Planning & Scheduling

Similar documents
6 PROJECT TIME MANAGEMENT

Week 5 Project Work Plan

Network Diagram 11/10/2016 WORK BREAKDOWN STRUCTURE (WBS)

Project Time Management

Project Management in Practice Fifth Edition

Scheduling. Adapted from John Musser

Project Time Management

Developing a Project Plan

CIPRIANI COLLEGE OF LABOUR & CO-OPERATIVE STUDIES BSC IN PROJECT MANAGEMENT PRM 135: PROPOSAL DEVELOPMENT & COSTING WEEK 8

PMP Exam Preparation Course Project Time Management

Constructing Networks

PMP EXAMINATION PREP CHAPTER 6 SCHEDULE MANAGEMENT. PMP Exam Prep

Time has the least. amount of flexibility; Schedule issues are the main reason for

Estimating Project Schedule-Time and Cost

For the PMP Exam using PMBOK Guide 5 th Edition. PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc.

Project Scheduling: Lagging, Crashing and Activity Networks

Artificial Intelligence

Project Scope Management

Week 5 Project Work Plan

Week 5 Project Work Plan

Cambridge International AS & A Level Computer Science

Project Time Management

IST 302 : Project Time Management

Week 5 Project Work Plan

Information Technology Project Management, Seventh Edition

Work Analysis and Design

Project Planning & CPM Scheduling using MS Project. APWA NorCal 2018 Annual Conference

Operations Management

Software Project Management

MGT/437. Project Management. Session #2 University of Phoenix 02/12/2004 Brian Smithson. 02/12/2004 MGT/437 #2 -- Brian Smithson 1

MnDOT Project Management Office Presents: Risk Management. Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc.

Lecture 7 PROJECT SCHEDULING. Ferdinand Fassa

ENGINEERING MANAGEMENT (GE

Introduction. Project Scheduling. Morgan State University ARCH 738: REAL ESTATE PROJECT MANAGEMENT. Jason E. Charalambides, PhD, M.

Luis R. Garcilaso March 13, Lecture #22. Service Processes & Systems Dept. of Mechanical Engineering - Engineering Mechanics

Time Management PLANNING

Global Project Management, LLC

Modern Systems Analysis and Design Seventh Edition

PROJECT TIME PLANNING. Process and Bar Chart Technique

Index. Backup plans for presentations, Backward pass, 55 59, 72 73, 102. Saleh Mubarak

GLOSSARY AND INDEX. Glossary Index Project Management Institute, 130 South State Road, Upper Darby, PA USA 155

PLANNING & SCHEDULING

PROJECT TIME MANAGEMENT

MnDOT Project Management Office Presents: Impact Schedules. Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc.

12/26/2013. Sharif University of Technology. Session#11. Instructor. Class time. Course evaluation. International Campus Kish

PDM. Precedence Diagramming Method (PDM) Part 1. Finish to Start (FS) PDM. Finish to Start (FS) (cont.) Start to Start (SS) Con E 441 P05

Operations Management, 11e (Heizer/Render) Chapter 3 Project Management. Section 1 The Importance of Project Management

CE2353-CONSTRUCTION PLANNING & SCHEDULING

MBP1133 Project Management Framework Prepared by Dr Khairul Anuar

A New Networking Technique The Beeline Diagramming Method Seon-Gyoo Kim

The recommended guided learning hours for this unit are 30 hours.

Views and Layouts for Program Management

Project Management THE MANAGERIAL PROCESS

Information Technology Audit & Cyber Security

THE PMP EXAM PREP COURSE

GPE engineering project management. Project Management in an Engineering Context

What Should an Owner Do With the Contractor s Schedules? Seminar for the FEFPA Ted Trauner Trauner Consulting Services, Inc.

Construction Scheduling and Estimating

Planning & scheduling

Lecture- 11. Project Scheduling. Dronacharya College of Engineering

Topic # 12. CIS Project Management: an overview

Chapter-7# Project Controlling and Scheduling

Project Management Professional (PMP) Exam Prep Course 6 - Project Schedule Management

Scheduling Resources and Costs

Team Member Application

SECTION CONSTRUCTION PROGRESS DOCUMENTATION

CHAPTER 1. Basic Concepts on Planning and Scheduling

RESOURCE MANAGEMENT. Dr. Ahmed Elyamany

Project Management. Learning Objectives. What are Projects? Dr. Richard Jerz. Describe or Explain:

Project Management. Dr. Richard Jerz rjerz.com

Chapter 3 Managing the Information Systems Project

Estimating and Scheduling

Project Management PSGLE 122. Time and Resources

East Central College

MBH1123 Project Scope, Time and Cost Management Prepared by Dr Khairul Anuar. Lecture 6b Project Time Management - II

Examinations for Semester I / 2014 Semester II

BA /14/2010. PSU Problem Solving Process. The Last Step 5. The Last Step 8. Project Management Questions PLAN IMPLEMENT EVALUATE

Project Forecast Survey Results Good Scheduling Practices June 2016

A D-A1I CRITICAL PATH METHOD NETNORKS AND THEIR USE IN CLAIMS 1/2 ANALYSIS(U) FLORIDA UNIV GAINESVILLE M J PATTERSON usi FE 1984

Software Process and Management

BUTE Department of Construction Management and Technology

Lecture- 10. Project Scheduling. Dronacharya College of Engineering

The Project Planning Process Group

Program Evaluation and Review Technique (PERT)

Geog 469 GIS Workshop. Project Management

Chapter 5 Project Scheduling. (Source: Pressman, R. Software Engineering: A Practitioner s Approach. McGraw-Hill,

EFFICIENCY OF CRITICAL PATH METHOD (CPM) AND PERT TECHNIQUE FOR YACHT CONSTRUCTION

PERT and CPM S K Mondal Chapter 5. Time (4) To Calculate ES. To Calculate LS 34, 32 = 34. ES = max ES + t ; ES + t = max 15, 21 = 21

Calculating and Using Float

Prepared by: Mr.M.SYED SHAHUL HAMEED CHAPTER 3 SYSTEMS PLANNING - MANAGING SYSTEMS PROJECTS

Introduction to Project Management

PROJECT PLANNING AND SCHEDULING

Seminar 6: Project Management Part 1 Semester 1, 2005

Calculating and Using Float

Seminar 6: Project Management Part 1 Semester 1, 2005

SCSD2613 System Analysis and Design. PART II: Project Planning Process

Project Management Glossary of Terms

Design Process & Project Management AN ITERATIVE DESIGN PROCESS. Prof Picone, Mississippi State University. Test Verification

CPM in Construction Management transition from 7 th to 8 th Edition. James J. O Brien Fredric L. Plotnick

1.Which of the items listed below is not one of the software engineering layers?

Transcription:

Planning & Scheduling Dr. Nabil I. El Sawalhi Assistant Professor of Construction Management Chapter 3 1

Planning Successful Project Management depends on continues planning. The activities of Designers, Manufacturer, Suppliers & Contractors and all their resources have to be organized & integrated to meet the project objectives. Purpose of Planning: To persuade people to perform before delaying other people involved in the project activities. To provide a framework for decision making in the event of change. 2

Activity/Tasks Activities consume resources (materials, labor, Time, Equipment) which are the productive aspects of the project. Sequence of activities will be linked on a time scale to ensure that priorities are identified. It should be expected that a plan will change. Plans must be updated quickly and regularly. The plan should be simple and flexible to be understood & updated quickly 3

Six Methods of Scheduling Activity On Arrow (AOA) Activity On Node (AON) GANTT Chart (Bar Chart) Line of Balance Program Evaluation & Review Technique (PERT) Simulation (Mont-Carlo) 4

Networks AON Network Activity On Node AOA Network Activity On Arrow 5

Critical path method (CPM) CPM critical path method identifies those chains of activities in the project that control how long the project will take. the critical path can be defined as the longest possible path through the "network" of project activities There are two variations of CPM The traditional technique is called activity-on-arrow (Aon-A), or an arrow diagram, because the activities are represented in the network as arrows or lines. The alternative approach is activity-on-node (A-on-N); it s also called the precedence diagram. 6

Activity-on-arrow (A-on-A)/activityon- Node (A-on-N) Diagrams Activity-on- Node (A-on-N) Diagram have the following advantages on Arrow diagram: Flexibility since logic is defined in two stages. Dummy activities are eliminated. Revision and introduction of new activities is simple. Overlapping and delaying of activities is easily defined. Use of pre-printed sheets is possible. 7

Example 1. Set of Project Activities and Precedence use AON Task Predecessor a -- b -- c d e f g a b b c, d e 8

Stage 1 of AON Network 9

Stage 2 of AON Network 10

A Completed AON Network 11

Stage 1 of AOA Network 12

Stage 2 of AOA Network 13

A Completed AOA Network 14

A Completed AOA Network Using a Dummy Task 15

Example 2. Find the Critical Path and Critical Time Activity Predecessor Duration a -- 5 days b -- 4 c a 3 d a 4 e a 6 f b, c 4 g d 5 h d, e 6 i f 6 j g, h 4 16

Stage 1 of AON Network 17

Complete Network 18

Float Float is a period of time that will be used to adjust the timing of activity to obtain best possible use of resources. Total Float: is the difference between activities earliest and latest starts or finishes. Free Float: is the min difference between the earliest finish time of that activity and the earliest start time of the succeeding activity. 19

Start and finish Early Start (ES): the earliest time that an activity can start as determined by the latest of the early finish of all immediately preceding activities. Early finish (EF): The earliest time that an activity can finish. It is determined by adding the duration of the activity to the early start of the activity. Late Finish(LF): the latest time that an activity can be finished without dealying the project. Late Start (LS): the latest time that an activity can start without delaying the project completion. It is determined by subtracting the duration from the late finish of the activity. 20

Precedent notation Early Start(ES) Late Start (LS) Total Float (TF) Activity Name Duration(D) Early Finish (EF) Late Finish(LF) 21

Logical relationships between activities Four logical relationship do exist: Finish to start (FS):the successor task can t start until the predecessor task finishes. Start-to-Finish (SF): the successor task cannot finish until the predecessor task starts. Start-to-Start (SS): the successor can t start until the predecessor starts. Finish-to-Finish (FF) : the successor task can t finish until the predecessor task finishes. 22

Activities that have different early and late start times (i.e., ES(i,j) < LS(i,j)) can be scheduled to start anytime between ES(i,j) and LS(i,j) The concept of float is to use part or all of this allowable range to schedule an activity without delaying the completion of the project if E(i) + D ij < L(j), then some float is available in which to schedule this activity. 23

if one activity is allowed to float or change in the schedule, then the amount of float available for other activities may decrease 24

Example 25

Example Construct a precedence diagram assuming no research restrictions and calculate the minimum duration of project. Schedule the earliest and latest start and finish for each activity and show the critical path method. If activity F is extended to a duration of 15 days, what is the effect on critical path 26

27

Precedence diagram 28

Traditional Statistics Versus Simulation Similarities must enumerate alternate paths Differences simulation does not require assumption of path independence 29