Bonner Bridge Replacement Update:

Similar documents
Ironton Russell Bridge Project

Ironton Russell Bridge Project

Ironton Russell Bridge Project

PROJECT UPDATE SOUTH NORFOLK JORDAN BRIDGE CITIES OF PORTSMOUTH AND CHESAPEAKE, VIRGINIA. April 2012

Ironton Russell Bridge Project

Ironton Russell Bridge Project

Grade Separation Systems. Single-Span Rail Bridge Construction Procedure. An innovation from art engineering inc.

Ironton Russell Bridge Project

Ironton Russell Bridge Project

Ironton Russell Bridge Project

Tilikum Crossing Transit Bridge. Portland, OR

John James Audubon Bridge

SUNSHINE SKYWAY BRIDGE

Lesner Bridge Replacement

2016 ACEC/PA ANNUAL MEETING

Design and Construction of the SH58 Ramp A Flyover Bridge over IH70. Gregg A. Reese, PE, CE, Summit Engineering Group, Inc.

Miami Marlins Baseball Park

Lecture 13 CONCRETE WORKS

Long Key Bridge, a spectacular example. Design Features and Prestressing Aspects of Long Key Bridge

2. Outline of the bridge 3-span continuous deck extradosed bridge Bridge length

Accelerated Bridge Construction (ABC) webinar Thursday, October 24, 2013 ABC Center at Florida International University (FIU) presents

Lesner Bridge Replacement

Construction of Long Key Bridge

Gilmerton Bridge Replacement Project Virginia Society of Professional Engineers (VSPE) March 27, 2013

Economical Design / Case Studies

SPECIAL SPECIFICATION 4584 Segmental Concrete Bridge Unit

Accelerated Bridge Construction in USA

KEYWORDS: Barge Stability, Steel Truss Erection, Horizontal Sliding of Steel Trusses

Prestressing of Carbon Fiber Elements in Virginia

Lecture 13: Practical Design, The Future of Prestressed Concrete, and Concluding Thoughts...

Progressive Erection Applied to Box Girder with Strutted Wing Slab

PRESENTATION PLAN A MODEL COMPARISON FLOOR CONSTRUCTION

Florida DOT efforts toward improving Post Tension Durability

Seven Wonders of the Ancient World

Construction Measurement III SBQ3314. Precast Pre stressed Concrete Works. Dr. Sarajul Fikri Mohamed

Civil Engineering Construction I (CBE5031)

US-131 Over the Muskegon River. Corey Rogers, P.E. Bridge Construction Engineer

NATIONAL HARBOR BUILDING M

The North Carolina Department of Transportation awarded a

The Hashemite University Department of Civil Engineering. Dr. Hazim Dwairi. Dr. Hazim Dwairi 1

Pushing the Envelope For 100 Years

APPENDIX G WHITTIER BRIDGE TYPE STUDY EVALUATION OF BRIDGE ALTERNATIVES

Well Road Project Accelerated Bridge Construction Using Self-Propelled Modular Transporters (SPMT s) By: Mark Bucci, P.E.

Introduction.» Demolition Concepts» Concept Design» Final Design» Construction» Health Monitoring

Anchor bolts ASTM F1554, Gr. 36 Wide flange beams ASTM A992, Fy = 50 ksi Misc. structural steel ASTM A36, Fy = 36 ksi

Challenging Skew: Higgins Road Bridge over I-90

Requirements for Measuring and Pricing of Structural Concrete

Critical Structures Construction Issues

I-70 over SR 121 Bridge Slide Construction and Engineering

2014 HDR, all rights reserved.

Learning Objectives. A Brief History

SR 0136-G10 ABC BRIDGE REPLACEMENT in Eighty Four, PA

PARTIAL-DEPTH PRECAST DECK PANEL DESIGN AND CONSTRUCTION IN TEXAS

Bridge Construction Methods

RESEARCH PROJECT AT UNIVERSITY OF NEVADA, RENO

SINGLE STEEL BOX GIRDER BRIDGES FOR THE TERMINAL DEVELOPMENT PROJECT AT TORONTO PEARSON INTERNATIONAL AIRPORT. Srdjan Brasic, M.Sc., P.Eng.

CONCRETE SPLICED GIRDERS IN TEXAS. Nicholas Nemec, P.E. TxDOT-BRG

RESEARCH PROJECT AT UNIVERSITY OF NEVADA, RENO

7 Bridges in 74 Days. NC 12 Detour

COURTYARD INFILL STRUCTURE DESIGN

SPECIAL INSPECTION AGREEMENT

DESIGN OF THE MAIN SPANS OF THE CHONGQING CAIYUANBA BRIDGE

DESIGN AND LAUNCHING OF A REDUNDANT TRUSS OVER RAILROAD YARD

With several years of detailing experience and a vast range of knowledge, we have successfully helped clients with numerous projects, including:

Introduction -- Tsing Ma Bridge

Structural Tests and Special Inspections Form. Inspection of Fabricators (1704.2)

Precast Prestressed Segmental Elevated Urban Motorway in Italy

Installing DELTABEAM. Installation of DELTABEAM. Deliveries. Storage on-site

Rt. 15/29 (SBL) Bridge Superstructure Replacement and Roadway Widening

MARTA Rapid Transit Bridges

1/26/2015 DETAILS CIP DETAIL EXAMPLES WHY SIMPLIFY DETAILS? CIP DETAIL EXAMPLES DETAILING FOR SIMPLICITY

Management of Half Joints in RTA Bridges Amie Nicholas, Project Engineer, NSW Roads and Traffic Authority

Concrete Framing Systems - Walls and Columns

Construction Techniques of The 3 rd Bosphorus Bridge in Istanbul, Turkey

Get In, Get Out, Stay Out!

HARRY H. EDWARDS INDUSTRY ADVANCEMENT AWARD. The Chesapeake and Delaware Canal Bridge Design-Construction Highlights

John James Audubon Bridge. Introduction

Precast Segmental Bridge Construction Part 4 - Balanced Cantilever Erection Method

Design, fabrication and construction of Railway Bridge over Södertälje canal

PAN PAC PULPMILL TREATMENT TANK

NSBA. Prize Bridge. Awards

Special Considerations for Maintenance of the Sunshine Skyway Bridge

CHEF MENTEUR BRIDGE REPLACEMENT

Smarter. Safer. Leaner.

Structural Technical Report #2 Pro/Con Study of Alternate Floor Systems

Statement of Special Inspections

Structural - Engineering Review Checklist

Launching technique for the Viaduc de Millau

Lowering a Cofferdam: Alternate Means to Constructing a Cofferdam

Teglvaerks Bridge, Copenhagen - Denmark Kjeld Thomsen, Civil Engineer, MSc - CEO ISC Consulting Engineers A/S

Replacing the Aging US 52 Mississippi River Bridge

Development Island Vehicle Access

SUMMARY SHEETS OF HYBRID CONNECTIONS

1. Cast-in-place concrete is specified in Section

This precast prestressed concrete pedestrian

715 - PRESTRESSED CONCRETE MEMBERS SECTION 715 PRESTRESSED CONCRETE MEMBERS

PAUL ZICK, PE NORTH SHORE CONSTRUCTORS JV

CONCRETE & MASONRY SAFETY

PHASING CONSIDERATIONS FOR BRIDGES

CONSTRUCTION SPECIFICATION FOR CONCRETE BARRIERS

Transcription:

Bonner Bridge Replacement Update: Jerry D. Jennings, PE - NCDOT Division 1 Engineer Pablo A. Hernandez, - NCDOT Resident Engineer September 18, 2017

Bonner Bridge Replacement Timeline Refresher Bonner Bridge opened in 1963. Many projects to maintain & protect existing bridge. Design build contract for replacement was awarded to PCL Civil Constructors, Inc., in July 2011. HDR Engineering, Inc. of the Carolinas lead design firm. Settlement agreement reached to replace bridge in 2015. Original bid was $215.8 million. Contract adjustments due to delays & enhancements $250 million. 2

Bonner Bridge Replacement (B-2500 Phase I) 3

Comparison of Existing Bridge to the New Bridge Old New Bridge length (miles) 2.4 2.8 Number of bents 207 83 Number of spans in navigation zone 3 11 Navigation zone width (ft.) 502 3550 Navigation channel width (ft.) 130 300 Design lifespan (years) 30 100 4

Design Visualization Becoming Reality Notice To Proceed: Oct 14, 2015. Onsite Activities Begin: March 2016. Substantial Completion: November 2018. Contract Completion: September 2019. Total Contract Expenditures to Date: $149.7 Million Approximately 60% Complete Design & Construction Support = $35 Million Large Percentage of Precast Concrete Members Fabricated Offsite. Construction Activities Approx. 50% Complete. 5

Materials & Work Activities Needed for New Bridge 20" Sq Pile 54" Cyl Pile 36" Sq Pile Footings Cast InPlace & Precast Caps Column Segments 45 Girders 96" Girders Cast In Place Decks Box Segments Plan (each) 16 138 532 37 83 156 18 285 71 264 Approx. Length 18,800 FT 68,000 FT 46,711 FT 3,450 FT 6

Work Areas of Project Approach South Navigation Zone Approach North Approaches: 71 spans,160 ft. to 182 ft. wide. 72 bents: 2 styles of foundations: 54 cylinder pile with precast cap & 36 square pile with cast in place footing, precast columns & cap. Navigation Zone: 11 spans 200 ft. to 350 ft. wide. 11 bents: 36 square pile with cast in place footing, precast columns & cap. 7

Pile Driving: 36 Square Precast Prestressed Piles In Navigation Zone & Transition Approaches 338 of 532 piles installed to date. Ave Length 130ft. (weight 60 to 65 tons or approx. 1,050lbs/LF) 17 of 37 bents completed with 10 to 30 piles/bent. Three more bents with large cluster of piles should be completed in November. 8

Pile Driving: 54 Cylinder Precast Prestressed Piles In Approaches to High Rise. 86 of 138 piles installed to date. Weigh 55 to 62 tons, 110 to 130 ft. long. (hollow with 6 walls) 28 of 44 bents completed. 3 to 4 piles/bent. 9

Precast Caps: Approaches 33 of 83 caps set. Caps are voided (hollow) to engage with a rebar cage that is cast into top of cylinder piles. Once cap is set, concrete is cast into voids in top of cap make a solid connection to the piles. Largest precast cap for NCDOT. 10

Cast In Place Footings: Navigation Zone & Approaches 14 of 37 footings cast. Largest are 300 to 640 CY. Total 8,045 CY Smaller footings are 110 to 260 CY. Cast in place concrete is supported by a precast slab that is left in place. 11

Cast In Place Footings: Navigation Zone Utilize stainless steel reinforcing. Up to 8 ft. thick. Concrete delivered to existing bridge deck and discharged into 8CY bucket. Ocean water circulated inside concrete to cool the mass. Largest approx. 50ft x 50ft 6 to 16 hours to place concrete. 12

Cast In Place Footings: Approaches Smaller footings 36ft x 36ft and 21ft x 36ft. 6 ft. thick. 13

Columns: Navigation Zone & Approaches 23 of 48 sections set. Post Tensioned with 2.5 inch diameter stainless steel and plain steel bars. Grout pumped in PT ducts. 14

Columns: Navigation Zone & Approaches Cast in Place Column Stub Precast sections: 11ft x16ft 4ft to 12 ft. tall 18inch thick walls Smaller sizes in approaches: 5ft x 5ft. 15

Columns: Navigation Zone & Approaches 16

Girders: Approaches Prestressed Precast Concrete Girders: 106 of 303 girders set. 26 of 71 spans set. 96 tall. 160 to 182 ft. long. 100 tons (approx. 50 CY of concrete per girder). Delivered by truck and barge. Truck has 13 to 16 axels 17

Girders: Approaches Two cranes to erect. Largest precast girders in NCDOT. Very large & heavy hardware for temporary bracing. 18

Girders: Approaches Girders span land, marsh & water. Access for setting girders is challenging due to narrow work site and adjacent traffic. Braced for 110mph to 140mph until deck is cast. 19

Cast In Place Decks: Approaches 23 of 71 Decks cast. 160ft to 182 ft. long. 42 ft. wide. Stainless steel reinforcing. 20

Cast In Place Decks: Approaches Approx. 225CY per deck. (Total 18,000 CY) Lightweight Concrete weighs 20% less than normal concrete. Cast In Place Deck Area = 480,950 SF or 11.04 acres. 21

Cast In Place Decks: Approaches Finished with burlap drag and covered with felt lined plastic for wet cure. Formwork for bridge rail that is cast in place. 22

Cast In Place Decks: Approaches Clear deck is 40ft wide: Two 12ft lanes and two 8ft shoulders. Deck will be ground and/or grooved for skid texture. 23

Cast In Place Decks: Approaches Clear deck is 40ft wide: Two 12ft lanes and two 8ft shoulders. Bridge rail is bicycle safe: 54 tall. 24

Box Segments: Navigation Zone 90 of 264 box segments set. Segments cast in Chesapeake VA. Shoring Tower needed for temporary support of the box segments. Two bearings assemblies per bent i.e. 22 bearings (approx. 5ft x 5ft) 25

Box Segments: Navigation Zone Barge strategically loaded for unloading. Segments are large & match cast. 8 to 19 ft. tall. 5 to 14 ft. long. 100 tons Pier segments set against frame on shore tower. Bolted and epoxy for the connection to each other. 26

Box Segments: Navigation Zone Set additional segments with crane for form Pier Table. Jacks and tie downs position and secure Pier Table. 27

Box Segments: Navigation Zone Segment lifters positioned on Pier Table. Shuttle Barge spudded below lifter, segment is lifted & connected to alternating sides. Balanced Cantilever Erection. 28

Box Segments: Navigation Zone Segments temporarily post tensioned to previous segments in upper corners and floor. Permanent threaded rods and cables (i.e. Tendons) installed at each pair of segments. Continue erecting cantilevers. 29

Box Segments: Navigation Zone Tendons installed though all segments @ each stage (12 stages i.e. 12 segments each side of the pier segments). 18 to 22 5/8 diameter strand bundled into a Tendon. Tendons are stressed to approx. 900,000 lbs. 30

Box Segments: Navigation Zone Construct two adjoining cantilevers with an approx. 4ft gap for cast in place Closure Pour. Once Closure Pour gains strength, stress interior Tendons. 31

Box Segments: Navigation Zone Interior accessible at ends of the navigation zone and underside doors. Also provides access to hollow columns for inspection. 32

Channel Width: Navigation Zone ~80 ft. ~70 ft. ~300 ft. Seven spans with horizontal & vertical clearances for navigation. 33

Box Segments: Navigation Zone 34

Under Construction Stay Tuned 35

Under Construction Stay Tuned 36

Under Construction Stay Tuned 37

Under Construction Stay Tuned 38

Under Construction Stay Tuned Questions? 39