Apparel Gallery Ltd.

Similar documents
S B Design Ltd. Famous Design Ltd. 246/1/F, West Agargaon, Sher-E-Bangla Nagar, Dhaka-1207 ( N, E) 17 February 2015

Suman Fashion Garments Ltd. Nipunika Ltd. Cha-72/1/B, Moddha Badda, Holland Centre, Progoti Sarani, Dhaka ( N, E) 09 March 2014

Purna Fashions Ltd. RH Attire Ltd

ABA Fashions Ltd. Plot #9, Block F, Tongi, Gazipur-1710 ( N, E) 08 MARCH 2014

Fakir Knitwears Ltd. Kayempur, Fatullah, Narayanganj-1400, Bangladesh ( N, E) 19 December 2013

Babylon Casualwear Ltd Aboni Fashions Ltd Suravee Garments Ltd

Dew Fashions Ltd. Le-Nouveautex Ltd. House-65,Board Bazar, Gazipur, Dhaka ( N, E) 22 June 2014

Warn Knit Fashion Sun Knitwear Ltd. ARS Printing Chanmari, Near New Court, Fatullah, Narayanganj 1400, Bangladesh ( N, 90.

Al Islam Textile Ltd.

Badhan Knit Fashions Ltd

Camlet Fashions Ltd. Simco Fashions Ltd Fine Craft Ltd Ayesha & Galeya Fashions Ltd

Sonnet Textile Industries Ltd.

Panwin Designs Ltd. Baniachala (Bagher Bazar), Bhabanipur, Gazipur , rd May 2014

Masco Cottons Ltd. 44, Redwan Complex, Gazipura Bustand, Tongi, Gazipur ( N, E) 25 January 2015

Kuliarchar Sweater Industries Ltd.

Saasco Tex (BD) Ltd Muksudpur Apparels Ltd Expo Dress Ltd Julfikar Fashions Ltd

Abanti Color Tex Ltd. Plot-S, A-646, Shashongaon Enayetnager, Fatullah, Narayangonj ( E, N) 28 June 2014

Structural Inspection Report

Tanzila Textile Ltd.

Alif Apparels Ltd. (9813) Goldstar Garments Ltd. (9844)

Mondol Fabrics Ltd. Nayapara,kasimpur, Gazipur ( N, E0) 8th March 2014

4A Yarn Dyeing Ltd. Kaichabari, Savar, Dhaka-1340, Bangladesh ( , ) 25 March 2014

EH Textiles Ltd EH Fabrics Ltd

Elite Garments Ind. Ltd.

Amity Design Ltd. House #7&9, Road #9 Block #D, Section #11 Mirpur Dhaka 1216, Bangladesh (23.820N, E) 03.MARCH.2014

A.M. Design Ltd. Diakhali, Beron, Jamgara, Ashulia, Bangladesh ( N, E) 3 May 2014

GMS Composite Ltd. Shardagonj, Kashimpur,Gazipur,Bangladesh ( , ) 22 March 2014

Libas Textiles Ltd (9500)

Aman Graphics and Design Ltd. Nazimnagar, Hemayetpur, Savar, Dhaka ( E, N) 29 April 2014

Tanaz Fashions Ltd. & Zayantex Ltd. L Usine Fashion Ltd (Unit 1)

KDS IDR Ltd. CDA Plot # 15 (P)+16, Mohora I/A, Chandgaon, Chittagong ( N, E) Survey Date: 11 th March 2015

A-One Polar Ltd. Bhulta,Rupgonj,Narayangonj. ( , ) 27th April 2014

Echotex Ltd. Chandra, Mouchak, Shafipur, Gazipur, Dhaka ( N, E) 6 February 2014

Posh Garments Ltd Ltd

Star Garments (Pvt Ltd.)

HELA Clothing Bangladesh Ltd

Cassiopea Fashions Ltd. Cassiopea Apparels Ltd.

Structural Safety Inspection

INITIAL STRUCTURAL INTEGRITY ASSESSMENT REPORT (SIAR)

Natural Sweater Village Ltd

INITIAL STRUCTURAL INTEGRITY ASSESSMENT REPORT (SIAR)

Graphic Textiles Ltd.

EQUIVALENT INITIAL STRUCTURAL SAFETY ASSESSMENT

INITIAL STRUCTURAL INTEGRITY ASSESSMENT REPORT (SIAR)

Epcot Apparels Ltd Epcot Jeans Ltd Chandana, Joydebpur, Gazipur ( N, E) 11 May 2014

INITIAL STRUCTURAL INTEGRITY ASSESSMENT REPORT (SIAR)

EQUIVALENT INITIAL STRUCTURAL SAFETY ASSESSMENT

Pimkie Apparels Ltd. (9205) Plot #328, Bloc #F, Tongi Industrial Area, Tongi ( N, E) 27.May.2014

EQUIVALENT INITIAL STRUCTURAL SAFETY ASSESSMENT

INITIAL STRUCTURAL INTEGRITY ASSESSMENT REPORT (SIAR)

Shin Shin Apparels Ltd. (9615) Dag RS. 228, JL 73, Gorat, East Norshinghapur, Zirabo, Savar ( N, E) 27.MAY.2014

INITIAL STRUCTURAL INTEGRITY ASSESSMENT REPORT (SIAR)

GK Garments Ltd (10378) Global Fashion Garments Ltd (10380) Global Outerwear Ltd (9991) Savar Shirts (10394)

K.L. Fashion Ltd. (10982) 75/1, Master Bari, Tongi, Gazipur ( N, E) 01.July.2014

INITIAL STRUCTURAL INTEGRITY ASSESSMENT REPORT (SIAR)

INITIAL STRUCTURAL INTEGRITY ASSESSMENT REPORT (SIAR)

INITIAL STRUCTURAL INTEGRITY ASSESSMENT REPORT (SIAR)

EQUIVALENT INITIAL STRUCTURAL SAFETY ASSESSMENT

BUILDING INTEGRITY DEA SUMMARY REPORT

EQUIVALENT INITIAL STRUCTURAL SAFETY ASSESSMENT

EQUIVALENT INITIAL STRUCTURAL SAFETY ASSESSMENT

New Era Fashions Mfrs (BD) Ltd

Utah Knitting & Dyeing Ltd #9533. Boran, Monipur, Mirzapur, Gazipur 03.May.2014

L Usine Fashions Ltd. (Ref. 9258) 36, Gazipura, Sataish Road, Tongi, Gazipur-1712, Bangladesh ( N, E) 08.MARCH.

INITIAL STRUCTURAL INTEGRITY ASSESSMENT REPORT (SIAR)

Avant Garde Fashion Ltd. Ring Shine Textiles Ltd.

ROOME & GUARRACINO, LLC Consulting Structural Engineers 48 Grove Street Somerville, MA Tel: Fax:

INITIAL STRUCTURAL INTEGRITY ASSESSMENT REPORT (SIAR)

Mark Sweater Ltd. Structural Inspection Report Observations & Actions Authors: Dariusz Tomiak Checked by: Dariusz Tomiak Approved by: Dariusz Tomiak

Lida Textile & Dyeing Ltd. Structural Inspection Report

Structural Conditions Assessment of Current Lapeer District Schools Administration Building 250 Second Street, Lapeer, Michigan

GAUTENG DEPARTMENT OF INFRUSTRUCTURE DEVELOPMENT

GAUTENG DEPARTMENT OF INFRUSTRUCTURE DEVELOPMENT

INITIAL STRUCTURAL INTEGRITY ASSESSMENT REPORT (SIAR)

INITIAL STRUCTURAL INTEGRITY ASSESSMENT REPORT (SIAR)

BISON PRECAST FLOORING SPECIFICATION

BUILDING INTEGRITY DEA SUMMARY REPORT

The difference is Guidance for the preparation of Deck Manufacturing Schedules

East Lyme Middle School EAST LYME MIDDLE SCHOOL

Spring Trade Ltd. (9522) Plot # 42, Konapara Tenguri, Zirani Bazar, B.K.S.P, Savar, Dhaka, Bangladesh. ( N, E) 28.APRIL.

Exterior Elevated Elements Inspection Guidelines

BUILDING INTEGRITY SUMMARY REPORT

PRELIMINARY STRUCTURAL INVESTIGATION REPORT

STRUCTURAL EVALUATION

INITIAL STRUCTURAL INTEGRITY ASSESSMENT REPORT (SIAR)

INITIAL STRUCTURAL INTEGRITY ASSESSMENT REPORT (SIAR)

FEMA P-593 STEP-BY STEP PRESCRIPTIVE RETROFIT FOR CRIPPLE WALL BRACING & ANCHORAGE TO FOUNDATION

assembly an open space between the roof and ceiling of a building attic balloon frame a joist constructed of steel with bars in the verticle web space

Elevated Slab Sequence

BUILDING INTEGRITY SUMMARY REPORT

Bison Precast Flooring Specification

Pandora Sweaters Ltd.

(Old examination format for reference only)

Regarding the refusal to issue a code compliance certificate for a 13-year-old house at 14 Patsy O Hara Place, Swanson, Auckland

BUILDING INTEGRITY SUMMARY REPORT

Christchurch City Council

INITIAL STRUCTURAL INTEGRITY ASSESSMENT REPORT (SIAR)

BUILDING INTEGRITY DEA SUMMARY REPORT

INITIAL STRUCTURAL INTEGRITY ASSESSMENT REPORT (SIAR)

IMPRESS FASHION LTD. Dag No. 2224, Matuial, Konapara Katherpool, Jatrabari, Dhaka-1362 ( N, E) 27 August 2015

Transcription:

Apparel Gallery Ltd. 147-148, Norshinghpur, Asulia, Savar, Dhaka (23.929985N,90.304914E) 23 March 2014 1

2 Observations

Building 1 Heavy loading due to raised floor area on Ground Floor 3

Building 1 Raised floor area, build up unknown. 4 Heavy loading due to raised floor area on Ground Floor

Building 1 Raised floor area on top of raise area, not identified on drawings. Build up unknown. 5 Heavy loading due to raised floor area on Ground Floor

Building 1 Floor cracking. 6

Building 1 Multiple cracking in floor finish. Floor cracking 7

Building 1 Opening in floor with exposed reinforcement and water ingress. 8

Building 1 Opening in slab, exposed reinforcement. Water draining through opening affecting exposed reinforcement. 9 Opening in floor with exposed reinforcement and water ingress.

Building 1 Repaired cracking in soffit of ground floor slab. 10

Recently repaired cracking in Soffit of ground floor slab adjacent to column with Basement slab cracking. Building 1 11 Repaired cracking in soffit of ground floor slab.

Building 1 Cracking in basement slab. 12

Cracking in Basement slab around column perimeter. Building 1 13 Cracking in basement slab

Building 1 Timber roof 14

Building 1 Lightweight timber roof on steel beam cut at one end Connection to be checked. Timber roof 15

Building 1 Façade cracking/spalling 16

Building 1 Vertical Crack between cantilever and main structure. 17 Check if crack is structural or cosmetic.

Building 1 Horizontal Crack. Horizontal Crack. 18 Check if cracks are structural or cosmetic.

Building 1 Spalling/Cracking, possibly due to corrosion of reinforcement. 19 Check for corrosion of reinforcement

Building 1 Water falling onto edges of all slabs, possible corrosion of reinforcement. 20 Check for corrosion of reinforcement

Building 1 Cracking in column face. Remove render to check. Diagonal Crack. Remove render to check. 21 Check if crack is structural or cosmetic.

Building 1 Drainage outlet falling onto cantilever edge below. Cracking/Spalling. Confirm if reinforcement is corroded. 22

Building 1 Façade steps out at 6 th floor level possibly due to construction tolerances. 23

Building 2 Water ponding 24

Building 2 Water ponding on unprotected concrete slab (roof structure removed) 25

Building 2 Water Storage 26

Building 2 6 No. 2500L water tanks. (Currently not connected or filled) 27

Building 2 Heavy Storage Loading 28

Building 2 High storage loads 29

Building 2 Floor Cracking 30

Building 2 Cracking on column line. 31

Building 2 Column without vehicle protection 32

Building 2 Column in loading bay vulnerable to vehicle impact. Impact protection should be provided. 33

34 Priority Actions

Problems Observed Building 1 1. High Concrete Stresses in platform area as indicated in page 5 in Raised floor in 2 locations on Ground Floor, build up unknown but likely to be at least partially filled with sand, urgent opening up works required by building engineer to confirm build up. 2. Cracking in slabs, detailed design check required. 3. Evidence of repairs to cracks in soffit of ground floor under raised floor area s, repair should be removed by local engineer and reinforcement behind check for possible signs of corrosion. 4. Opening in floor with exposed reinforcement to be addressed by the Building Engineer and repaired. 5. Evidence of water draining down façade of building causing possible reinforcement corrosion, remove source of water/divert and check slab edges for spalling/corrosion 6. Check adequacy of timber roof (connections for uplift) following part removal of roof. 35

Problems Observed Building 2 7. Building 2 - Check on column loads and design required in order to inform loading limits in warehouse. 8. Building 2 - Column without vehicle protection 36

Item No. Observation Recommended Action Plan Recommended Timeline 1 2 3 Building 1 Heavy loading due to raised floor area on Ground Floor Building 1 Heavy loading due to raised floor area on Ground Floor Building 1 Heavy loading due to raised floor area on Ground Floor A full Detailed Engineering Assessment is to be commenced for columns in the area of the raised platform at ground floor Until DEA is complete reduce load at all levels to less than 1.5kN/m2 and especially from stacked garments from area highlighted on page 5 At ground floor (grid B2-D4) remove the second lift of raised platform and investigate the construction of the lower platform. If found to be solid or filled with sand, remove material or evacuate areas above until structure and foundations proven. Immediate - Now Immediate - Now Immediate - Now 4 Building 1 Heavy loading due to raised floor area on Ground Floor Conduct concrete tests to prove concrete strength Immediate - Now 5 6 7 Building 1 Heavy loading due to raised floor area on Ground Floor Building 1 Heavy loading due to raised floor area on Ground Floor Building 1 Heavy loading due to raised floor area on Ground Floor DEA to prove adequacy of foundations in the area B2 to E7 noting the cracking to basement slab at column D3. DEA to confirm if movement is still live as it was noted that the soffit of the ground floor slab had been freshly painted Detail Engineering Assessment and strengthening / remedial works as specified by the building engineer to be completed Produce and actively manage a loading plan for all floor plates within the factory giving consideration to floor capacity and column capacity. Immediate - Now 6-weeks 6-months 37

Detail Engineering Assessment This Schedule develops a minimum level of information, Analysis and testing expected as part of a Detail Engineering Assessment. The Building(s) have been visually assessed and it is deemed necessary that a detailed engineering assessment be carried out by a competent Engineering Team employed by the factory Owner. This Request should be read in conjunction with the BUET developed Tripartite Guideline document for Assessment of Structural Integrity of Existing RMG Factory Buildings in Bangladesh (Tripartite Document), the latest version of this document should be referenced. T his document also gives guidance on required competency of Engineering Team. We expect that the following will be carried out: 1. Development of Full Engineering As-Built Drawings showing Structure, loading, elements, dimensions, levels, foundations and framing on Plan, Section and Elevational drawings. 2. The Engineering team are to carry out supporting calculations with a model based design check to assess the safety and serviceability of the building against loading as set out in BNBC-2006, Lower rate provisions can be applied in accordance with the Tripartite Guidelines following international engineering practice, justification for these lower rate provisions must be made. 3. A geotechnical Report describing ground conditions and commenting on foundation systems used/proposed. 4. A report on Engineering tests carried out to justify material strengths and reinforcement content in all key elements studied. 5. Detailed load plans shall be prepared for each level showing current and potential future loading with all key equipment items shown with associated loads. 6. The Engineering team will prepare an assessment report that covers the following: As-Built drawings including Plans at each level calling up and dimensioning all structural components Cross sectional drawings showing structural beams, slabs, floor to floor heights, roof build-ups and Basic design information of the structure Highlight any variation between As-built compared to the designed structure Results of testing for strength and materials Results of geotechnical assessment and testing/investigation Details of loading, inputs and results of computer modelling Commentary on adequacy/inadequacy of elements of the structure Schedule of any required retrofitting required for safety or performance of Structure Any proposals for Retrofitting to follow guidance developed in the Tripartite Document 38

Item No. Observation Recommended Action Plan Recommended Timeline 8 9 Building 1 A check on slab design is required due to consistent cracking observed across all floors Building 1 A check on slab design is required due to consistent cracking observed across all floors Create controlled loading plans for all floors, designating where storage can be placed and can not be placed Provide calculations showing the structural adequacy of all slabs/beams, taking into account the loading plans and all built structure including additions beyond the original design. Provide concrete strength tests. 6-months 6-months 10 Evidence of repairs to cracks in soffit of ground floor under Evidence of repairs to cracks in soffit of ground floor under raised floor area s, repair raised floor area s, repair should be removed by Building should be removed by local Engineer and reinforcement behind check for possible signs engineer and reinforcement of corrosion. behind check for possible signs of corrosion 6-weeks 11 Evidence of repairs to cracks in soffit of ground floor under raised floor area s, repair Repairs as detailed by the Building Engineer to be should be removed by local completed should investigations above reveal corrosion of engineer and reinforcement reinforcement behind check for possible signs of corrosion 6-months 39

Item No. Observation Recommended Action Plan Recommended Timeline 12 Opening in floor with Remove source of water to avoid further corrosion to exposed reinforcement to be reinforcement. Clean all affected reinforcement back to addressed by engineer and bare steel. Repair concrete using suitable structural mortar repaired 6-weeks 13 Opening in floor with exposed reinforcement to be Provide calculations showing the structural adequacy of addressed by engineer and floor with opening repaired 6-months 14 Evidence of water draining down façade of building causing possible reinforcement corrosion, remove source of water/divert and check slab edges for spalling/corrosion Engineer to inspect water leakage and damaged structure including the exterior and propose a suitable repair. 6-months 15 Roof partially removed. Timber joists and connection of cut steel rafters to be checked for uplift Building Engineer to inspect section of roof that remains and verify its adequacy against uplift giving consideration to open door on roof 6-weeks 40

Item No. Observation Recommended Action Plan Recommended Timeline 16 17 18 19 20 Building 2 Verify concrete strengths in columns in locations Factory Engineer to review design, loads and columns supporting bonded stresses in area identified above. warehouse areas due to high observed loads Building 2 Verify concrete strengths in columns in locations supporting bonded warehouse areas due to high observed loads Building 2 Verify concrete strengths in columns in locations supporting bonded warehouse areas due to high observed loads Verify insitu concrete stresses either by cores or existing cylinder strength data for columns. We note that cylinders have been provided for slabs and foundations but also note that these elements were specified with a different concrete mix and target strength. Produce and actively manage a loading plan for all floor plates within the factory giving consideration to floor capacity and column capacity Building 2 Verify concrete strengths in columns in locations Continue to implement load plan supporting bonded warehouse areas due to high observed loads Column in loading bay vulnerable to vehicle impact Impact protection should be provided 6-weeks Immediate - Now Immediate - Now 6-weeks 6-months 41