June 1, Dear Mr. Simpson:

Similar documents
GRADING, EROSION AND SEDIMENTATION CONTROL

ROVER PIPELINE LLC. Rover Pipeline Project HORIZONTAL DIRECTIONAL DRILL CONTINGENCY PLAN

ROVER PIPELINE LLC. Rover Pipeline Project HORIZONTAL DIRECTIONAL DRILL CONTINGENCY PLAN

Response: Eastern Shore will require additional permanent easement and temporary workspace (TWS) in the following municipalities:

FEDERAL ENERGY REGULATORY COMMISSION FIELD INSPECTION REPORT

November 16, 2017 Via Electronic Filing

The compliance monitors are responsible for reviewing NEXUS s construction and documenting compliance with the FERC Certificate.

BLOCKING AND FILLING SURFACE DRAINAGE DITCHES

1. All underground utilities under railroad tracks shall be encased in a larger pipe or conduit called the casing pipe.

The compliance monitors are responsible for reviewing NEXUS s construction and documenting compliance with the FERC Certificate.

MINNEHAHA CREEK WATERSHED DISTRICT BOARD OF MANAGERS REVISIONS PURSUANT TO MINNESOTA STATUTES 103D.341. Adopted April 24, 2014 Effective June 6, 2014

Town of Friday Harbor PO Box 219 / Friday Harbor / WA / (360) / fax (360) /

HDD Training. Mitigation. Mark Miller, PE Jon Robison, PE

Erosion & Sedimentation Control Policy

DRAFT SEDIMENT and EROSION CONTROL PLAN. BLUE LAKE HYDROELECTRIC PROJECT (FERC No. 2230) EXPANSION. Prepared by:

Maine s Land Use Regulations and Erosion Control Techniques

Phase II: Proposed (regulated) Impervious in disturbed area (ac) Long Lake Existing Impervious in disturbed area (ac)

Appendix 14-I Description of Stream Crossing for Electrical Interconnect

Quintillion Subsea Project Applicant Proposed Mitigation Statement

Pipeline CSI. Compliance Review Overview. Compliance Review. Pipeline Compliance Surveillance Initiative (CSI) abralliance.org pipelineupdate.


E. STORMWATER MANAGEMENT

January 2, Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C Attention: Ms. Kimberly D.

APPENDIX P -2 TRENCHLESS ANALYSIS

Lyon Creek Cedar Way Stormwater Detention Dam Operation and Maintenance Manual

Pipeline CSI. Aerial Photo Review. Pipeline Compliance Surveillance Initiative (CSI) abralliance.org pipelineupdate.

Short-term (Construction) Impacts and Potential Mitigation

NEW CASTLE CONSERVATION DISTRICT. through. (Name of Municipality) PLAN REVIEW APPLICATION DRAINAGE, STORMWATER MANAGEMENT, EROSION & SEDIMENT CONTROL

Operating and Reclamation Plan

Appendix A Stormwater Site Plan Report Short Form

FEDERAL ENERGY REGULATORY COMMISSION FIELD INSPECTION REPORT

Warren Wagon Road Improvement Project McCall Ranger District, Payette National Forest Project Description

The Construction General Permit and Erosion Prevention and Sedimentation Control

and Timber Removal Plan Updated, Rev. 1

CHARLES SOIL CONSERVATION DISTRICT COMPLIANCE AGREEMENT FOR THE STANDARD EROSION AND SEDIMENT CONTROL PLAN FOR FOREST HARVEST OPERATIONS

CEAA ENVIRONMENTAL ENVIRONMENTAL IMPACT ASSESSMENT AMBASSADOR BRIDGE ENHANCEMENT PROJECT. Replacement Span and Plaza Expansion APPENDIX E

Information for File # KAL

SITE C FIELD WORK FOR 2019

Details of the Proposed Action

Checklist for Joint Agency Review Stormwater Management / Erosion and Sediment Control

The Manitoba Water Services Board SECTION Standard Construction Specifications September 2013 Page 1 of 8

WETLAND AND WATERBODY CONSTRUCTION AND MITIGATION PROCEDURES

WETLAND AND WATERBODY CONSTRUCTION AND MITIGATION PROCEDURES

SOUTH BRANCH SUBWATERSHED

Attachment C Applicant s Proposed Mitigation Statement Alaska DOT&PF Northern Region Pilot Station Airport Relocation Project POA

Step 1. Determine if a Small Utility GESC Permit is Applicable and if a Project Specific GESC Plan is Required.

TEMPORARY STREAM DIVERSION

Kobe Pumping Plant and Pipeline Project Narrative UPDATED 6/28/13

Storm Water Permitting Requirements for Construction Activities. John Mathews Storm Water Program Manager Division of Surface Water

204 - EXCAVATION AND BACKFILL FOR STRUCTURES SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES. Granular Backfill (Wingwalls) (Set Price)

Transcontinental Gas Pipe Line Company, LLC. Response to Technical Deficiency Pennsylvania Department of Environmental Protection

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING)

File No Supplemental November Geotechnical and Environmental Consulting Engineers

October 2016 CDRPC Workshop

Blue Book Update Overview

STATE OF VERMONT PUBLIC SERVICE BOARD PREFILED TESTIMONY AND EXHIBITS OF IAN A. JEWKES

Boardman River Townships Project EAST BAY TOWNSHIP. WATER QUALITY ACTION PLAN Fall 2009

6 Preliminary Assessment of Construction Method and Constructability Issues

Common Construction-Site BMPs Quick Reference Guide

FEDERAL ENERGY REGULATORY COMMISSION FIELD INSPECTION REPORT

CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING

SECTION 10: WETLANDS PROTECTION

Stormwater Erosion Control & Post-Construction Plans (Stormwater Quality Plans)

March 14,2014. Please contact me at (716) , if you have any questions concerning this matter.

WELCOME TO THE CONSTRUCTION STORMWATER PERMIT WEBINAR

Erosion Control Inspection Form

GRADING PERMIT APPLICATION

Municipal Stormwater Management Plan Prepared For The Borough of Cape May Point By Van Note-Harvey Associates VNH File No.

STANDARD GRADING AND SOIL EROSION & SEDIMENT CONTROL PLAN FOR SINGLE LOT SINGLE FAMILY RESIDENTIAL CONSTRUCTION AND MINOR EARTH DISTURBANCES

SPECIAL CONDITIONS FOR HORIZONTAL AUGER BORING (HAB) October, 2006

Construction Inspection Checklists

General Construction

TOWN OF BETHLEHEM SWPPP APPLICATION REVIEW CHECKLIST

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING)

Briefing to House Environmental Matters Committee February 9, Robert M. Summers, Ph.D. Acting Secretary Maryland Department of the Environment

Section 8 Minimum Horizontal and Vertical Setback Distances

Riparian Buffer Requirements. Department of Environmental Protection Bureau of Watershed Management

BASIS OF REVIEW SITE PLAN REVIEW

Permit Application: Soil Erosion and Sediment Control Program

CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING

Larimer County Land Use Code Section 5.8: Rural Land Use Process

3.2 INFILTRATION TRENCH

SILT FENCE FLOW CHECK

McElroy s Run Impoundment Structural Stability Assessment Report

CON APPENDIX C USAG HI Storm Water Pollution Prevention Plan Content Review Checklist

The compliance monitors are responsible for reviewing NEXUS s construction and documenting compliance with the FERC Certificate.

NDDOT Erosion & Sediment Control Construction Course

By Mark Gallagher Princeton Hydro LLC. From FERC Leidy Line EA

STAFF REPORT FOR POLICY PLAN AMENDMENT S10-CW-1CP

15A NCAC 02B.0238 NEUSE RIVER BASIN-NUTRIENT SENSITIVE WATERS MANAGEMENT STRATEGY: AGRICULTURAL NITROGEN REDUCTION STRATEGY The following

VALLEY LATERAL PROJECT. RESOURCE REPORT 1 General Project Description. FERC Docket No. CP

GUIDE TO THE DEVELOPMENT OF A MINING AND RECLAMATION PLAN IN NEW BRUNSWICK

FORM B: DAMMING AND DIVERSION OF WATER

Best Management Practice (BMP) Guidance Manual

3.10 Hydrology and Water Quality. Environmental Setting

TORCH LAKE TOWNSHIP WATER QUALITY ACTION PLAN

TOWN OF MANCHESTER PLANNING AND ZONING COMMISSION Subdivision Application Minimum Submission Requirements

STATE OF MISSOURI CLEAN WATER ACT SECTION 401 WATER QUALITY CERTIFICATION 2012 GENERAL AND SPECIFIC CONDITIONS

NEW YORK STATE DEPARTMENT OF ENVIRONMENTAL CONSERVATION

Direct Pipe Installations underneath USACE Levees Keeping Permitted Minimum Hydraulic Fracture Factor of Safety

Transcription:

10 Main Street Suite 321 New Paltz, NY 12561 T 845.255.0210 F 845.256.8110 www.willinghamengineering.com 1 June 1, 2016 Mr. Philip T. Simpson Robinson Brog Leinwand Greene Genovese & Gluck, P.C. 875 Third Avenue New York, NY 10022 Re: Atlantic Bridge Project - Environmental Assessment Impacts to Lands of Almar, LLC. Town of Yorktown, New York Engineering & Environmental Impact Review Dear Mr. Simpson: As you know, our firm has been retained by Almar LLC ( Almar ), an intervenor in this proceeding, concerning the Environmental Assessment for the proposed Atlantic Bridge Project ( Project ) dated May 2, 2016. Almar is gravely concerned with the potential impacts of the Atlantic Bridge pipeline installation proposed directly through its lands. We have conducted a detailed review of the Project s Environmental Assessment, prepared by the Federal Energy Regulatory Commission ( FERC ), and have determined that indeed, substantial long term impacts to the Almar property are likely forthcoming if the project is executed. We are submitting our comments to you on behalf of our client Almar, for inclusion in your submission to FERC, thereby becoming part of the Project s public comment record. Almar Property Setting Almar owns two adjacent parcels totaling 82.8 acres identified as Section-Block-Lot 26.1-1-3 and 26.1-1-5 in the Town of Yorktown, New York. The land contains three homes, additional buildings, a large & productive, established garden, and a recreational pond that is also the source of a tributary to the Hunter Brook which feeds the Croton Reservoir and indeed, also supplies New York City with potable water. Algonquin Gas Transmission, LLC ( Algonquin ) has an existing rightof-way, approximately 75 feet in width, extending 1,900 +/- feet in length through the Almar property. The right-of-way, established in the early 1950 s, contains existing 30-inch and a 26-inch diameter gas pipelines. The right-of-way and associated gas lines run generally west-to-east from Stoney Street, through the Almar property, through the adjacent property to the north, and under the Taconic Parkway.

The areas on the Almar property proposed to be disturbed by the Project are highly sensitive in several regards. The areas contain large expanses of New York State Department of Environmental Conservation ( NYSDEC ) regulated forested and emergent wetlands, many of which are located on steep slopes (15-25%). The area to be impacted also includes three separate cold water spring-fed tributaries to the Hunter Brook, classified by the NYSDEC as suitable for trout spawning. The Almar property and proposed disturbance are fully located in the Croton Reservoir watershed, a drinking water supply serving 8.5 million people and regulated by the New York City Department of Environmental Conservation ( NYCDEP ). Proposed Project Despite the unique environmental qualities and highly sensitive setting, the Environmental Assessment describes a massive industrial operation that will have extensive impacts to the wetlands, streams and steep slopes of the Almar property. Algonquin has chosen the Almar property to propose the staging of a Horizontal Directional Drilling ( HDD ) operation, a process with widespread multi-faceted impacts. First, the steeply sloped, largely forested, NYSDEC regulated wetland area in the western portion of the Almar property (Pipe Station 2+60 11+00) is proposed to stage long sections of 42 diameter gas pipe to be welded on site in preparation for the HDD installation. Specifically, as we understand, approximately 4 800 foot long pipe sections, set side by side at 35 feet apart are proposed to be welded in this sensitive area. The existing 75 foot wide right of way is almost completely disregarded. The proposed width of the Area of Temporary Workspace ( ATWS ) adjacent to Stoney Street is 230 feet in width, and averages approximately 180 feet in width in this area. Second, the base of the hill on the Almar property (Pipe Station 11+00 17+50) is proposed to contain the HDD entry/exit point and full HDD installation operation. The 75 right of way is again disregarded by the Applicant, with an average ATWS width of 190 feet in this area. Although the documents are shockingly silent in this regard, we understand this area is proposed for the HDD boring and receiving pit, HDD hydraulic fluid dewatering pit, spoils stockpiling, roadways, and parking/maneuvering areas to support the HDD operation. The vast majority of the work is within NYSDEC regulated wetlands, with multiple crossings of Hunter Brook Tributaries. Lack of Detail and Failed Assessment of Environmental Impacts Although the documents submitted by the Applicant are voluminous, they are highly general in nature and grossly inadequate with regard to site-specific details. The Project s Erosion & Sediment Control Plan ( E&SCP ) contains generic information about practices for controlling sediment and erosion on the site. A Stormwater Pollution Prevention Plan, which will be required by the NYSDEC, has not been completed to date. Substantial erosion and stormwater control measures will need to be implemented on the Almar property to avoid potential catastrophic impacts to the steeply sloped wetland areas. However, the project documents include no 2

particular locations for any erosion control measures or stormwater control measures. Without any project specific measures proposed, the impacts associated with erosion and sediment control cannot be assessed. A generic description of erosion and sediment control measures is wholly insufficient. Similarly, specific methods of crossing the substantial areas of wetlands and multiple stream crossings on the Almar property are absent from the documentation. Again, generic methods for crossings are discussed, but no specific plans for implementation. The impacts to the wetlands and streams cannot be assessed with no indication of specific means and methods. The specific process and configuration of the HDD operation is completely absent from the project documentation. From our conversations with the Applicant s representatives, the HDD operation will include an extensive road system to transport equipment and materials, large areas for staging and welding HDD pipe sections, a parking/maneuvering area adjacent to the HDD boring hole, and areas to be cleared to allow maneuvering of the cranes that will support the large pipe sections during HDD installation. We also understand that there will be a large boring entry/exit hole and extensive dewatering operations associated with HDD. None of this information is indicated on the project documents. The Alignment Sheets simply show the limits of work, with no indication of the location or configuration of any of these operations. The limits of work are significantly wider than the designated 75 foot wide right-of-way and wider than the majority of pipeline work proposed in this project. However, the need for this addition area on the Almar property has not been demonstrated, since the specific elements of the operation have not been defined. The impacts of this project and justification for the inordinately large construction areas on the Almar property cannot be determined without this information. During the environmental review of land development projects, it is common for an Applicant to specify site-specific mitigation measures and construction methods to verify that impacts are mitigated. Alternatively, this Applicant has provided generic information that can apply to virtually any pipeline project. Accordingly, the environmental impacts cannot be determined. Impacts to Wetlands & Streams As discussed above, the vast majority of the ATWS on the Almar Property is located directly in wetlands, wetlands buffers and streams. Significantly, of the total of 9.21 acres of impacted wetland resulting from the Atlantic Bridge Project, 3.09 acres are located on the Almar Property. And more significantly, of the total of 1.68 acres of forested wetland to be impacted by the Project, 1.47 acres are located on the Almar Property. Although the Applicant refers to the impacts as temporary, the effects will be long term. Per page 2-24 of the Environmental Assessment ( EA ), In forested wetlands, the impact from 3

construction would be temporary but long term and may take 20 years or longer for the wetland forests on temporary rights-of-way to regenerate. Whether this Project is enormous or in this case, small in scope only 4 miles Almar is entitled to a substantive and detailed review given the enormity of the usage proposed for its lands. Many of the wetlands to be disturbed are on steeply sloped areas (15-25%). These wetlands are seepage wetlands, where the water table seeps to the surface and allows the wetland to exist in sloped areas. The vegetation is critical in maintaining the stability of the slope due to the steepness and presence of a high water table. The removal of trees and brush will compromise the slope stability. The EA indicates that emergent wetlands regenerate quickly. However the long term placement of timber mats and/or vehicle compaction over emergent wetland areas will certainly cause short term lack of vegetation. During this period, the wetland slopes will be highly susceptible to erosion. The project information is general in nature in describing how this impact will be mitigated, and does not include any site-specific measures. Page 2-24 of the Environmental Assessment indicates Pipe fabrication would occur outside the wetland in an approved upland ATWS. This is in fact not the case. As we understand, pipe fabrication is proposed directly within wetlands on the Almar property. As detailed in the Bagdon Environmental report, the high quality, cold water, spring-fed streams located directly within the ATWS area are less than 30 feet from the HDD entry/exit point. The streams are highly sensitive to impacts from sediment erosion. Impacts to these Class C(t) streams would severely effect suitability for trout spawning. Erosion is also a major contributor of phosphorus, which is the main contaminant of concern for the Croton Reservoir watershed. There are no specific plans to revegetate the forest, forested wetland, emergent wetland and meadow areas on the Almar property. The EA discusses a general plan to plant trees in disturbed forested areas, but does not include a planting plan or any specific landscaping mitigation. Trench excavation in wetlands may cause inadvertent draining of the adjacent wetlands and waterbodies. The EA does not consider these potential impacts and does not require wetland/stream monitoring to ensure that the water source remains intact and uncompromised post construction. HDD Drilling Impacts The following issues are associated with the proposed HDD operation on the Almar property: 4

1. The general construction sequence for HDD is not described in detail. The EA does not describe in necessary detail the sequence of work for HDD, such as the direction of work, equipment and materials used, size of the boring/receiving pits (if any), size of the drilled hole, volume of soil/rock removed, soil/rock disposal methods and locations, water supply/processing/recycling for cooling/drilling fluids, excavation dewatering, and pipe installation operation (welding, pulling, annular grouting). As such, the full extent of the potential impacts are unknown and the proposed limits of construction/disturbance and associated impacts are not justified in the EA. 2. Page 2-19 of the EA states that "in the event that there are construction issues with the HDD crossing method, they would [...] attempt the HDD crossing using an alignment that would be slightly offset from the initial crossing location. In the event that a second HDD crossing were to prove unsuccessful Algonquin would use a conventional bore method or hand tunneling method." An offset alignment or different construction method may have significantly different impacts to the environment and property owners. The EA does not evaluate all potential outcomes or other construction methods such as micro tunneling. 3. The EA should specify the proposed direction of boring/pipe installation (i.e. clarify whether the proposed entry/exit point on the Almar property will be for boring or receiving). The EA should indicate if multiple passes of the boring are anticipated (e.g. at increasing diameters at each pass) 4. The specific impacts at both the boring pit and the receiving pit (i.e. stored materials, equipment, staging area, stockpiled soil, drilling fluid, dewatering, etc.) must be identified. The size and depth of the pits would be dependent upon the equipment being used, boring depth, pipe length and pipe diameter. The EA does not specify the size and depth of the proposed pits. The lack of detailed or specific information prevents any meaningful assessment of these impacts. 5. Page 2-18 of the EA discusses potential inadvertent discharge of hydraulic HDD fluid - the fact that the HDD entry and exit holes are far from the creek. would minimize the risk of an in advertent return into the stream. However, the HDD entry/exit on the Almar property is less than 30 feet from a Hunter Brook Tributary and less than 30 feet from a NYSDEC designated wetland. That distance can in no way be considered far from the creek. 6. The size of the boring/receiving pit is not shown, and therefore the wetland/stream impacts are not known. There are no requirements in the EA to minimize the size of the boring/receiving pits to minimize disturbance to wetlands by installing excavation protection systems (i.e. sheet piles). 7. If sheet piles are proposed, the EA should specify the acceptable methods used to install sheeting. Hydraulic impact hammers, which often spray diesel/oil when used, should be avoided, especially near environmentally sensitive areas. 8. Despite the close proximity of the ATWS to the dam (impounding the recreational pond) on the Almar property, the impacts to the dam as a result of the adjacent site work, HDD drilling operation and sheet pile drilling has not been discussed. 9. The EA does not specify whether bentonite slurry or grout will be used to fill the annular space between the pipe and drilled hole and how the slurry/grout will be installed. 5