Manajemen Persediaan. MRP Lot For Lot. Modul ke: Fakultas FEB. Program Studi Manajemen

Similar documents
Net Requirements Plan. The logic of net requirements. MRP Planning Sheet. Gross Requirements Schedule

Material Requirements Planning (MRP) and ERP 14. Outline

Materials Requirements Planning

History IE 376 PRODUCTION INFORMATION SYSTEMS. Course Notes Lecture #2.A Material Requirements Planning

7/14/2010. Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall.

Material Resources Planning

Materials and Resource Requirements Planning

Planning. Dr. Richard Jerz rjerz.com

IV/IV B.Tech (Mech. Engg.) 7th sem, Regular Exam, Nov Sub: OPERATIONS MANAGEMENT [14ME705/A] Scheme of valuation cum Solution set

Planning. Planning Horizon. Stages of Planning. Dr. Richard Jerz

Planning. Planning Horizon. Stages of Planning. Dr. Richard Jerz

Resources Planning. Introduction

Notes for Production and Operations Management- I

Material Requirements Planning (MRP), chap 15

Chapter 18. Materials Requirements Planning


A typical manufacturing plant

LOT SIZING IN MRP. Week Gross requirements Scheduled receipts Projected available balance Net Requirements

Oman College of Management and Technology

MATERIAL AND CAPACITY REQUIREMENTS PLANNING (MRP AND CRP) Part -1. Dr. Mahmoud Abbas Mahmoud Al-Naimi Assistant Professor

Enterprise Resource Planning

Chapter 6 RESOURCE PLANNING SYSTEMS. Prepared by Mark A. Jacobs, PhD

Hybrid Manufacturing Methods

Priority for MRP. Run MRP based on actual orders, forecasts or static requirements. Run MRP simulations until you re satisfied with the plans

PLANNING FOR PRODUCTION

Introduction. Introduction. Introduction LEARNING OBJECTIVES LEARNING OBJECTIVES

Introduction Manufacturing Data Management

Al-Qadisiya Journal For Engineering Sciences Vol. 4 No. 3 Year 2011

UNIT II PRODUCTION PLANNING AND CONTROL AND COMPUTERISED PROCESS PLANNING

Factory Modeling. The Priority Enterprise Management System. Contents

LFL. KEYWORDS: Lot sizing techniques, Material requirements planning.

AUTOSIMPLY. Manufacturing Order. Features. About AutoSimply

One Software to manage your entire bakery business.

Note 8: Materials Requirements Planning

Microsoft Business Solutions-Axapta Production enables you to flexibly manage your manufacturing processes for increased profitability.

Managing Items. Explanation on beas extended view of Item Master Data

Akuntansi Biaya. Modul ke: 09FEB. Direct Material Cost. Fakultas. Diah Iskandar SE., M.Si dan Nurul Hidayah,SE,Ak,MSi. Program Studi Akuntansi

MATERIAL REQUIREMENT PLANNING

Chapter 12. Enterprise Resource Planning

Operational Logistics Management (OLM612S)

WHITE PAPER. Control Manufacturing Costs with Odoo Open ERP

MANUFACTURING SYSTEMS MATERIAL REQUIREMENTS PLANNING

PRODUCTION SCHEDULING PART-A

Operation Management QUESTION BANK

AVANTUS TRAINING PTE LTD

9. What are the activities within the scope of production planning? 1. Aggregate production planning

Outline. Push-Pull Systems Global Company Profile: Toyota Motor Corporation Just-in-Time, the Toyota Production System, and Lean Operations

KEY ISSUES in Advanced Operations Management. Timo Seppälä

Subbu Ramakrishnan. Manufacturing Finance with SAP. ERP Financials. Bonn Boston

MULTIPLE CHOICE. Choose the one alternative that best completes the statement or answers the question.

02/10/2016. Functional Area Systems Production / Operation Systems. Examples: Functional Area Info Systems. Functional Area Information Systems

Breakdown. Learn the implications of the breakdown field in Item Master Data

Manufacturing Resource Planning

TU-E2020 ADVANCED OPERATIONS MANAGEMENT. Master Production Scheduling Material Requirements Planning

FAQ: Efficiency in the Supply Chain

IMPORTED RAW MATERIAL INVENTORY CONTROL SYSTEM AS AN EFFORT TO MINIMIZE INVENTORY COST (A CASE STUDY IN PT APPAREL ONE INDONESIA)

University of Puerto Rico Mayagüez Campus Industrial Engineering Department

MASTER PRODUCTION SCHEDULE (MPS)

Management Tool based on MRP and Lot-sizing A case study for comparing different cases

Dynamics AX 2012 Trade & Logistics

Chapter 6 Resource Planning Systems

Sage 200 Manufacturing Datasheet

Part IV Methods for Dependent Demand

Functional Area Systems Production / Operation Systems

STP351: Purchase Order Collaboration in SNC

What is ERP? Source: Wikipedia

Manufacturing Functionlity in Microsoft Dynamics GP. Gain complete control over your inventory, production and orders.

What can Visual Planner do for you Rick Worley TriMin Systems April 2016

Introduction to Production Planning

What is MRP (I, II, III) 1. MRP-I

Operation Process Charting: How It s Made Here. APICS Fraser Valley November 2016 Presented by: Richard Ranftl (BCIT)

Test-king.C_TSCM42_65.80 Questions

Chapter two. Product and Process design

Which of the following are subareas of the People Integration subcomponent of SAP NetWeaver?

Yuji Yamamoto PPU411. Today s topic. What is MPS and MRP Developing MPS How to make MRP Enterprise Resource Planning Kanban system

Product Costing: Analyze the Financial Entries in Make-to-Stock. Birgit Starmanns SAP Marketing

INVENTORY CONTROL SYSTEM ANALYSIS OF GOODS AT COMPANY X S MODERN TRADE

Time to Shipment MRP Guide DBA Software Inc.

CP-81 The best waze to get to destination MRP! Paul Whiteman Lexell Blue Susan Pucciano Lexell Blue

GBI - Introductory Course 6/11/2015

Resource Portal for Management Sciences Students, Teachers and Business Professionals. Visit

Principles of Production & Inventory Management PPIM

There are three options available for coping with variations in demand:

FEATURES IN TRIMIT FURNITURE 2017

MANUFACTURING RESOURCE PLANNING AND ENTERPRISE RESOURCE PLANNING SYSTEMS: AN OVERVIEW

PRODUCTION EXECUTION

Inventory Control. Inventory. Inventories in a manufacturing plant. Why inventory? Reasons for holding Raw Materials. Reasons for holding WIP

CRC Press Taylor &. Francis Croup Boca Raton London New York CRC Press is an imprint of the Taylor & Francis Group, an Informa business

THE USE OF SPREADSHEETS TO TEACH MASTER PRODUCTION SCHEDULE (MPS) AND MATERIALS REQUIREMENTS PLANNING (MRP)

APICS PRINCIPLES OF OPERATIONS MANAGEMENT TOPIC OUTLINE CONCEPTS AND APPLICATIONS

Foreword 7. 1 Production planning Planning approaches Planning strategies Definition of the example 17

Job Manager for Job Shops

PP 1: Display Stock/Requirements List

Accounting Information Systems, 12e (Romney/Steinbart) Chapter 14 The Production Cycle

Best practices in demand and inventory planning

SAP Material Master A Practical Guide. Matthew Johnson

Distribution and Trade in Microsoft Dynamics AX 2012

Manufacturing Information Systems. deden08m.com 1

Infor LN DEM Content Pack Content Description

The Priority Enterprise Management System

Transcription:

Modul ke: 10 Manajemen Persediaan MRP Lot For Lot Fakultas FEB Program Studi Manajemen

Learning Objectives Describe the conditions under which MRP is most appropriate. Describe the inputs, outputs, and nature of MRP processing. Explain how requirements in a master production schedule are translated into material requirements for lower-level items. Discuss the benefits and requirements of MRP.

Learning Objectives Explain how an MRP system is useful in capacity requirements planning. Outline the potential benefits and some of the difficulties users have encountered with MRP. Describe MRP II and its benefits. Describe ERP, what it provides, and its hidden costs.

MRP Material requirements planning (MRP): Computer-based information system that translates master schedule requirements for end items into time-phased requirements for subassemblies, components, and raw materials. End products MRP Time-phase based Subassemblies Components Raw materials

Independent and Dependent Demand Independent Demand A Dependent Demand B(4) C(2) D(2) E(1) D(3) F(2) Independent demand is uncertain. Dependent demand is certain.

Dependant Demand Dependent demand: Demand for items that are subassemblies or component parts to be used in production of finished goods. Once the independent demand is known, the dependent demand can be determined.

Amount on hand Amount on hand Demand Demand Demand Stable demand Lumpy demand Time Time Safety stock Time Time

Overview of MRP MRP Inputs MRP Processing MRP Outputs Master schedule Bill of materials MRP computer programs Primary reports Secondary reports Changes Order releases Planned-order schedules Exception reports Planning reports Performancecontrol reports Inventory records Inventory transaction

MPR Inputs Master Production Schedule Time-phased plan specifying timing and quantity of production for each end item. Material Requirement Planning Process

Master Schedule Master schedule: One of three primary inputs in MRP; states which end items are to be produced, when these are needed, and in what quantities. Cumulative lead time: The sum of the lead times that sequential phases of a process require, from ordering of parts or raw materials to completion of final assembly.

Planning Horizon Assembly Subassembly Procurement Fabrication 1 2 3 4 5 6 7 8 9 10 Time Period (weeks)

Bill-of-Materials Bill of materials (BOM): One of the three primary inputs of MRP; a listing of all of the raw materials, parts, subassemblies, and assemblies needed to produce one unit of a product. Product structure tree: Visual depiction of the requirements in a bill of materials, where all components are listed by levels. Low-level coding: Restructuring the bill of materials so that multiple occurrences of a component all coincide with the lowest level the component occurs

Level 0 Product Structure Tree Chair 1 Leg Assembly Seat Back Assembly 2 Legs (2) Cross bar Side Rails (2) Cross bar Back Supports (3) Level 0 X X 1 B (2) C B (2) C 2 D (3) E E (2) F (2) D (3) E E (2) F (2) 3 E (4) E (4) E E (2)

Inventory Records One of the three primary inputs in MRP Includes information on the status of each item by time period Gross requirements Scheduled receipts Amount on hand Lead times Lot sizes And more

Inventory Requirements Net requirements: Net Requirements = Gross Requirements Available Inventory Available Inventory: Available Inventory = Projected on hand Safety stock Inventory allocated to other items

Assembly Time Chart Procurement of raw material D Procurement of raw material F Fabrication of part E Procurement of part C Procurement of part H Subassembly A Subassembly B Final assembly and inspection Procurement of raw material I Fabrication of part G 1 2 3 4 5 6 7 8 9 10 11

Time-Phased Product Structure Start production of D Must have D and E completed here so production can begin on B Lead time 2 weeks 1 week G (1) D (2) 2 weeks 1 week 3 weeks 2 weeks D (2) E (2) 2 weeks to produce E (2) 1 week F (2) B (2) 1 week C (3) 1 2 3 4 5 6 7 8 Time in weeks A A B C D E F G 1 2 1 1 2 3 2 weeks weeks weeks weeks weeks weeks weeks

Gross Requirements Plan Week 1 2 3 4 5 6 7 8 Lead Time A. Required date 50 Order release date 50 1 week B. Required date 100 Order release date 100 2 weeks C. Required date 150 Order release date 150 1 week E. Required date 200 300 Order release date 200 300 2 week F. Required date 300 Order release date 300 3 weeks D. Required date 600 200 Order release date 600 200 1 week G. Required date 300 Order release date 300 2 week

MRP Structure Data Files BOM Lead times (Item master file) Master production schedule Output Reports MRP by period report MRP by date report Planned order report Inventory data Purchasing data Material requirement planning programs (computer and software) Purchase advice Exception reports Order early or late or not needed Figure 14.5 Order quantity too small or too large

Determining Gross Requirements Starts with a production schedule for the end item 50 units of Item A in week 8 Using the lead time for the item, determine the week in which the order should be released a 1 week lead time means the order for 50 units should be released in week 7 This step is often called lead time offset or time phasing

Determining Gross Requirements From the BOM, every Item A requires 2 Item Bs 100 Item Bs are required in week 7 to satisfy the order release for Item A The lead time for the Item B is 2 weeks release an order for 100 units of Item B in week 5 The timing and quantity for component requirements are determined by the order release of the parent(s)

Determining Gross Requirements The process continues through the entire BOM one level at a time often called explosion By processing the BOM by level, items with multiple parents are only processed once, saving time and resources and reducing confusion Low-level coding ensures that each item appears at only one level in the BOM

Net Requirements Plan

Net Requirements Plan

MRP Processing Gross requirements Schedule receipts Projected on hand Net requirements Planned-order receipts Planned-order releases

MPR Processing Gross requirements Total expected demand Scheduled receipts Open orders scheduled to arrive Projected on hand Expected inventory on hand at the beginning of each time period

MPR Processing Net requirements Actual amount needed in each time period Planned-order receipts Quantity expected to be received at the beginning of the period Offset by lead time Planned-order releases Planned amount to order in each time period

Lot-Sizing Techniques Lot-for-lot techniques order just what is required for production based on net requirements May not always be feasible If setup costs are high, costs may be high as well Economic order quantity (EOQ) EOQ expects a known constant demand and MRP systems often deal with unknown and variable demand

Lot-Sizing Techniques Part Period Balancing (PPB) looks at future orders to determine most economic lot size EPP = setup cost / holding cost Programming technique Assumes a finite time horizon Effective, but computationally burdensome

Lot-for-Lot Example Week 1 2 3 4 5 6 7 8 9 10 Gross requirements Scheduled receipts Projected on hand Net requirements Planned order receipts Planned order releases 35 30 40 0 10 40 30 0 30 55 35 35 0 0 0 0 0 0 0 0 0 0 30 40 0 10 40 30 0 30 55 30 40 10 40 30 30 55 30 40 10 40 30 30 55 Holding cost = $1/week; Setup cost = $100/times; Lead time = 1 week

Gross requirements Scheduled receipts Projected on hand Lot-for-Lot Example No on-hand inventory is carried through the system Total holding cost = $0 Net requirements Planned order receipts 1 2 3 4 5 6 7 8 9 10 There are seven setups for this item in this plan Total setup cost = 7 x $100 = $700 Planned order releases 35 30 40 0 10 40 30 0 30 55 35 35 0 0 0 0 0 0 0 0 0 0 30 40 0 10 40 30 0 30 55 30 40 10 40 30 30 55 30 40 10 40 30 30 55 Holding cost = $1/week; Setup cost = $100/times; Lead time = 1 week

EOQ Lot Size Example Week 1 2 3 4 5 6 7 8 9 10 Gross requirements Scheduled receipts Projected on hand Net requirements Planned order receipts Planned order releases 35 30 40 0 10 40 30 0 30 55 35 35 0 43 3 3 66 26 69 69 39 0 30 0 0 7 0 4 0 0 16 73 73 73 73 73 73 73 73 Holding cost = $1/week; Setup cost = $100/times; Lead time = 1 week Average weekly gross requirements = 27; EOQ = 73 units

Scheduled receipts Projected on hand Planned order receipts Planned order releases EOQ Lot Size Example Annual demand = 1,404 Total cost = setup cost + holding cost Total cost = (1,404/73) x $100 + (73/2) x ($1 x 52 weeks) Total Gross cost = $3,798 /year requirements Cost for 10 weeks = $3,798 x (10/52) = $730 Or 1 2 3 4 5 6 7 8 9 10 35 30 40 0 10 40 30 0 30 55 35 35 0 0 0 0 0 0 0 0 0 Total Net cost = setup cost + holding cost requirements Total cost = 4 x $100 + 318 x ($1 /weeks) Total cost = $718 0 30 0 0 7 0 4 0 0 16 73 73 73 73 73 73 73 73 Holding cost = $1/week; Setup cost = $100/times; Lead time = 1 week Average weekly gross requirements = 27; EOQ = 73 units

PPB Example 1 2 3 4 5 6 7 8 9 10 Gross requirements Scheduled receipts Projected on hand Net requirements Planned order receipts Planned order releases 35 30 40 0 10 40 30 0 30 55 35 35 0 50 10 10 0 60 30 30 0 0 30 0 0 0 40 0 0 0 55 80 100 55 80 100 55 Holding cost = $1/week; Setup cost = $100; Lead time = 1 week ; EPP = 100 units

Gross requirements Scheduled receipts Projected on hand Net requirements Planned order receipts Planned order releases PPB Example Trial Lot Size Periods (cumulative net Costs Combined requirements) Part Periods Setup Holding Total 2 30 0 2, 3 70 1 2 40 = 340 x 14 5 6 7 8 9 10 2, 3, 4 70 40 = 40 x 1 35 30 40 0 10 40 30 0 30 55 2, 3, 4, 5 80 70 = 50 x 1 + 10 x 2 100 + 70 = 170 2, 3, 4, 5, 6 120 230 = 90 x 1 + 50 x 2 + 40 x 1 Combine periods 2-5 as this results in the Part Period closest to 35 the EPP 6 40 0 6, 7 70 30 = 30 x 1 6, 7, 8 70 30 = 30 x 1 6, 7, 8, 9 100 120 = 60 x 1 + 30 x 2 100 + 120 = 220 Combine periods 6-9 as this results in the Part Period closest to the EPP 10 55 0 100 + 0 = 100 Total cost 300 + 190 = 490 Holding cost = $1/week; Setup cost = $100; EPP = 100 units

Lot-Sizing Summary For these three examples Lot-for-lot $700 EOQ $730 PPB $490 Wagner-Whitin would have yielded a plan with a total cost of $455 for this example

Example 1 2 3 4 5 6 7 8 9 10 Gross requirements Scheduled receipts Projected on hand Net requirements Planned order receipts Planned order releases 35 30 40 0 10 40 30 0 30 55 35 35 0 50 10 10 0 30 0 0 55 0 30 0 0 0 40 0 0 30 0 80 70 85 80 70 85 Holding cost = $1/week; Setup cost = $100; Lead time = 1 week ; EPP = 100 units

Lot-Sizing Summary In theory, lot sizes should be recomputed whenever there is a lot size or order quantity change In practice, this results in system nervousness and instability Lot-for-lot should be used whenever economical Lot sizes can be modified to allow for scrap, process constraints, and purchase lots

Lot-Sizing Summary Use lot-sizing with care as it can cause considerable distortion of requirements at lower levels of the BOM When setup costs are significant and demand is reasonably smooth, PPB, Wagner-Whitin, or EOQ should give reasonable results

Updating the System Regenerative system Updates MRP records periodically Net-change system Updates MPR records continuously

MRP Primary Reports Planned orders - schedule indicating the amount and timing of future orders. Order releases - Authorization for the execution of planned orders. Changes - revisions of due dates or order quantities, or cancellations of orders.

MRP Secondary Reports Performance-control reports system evaluation, deviation, late delivery, stockouts Planning reports useful for forecasting future inventory, assess future material requirement Exception reports late or overdue orders, excessive scrap rate, requirement of nonexisting parts

Material Checking & Balancing Use for monitoring of amount of part and product during processes Needs information to balance materials Accumulative production planning or target plan BOM or Assembly diagram Normally periodic checked

Accumulative production Material Checking & Balancing B C G Assembly diagram D A E H I J K F 9 8 7 6 5 4 3 2 1 0 Target Plan Week Balancing chart J F M A M J J A S O N D A B C D E F G H I J K

Standard labor hours Standard labor hours Resource Requirements Profile 200 Capacity exceeded in periods 4 & 6 200 Lot 6 split Lot 11 moved 150 100 50 Lot 1 Lot 2 Lot 3 Lot 4 Lot 5 Lot 6 Lot 7 Lot 8 Lot 11 Lot 9 Lot 12 Lot 10 Lot 13 Available capacity Lot 15 Lot 14 Lot 16 1 2 3 4 5 6 7 8 Period (a) 150 100 50 Lot 1 Lot 2 Lot 3 Lot 4 Lot 5 Lot 6 Lot 7 Lot 8 Lot 9 Lot 12 Lot 10 Lot 13 Available capacity Lot 11 Lot 15 Lot 14 Lot 16 1 2 3 4 5 6 7 8 Period (b)

Smoothing Tactics 1. Overlapping Sends part of the work to following operations before the entire lot is complete Reduces lead time 2. Operations splitting Sends the lot to two different machines for the same operation Shorter throughput time but increased setup costs 3. Lot splitting Breaking up the order into smaller lots and running part ahead of schedule

Other Considerations Safety Stock Lot sizing Lot-for-lot ordering Economic order quantity Fixed-period ordering

MRP in Services Food catering service End item => catered food Dependent demand => ingredients for each recipe, i.e. bill of materials

Benefits of MRP Low levels of in-process inventories Ability to track material requirements Ability to evaluate capacity requirements Means of allocating production time Ability to easily determine inventory usage by backflushing Backflushing: Exploding an end item s bill of materials to determine the quantities of the components that were used to make the item.

Requirements of MRP Computer and necessary software Accurate and up-to-date Master schedules Bills of materials Inventory records Integrity of data

MRP II Expanded MRP with emphasis placed on integration Financial planning Marketing Engineering Purchasing Manufacturing

Adjust master schedule MRP II Finance Market Demand Manufacturing Master production schedule Marketing Production plan MRP Adjust production plan Rough-cut capacity planning Capacity planning Yes No Requirements No Yes Problems? Problems? schedules

ERP Enterprise resource planning (ERP): Next step in an evolution that began with MPR and evolved into MRPII Integration of financial, manufacturing, and human resources on a single computer system.

ERP Software ERP software provides a system to capture and make data available in real time to decision makers and other users in the organization Provides tools for planning and monitoring various business processes Includes Production planning and scheduling Inventory management Product costing Distribution

MRP in Services Service applications such as: Professional services Postal services Retail Banking Healthcare Higher education Engineering Logistical services Real estate

ERP Strategy Considerations High initial cost High cost to maintain Future upgrades Training

Daftar Pustaka Richardus Eko Indrajit, (2005), Manajemen Persediaan, Grasindo, Jakarta Heizer Jay, B.Rander, (206), Manajemen Operasi, Salemba Empat, Jakarta Hani handoko, (2002), Manajemen Produksi dan Operasi, BPFE, Yogyakarta Siswanto, (2005), Riset Operasi, Erlangga, Jakarta M. Syamsul Ma arif, (2003), Manajemen Operasi, Grasindo, Jakarta Sofyan Assauri, (2001), Manajemen Operasi, BPFE, Jakarta Martinich, (2003), Operation Manaement, Prenice hall, New Yory

Terima Kasih