10X10X8 Beaver County, Rochester Stockpile# Project# Building#

Guidance for Rating Each Performance Category on Contractor Performance Evaluation

As a state agency, the College administration is required to develop procedures for Construction Manager selection.

STATEMENT OF PRINCIPLE

NAPA SANITATION DISTRICT

Fair Oaks Water District

CONSTRUCTION PROCEDURES MANUAL PROJECT

EXHIBIT 6 Preconstruction Work

130A Alternative process for wastewater system approvals. (a) Engineered Option Permit Authorized. A professional engineer licensed under

Transcription:

I.T.U. Faculty of Architecture Division of Construction Management Construction Management and ECONOMICS COURSE CONSTRUCTION ADMINISTRATION Preconstruction Operations Dr. Alaattin Kanoðlu (Assoc.Prof.) I.T.U. Faculty of Architecture Spring, 2002

Outline The preconstruction conference Preconstruction conference agenda Starting a project CONSTRUCTION MANAGEMENT & ECONOMICS 2

The preconstruction conference The preconstruction conference allows the key personnel of both sides to be introduced, and the responsibilities and authorities of each can be defined at that time. CONSTRUCTION MANAGEMENT & ECONOMICS 3

The preconstruction conference It also allows the parties to get a clear understanding of the procedures involved in contractor submittals, sampling and testing, construction surveys, inspections by outside agencies, payment requests, procedures for claims and disputes, unforeseen job conditions, change order requests, and similar items. CONSTRUCTION MANAGEMENT & ECONOMICS 4

The preconstruction conference During the course of preconstruction meeting, mention can be made of the contractor s responsibility to provide insurance documents as specified and all required bonds as well as to obtain (and pay for) all permits from building departments, street departments, police departments (for traffic control) environmental protection agencies, or other agencies having jurisdiction. The contractor should be reminded at this meeting that all such documentation is required to be submitted before work can begin. CONSTRUCTION MANAGEMENT & ECONOMICS 5

The preconstruction conference Another item that should be brought up at this meeting is the schedule of job site and management meetings, the location and frequency of such meetings, and who should be in attendance. CONSTRUCTION MANAGEMENT & ECONOMICS 6

The preconstruction conference Before closing the conference, the subject of the construction schedule should be raised. It may be necessary to remind the contractor that the initial project schedule submitted at the beginning of the project will require periodic adjustment, and that all such adjustments must meet with the approval of the design firm and the owner. CONSTRUCTION MANAGEMENT & ECONOMICS 7

Starting a project The beginning of a construction project normally starts with the award of the construction contract. This may be accomplished in the minutes of a city council or county board of supervisors action, by letter, or by issuance of a preprinted Notice of Award form. CONSTRUCTION MANAGEMENT & ECONOMICS 8

Starting a project The giving of a Notice of Award is similar in its legal effect to the issuance of a letter of intent, as it obligates the owner to sign the construction contract if the contractor does what is required of it within the time specified. CONSTRUCTION MANAGEMENT & ECONOMICS 9

Starting a project The Notice of Award does not authorize the start of construction, because no work is supposed to start until after the owner/contractor agreement has ben signed by both parties. The contract time will begin running on the thirtieth day after the owner has signed and delivered a fully executed agreement, but it may start sooner if a formal Notice to Proceed is issued. CONSTRUCTION MANAGEMENT & ECONOMICS 10

Starting a project Under the AIA General Conditions, if no Notice to Proceed is issued, the contract time will begin as of the date of signing of the agreement. Under FIDIC Conditions of Contract, the work must begin as soon as is reasonably possible after receipt of a notice (to proceed). Many public agencies allow a 10-day period after the issuance of a formal Notice to Proceed for the contractor to begin work at the site. CONSTRUCTION MANAGEMENT & ECONOMICS 11

Starting a project The issuance of a Notice to Proceed formalizes the date that the project is to begin and sets the stage for computation of the total project construction time. This will greatly facilitate the establishment of an accurate count of construction time for the computation of Liquidated Damages (recovered damages). CONSTRUCTION MANAGEMENT & ECONOMICS 12

Starting a project A construction contract can but should not designate a specific commencement date because of the uncertainty of when the work can begin. Before the contractor can begin it must be given Access to the Site. CONSTRUCTION MANAGEMENT & ECONOMICS 13

Starting a project This can require that easements be obtained, public approvals be given, and funds be obtained. As a result, the commitment to begin work is usually expressed in terms of a number of days after Access to the Site ite. The owner also uses this approach to avoid responsibility for delay in its ability to grant access to the site. CONSTRUCTION MANAGEMENT & ECONOMICS 14