Accelerated Bridge Construction (ABC) webinar Thursday, October 24, 2013 ABC Center at Florida International University (FIU) presents

Similar documents
Accelerated and Innovative Bridge Construction In Washington State

Bonner Bridge Replacement Update:

New Development in Accelerated Bridge Design and Construction in WA

SIBLEY POND DESIGN-BUILD BRIDGE REPLACEMENT ROUTE 2 CANAAN/PITTSFIELD, MAINE

Rt. 15/29 (SBL) Bridge Superstructure Replacement and Roadway Widening

I-70 over SR 121 Bridge Slide Construction and Engineering

Ironton Russell Bridge Project

Structural Lightweight Concrete for Accelerated Bridge Construction

Well Road Project Accelerated Bridge Construction Using Self-Propelled Modular Transporters (SPMT s) By: Mark Bucci, P.E.

APPENDIX G WHITTIER BRIDGE TYPE STUDY EVALUATION OF BRIDGE ALTERNATIVES

Ironton Russell Bridge Project

August 4, 2015; 11:00am-noon (MST)

Ironton Russell Bridge Project

Design and Construction of the SH58 Ramp A Flyover Bridge over IH70. Gregg A. Reese, PE, CE, Summit Engineering Group, Inc.

SR 0136-G10 ABC BRIDGE REPLACEMENT in Eighty Four, PA

NSBA. Prize Bridge. Awards

Boeing North Bridge in Washington State

Accelerated Bridge Construction Award

Steve Haines, P.E., Parsons, (303) , James Studer, Kiewit, (926) ,

Ironton Russell Bridge Project

Accelerated Bridge Construction (ABC)

Ironton Russell Bridge Project

Ironton Russell Bridge Project

SIBLEY POND DESIGN-BUILD BRIDGE REPLACEMENT PROJECT ROUTE 2, CANAAN/PITTSFIELD, MAINE

St. Anthony Falls I-35W Bridge Replacement. ASHE National Conference June 13, Dustin Thomas, P.E. I-35W Bridge Construction Engineer

West Virginia s First ABC Deck Replacement Project Bill Manuel & Johann Aakre HNTB Corporation

Prestressed Concrete Girder Continuity Connection

Ironton Russell Bridge Project

Fort (M-85) Street Bascule Bridge

SHRP 2 - R04 Innovative Bridge Designs for Rapid Renewal

ABC Techniques for Rapid Bridge Replacement. Bala Sivakumar HNTB Corporation. Purdue Road School 2017

BRIDGE CONSTRUCTION USING SELF-PROPELLED MODULAR TRANSPORTERS (SPMT)

Introduction.» Demolition Concepts» Concept Design» Final Design» Construction» Health Monitoring

Boeing North Bridge: Lessons Learned in Accelerated Bridge Construction

Bridge Development Update

Innovative Bridge Designs in Colorado by Pete Chomsrimake, P.E. ABC Project SME, CDOT Staff Bridge

DESIGN AND ANALYSIS OF PRECAST CONCRETE BRIDGES IN AREAS OF HIGH OR MODERATE SEISMICITY

Ironton Russell Bridge Project

PHASING CONSIDERATIONS FOR BRIDGES

KEYWORDS: Barge Stability, Steel Truss Erection, Horizontal Sliding of Steel Trusses

Northeast Extreme Tee (NEXT) Beam with Rochester VT Case Study

BRIDGE STANDARD PLANS AND SPECIAL DETAILS ADAM LANCASTER, P.E. FEB. 27, 2018

1/26/2015 DETAILS CIP DETAIL EXAMPLES WHY SIMPLIFY DETAILS? CIP DETAIL EXAMPLES DETAILING FOR SIMPLICITY

SUMMARY SHEETS OF INTEGRAL CONNECTIONS

Bijan Khaleghi, Ph, D. P.E., S.E.

Accelerated Bridge Construction in USA

Design & Seismic Detailing of Nonstandard Deep Precast Concrete Box Girders For Long Span Railroad Bridges By:

Accelerated Bridge Construction (ABC) National Status

STRUCTURES INSPECTION CERTIFICATION TRAINING COURSE

Northeast Bridge Preservation Partnership Meeting

SOUTH MEDFORD INTERCHANGE BRIDGES

ASCE STRUCTURAL ENGINEERING CONFERENCE. Ames Iowa

Presented by: Taya Retterer BRG Webinar July 30, 2012

CONCRETE SPLICED GIRDERS IN TEXAS. Nicholas Nemec, P.E. TxDOT-BRG

AGENDA AGENDA. Route 15/29 SBL Bridge Superstructure Replacement & Widening. NOVA District. Bridge Views SCOPE. Existing Structure.

7 Bridges in 74 Days. NC 12 Detour

PROJECT UPDATE SOUTH NORFOLK JORDAN BRIDGE CITIES OF PORTSMOUTH AND CHESAPEAKE, VIRGINIA. April 2012

MARTA Rapid Transit Bridges

Seismic Performance of Precast Concrete Bents used for Accelerated Bridge Construction. Bijan Khaleghi 1

John James Audubon Bridge

PRECAST CONCRETE GIRDER ERECTION

REHABILITATION PACKAGE 4-a

ABC in Nevada PBES/ABC Practices in Nevada Past, Present and Future. Nevada Department of Transportation

Long Key Bridge, a spectacular example. Design Features and Prestressing Aspects of Long Key Bridge

MIDAS Civil 2016 v2.1 Release Webinar. PSC Composite Design Check / Load rating

RESILIENT INFRASTRUCTURE June 1 4, 2016

Title Page: Modeling & Load Rating of Two Bridges Designed with AASHTO and Florida I-Beam Girders

Jane Addams Memorial Tollway (I 90) Fox River Bridge Traffic Needs Drive Innovative Solutions

SINGLE STEEL BOX GIRDER BRIDGES FOR THE TERMINAL DEVELOPMENT PROJECT AT TORONTO PEARSON INTERNATIONAL AIRPORT. Srdjan Brasic, M.Sc., P.Eng.

The Pennsylvania Rapid Bridge Replacement Project

ABC Technology and Steel Bridges

Get In, Get Out, Stay Out!

CHEF MENTEUR BRIDGE REPLACEMENT

An Overview of the SIBC Process and Projects. Presented By: Rebecca Nix, SE Michael Arens, SE Michael Baker International February 2015

US-131 Over the Muskegon River. Corey Rogers, P.E. Bridge Construction Engineer

Highway Bridge Structure Components

Nancy Daubenberger, MnDOT Assistant Commissioner Engineering Services

NEWINGTON-DOVER WELCOME

SUNSHINE SKYWAY BRIDGE

ABC, FHWA SHRP2 R04: Project update, lessons learned. Finn Hubbard, Fish & Associates Inc. SHRP2 ABC/PBES Implementation Technical Lead

SR 7 Emergency Bridge Repairs During Design

EGCE 406: Bridge Design

MICHIGAN DEPARTMENT OF TRANSPORTATION BRIDGE DESIGN GUIDES TABLE OF CONTENTS

Grade Separation Systems. Single-Span Rail Bridge Construction Procedure. An innovation from art engineering inc.

Critical Structures Construction Issues

COMMONWEALTH OF PENNSYLVANIA DEPARTMENT OF TRANSPORTATION BUREAU OF DESIGN

ATHABASCA RIVER BRIDGE REHABILITATION PROJECT

Launching Bridges in to the Future. CBDG Annual Conference. Simon Bourne Managing Director. 26 June 2008

Applications of Ultra High Performance Concrete and Prefabricated Concrete Elements in Accelerated Bridge Construction

PUBLIC INFORMATION MEETING June 24, 2015

MIDAS Training Series

Dan Carrier Parsons Brinckerhoff Project Manager Cooper River Bridge Charleston, South Carolina

Replacing the Aging US 52 Mississippi River Bridge

Oatman Highway at Sacramento Wash Crossing Federal Aid No. 000-MMO-0(216)T ADOT Project No MO MMO T C

Accelerated Bridge Strengthening using UHP(FR)C

Concrete Bridge Design and Construction series

ACCELERATED BRIDGE CONSTRUCTION IN WASHINGTON STATE FROM RESEARCH TO PRACTICE

John James Audubon Bridge. Introduction

CONSTRUCTION MANAGER S WEEKLY PROGRESS REPORT From 06/04/2017 to 06/10/2017

Innovative Fisheries Protection for MassDOT Design-Build Projects. Frank Welch Resident Engineer MassDOT District 4 Construction

Transcription:

Accelerated Bridge Construction (ABC) webinar Thursday, October 24, 2013 ABC Center at Florida International University (FIU) presents Washington State s Skagit River Bridge Emergency Slide Bijan Khaleghi khalegb@wsdot.wa.gov Washington State s Skagit River Bridge Acknowledgement: FHWA Wash. DC, and WA Division WSDOT: HQ, Region, Bridge Office Design Build Team-Permanent Bridge: Max Kuney Construction Parsons Brinkerhoff Omega Morgan Girder Fabrication: Concrete. Tech Corp. 1

I-5 - Skagit River Bridge Collapse Truss Collapse, I-5 near Mount Vernon on May 23 Over height load struck critical steel supports. I-5 carries ADT = 71,000 only north/south interstate in WA I-5 - Skagit River Bridge Collapse NTSB Coordination Demolition of a collapsed structure 2

I-5 - Skagit River Bridge Collapse Span 8 of 12 Span Structure (4 of 4 Truss Span) Span Length, L=160 Pavement To Water Surface ~ 45 Roadway Width = 57 (2 Lanes Each Direction) Emergency Response WSP coordinated with WSDOT for detours Demolition of a collapsed structure Planning and launching a Temporary bridge Design coordination WSDOT-Atkinson- Temporary Bridge 3

Emergency and Final Bridge Replacement Phase #1 Temporary Span Emergency Repair Inspection of remaining trusses and piers Removal of collapsed span Phase #2 Permanent Span ABC Replace the temporary bridges with a permanent span Minimize the detour impacts Phase #3 Rehab. of Remaining Trusses General Project Timeline May 23- Bridge collapses Phase #1: -Atkinson Temporary Bridge Temporary Bridge - May 24- June 19 Phase #2: Max Kuney, PB, Omega Morgan Permanent Bridge - June 19 September 14 Phase #3: DBB Contract Rehabilitation of Remaining truss spans in Progress 4

Existing Piers Support for Temporary and Permanent Span Structure Existing Piers to Support: Temporary Span Permanent span replacement Limitations: Support Dimensions o Width o depth Weight Limitation 915 kips/support Temporary Span Incremental Launching Temporary Span: 2 11 ft Lanes NB and SB lanes, 1 ft. shoulders, 40 mph speed limit 5

Phase 2 - Permanent Span Decision to use emergency Design-Build contract with accelerated RFP process. Two Week Procurement Awarded on A+B+C = Best Value approach. A = # of hours of total closure for span placement x $660k/day B = Days past Sept 4 th x $50k C = Price Proposal Scheduled open to traffic Sept. 5 th with 12 hour total closure Phase 2 - Permanent Span Replacement Four Proposals: 1. Concrete Girders - precast concrete W59DG Deck Bulb Tee girders. 2. Concrete Girders - lightweight W65DG girders with an improved closure detail between adjacent girders 3. Steel Girders - six 6 ft six foot deep steel-3.5" precast stay in place deck panels with a 5" cast in place overlay plate girders. 4. Steel Girders- 5-65 deep plate girders with CIP slab Best value award $6.9M. to Max J Kuney/PB team Notice Proceed issued June 19th 6

Permanent Span WSDOT Commitment WSDOT obtained all environmental permits WSDOT obtained all ROW, detour agreements, street use, etc. WSDOT arranged for transfer of Temporary Bridge lease from Atkinson to WSDOT to DB WSDOT takes the lead on Public Information with DB support 13 Span Replacement Skidding Options Option 1: Construct on Land Roll in via I-5 Option 2: Construct over Water Float in on Barge Skid in on Beam Float in on barges 7

Superstructure Design Alternatives Concrete Girders: Conventional girders Precast or CIP deck Deck Bulb Tee Girders Steel Girders: Conventional girders Precast or CIP decks Others: Truss Repair, etc. Concrete Girder Alternatives Advantages: Shorter fabrication time Ability to control schedule Conventional construction Limitations: Total weight < 915 tons Girder weight for Shipping and erection Girder Type High ADT 8

Steel Girder Alternatives Advantages: Limitations: Lower span weight Lower girder weight Fewer beam lines Conventional construction Fabrication time Plate Availability Schedule Fabricator on critical path Selected Proposal: Concrete DBT Girder DBT Superstructure Features: Skidding Conventional bearing locations Temporary support at intermediate diaphragms Beam spacing accommodates pedestals Meet the superstructure depth limitation 9

Lightweight Concrete Superstructure DBT Girders: Source: Stalite N.C ½ max, 10% Absorption Weight Unit: 122pcf Concrete, 133pcf Girder Concrete Mix Design: CTC 9 ksi LWC mix Material Testing: CR, SH, E (Test Data Available) Diaphragms and Traffic Barriers : LWC, compressive strength= 4.0 ksi Closures: o Normal Weight Concrte o Overlapping Headed Bars Staggered to avoid conflict Date, time and initials of last edit 19 LWC Precast Girder Fabrication Replacement Span: First WSDOT lightweight girder Full moment girder-to-girder connection Span designed to be lifted 20 from ends 10

Precast Girder Erection Two temporary bents Twelve 24 ɸ pipe piles Approx. 50 about mud-line Lightweight Girder Camber Camber Challenges: Span to depth ratio = 29.5 48-0.6 strands Predicted camber= 5.5 Higher Measured Camber Precamber forms 4.375 Vertical profile 1.5 Camber Adjustment Concrete Overlay 11

Deck Closure, Barrier and Diaphragm Modified Concrete Deck Overlay WSDOT Type 2 Deck Protection System 1½ Modified Concrete Overlay cure Time: 42 hours deck temperature between 45 F - 75 F wind speed less than 10 mph 12

Superstructure Skidding Details Skidding: Push and reset system 2 x 150 M-tons Jacks (one on each side) Total Lateral Move: 75 ft Skidding over Tracks on both sides Skid Beams with Clad Stainless Steel sheets Support Beams with Teflon Surface Skidding System Features 13

Skid Tracks Details Located 20 from each end Avoids conflict - temporary piles and existing piers 56-24 ɸ pipe piles Temporary Bents - Features Heavy Trussed Beams Span 77 Under Temp span Pile clusters to support main span/conflict 50 high above mudline 14

Superstructure Skidding Details Permanent span moved 30 above final Position 4-150 M-tons Jacks one at each corner for vertical deck movement to final position 24 Jacking stoke for vertical movement Skid Track Details Clad Stainless Steel Teflon Surface 3 alignment tolerance 15

Skidding Support Skidding Support Four point support Transition across skid beams Temporary Bents for Span Sliding Pedestals for: Temporary Bridge Support Permanent Bridge Bearings 16

Permanent Span Skid Summary Temporary Piles Temporary Piers Permanent Span Temporary Piers Temporary Span Permanent Span Erection Next Steps Span Slides Permanent Span Completion Move bridge Scheme Move Complete - Disassembling Open to Traffic Temp Pile Remove 17

Sliding High over Girder Stops Lowering Span to final position 18

Bridge Move Summary: 19 Hours Road Closure 7 pm Saturday September 14 th 2 pm Sunday September 15 th Bridge Move Summary: 1. Temporary Span out (25 min.) 2. Permanent Span in (45 min.) 3. Deck Lowering (30 min.) Permanent Span Completion 19

Permanent Span Time Lapse Skagit River Bridge Switchover_mpeg2video.mpg Available on WSDOT Bridge and Structure Website: This Webinar Time Lapse Video of Temporary Span Placement Time Lapse Video of Girder Erection Time Lapse Video of Bridge Slide Skagit River Showcase Presentations Other WSDOT ABC Projects and Research Reports http://wwwi.wsdot.wa.gov/eesc/bridge/abc/ Max Kuney President Max J. Kuney Co. max@maxkuney.com Patrick Fuller WSDOT Region Project Construction Engineer FulleP@wsdot.wa.go v Contact Information Chris Vanek Structural Engineer Parsons Brinckerhoff vanekcm@pbworld.com Derek Case WSDOT Bridge Construction Office DB Manager CaseD@wsdot.wa. gov Ralph DiCaprio Chief Engineer Omega Morgan Ralph.dicaprio@ omegamorgan.com Steve Seguirant CTC Vice President Girder Fabrication sseguirant@concret etech.com Bijan Khaleghi WSDOT Bridge and Structures Office khalegb@wsdot.wa.gov 20

Completed Bridge September 15 th Questions? Bijan Khaleghi WSDOT Bridge and Structures Office khalegb@wsdot.wa.gov Time Lapse Videos Collision 51 sec. Temporary Bridge 1:17 Girder Erection 59 sec. Switchover 1:27 Skagit River Bridge collapse footage.mp4 I-5 Skagit River Bridge ACROW Time-Lapse.mp4 girderstimelapse.wmv Skagit River Bridge Switchover_mpeg2video.mpg Date, time and initials of last edit 42 21