All Approved Contractors / Interested Parties Re: ADDENDUM #1 Project: Burton ISD Rock Building Renovation Date: April 9, 2015

Similar documents
Addendum No. 1. Joliet Junior College 1215 Houbolt Road Joliet, IL DATE: October 11, 2017

Addendum No. 1 Page 1 of 1

Addendum No. 1. Joliet Junior College 1215 Houbolt Road Joliet, IL DATE: October 16, 2017

CITY OF OCEAN CITY COUNTY OF CAPE MAY, NEW JERSEY ADDENDUM #1 FEBRUARY 16, 2016 CITY CONTRACT NO

Addendum No. 1 Page 1 of 2

The following shall be incorporated into the Contract Documents dated 12 MARCH 2018.

MEMORANDUM. Taylor Schoel with Walter Schoel Engineering. DATE: August 29, Addendum 1 - Green Drive Culvert Replacement.

The Home Depot U.S.A., Inc. Instructions to Bidders

Cattaraugus County Little Valley County Center Court Renovations Second Floor Little Valley, NY

REVISED BID FORM. To Procurement Services, Room 1104, 900 East Broad Street, Richmond, Virginia:

The bid is being postponed to comply with State rules requiring 4 calendar days for receipt of bids after an addendum.

DOCUMENT ADDENDUM

Northwest Business Park, Building 5, Bay 3. Issued for Tender: August 24, Substantial Date: November 17, 2017

revisions to project manual Bid Form: Added deduct alternate 07. Refer to written responses below for explanation.

1. Pre-Bid Meeting: The Meeting was held on July 15, 2013 at 1:30PM at Kiser Middle School.

ADVERTISEMENT FOR BIDS

ARCHITECTURE, PLANNING AND HISTORIC PRESERVATION, INC. ADDENDUM NO. 1. September 9, to the BIDDING DOCUMENTS for

ADDENDUM ITEMS: This addendum consists of 2 pages and the following attachments: Pre-Bid Conference Sign-in Sheets, and SE-330, Lump Sum Bid Form.

Main Building Auditorium

NO. 1 TO THE DRAWINGS AND THE PROJECT MANUAL. PROJECT NAME: Anna High School Additions and Renovations. CLIENT NAME: Anna ISD. LOCATION: Anna, Texas

DOCUMENT BID FORM - STIPULATED SUM

DEAN + TYLER + BURNS ARCHITECTURE

This Addendum is directed to all prime Contract Bidders, and all others to whom Drawings and Specifications have been issued by the Architect.

The Town will coordinate with the adjacent property Owner for access allowing work to the East side of the building.

DATE: August 22, All Proposers

ADDENDUM #3. GRW Project No.: Date: March 19, 2019 Subject: City of Nicholasville Fire Station #4

Cooling Tower Replacement Western Guilford High School Guilford County Schools. Pre-bid Conference May 3, 2018

PROJECT MANUAL FOR: CP AGRICULTURAL ENGINEERING RAIN TOWER REPAIRS CP HULSTON HALL STAIR TOWER REPAIRS

PAWLEYS ISLAND TOWN HALL

BASE BID Description Written & Numeric Price

CITY OF PANAMA CITY BEACH WWTF INFLUENT SCREENS REPLACEMENT April 14, 2017

A NEW GYMNASIUM AND RENOVATED FINE ARTS FOR MONTGOMERY CATHOLIC PREPARATORY SCHOOL MONTGOMERY, ALABAMA

This Addendum is directed to all prime Contract Bidders, and all others to whom Drawings and Specifications have been issued by the Architect.

Blatt PE Center Fire Alarm Upgrades November 12, 2012 State Project No. H27-I851-B

Haywood County Auxiliary Services and Haywood County Auxiliary Services: Building Shell Renovation Waynesville, North Carolina

GOREE ARCHITECTS, INC Bellaire Blvd., Suite 105 Bellaire, TX Tel (713)

SECTION BID FORM. Construction of Water Mains: Jonestown, PA. Market Street Project No. W-1-19

PART I PERTAINING TO THE SPECIFICATIONS: Specification section (0.04) o Page 4, The bid form has been revised to include Alternate 4.

BIDDING INFORMATION FOR HOLLY HILL ADMINISTRATION COMPLEX RENOVATION AND ADDITION. for the COUNTY OF ORANGEBURG. Project Number: FY

For Receipt Prior To 3:00 PM Local Time Wednesday, March 29, 2017 And Will Be Publicly Opened And Read At 3:30 PM.

CONTRA COSTA COMMUNITY COLLEGE 500 Court St, Martinez, CA 94553

OFFICE OF PROCUREMENT COOLING TOWER REPLACEMENT, CT BUILDING RFP NO.: RFP OPENING DATE: APRIL 16, 3:00 PM ADDENDUM #4.

THE CITY OF MT. PLEASANT, MICHIGAN

Memphis Housing Authority Capital Improvements Department 700 Adams Street, Room 107 Memphis, Tennessee

ADDITIONS, RENOVATIONS AND IMPROVEMENTS AT BEAUREGARD HIGH SCHOOL FOR THE LEE COUNTY BOARD OF EDUCATION OPELIKA, ALABAMA

REROOFING THE CAREER TECHNICAL SCHOOL FOR THE CLEBURNE COUNTY BOARD OF EDUCATION HEFLIN, ALABAMA

ADDENDUM TWO. Peoria Park District ADDENDUM NO. 2 Planning, Design and Construction Department 1314 N. Park Road PROJECT TITLE: Asbestos Abatement


ADDENDUM NO. 2 Page 1 of 13

A D D E N D U M N O. 4

ADDENDUM NO. B. TO THE BID DOCUMENTS, dated 1/5/16 FOR THE

DOCUMENT BID FORM - STIPULATED SUM (MULTIPLE-PRIME CONTRACTS) Bidder:.

ADDENDUM TO INVITATION FOR BIDS Fieldbrook Elementary School District Proposition 39 HVAC Upgrade Project Bid No Addendum #1 May 17, 2017

Peralta Community College District th Avenue Oakland, California Phone (510) Fax (510) Purchasing Department

2. Clarification: The building address is 801 Henderson Street.

ADDENDUM #1 MARCH 10, CENTRAL WINDS PARK ROADWAY IMPROVEMENTS Bid # ITB-02/16/BF

Document Bid Form (General Contract) State of Ohio Standard Requirements for Public Facility Construction

ADDENDUM NO. 1 FOR CITY OF CUMMING 900-HP RAW WATER INTAKE PUMP. ADDENDUM DATE: February 10, BID DATE: February 15, 2017, 11:30 a.m.

JEFCO GYM HVAC ADDITIONS TO ARCHITECT'S NO AES, BES, CES, PGES, SRES B.C. NO

BID PROPOSAL FOR TOWN OF HIGHLAND PARK, TEXAS FOR

FORRENCE RECREATION CENTER ROOF REPLACEMENT

Construction Contract Basics

1. Meeting minutes from the pre-bid conference are attached for inclusion in the Bid Documents.

The purpose of this addendum is to respond to RFI s submitted to the County and issue a revised SECTION BID FORM.

REQUEST FOR PROPOSAL (RFP) No.: J-19 PRECONSTRUCTION AND CONSTRUCTION SERVICES, MEDIUM VOLTAGE SUBSTATION REPLACEMENT, LAS POSITAS COLLEGE

SAN JOSE / EVERGREEN COMMUNITY COLLEGE DISTRICT DOCUMENT BID PROPOSAL

Bidding Conditions. March 22, (Project# 0192) at the. Fresno Chaffee Zoo. Project : Warthog Exhibit. Located at. 894 West Belmont Avenue

Dayton Metropolitan Housing Authority Rosemont/Hoch Electrical Upgrades

ADDENDUM NO. 3 REQUEST FOR PROPOSALS HANGAR 1610/1612 FIRE SUPPRESSION RETROFIT PROJECT

ADDENDUM NO. 3. Item 3 NOTICE OF OPPORTUNITY - REPLACE in its entirety with the attached ***REVISED 08/03/2018

August 19, Addendum No. 2 Roosevelt Hall Interior Renovation Brooklyn College Project No.: BY

PORTLAND COMMUNITY COLLEGE SW 49 th Avenue Portland, Oregon ADDENDUM NO. 4

A D D E N D U M. REPLACE: Project Summary with attached revised Project Summary. 1 Specification Section Project Summary

REVISED BID FORM WILLIAM PATERSON UNIVERSITY OF NEW JERSEY. PROJECT NAME: Renovations & Addition to Hunziker Hall & Wing

ADDENDUM #001 Date: March 21, 2019

WINDOW REPLACEMENT FOR ARCHITECT'S NO NORWOOD ELEMENTARY SCHOOL. A. Project Name: Window Replacement for Norwood Elementary School.

TRIAD ENGINEERING CONSULTANTS, INC.

ADDENDUM NO. 3 February 28, 2017

The following revisions supersede previous information and become a part of the Contract Documents by this issue. PROJECT MANUAL / SPECIFICATIONS

Project Location: 2220 E. League City Parkway, League City, Texas 77573

SAN ANTONIO WATER SYSTEM DOS RIOS WATER RECYCLING CENTER (DRWRC) DIGESTER MIXING AND SYSTEM ENHANCEMENTS - PHASE 1

STANTEC ARCHITECTURE ARCHITECTS PLANNERS ENGINEERS 3001 Bee Caves Road Suite 300 Austin, TX April 29, 2016

ADDENDUM NO. 1 FOR RENOVATIONS TO LINCOLN ANIMAL SHELTER RFP # February 1, 2018

SAN ANTONIO WATER SYSTEM University Pump Station Improvements Project SAWS Job No Solicitation No. B DD

AG Permit Set Addendum #03 Addendum Date: 9/26/2016

BID PROPOSAL FOR TOWN OF HIGHLAND PARK, TEXAS FOR 2014 WATER MAIN AND SEWER MAIN REPLACEMENT IN EASEMENTS

707 Minnesota Ave., Suite 506 Kansas City, Kansas Tel Fax

Chilled Water Plant Improvements Project Solicitation Number: CO Job No.: ADDENDUM 2 February 9, 2016

John Barton Architect, LLC

ADDENDUM #1 AUGUST 25, INTERSECTION IMPROVEMENTS AT SR 434 AND TUSCORA DRIVE Bid # ITB-06/16/BF

ADVERTISEMENT TO BID PARTIAL

DOCUMENT BID PROPOSAL

PROPOSAL AND BID FORM (Submit in triplicate)

CITY OF MARSHALL, MINNESOTA

I INVITATION TO BID City of Fort Morgan Water Distribution Department Waterline Isolation Project

Sample. Bid Proposal. Not Valid for Use

SAN FRANCISCO UNIFIED SCHOOL DISTRICT FACILITIES, DESIGN AND CONSTRUCTION ADDENDUM NO. 1

PROJECT MANUAL for Phantom Canyon Tunnel Repair Project. Location On Fremont County Road miles North of Intersection US Highway 50 with FCR 67

#2 Daniel Drive O Fallon, Missouri BaalmanArchitects.com

Union Fire District Tower Hill Fire Station Addition & Renovations

Transcription:

T S G TSG Architects AIA 427 Saint George, Suite 300 Gonzales, Texas 78629 8 3 0. 6 7 2. 7 8 0 1 8 3 0. 6 7 2. 4 3 4 0 f a x Member of the American Institute of Architects To: All Approved Contractors / Interested Parties Re: ADDENDUM #1 Project: Burton ISD Rock Building Renovation Date: April 9, 2015 Include the following adjustments and/or clarifications to the Plans & Specifications: SPECIFICATIONS: 1. SECTION 00 4200 PROPOSAL FORM a. Refer to attached revised proposal form. DRAWINGS: 2. SHEET A0.1 DEMOLITION PLAN b. Refer to MEP sheets for demolition of all existing MEP items. 3. MISC MEP: c. (see attached MEP narrative and revised M sheets) End Addendum #1 Page 1 of 12 page(s) (including this page) 5

DIVISION 0 00 4200 1 of 3 SECTION 00 4200 PROPOSAL FORM (as revised 4-9-15) To: ALL APPROVED OFFERORS Project: Date: Submitted by:. (full name and address).... (Fill-in blanks) 1. BASE PROPOSAL Having examined the Place of The Work and all matters referred to in the Instructions to Offerors, Bid Documents and Contract Documents prepared by the Architect for the above mentioned project, we the undersigned, hereby offer to furnish all materials, labor, tools, and equipment to complete this project, and propose to enter into a Contract to perform the work for the Contract Sum of: dollars $ 00 in lawful money of the United States of America. 2. ACCEPTANCE We have examined the site and the Contract Documents and in submitting this proposal we agree to the following: - This offer shall be open to acceptance and is irrevocable for forty-five (45) days from the proposal closing date. - A Bid Bond as required by the Instructions to Offerors and Performance and Labor Bond is included as specified. - A contingency allowance as specified in Section 00 2110 is included in the Contract Amount. - All applicable taxes are exempt upon certification by Burton ISD. - We shall commence work immediately of receipt of Notice to Proceed by Burton ISD. - We shall furnish the required bonds and insurance within seven (7) days of receipt of Notice of Award in the form described in Supplementary Conditions. - All permits shall be delivered through the Contractor. - To accomplish all work in accordance with the Contract Documents. TSG Architects AIA Burton ISD Rock Building Renovation

DIVISION 0 00 4200 2 of 3 If this proposal is accepted within the time stated, and we fail to commence the Work or we fail to provide the required Bond(s), the security deposit shall be forfeited as damages to the Owner by reason of our failure, limited in amount to the lesser of the face value of the security deposit or the difference between this proposal and the proposal upon which the Contract is signed. 3. PROPOSAL ALTERNATES Provide the following prices for the alternates listed below. If accepted by the Owner selected alternates will be added or deducted from the base proposal amount. 1. DELETE new wood stage flooring and sub-flooring as shown on drawings and as specified. Existing stage flooring shall remain. New added stage area shall match existing and entire stage to be re-finished to match what was existing. DEDUCT...... dollars ($)......00 2. ADD an extended warranty for the 15 ton Carrier unit. Contact JB & Associates at www.jbandassociates.biz. ADD...... dollars ($)......00 4. UNIT PRICES Concrete Sidewalks: Provide unit cost for additional sidewalks as described in the construction documents for Owner s discretion to delete or add to other locations. a.) $ per square foot 5. CONTRACT TIME If this proposal is accepted, we will: Complete the Work in consecutive calendar days from Notice to Proceed. Liquidated damages for days beyond proposed days indicated will be as set forth in 800.9.8 of the Supplemental Conditions or as otherwise agreed at contract signing. 6. ALLOWANCES (S) Provide an allowance for the following item(s) which will be included in the contractor s base proposal amount. A. Contingency as stated in Section 00 2110. 7. ADDENDA The following Addenda have been received. The modifications to the Contract Documents noted therein have been considered and all costs thereto are included in the Proposal Sum. Addendum No. Dated Addendum No. Dated Addendum No. Dated TSG Architects AIA Burton ISD Rock Building Renovation

DIVISION 0 00 4200 3 of 3 The lowest three (3) proposers in base bid amount must submit their complete proposed subcontractor list no later than twenty-four (24) hours after bid date. PROPOSAL FORM SIGNATURES The Corporate Seal of (Offeror - please print the full name of your Proprietorship, Partnership or Corporation) was hereunto affixed in the presence of: (Authorized signing officer Title) (Seal) If the proposal is a joint venture or partnership, add additional forms of execution for each member of the joint venture in the appropriate form or forms as above. END OF PROPOSAL FORM TSG Architects AIA Burton ISD Rock Building Renovation

Burton ISD Rock Building Project Addendum #1 MEP NARRATIVE 1. The 25 ton unit was show on the schedule utilizing the ARI values for reference. 2. Verify exact location of stage lighting prior to mounting. 3. The Condensing units shall be provided with low ambient controls, evaporator defrost control as required to allow operation down to 0F ambient, anti short cycle relay, timed off control, hail guards, and 5 year compressor warranty. 4. The contractor shall determine the exact lengths of the refrigerant lines required and submit to the manufacturer for required sizing of the refrigerant piping. 5. The contractor shall install the equipment and refrigerant piping per the manufacturer s recommended installation instructions. 6. In order to accomplish defrost control the Motormaster component KAAFT0101AAA or HH18HB031 must be utilized in order for the defrost control option to function properly. 7. Provide hail guard(s) for all exterior equipment component number 38ap 900 002. 8. Provide any and all other components as recommended by the equipment manufacturer for proper operation of the equipment. 9. Commercial equipment from Carrier has 1 year parts warranty from date of installation or 18 months from date of shipment from the factory, whichever is the first to occur. The compressor has a 5 year warranty. 10. Provide separate cost as indicated on revised bid form for extended warranty for commercial Carrier systems over 15 tons.

Project No.: Date: 03/26/15 Dwn: EEIII 14-0801 Chk: MCB No. Description Date SYMBOLS & ABBREVIATIONS

Project No.: Date: 03/26/15 Dwn: EEIII 14-0801 Chk: MCB No. Description Date GENERAL NOTES & SPECIFICATIONS

201 Project No.: Date: 03/26/15 Dwn: EEIII 14-0801 Chk: MCB No. Description Date PLAN - DEMOLITION

ROOM 200 201 CLASSROOM 112 CLASSROOM 113 CLASSROOM 111 CLASSROOM 114 LIFT ROOM 104 AUDITORIUM 103 CLASSROOM 110 ELECTRICAL ROOM 118 IT 102 HALLWAY 109 VESTIBULE 117 COUNSELOR 115 STORAGE 116 WOMEN'S R.R. 108 MEN'S R.R. 107 FOYER 100 N.I.C. STAGE 105 N UN ACCESSIBLE AREA 106 STORAGE RM 101 Date: 03/26/15 Dwn: EEIII Chk: MCB Project No.: 14-0801 No. Description Date PLAN - NEW

Date: 03/26/15 Dwn: EEIII Chk: MCB Project No.: 14-0801 No. Description SCHEDULES Date

Project No.: Date: 03/26/15 Dwn: EEIII 14-0801 Chk: MCB No. Description Date DETAILS

Project No.: Date: 03/26/15 Dwn: EEIII 14-0801 Chk: MCB No. Description Date DETAILS