FEDERAL ENERGY REGULATORY COMMISSION FIELD INSPECTION REPORT

Size: px
Start display at page:

Download "FEDERAL ENERGY REGULATORY COMMISSION FIELD INSPECTION REPORT"

Transcription

1 FIELD INSPECTION REPORT Date May 22, 2018 Project Northern Natural Gas Company Cedar Station Upgrade Project Dakota County, Minnesota Authority: Sections 7(c) Personnel FERC Staff: Company Staff: S. Xiah Kragie Terry Plucker, Trevor Poland, John Baus Jr. Inspection Summary 0 Problem Areas 0 Noncompliances No No Follow-Up Letter Required Refer to Enforcement Introduction On May 22, 2018, S. Xiah Kragie of the Federal Energy Regulatory Commission (FERC or Commission) performed a construction inspection of the Northern Natural Gas Company (Northern) Cedar Station Upgrade Project (Project), under contract to the FERC and per the request of the FERC Project Manager, David Hanobic. The Project consists of the construction and operation of an approximately 7.8-mile-long, 20-inchdiameter natural gas pipeline loop 1 and appurtenant facilities in Dakota County, Minnesota. More specifically, the Project includes the: construction of an approximately 7.86-mile-long, 20-inch-diameter natural gas pipeline that will loop Northern s existing lateral pipeline, originating at Northern s existing Rosemount Junction facility in Rosemount, Minnesota, and extending to its existing Cedar Station in Eagan, Minnesota (Cedar Station Upgrade); construction of a pig launcher 2 and takeoff valve setting at Station Number (Sta. No.) 0+00 within the existing Rosemount Junction facility; 1 A pipeline loop is a segment of pipe installed parallel to an existing pipeline. 2 A pig is a tool that moves through the pipeline, and is used for cleaning, internal inspections, or other purposes. A launcher/receiver is an aboveground structure used to install/retrieve pigs from the pipeline.

2 construction of a pig receiver, tie-in valve setting, and modifications to existing regulators within the existing Cedar Station facility near Sta. No of Northern s existing lateral pipeline; replacement of a 10-foot-long segment of existing 12-inch-diameter pipeline with the same size and diameter pipeline; and replacement of approximately 105 feet of existing 8-inch-diameter bypass pipeline with approximately 260 feet of new 10-inch-diameter pipeline, both within the Cedar Station, to facilitate tie-ins of the new pipeline to existing station piping. Northern states that this Project will not add any new service. The anticipated in-service date for the entire Project is September 1, The purpose of the inspection was to determine Northern s compliance with the environmental conditions of the Commission s August 22, 2017 Order Issuing Certificate and to inspect the construction conditions of the pipeline right-of-way (ROW) and other Project facilities. The findings of the inspection were that no instances of noncompliance or problem areas were identified. A site map and photographic record are presented in this report. Inspection On May 22, 2018, weather conditions were partly cloudy with temperatures ranging in the mid-70s ( F). A total of approximately 1.4 inches of rain was recorded during the two weeks preceding the inspection, including approximately 1.1 inches of rain recorded on May 9, The inspection began at Northern s existing Cedar Station at the Project s terminus, and ended near Northern s existing Rosemount Junction facility and a Project staging area (Photo Numbers [Nos.] 1 to 20). Construction, including grading and site work, had begun at most of the horizontal directional drill (HDD) crossing entry and exit sites (Photo Nos. 2 to 4, 6 to 8, 10 to 12, 14 to 16, 18, and 19). Active drilling operations were underway along the HDD #1, #3, #4, and #9 crossings. Northern stated that conventional open trench construction had not begun yet, and clearing between Sta. No and Sta. No , near a school, was delayed until the end of the school year. One inadvertent release of drilling mud was observed near the HDD #3 exit site at Sta. No (Photo No. 15). Northern estimated that approximately 175 gallons of drilling mud were released just outside the ROW limits. Hand tools and a vac truck were being used to contain and clean-up the spill. Where grading of the HDD sites was complete, topsoil was properly segregated and seeded, but not growing or well established, yet. Silt fences and other erosion control devices (ECDs) were installed, as needed. Sound walls were also installed at most of the HDD drill sites to mitigate noise impacts at proximate residences or commercial properties (Photo Nos. 4, 8, 11, 12, 14, 16, and 18). A cursory check of noise loudness on either side of a sound wall at the HDD #4 entry site demonstrated a reduction in noise levels from 75 dba 3 to 61 dba. The closest residence impacted by HDD noise was at the combined HDD #1 and HDD #2 entry site near Sta. No (Photo No. 18), where noise just outside the wall was measured at 69 dba during drilling operations. With the exception of HDD pipe 3 dba is the A-weighted decibel value of sound.

3 pullback activities, Northern stated that it limited drilling activity to normal construction hours (7am to 7pm). Pipe segments were being delivered to the staging areas and readied for HDD pullback; the HDD pullback pipe for HDD #1 and HDD #14 were already welded (Photo Nos. 2 and 19). At Cedar Station, limited trees were cleared, and the locations of existing pipelines were physically confirmed by hydrovac excavation and marking those existing underground lines every 50 feet. Northern stated that all hydrovac spoils were taken to holding tanks at the staging area for testing before disposal. At three locations along the ROW, Northern temporarily changed the contours of the existing ground surface, cutting and filling slopes to create a safe, level surface to work from. These occurred at Sta. No (Photo No. 6), at Sta. No in Lebanon Hills Park (Photo No. 11), and at Sta. No (Photo No. 17). In all cases, Northern committed to restoring the ROW contours. Overall, ECDs were properly installed and maintained along the ROW and at resource crossings, where necessary; and equipment mats and/or gravel were installed to stabilize staging areas and construction entrances. No tracking of mud or debris onto public roadways was observed (Photo Nos. 2 to 5, 7 to 18, and 20). Conclusions and Recommendations A follow-up letter is not required at this time, because no instances of noncompliance were identified. Overall, construction was progressing acceptably, and no environmental concerns were identified. Another inspection is tentatively scheduled for the week of June 18, 2018.

4 FERC PDF (Unofficial) 06/27/2018 SITE MAP

5 Photo No.: 1 MP/Sta. No.: Direction: North Comments: Residential and Industrial ROW. Trees lining the existing Cedar Station were cleared in February, according to Northern. Limited ground disturbing activities were observed. Every 50 feet, existing pipelines were excavated by hydrovac and marked with story poles. Hydrovac spoils were taken to holding tanks at the staging area for testing before disposal, according to Northern. Photo No.: 2 MP/Sta. No.: Direction: North Comments: Residential and Commercial ROW, HDD #13 Entry Site, HDD #14 Exit Site, wetland/waterbody W-48. A doublerow of silt fence was installed along the adjacent stormwater management facility. Where the workspace was cut into the hill, orange exclusion fencing was installed for safety.

6 Photo No.: 3 MP/Sta. No.: Direction: South Comments: Residential and Commercial ROW, HDD #13 Entry Site, HDD #14 Exit Site. Visual screening trees were preserved along the residential road. Topsoil was graded and segregated from the HDD workspace was, and the topsoil stockpile was seeded; although the seed had not germinated, yet. Northern stated that a sound wall will be installed prior to drilling. Photo No.: 4 MP/Sta. No.: Direction: South Comments: Commercial and Highway ROW, HDD #13 Entry Site. Topsoil was graded and properly segregated from the HDD #13 drill site, Wetland W-41 A sound wall was installed between adjacent commercial properties and the ROW, and topsoil was stockpiled and seeded against sound wall. The wetland boundaries were marked, and silt fence was installed along the ROW limits. Inspection participants discussed reinforcing the silt fence at the lowest point of the workspace.

7 Photo No.: 5 MP/Sta. No.: Direction: West Comments: Forested ROW, Staging Area. The staging area was cleared. Northern stated that it planned to use less of the staging area than what was Certificated. Equipment mats were installed extensively to prevent trackout and create stable conditions for heavy machinery, according to Northern. Photo No.: 6 MP/Sta. No.: Direction: West Comments: Residential and Highway ROW, HDD #11 Entry Site, HDD #12 Exit Site. Topsoil was graded and properly segregated from the entire ROW in this area. The existing slope was graded by cutting and filling to create a safe, level surface for pipe stringing and HDD pullback pipe.

8 Photo No.: 7 MP/Sta. No.: Direction: Southeast Comments: Residential and Highway ROW, HDD #11 Entry Site, HDD #12 Exit Site. The drainage from the workspace leads to residential cul-de-sac, although no drainage was evident. Northern committed to utilize straw bales and install equipment mats at the construction entrance to reduce track out and sediment transfer to the residential road. Photo No.: 8 MP/Sta. No.: Direction: East Comments: Residential and Utility ROW, HDD #9 Entry Site, Staging Area. The orange exclusion fencing delineates the re-routed High Line (pedestrian) Trail next to the ROW. Topsoil was segregated from all workspaces and pipe was strung along the ROW. The HDD workspace was stabilized with equipment mats. Noise levels measured within the sound walls approximately 30 feet from the drilling rig were measured at 86 dba; but outside of the sound walls, ambient noise was dominated by audible traffic and overhead airplanes, instead.

9 Photo No.: 9 MP/Sta. No.: Direction: West Comments: Residential and Utility ROW. Orange exclusion fence was installed along the existing High Line Trail next to the ROW. No tracking of mud or debris onto the residential street was evident. Northern stated that it would extend the orange exclusion fence where the ROW abuts immediate backyards. Photo No.: 10 MP/Sta. No.: Direction: West Comments: Residential and Open ROW, HDD #8 Exit Site, wetland/waterbody W-30. An approximately 200-foot-long section of the ROW was left undisturbed between the HDD exit point and the wetland/waterbody crossing, except for silt fence that was installed along the edge of the ROW and wetland/waterbody crossing.

10 Photo No.: 11 MP/Sta. No.: Direction: East Comments: Open and Forested ROW, HDD #5 Entry Site, HDD #4 Exit Site, Lebanon Hills Park. Full topsoil segregation and substantial grading were conducted to create a stable, level workspace. Northern stated that spoil piles were seeded the week before the inspection; seed had not germinated, yet. Photo No.: 12 MP/Sta. No.: Direction: Southeast Comments: Open and Forested ROW, HDD #5 Entry Site, HDD #4 Exit Site, Lebanon Hills Park, Wetland around Buck Pond (W-26) The workspace was encircled with a double row of silt fences for sediment control and wildlife exclusion. Wetland boundaries were clearly labeled. Additional signage was installed for the environmentally sensitive resource. A sound wall is visible in the background.

11 Photo No.: 13 MP/Sta. No.: Direction: Northwest Comments: Residential ROW. Northern was hydrostatic pressure testing the existing mainline. Testing activities were being performed within the ROW limits. The ROW was cleared of topsoil; however, Northern s workspace were not appreciably distinct from the workspace for the new residential development construction. Photo No.: 14 MP/Sta. No.: Direction: Northwest Comments: Open and Residential ROW, HDD #4 Entry Site. Drilling operations were underway. Silt fence was installed along the workspace limits, and sound walls were installed to the southwest and northwest of drilling operations to mitigate noise for nearby residences. Noise measurements taken within the sound wall approximately 50 feet from the drill rig were 75 dba; but were 61 dba immediately outside the sound wall, representing a 14 dba reduction in noise levels.

12 Photo No.: 15 MP/Sta. No.: Direction: Southeast Comments: Open and Residential ROW, HDD #3 Exit Site. The HDD #3 exit site was approximately 650 feet from the HDD #4 entry site. During active drilling of HDD #4, noise levels were measured at dba at this distance (approximately 650 feet). In the background, a vacuum truck was parked at the edge of the workspace with a hose leading to a recent off-row inadvertent release of approximately 175 gallons of drilling mud from the HDD #3 crossing. Northern stated that hand tools were used to clean-up the spill and install a silt fence to contain the spill and protect the adjacent wetland/waterbody (Waterbody W- 20).

13 Photo No.: 16 MP/Sta. No.: Direction: West Comments: Residential Road ROW, HDD #3 Entry Site. Sound walls were installed between the HDD #3 drill site and residences directly to the south. Topsoil was properly segregated, and the site was stabilized with a combination of equipment mats and gravel to prevent rutting and the tracking of mud and debris onto the roadway. A spill kit was verified on site. Photo No.: 17 MP/Sta. No.: Direction: Southeast Comments: Residential ROW, Wetland W-07. The ROW was graded. Wetland spoils were segregated from topsoil, and silt fence was installed. Northern stated that it will install equipment mats along both the upland and wetland sides of the ROW during trenching. Northern also stated that it will install hay bales across the ROW at the wetland crossing when not actively crossing the ROW.

14 Photo No.: 18 MP/Sta. No.: Direction: Southeast Comments: Residential ROW, HDD #1 and HDD #2 Entry Sites. Sound walls were installed on three sides of the workspace to mitigate noise for nearby residences and an associated horse paddock. Noise was measured at 69 dba on the residence side of the sound wall during drilling, consistent with predictions. Drilling activity was limited to 7am to 7pm, according to Northern. Access along the existing driveway was maintained. Photo No.: 19 MP/Sta. No.: Direction: East Comments: Agricultural ROW. The Rosemont Junction facility (an industrial interconnect) is visible in the distance. The HDD #1 pullback pipe was welded in sections and staged at the edge of the staging area. The segregated topsoil piles had stabilizing annual grass growing. Silt fences were installed down gradient of the workspace.

15 Photo No.: 20 MP/Sta. No.: Direction: Northwest Comments: Open and Agricultural ROW, Staging Area. The topsoil from the agricultural field was graded within the staging area and properly segregated. A subsection of the staging area was graded but unused; all utilized areas were overlain with geotextile fabric and gravel.

16 Document Content(s) NNG Cedar Station CP DOCX

FEDERAL ENERGY REGULATORY COMMISSION FIELD INSPECTION REPORT

FEDERAL ENERGY REGULATORY COMMISSION FIELD INSPECTION REPORT FIELD INSPECTION REPORT Date June 19, 2018 Project Northern Natural Gas Company (Northern) Cedar Station Upgrade Project Dakota County, Minnesota Authority: Section 7(c) Personnel FERC Staff: Company Staff:

More information

FEDERAL ENERGY REGULATORY COMMISSION FIELD INSPECTION REPORT

FEDERAL ENERGY REGULATORY COMMISSION FIELD INSPECTION REPORT FIELD INSPECTION REPORT Date July 10 and 11, 2018 Project WBI Energy Transmission, Inc. Valley Expansion Project Clay County, Minnesota; and Cass County, North Dakota Authority: Section 7(c) Personnel

More information

/s/ Michael T. Loeffler. Michael T. Loeffler Senior Director, Certificates and External Affairs. Attachment. May 24, 2018.

/s/ Michael T. Loeffler. Michael T. Loeffler Senior Director, Certificates and External Affairs. Attachment. May 24, 2018. Northern Natural Gas Company P.O. Box 3330 Omaha, NE 68103-0330 402 398-7200 May 24, 2018 Via efiling Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington,

More information

FEDERAL ENERGY REGULATORY COMMISSION FIELD INSPECTION REPORT

FEDERAL ENERGY REGULATORY COMMISSION FIELD INSPECTION REPORT FIELD INSPECTION REPORT Date August 4, 2016 Project Transcontinental Gas Pipe Line Company, L.L.C./Sabine Pass Liquefaction, L.L.C. & Sabine Pass LNG, L.P. Gulf Trace Expansion Project Cameron, Calcasieu,

More information

/s/ Michael T. Loeffler. Michael T. Loeffler Senior Director, Certificates and External Affairs. Attachment. October 12, 2018.

/s/ Michael T. Loeffler. Michael T. Loeffler Senior Director, Certificates and External Affairs. Attachment. October 12, 2018. Northern Natural Gas Company P.O. Box 3330 Omaha, NE 68103-0330 402 398-7200 October 12, 2018 Via efiling Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington,

More information

/s/ Michael T. Loeffler. Michael T. Loeffler Senior Director, Certificates and External Affairs. Attachment. October 11, 2018.

/s/ Michael T. Loeffler. Michael T. Loeffler Senior Director, Certificates and External Affairs. Attachment. October 11, 2018. Northern Natural Gas Company P.O. Box 3330 Omaha, NE 68103-0330 402 398-7200 October 11, 2018 Via efiling Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington,

More information

/s/ Michael T. Loeffler. Michael T. Loeffler Senior Director, Certificates and External Affairs. Attachment. July 9, 2018.

/s/ Michael T. Loeffler. Michael T. Loeffler Senior Director, Certificates and External Affairs. Attachment. July 9, 2018. Northern Natural Gas Company P.O. Box 3330 Omaha, NE 68103-0330 402 398-7200 July 9, 2018 Via efiling Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington,

More information

/s/ Michael T. Loeffler. Michael T. Loeffler Senior Director, Certificates and External Affairs. Attachment. July 18, 2017.

/s/ Michael T. Loeffler. Michael T. Loeffler Senior Director, Certificates and External Affairs. Attachment. July 18, 2017. Northern Natural Gas Company P.O. Box 3330 Omaha, NE 68103-0330 402 398-7200 July 18, 2017 Via efiling Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington,

More information

The compliance monitors are responsible for reviewing NEXUS s construction and documenting compliance with the FERC Certificate.

The compliance monitors are responsible for reviewing NEXUS s construction and documenting compliance with the FERC Certificate. FEDERAL ENERGY REGULATORY COMMISSION ENVIRONMENTAL COMPLIANCE MONITORING PROGRAM WEEKLY SUMMARY REPORT NEXUS GAS TRANSMISSION PROJECT DOCKET NO.: CP16-22-000 FOR THE PERIOD: NOVEMBER 13 THROUGH NOVEMBER

More information

/s/ Michael T. Loeffler. Michael T. Loeffler Senior Director, Certificates and External Affairs. Attachment. November 15, 2018.

/s/ Michael T. Loeffler. Michael T. Loeffler Senior Director, Certificates and External Affairs. Attachment. November 15, 2018. Northern Natural Gas Company P.O. Box 3330 Omaha, NE 68103-0330 402 398-7200 November 15, 2018 Via efiling Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington,

More information

The compliance monitors are responsible for reviewing NEXUS s construction and documenting compliance with the FERC Certificate.

The compliance monitors are responsible for reviewing NEXUS s construction and documenting compliance with the FERC Certificate. FEDERAL ENERGY REGULATORY COMMISSION ENVIRONMENTAL COMPLIANCE MONITORING PROGRAM WEEKLY SUMMARY REPORT NEXUS GAS TRANSMISSION PROJECT DOCKET NO.: CP16-22-000 FOR THE PERIOD: MARCH 19 THROUGH MARCH 25,

More information

/s/ Michael T. Loeffler. Michael T. Loeffler Senior Director, Certificates and External Affairs. Attachment. May 31, 2017.

/s/ Michael T. Loeffler. Michael T. Loeffler Senior Director, Certificates and External Affairs. Attachment. May 31, 2017. Northern Natural Gas Company P.O. Box 3330 Omaha, NE 68103-0330 402 398-7200 May 31, 2017 Via efiling Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington,

More information

November 16, 2017 Via Electronic Filing

November 16, 2017 Via Electronic Filing 414 Nicollet Mall Minneapolis, MN 55401 November 16, 2017 Via Electronic Filing Daniel P. Wolf Executive Secretary Minnesota Public Utilities Commission 121 7 th Place East, Suite 350 St. Paul, MN 55101

More information

May 24, Via efiling. Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C.

May 24, Via efiling. Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. Northern Natural Gas Company P.O. Box 3330 Omaha, NE 68103-0330 402 398-7200 May 24, 2018 Via efiling Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington,

More information

The compliance monitors are responsible for reviewing NEXUS s construction and documenting compliance with the FERC Certificate.

The compliance monitors are responsible for reviewing NEXUS s construction and documenting compliance with the FERC Certificate. FEDERAL ENERGY REGULATORY COMMISSION ENVIRONMENTAL COMPLIANCE MONITORING PROGRAM WEEKLY SUMMARY REPORT NEXUS GAS TRANSMISSION PROJECT DOCKET NO.: CP16-22-000 FOR THE PERIOD: OCTOBER 23 THROUGH OCTOBER

More information

Rock Sock (RS) Rock Sock height.

Rock Sock (RS) Rock Sock height. Rock Sock (RS) SC-5 Description A rock sock is constructed of gravel that has been wrapped by wire mesh or a geotextile to form an elongated cylindrical filter. Rock socks are typically used either as

More information

January 2, Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C Attention: Ms. Kimberly D.

January 2, Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C Attention: Ms. Kimberly D. January 2, 2019 Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 Attention: Ms. Kimberly D. Bose, Secretary Re: El Paso Natural Gas Company, L.L.C.; Docket No. CP18-332-000;

More information

Information for File # KAL

Information for File # KAL Information for File # 2016-03711-KAL Applicant Corps Contact Enbridge Energy, Limited Partnership Kristoffer A. Laman Address 600 South Lake Avenue, Suite 211, Duluth, MN 55802 E-Mail Kristoffer.A.Laman@usace.army.mil

More information

UPDATE CONSTRUCTION ASKED AND ANSWERED: RESTORING AGRICULTURAL LAND. COMMUNITY BENEFITS Williams hiring veterans CONTACT ATLANTIC SUNRISE 310 SR 29 N

UPDATE CONSTRUCTION ASKED AND ANSWERED: RESTORING AGRICULTURAL LAND. COMMUNITY BENEFITS Williams hiring veterans CONTACT ATLANTIC SUNRISE 310 SR 29 N CONSTRUCTION UPDATE JUNE 2018 Nine months into our construction schedule, our crews are making safe, steady and environmentally responsible progress on activities such as backfilling, welding, coating,

More information

June 6, Via efiling. Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C.

June 6, Via efiling. Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. Northern Natural Gas Company P.O. Box 3330 Omaha, NE 68103-0330 402 398-7200 June 6, 2018 Via efiling Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington,

More information

Construction Best Management Practices Handbook BEST MANAGEMENT PRACTICES

Construction Best Management Practices Handbook BEST MANAGEMENT PRACTICES Construction Best Management Practices Handbook www.montereysea.org BEST MANAGEMENT PRACTICES 26 www.montereysea.org Construction Best Management Practices Handbook VEHICLE TRACKING AND DUST CONTROL IN

More information

Appendix 14-I Description of Stream Crossing for Electrical Interconnect

Appendix 14-I Description of Stream Crossing for Electrical Interconnect Appendix 14-I Description of Stream Crossing for Electrical Interconnect 14.0 Ecology Appendix 14-I CPV Valley Energy Project Description of Stream Crossing for Electrical Interconnect The CPV Valley Energy

More information

Soil Erosion and Sedimentation Control Application Packet 2011

Soil Erosion and Sedimentation Control Application Packet 2011 Soil Erosion and Sedimentation Control Application Packet 2011 The following items are required to apply for a Soil Erosion and Sedimentation Control permit for a construction project in Chippewa County:

More information

CORNERSTONE RIVER VALLEY VILLAGE FILING NO. 1 STORMWATER MANAGEMENT PLAN

CORNERSTONE RIVER VALLEY VILLAGE FILING NO. 1 STORMWATER MANAGEMENT PLAN CORNERSTONE RIVER VALLEY VILLAGE FILING NO. 1 STORMWATER MANAGEMENT PLAN SITUATED IN THE SW ¼ OF SECTION 18, T.2S., R.67W., OF THE 6 TH P.M. COUNTY OF ADAMS, STATE OF COLORADO PREPARED FOR: Thornton Cornerstone

More information

Response: Eastern Shore will require additional permanent easement and temporary workspace (TWS) in the following municipalities:

Response: Eastern Shore will require additional permanent easement and temporary workspace (TWS) in the following municipalities: 2. There are multiple properties throughout the Chester County portion of the 2017 Expansion Project area which contain preservation easements on them. Eastern Shore Natural Gas Company should be aware

More information

ADELPHIA GATEWAY PROJECT

ADELPHIA GATEWAY PROJECT ADELPHIA GATEWAY PROJECT RESOURCE REPORT NO. 10 Alternatives ADELPHIA GATEWAY PROJECT January 2018 SUMMARY OF FILING INFORMATION INFORMATION Data Sources a Found in Section To be Filed Minimum Requirements

More information

VISUAL SITE INSPECTION REPORT 2018

VISUAL SITE INSPECTION REPORT 2018 VISUAL SITE INSPECTION REPORT 2018 SOUTHERN INDIANA GAS AND ELECTRIC A. B. BROWN GENERATING STATION TYPE III RESTRICTED WASTE LANDFILL WEST FRANKLIN, IN ATC PROJECT NO. 170LF00614 January 9, 2019 PREPARED

More information

Enclosure 23 Revised Invasive Species Plan

Enclosure 23 Revised Invasive Species Plan ROVER PIPELINE, PANHANDLE BACKHAUL, AND TRUNKLINE BACKHAUL PROJECTS Implementation Plan Enclosure 23 Revised February 2017 ROVER PIPELINE PROJECT ROVER PIPELINE LLC Rover Pipeline Project September 2016

More information

Phase II: Proposed (regulated) Impervious in disturbed area (ac) Long Lake Existing Impervious in disturbed area (ac)

Phase II: Proposed (regulated) Impervious in disturbed area (ac) Long Lake Existing Impervious in disturbed area (ac) Permit Application No.: 17-181 Rules: Erosion Control, Wetland Protection, and Waterbody Crossings & Structures Applicant: Hennepin County Received: 4/27/17 Project: CSAH 112 Phase II Complete: 9/5/17

More information

City of Doral 8401 NW 53 rd Ter. Doral, FL 33166

City of Doral 8401 NW 53 rd Ter. Doral, FL 33166 City of Doral 8401 NW 53 rd Ter. Doral, FL 33166 Project Address: (305) 593-6700 Permit Number: National Pollution Discharge Elimination System (NPDES) Construction Site Erosion and Sedimentation Control

More information

CITY OF MILTON CONSTRUCTION NOTES

CITY OF MILTON CONSTRUCTION NOTES CITY OF MILTON CONSTRUCTION NOTES 1. Driveways shall be constructed of concrete and sloped per Georgia Highway standard 9031-J. Curb shall not be broken from gutter. Curb and gutter to be removed to existing

More information

Building Better Storm Water Quality

Building Better Storm Water Quality Building Better Storm Water Quality s Storm Water Pollution Prevention Guidelines for Development Construction Projects City of El Segundo 350 Main Street (310) 524-2380 El Segundo, California 90245 Introduction

More information

June 1, Dear Mr. Simpson:

June 1, Dear Mr. Simpson: 10 Main Street Suite 321 New Paltz, NY 12561 T 845.255.0210 F 845.256.8110 www.willinghamengineering.com 1 June 1, 2016 Mr. Philip T. Simpson Robinson Brog Leinwand Greene Genovese & Gluck, P.C. 875 Third

More information

SUMMARY OF PRE-CROSSING CONSTRUCTION PLANNING PROCESS

SUMMARY OF PRE-CROSSING CONSTRUCTION PLANNING PROCESS SUMMARY OF PRE-CROSSING CONSTRUCTION PLANNING PROCESS I. Introduction As requested by the New York State Department of Environmental Conservation ( DEC ) during a October 21, 2016 meeting with National

More information

January 23, Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, D.C

January 23, Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, D.C NEXUS GAS TRANSMISSION, LLC 5400 Westheimer Court Houston, TX 77056 January 23, 2018 Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, D.C. 20426 Re:,

More information

Constructability Guidelines

Constructability Guidelines Constructability Guidelines The Constructability Guidelines offer a list of items that should be considered by Constructability function personnel during the Concept Development Phase through the Final

More information

FERC PDF (Unofficial) 10/08/2014. Environmental Impact Statement ES-1 Corpus Christi LNG

FERC PDF (Unofficial) 10/08/2014. Environmental Impact Statement ES-1 Corpus Christi LNG EXECUTIVE SUMMARY The staff of the Federal Energy Regulatory Commission (FERC or Commission) prepared this Environmental Impact Statement (EIS) to assess the environmental issues associated with the construction

More information

October 25, Via efiling. Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C.

October 25, Via efiling. Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. Northern Natural Gas Company P.O. Box 3330 Omaha, NE 68103-0330 402 398-7200 October 25, 2018 Via efiling Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington,

More information

STATE OF MINNESOTA MINNESOTA POLLUTION CONTROL AGENCY FINDINGS OF FACT

STATE OF MINNESOTA MINNESOTA POLLUTION CONTROL AGENCY FINDINGS OF FACT STATE OF MINNESOTA MINNESOTA POLLUTION CONTROL AGENCY IN THE MATTER OF THE DECISION ON THE NEED FOR AN ENVIRONMENTAL IMPACT STATEMENT FOR THE PROPOSED METROPOLITAN COUNCIL ENVIRONMENTAL SERVICES ST. LOUIS

More information

VALLEY LATERAL PROJECT. RESOURCE REPORT 1 General Project Description. FERC Docket No. CP

VALLEY LATERAL PROJECT. RESOURCE REPORT 1 General Project Description. FERC Docket No. CP VALLEY LATERAL PROJECT RESOURCE REPORT 1 General Project Description FERC Docket No. CP16- -000 November 2015 Section TABLE OF CONTENTS Page 1.0 RESOURCE REPORT 1 GENERAL PROJECT DESCRIPTION... 1-1 1.1

More information

August 31, Via efiling. Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C.

August 31, Via efiling. Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. Northern Natural Gas Company P.O. Box 3330 Omaha, NE 68103-0330 402 398-7200 August 31, 2018 Via efiling Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington,

More information

Attachment C Applicant s Proposed Mitigation Statement Alaska DOT&PF Northern Region Pilot Station Airport Relocation Project POA

Attachment C Applicant s Proposed Mitigation Statement Alaska DOT&PF Northern Region Pilot Station Airport Relocation Project POA Attachment C Applicant s Proposed Mitigation Statement Alaska DOT&PF Northern Region Pilot Station Airport Relocation Project POA-2004-1223 Introduction This mitigation statement was prepared as an attachment

More information

Forest Recreation Management

Forest Recreation Management Forest Recreation Management 1 Forest Recreation Management Introduction...3 CONTENTS The Benefits of Guidelines...3 Considerations...4 Planning...5 Construction of Recreation Areas...6 Protecting Cultural

More information

Table Related Arlington County Standards, Specification and Policies

Table Related Arlington County Standards, Specification and Policies 2.1 GENERAL 2.1.1 DESCRIPTION SITE WORK V02000 2.1 GENERAL 2.1.1 Description This standard identifies minimum requirements that shall be met for all site work in the design and construction of elements

More information

STATE OF MINNESOTA MINNESOTA POLLUTION CONTROL AGENCY FINDINGS OF FACT

STATE OF MINNESOTA MINNESOTA POLLUTION CONTROL AGENCY FINDINGS OF FACT STATE OF MINNESOTA MINNESOTA POLLUTION CONTROL AGENCY IN THE MATTER OF THE DECISION ON THE NEED FOR AN ENVIRONMENTAL IMPACT STATEMENT FOR THE PROPOSED LESTER PRAIRIE WASTEWATER TREATMENT FACILITY EXPANSION

More information

SACHSE EROSION CONTROL GUIDELINES

SACHSE EROSION CONTROL GUIDELINES SACHSE EROSION CONTROL GUIDELINES Section I. Definitions The following words, terms, and phrases, when used in this guideline, shall have the meanings ascribed to them in this Section, except where the

More information

PRESS KIT MEDIA CONTACT. Chris Stockton Office Number: Cell Number:

PRESS KIT MEDIA CONTACT. Chris Stockton   Office Number: Cell Number: PRESS KIT MEDIA CONTACT Chris Stockton Email: Christopher.L.Stockton@williams.com Office Number: 713-215-2010 Cell Number: 713-562-2939 ABOUT WILLIAMS Williams is a nearly 110-year-old energy company that

More information

APPENDIX C EROSION AND SEDIMENTATION CONTROL STANDARDS

APPENDIX C EROSION AND SEDIMENTATION CONTROL STANDARDS APPENDIX C EROSION AND SEDIMENTATION CONTROL STANDARDS City of Bradenton January 2017 1 INTRODUCTION This appendix to the City of Bradenton Department of Public Works and Utilities Utility Specifications

More information

Item Name Description Unit of Measure Mobilization Per WSDOT Lump Sum

Item Name Description Unit of Measure Mobilization Per WSDOT Lump Sum Page 1 of 6 DESIGN STANDARDS FOR: MEASUREMENT AND PAYMENT Where bids are utilities for construction, repair or alteration for Public Work park projects, the following bid item descriptions and units of

More information

Common Construction-Site BMPs Quick Reference Guide

Common Construction-Site BMPs Quick Reference Guide Common Construction-Site BMPs Quick Reference Guide Installation and Inspection Requirements For more information visit the Town of Truckee Clean Water Program Website: http://www.townoftruckee.com/engineering/clean-water-program

More information

SECTION B. Prevention of sedimentation of waterways, open drainage ways, and storm and sanitary sewers due to construction activities.

SECTION B. Prevention of sedimentation of waterways, open drainage ways, and storm and sanitary sewers due to construction activities. SECTION 01 5713 TEMPORARY EROSION AND SEDIMENT CONTROL PART 1 GENERAL 1.01 SECTION INCLUDES A. Prevention of erosion due to construction activities. B. Prevention of sedimentation of waterways, open drainage

More information

T ECHNICAL M EMORANDUM TO: FROM: Lauren A. Wasilauski Open Space Coordinator, Montgomery Township Kris Hadinger Montgomery Township Attorney Jamie Morgan Ecologist and CPSS, Kleinfelder DATE: February

More information

SOUTHSIDE TOWNSHIP ROADWAY STANDARDS POLICY Adopted September 7, 2004

SOUTHSIDE TOWNSHIP ROADWAY STANDARDS POLICY Adopted September 7, 2004 SOUTHSIDE TOWNSHIP ROADWAY STANDARDS POLICY Adopted September 7, 2004 General: Sections of the Minnesota Department of Transportation (Mn/DOT), Standard Specification for Construction, 2000 or Current

More information

Please print or type.

Please print or type. SOIL EROSION AND SEDIMENTATION CONTROL PERMIT APPLICATION 6-18-07 Ann kjjkjkff- ANN ARBOR CHARTER TOWNSHIP 3792 Pontiac Trail, Ann Arbor, Michigan 48105-9656 Phone (734) 663-3418 Website: www.aatwp.org

More information

Short-term (Construction) Impacts and Potential Mitigation

Short-term (Construction) Impacts and Potential Mitigation 4 Short-term (Construction) Impacts and Potential Mitigation CHAPTER 4. SHORT-TERM (CONSTRUCTION) IMPACTS AND POTENTIAL MITIGATION This chapter describes short-term (construction) impacts that could result

More information

EROSION CONTROL AND GRADING PERMIT APPLICATION

EROSION CONTROL AND GRADING PERMIT APPLICATION EROSION CONTROL AND GRADING PERMIT APPLICATION COMMUNITY DEVELOPMENT DEPARTMENT 1735 MONTGOMERY STREET OROVILLE, CA 95965 530-538-2420 FAX (530) 5382426 www.cityoforoville.org APPLICATION DATE PERMIT FEE

More information

2-16 EROSION, SEDIMENT & STORM WATER CONTROL REGULATIONS APPENDIX B1

2-16 EROSION, SEDIMENT & STORM WATER CONTROL REGULATIONS APPENDIX B1 2-16 EROSION, SEDIMENT & STORM WATER CONTROL REGULATIONS APPENDIX B1 There are three ways to accomplish urban soil erosion and sedimentation control: Allow erosion to take place and then control sediment

More information

WETLAND AND WATERBODY CONSTRUCTION AND MITIGATION PROCEDURES

WETLAND AND WATERBODY CONSTRUCTION AND MITIGATION PROCEDURES Federal Energy Regulatory Commission Office of Energy Projects May 2013 www.1169certified.com WETLAND AND WATERBODY CONSTRUCTION AND MITIGATION PROCEDURES Washington, DC 20426 WETLAND AND WATERBODY CONSTRUCTION

More information

WETLAND AND WATERBODY CONSTRUCTION AND MITIGATION PROCEDURES

WETLAND AND WATERBODY CONSTRUCTION AND MITIGATION PROCEDURES Federal Energy Regulatory Commission Office of Energy Projects May 2013 WETLAND AND WATERBODY CONSTRUCTION AND MITIGATION PROCEDURES Washington, DC 20426 WETLAND AND WATERBODY CONSTRUCTION AND MITIGATION

More information

Schedule A DISTRICT OF MAPLE RIDGE Watercourse Protection Bylaw

Schedule A DISTRICT OF MAPLE RIDGE Watercourse Protection Bylaw Schedule A DISTRICT OF MAPLE RIDGE Watercourse Protection Bylaw 6410 2006 The Erosion and Sediment Control plan should seek (i) to protect the soil surface from erosion where possible and (ii) capture

More information

New Administration Building

New Administration Building New Administration Building Stormwater Pollution Prevention Plan Hudson Valley Community College Troy, New York Prepared for: Hudson Valley Community College 80 Vandenburgh Avenue Troy, New York 12180

More information

ATTACHMENT A: FINDINGS

ATTACHMENT A: FINDINGS ATTACHMENT A: FINDINGS 1.0 CEQA FINDINGS 1.1 CEQA Exemption The County Planning Commission finds that the proposed project is exempt from environmental review under the California Environmental Quality

More information

Step 1. Determine if a Small Utility GESC Permit is Applicable and if a Project Specific GESC Plan is Required.

Step 1. Determine if a Small Utility GESC Permit is Applicable and if a Project Specific GESC Plan is Required. Overview of Section 9 9.0 The GESC Permit Section provides a description of the Small Utility GESC Permit Program. Step 1. Determine if a GESC Permit is Applicable and if a Project Specific GESC Plan is

More information

ROVER PIPELINE LLC. Rover Pipeline Project HORIZONTAL DIRECTIONAL DRILL CONTINGENCY PLAN

ROVER PIPELINE LLC. Rover Pipeline Project HORIZONTAL DIRECTIONAL DRILL CONTINGENCY PLAN ROVER PIPELINE LLC Rover Pipeline Project HORIZONTAL DIRECTIONAL DRILL CONTINGENCY PLAN April 2015 Section TABLE OF CONTENTS 1.0 INTRODUCTION... 1 2.0 PLANNED HDD CROSSINGS... 1 3.0 MONITORING PROCEDURES...

More information

Storm Water Pollution Prevention Plan for CES Gravel #3800

Storm Water Pollution Prevention Plan for CES Gravel #3800 David Lewis Cell: (870) 310-2757 Rickey Vaughn Cell: (870) 310-9602 Buddy McAdams Cell: (870) 310-8733 Local (870) 881-8830 Fax: (870) 881-8809 LICENSED, BONDED & INSURED Howard Cupp, Jr. Cell: (870) 314-2877

More information

GRADING, EROSION AND SEDIMENTATION CONTROL

GRADING, EROSION AND SEDIMENTATION CONTROL SECTION 500 GRADING, EROSION AND SEDIMENTATION CONTROL 501 Erosion and Sedimentation Control Plan All engineering plans for projects that propose to construct new, or modify existing drainage facilities,

More information

ROVER PIPELINE LLC. Rover Pipeline Project HORIZONTAL DIRECTIONAL DRILL CONTINGENCY PLAN

ROVER PIPELINE LLC. Rover Pipeline Project HORIZONTAL DIRECTIONAL DRILL CONTINGENCY PLAN ROVER PIPELINE LLC Rover Pipeline Project HORIZONTAL DIRECTIONAL DRILL CONTINGENCY PLAN February 2015 Section TABLE OF CONTENTS 1.0 INTRODUCTION... 1 2.0 PLANNED HDD CROSSINGS... 1 3.0 MONITORING PROCEDURES...

More information

PART 1 GENERAL REQUIREMENTS

PART 1 GENERAL REQUIREMENTS PART 1 GENERAL REQUIREMENTS Contract Closeout Plan 110 Arrow diagram for project close-out...3 Erosion Control 121 Straw bale barrier... 5 122 Silt fence... 7 123 Diversion dike... 9 124 Inlet protection...

More information

Section 208. SOIL EROSION AND SEDIMENTATION CONTROL

Section 208. SOIL EROSION AND SEDIMENTATION CONTROL 208.01 Section 208. SOIL EROSION AND SEDIMENTATION CONTROL 208.01. Description. This work consists of installing and maintaining erosion and sedimentation controls to minimize soil erosion and control

More information

DEPARTMENT OF THE ARMY JACKSONVILLE DISTRICT CORPS OF ENGINEERS POST OFFICE BOX 4970 JACKSONVILLE, FLORIDA May 9, 2016

DEPARTMENT OF THE ARMY JACKSONVILLE DISTRICT CORPS OF ENGINEERS POST OFFICE BOX 4970 JACKSONVILLE, FLORIDA May 9, 2016 DEPARTMENT OF THE ARMY JACKSONVILLE DISTRICT CORPS OF ENGINEERS POST OFFICE BOX 4970 JACKSONVILLE, FLORIDA 32232 REPLY TO ATTENTION OF May 9, 2016 Regulatory Division North Permits Branch Jacksonville

More information

Q. CONSTRUCTION IMPACTS

Q. CONSTRUCTION IMPACTS Q. CONSTRUCTION IMPACTS 1. Construction Plan As noted on Exhibit 3Q-1, Overall Phasing Plan and SWPPP Notes, construction of the Proposed Project is anticipated to include five phases. The entire construction

More information

Noise Variance Review

Noise Variance Review Noise Variance #: NVAR17-0012 Noise Variance Review The noise variance (NVAR17-00012) request dated May 5, 2017 was evaluated based on the information provided in the variance submitted and any additional

More information

Single Family Residential Construction Erosion/Sediment Control Standards

Single Family Residential Construction Erosion/Sediment Control Standards Single Family Residential Construction Erosion/Sediment Control Standards Introduction: This booklet contains standard plans and procedures sufficient for typical building construction. It is not intended

More information

Details of the Proposed Action

Details of the Proposed Action Details of the Proposed Action Proposed Action This alternative is based on the proposed Plan of Operations submitted to the Forest Service on June 4, 2010 by Shoshone Silver/Gold Mining Company for the

More information

SECTION TRENCHING & BACKFILLING

SECTION TRENCHING & BACKFILLING SECTION 02225 - TRENCHING & BACKFILLING 1.0 GENERAL 1.1 Work included in this Section includes trenching and backfilling for underground pipelines and related structures only. 1.2 Reference Specifications

More information

No. 6 December, Wisconsin s Forestry Best Management Practices for Water Quality Forest Roads

No. 6 December, Wisconsin s Forestry Best Management Practices for Water Quality Forest Roads No. 6 December, 1995 Wisconsin s Forestry Best Management Practices for Water Quality Forest Roads Steve Holaday, Wisconsin Dept. of Natural Resources, and Jeff Martin, Dept. of Forestry, UW-Madison BMPs

More information

STATE OF VERMONT PUBLIC SERVICE BOARD PREFILED TESTIMONY AND EXHIBITS OF IAN A. JEWKES

STATE OF VERMONT PUBLIC SERVICE BOARD PREFILED TESTIMONY AND EXHIBITS OF IAN A. JEWKES STATE OF VERMONT PUBLIC SERVICE BOARD Docket No. Petition of Dairy Air Wind, LLC for a certificate of public good, pursuant to 0 V.S.A., for the installation of a single turbine,. MW wind-powered electric

More information

6 Preliminary Assessment of Construction Method and Constructability Issues

6 Preliminary Assessment of Construction Method and Constructability Issues 6 Preliminary Assessment of Construction Method and Constructability Issues 6.1 Construction Approach Appendix C includes conceptual designs of the alternatives discussed below. Generally, the conceptual

More information

Construction Site Inspections

Construction Site Inspections Construction Site Inspections Keep The Mud Out of The Creek Barry Tonning, Tetra Tech Inspections help to identify and correct problems! Inspection requirements Must inspect site every 14 days (LA) Some

More information

SITE DESIGN ENGINEER'S STATEMENT:

SITE DESIGN ENGINEER'S STATEMENT: SITE DESIGN ENGINEER'S STATEMENT: THESE DETAILED PLANS AND SPECIFICATIONS WERE PREPARED UNDER MY DIRECTION AND SUPERVISION. SAID PLANS AND SPECIFICATIONS HAVE BEEN PREPARED ACCORDING TO THE CRITERIA ESTABLISHED

More information

Technical Data

Technical Data 4906-17-05 Technical Data (A) PROJECT AREA SITE have occurred in this section. (1) Geography and Topography have occurred in this section. (2) Aerial Photography have occurred in this section. (3) Site

More information

Nonmetallic Mining Reclamation & Operation Plan. Amendment No. 1 (Includes modifications for Wash Plant construction) DRAFT

Nonmetallic Mining Reclamation & Operation Plan. Amendment No. 1 (Includes modifications for Wash Plant construction) DRAFT Nonmetallic Mining Reclamation & Operation Plan Amendment No. 1 (Includes modifications for Wash Plant construction) Mondovi Mine Town of Mondovi, Wisconsin Prepared for: Buffalo White Sand, LLC PO Box

More information

Williams Transco Pipeline

Williams Transco Pipeline open house Williams Transco Pipeline Williams Transco pipeline is a major transporter of natural gas, delivering much of the natural gas consumed in the northeastern and southeastern United States. Transco

More information

BAYFRONT CANAL AND ATHERTON CHANNEL PROJECT DESCRIPTION

BAYFRONT CANAL AND ATHERTON CHANNEL PROJECT DESCRIPTION APPENDIX I BAYFRONT CANAL AND ATHERTON CHANNEL PROJECT DESCRIPTION South Bay Salt Pond Restoration Project Phase 2 July 2015 Draft Environmental Impact Statement/Report 2185 N. California Blvd., Suite

More information

Typical Local Erosion Control Requirements (Storm Water Management Authority, Inc.)

Typical Local Erosion Control Requirements (Storm Water Management Authority, Inc.) Module 2: Selection of Controls and Site Planning for Construction Site Erosion Prevention Robert Pitt Department of Civil, Construction, and Environmental Engineering University of Alabama Tuscaloosa,

More information

Erosion Control Inspection Form

Erosion Control Inspection Form Project Name Address Inspection Date Time Name of Certified Erosion Sediment Lead (CESCL) or qualified inspector if less than one acre Print Name: Approximate rainfall amount since the last inspection

More information

SECTION UNCLASSIFIED EXCAVATION AND GRADING

SECTION UNCLASSIFIED EXCAVATION AND GRADING SECTION 02210 UNCLASSIFIED EXCAVATION AND GRADING PART 1 GENERAL 1.1 DESCRIPTION Work in this section includes the excavation, undercut excavating, grading, earthwork and compaction required as shown on

More information

CHARLES SOIL CONSERVATION DISTRICT COMPLIANCE AGREEMENT FOR THE STANDARD EROSION AND SEDIMENT CONTROL PLAN FOR FOREST HARVEST OPERATIONS

CHARLES SOIL CONSERVATION DISTRICT COMPLIANCE AGREEMENT FOR THE STANDARD EROSION AND SEDIMENT CONTROL PLAN FOR FOREST HARVEST OPERATIONS CHARLES SOIL CONSERVATION DISTRICT COMPLIANCE AGREEMENT FOR THE STANDARD EROSION AND SEDIMENT CONTROL PLAN FOR FOREST HARVEST OPERATIONS I. Site Information A. Location (Include site map of harvest area)

More information

TES Industrial Development SW ¼ SEC Lacombe County Outline Plan

TES Industrial Development SW ¼ SEC Lacombe County Outline Plan TES Industrial Development Lacombe County Outline Plan 112849297 June 2012 am v:\1128\active\112849297\07_reports_studies\rpt_tes_20120508.doc i Table of Contents 1.0 INTRODUCTION... 1 1.1 PURPOSE... 1

More information

STANDARD GRADING AND SOIL EROSION & SEDIMENT CONTROL PLAN FOR SINGLE LOT SINGLE FAMILY RESIDENTIAL CONSTRUCTION AND MINOR EARTH DISTURBANCES

STANDARD GRADING AND SOIL EROSION & SEDIMENT CONTROL PLAN FOR SINGLE LOT SINGLE FAMILY RESIDENTIAL CONSTRUCTION AND MINOR EARTH DISTURBANCES DIVISION OF ENGINEERING & CONSTRUCTION MANAGEMENT PLAN REVIEW DEPARTMENT WASHINGTON COUNTY SOIL CONSERVATION DISTRICT 1260 Maryland Avenue, Suite 101 Hagerstown, MD 21740 Telephone: (301) 797-6821, Ext.

More information

CONSTRUCTION PLANS FOR ENTERPRISE RENTAL CAR

CONSTRUCTION PLANS FOR ENTERPRISE RENTAL CAR CONSTRUCTION PLANS FOR VICINITY MAP (NOT TO SCALE) DEVELOPER/OWNER: CHRISTOPHER SLOVAN ENTERPRISE HOLDINGS, INC. 284 MALLORY STATION RD, SUITE 120 FRANKLIN, TN 37067 PH: 615-309-9621 DAVIDSON CO., TENNESSSEE

More information

SECTION 10 - TRENCHING AND BACKFILLING

SECTION 10 - TRENCHING AND BACKFILLING SECTION 10 - TRENCHING AND BACKFILLING 10.1 General A. Work included in this Section includes trenching and backfilling for underground pipelines and related structures only. 10.1.1 Related requirements

More information

Construction Site Erosion Control and Phase II of the Stormwater Permit Program

Construction Site Erosion Control and Phase II of the Stormwater Permit Program Construction Site Erosion Control and Phase II of the Stormwater Permit Program Robert Pitt Department of Civil and Environmental Engineering University of Alabama Tuscaloosa, AL Some Features of Phase

More information

Larimer County Land Use Code Section 5.8: Rural Land Use Process

Larimer County Land Use Code Section 5.8: Rural Land Use Process Larimer County Land Use Code Section 5.8: Rural Land Use Process 5.8.6 PRINCIPLES D. Development Standards 3. Engineering Standards and Guidelines for Roads and Drainage The following Standards and Guidelines

More information

THIS PAGE LEFT BLANK FOR TWO-SIDED DUPLICATION.

THIS PAGE LEFT BLANK FOR TWO-SIDED DUPLICATION. PROJECT DESCRIPTION THIS PAGE LEFT BLANK FOR TWO-SIDED DUPLICATION. Table of Contents Article 4.203.B.5 Project Description... 1 Facility Operations... 2 Construction:... 2 Drilling and Completions Phases:...

More information

Understanding Stormwater Pollution Prevention Plans (SWPPPs) (SWPPPS)

Understanding Stormwater Pollution Prevention Plans (SWPPPs) (SWPPPS) Understanding Stormwater Pollution Prevention Plans (SWPPPs) (SWPPPS) Definitions SWPPP: Storm Water Pollution Prevention Plan BMP: Best Management Practice(s) to control pollution IDNR: Iowa Department

More information

APPENDIX B Construction Surface Water Management Plan PLANT CITY, FLORIDA SYDNEY ROAD RECLAIMED WATER PROJECT INVITATION TO BID ITB NO.

APPENDIX B Construction Surface Water Management Plan PLANT CITY, FLORIDA SYDNEY ROAD RECLAIMED WATER PROJECT INVITATION TO BID ITB NO. APPENDIX B Construction Surface Water Management Plan PLANT CITY, FLORIDA SYDNEY ROAD RECLAIMED WATER PROJECT INVITATION TO BID ITB NO. 11-91360-001 ADVERTISED: November 5, 2010 MANDATORY PRE-BID MEETING:

More information

Stormwater Management Permit Application LESS Than One Acre. Public Works Department st Ave East Kalispell, Montana (406)

Stormwater Management Permit Application LESS Than One Acre. Public Works Department st Ave East Kalispell, Montana (406) Public Works Department 201 1 st Ave East Kalispell, Montana 59901 (406) 758-7720 Note: This permit is separate from any permits required by the Montana Department of Environmental Quality. A State Stormwater

More information