SEMINAR ON WATER SECURITY IN BULGARIA SOFIA, SEPTEMBER 18-19, 2017 DAM SAFETY IN ROMANIA

Similar documents
Q93 SAFETY. Gerald Zenz. Graz University of Technology Institute of Hydraulic Engineering and Water Resources Management

SMALL HYDRO BIG CHALLENGES Renewable Energy World Asia 2016 Martin P. Bieri. September 21, 2016

(b) Discuss in brief shaft spillway with neat sketches. Marks 04. OR Q (2) Explain in brief USBR stilling basin. Marks 08

Asst.Prof.Dr. Jaafar S. Maatooq. 1 st Semester HYDRAULIC STRUCTUER, KINDS & FUNCTIONS 1 of 26

Travers Reservoir Rehabilitation Project Irrigation Technical Conference Lethbridge, AB June 2, 2010

USACE LEVEE RISK ASSESSMENT PROCESS LESSONS LEARNED

Volume II: Hazard Annex Dam Failure

Dam Safety Surveillance. Templates for very low, low consequence category dams

REHABILITATION OF THE LANGETENTAL FLOOD DIVERSION TUNNEL

Chapter 4. Main problems in a canal network 4.1 INTRODUCTION

Project ID: P Global Supplemental ID: P Project: HAZARD RISK MITIGATION AND

Types of Inspections. Prior to Inspection. Types of Inspections. Typical Inspection Equipment. Embankment Dams

Current / Recent Construction Projects

Types of Inspections

HISTORY OF CONSTRUCTION 40 CFR (c)(1)(i)-(xii) PLANT WANSLEY ASH POND (AP-1) GEORGIA POWER COMPANY. Carrollton, Georgia 30116

McElroy s Run Impoundment Structural Stability Assessment Report

HISTORY OF CONSTRUCTION 40 CFR (c)(1)(i) (xii) PLANT HAMMOND ASH POND (AP 2) GEEORGIA POWER COMPANY

A Brief History of Dams in Iraq. The Case of Mosul Dam Presented to Al-Diwan, April 10, 2016 by Mosaid Al-Hussaini, Ph.D, PE

Lyon Creek Cedar Way Stormwater Detention Dam Operation and Maintenance Manual

Water Resources. Associate Prof. Ahmed Moustafa Moussa Lecture -1 Lecture 4

CCR Rule Annual Inspection Report 2

Mangla Dam Raising: Effectiveness of Seepage Reduction Measures for Sukian Dyke

Formal Annual Inspection It is recommended that you customize this form to fit your dam. Pre-Inspection Information

Keeyask Generation Project. Physical Environment. Supporting Volume. Environmental Impact Statement

Complying with Dam Safety Regulations The Sleepy Hollow Lake Story

Supplemental Watershed Plan Agreement No. 10 for Neshaminy Creek Watershed Core Creek Dam (PA-620) Bucks County, Pennsylvania

Mr. Paul Dunlap, California Department of Water Resources

Created by Simpo PDF Creator Pro (unregistered version) Asst.Prof.Dr. Jaafar S. Maatooq

Request Number 9: Accidents & Malfunctions Dam Safety Cumulative Effects

Limited Visual Dam Safety Inspections OA Wahiawa Dam. Oahu, Hawaii

EARTHQUAKE SAFETY OF EXISTING DAMS

Mining, Tailings and Dam Safety: the Mt. Polley Disaster and Next Steps. Dr. Andrea Kennedy, Ph.D. Bridgeway Consulting for Adams Lake Indian Band

Hydropower and Water Resources

Inflow pipe. Drain. Drain

DAMS AND OTHER HYDRAULIC STRUCTURES

CASE STUDY OKUYOSHINO, JAPAN

Earth Brickwork Concrete Plain Radial Drum Roller Flap. fixed. Weirs Barrages. mobile. rockfills. Gravity butress Arch Arch-gravuty Cupola.

The dam authority of Saxony (LTV) is responsible

PARR HYDROELECTRIC PROJECT PARR HYDRO DEVELOPMENT & FAIRFIELD PUMPED STORAGE FACILITY DEVELOPMENT FERC PROJECT No SC SEPTEMBER 19, 2012

DAMS AND APPURTENANT HYDRAULIC STRUCTURES

BOARD BRIEFING DAM SAFETY QUARTERLY REPORT

Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent [1]

Visual Inspection Checklist

Justus B.C Mtolera Mtera Hydro plant Manager TANESCO TANZANIA

Hydropower & Dams Services

SAN GABRIEL RIVER 1 LEVEE SYSTEM LOS ANGELES COUNTY, CALIFORNIA NLD SYSTEM ID #

HYDROPOWER AND WATER RESOURCES

Ponds. Pond A water impoundment made by excavating a pit, or constructing a dam or an embankment.

REVIEW PLAN For Plans and Specifications For Toe Drain Repairs Falls Lake Dam Wake County, North Carolina Wilmington District

City of Edmonton Drainage Services Summary Notes of Riverdale Flood Mitigation Meeting Held May 14, 2015 at Riverdale School

Coal Combustion Facility Assessment Report. October 20, 2010

DAM SAFETY in Vietnam CHALLENGES AND ISSUES

Water Control Structures Selected Design Guidelines Alberta Environment Page 17-1

CBC Aids WVDEP with Fresh Water Reservoir - Chief Logan State Park

Evaluation of the hydrological risk during the construction phase of Kavsakbendi Dam and HEPP

TUG - Institute of Hydraulic Engineering and Water Resources Management 1

LAKE CHEMUNG DAM LOCATION MAP

Appendix 3-G SWM AND BMP CONSTRUCTION INSPECTIONS

Pier (TYP) Tainter Gate (TYP) Chapter 2 Applications General

Dam Safety and Low Cost Spillway Designs

Report. Inflow Design Flood Control System Plan Belle River Power Plant East China, Michigan. DTE Energy Company One Energy Plaza, Detroit, MI

Important Role of Filters in Hydraulic Soil Structures Hamid Fallah Apr. 19, 2013

SEEPAGE FAILURE, EVALUATION AND REMEDIATION OF PENN FOREST DAM

IMPACT AND PUNCTURING OF JARI TUNNEL AND ENLARGEMENT OF EXISTING TAPPINGS FOR ADDITIONAL WATER SUPPLY AND POWER GENERATION

Distribution Restriction Statement Approved for public release; distribution is unlimited.

Modern Dam Safety Concepts and Seismic Safety Aspects of Sustainable Storage Dams

2015 INSPECTION REPORT FLY ASH DAM and BOTTOM ASH POND COMPLEX JOHN AMOS PLANT ST. ALBANS, WEST VIRGINIA. June 2015

Abstract. 1. Main features of the Cua Dat scheme. Hong Giang VNCOLD. Hanoi Vietnam. the Northern Central The reservoir storage purposes: - water

2018 Annual Dam and Dike Inspection Report

Report. Inflow Design Flood Control System Plan St. Clair Power Plant St. Clair, Michigan. DTE Energy Company One Energy Plaza, Detroit, MI

Regulation 18 August 2009 NO Operations and Maintenance LEVEE ENCROACHMENT STANDARDS AND PROCEDURES

Overview of the IWAYA Dam project. Specifications

Appendix H. Waimakariri Irrigation Limited Ponds Design Report (February 2013) Prepared by Damwatch Services

DTE Energy St. Clair Power Plant

Seismic Design and Safety Aspects of Bottom Outlets, Spillways and Intake Structures of Large Storage Dams

Remedial grouting works to two dams in Hong Kong

ROLE OF THE FIRM IN THE PROJECT

WORKING PAPER 5 IRRIGATION AND DRAINAGE IMPROVEMENT PROJECT 2 (IDIP-2) MISSION FOR EVALUATION OF DAM SAFETY KAZAKHSTAN

Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control [1] Soil Treatment Permanent

Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control [1] Soil Treatment Permanent

HydroHelp 5 AN EXCEL PROGRAM DEVELOPED FOR PRE-FEASIBILITY ASSESSMENT PUMP-STORAGE HYDROELECTRIC SITES. J. L. GORDON P.Eng.

East Branch Dam Safety Initiative

Watershed size and name: The drainage area is acres. The pond is located within the Ohio River watershed. (2016 Inflow Design Plan)

McElroy s Run Impoundment Coal Combustion Residual Annual Report

Review of the 2014 Annual Dam Safety Inspection Report, 2-North Pit Tailings Disposal Facility, Quinsam Coal Mine

Irrigation System. BWCDD Zanjero Training 2/13/2008

Passion for Progress... and Progress in Water Resource Development

MILL CREEK LEVEE SYSTEM SAN BERNARDINO COUNTY, CALIFORNIA NLD SYSTEM ID #

11.1 INTRODUCTION 11.2 SLOPE MANAGEMENT SYSTEM 11.1 GEOTECHNICAL AND SLOPE STABILITY

consulting engineers hydraulic steel structures

Highway Drainage 1- Storm Frequency and Runoff 1.1- Runoff Determination

Screening Level Risk Assessment for Low Hazard Dams

LOS ANGELES RIVER/RIO HONDO DIVERSION 2 LEVEE SYSTEM LOS ANGELES COUNTY, CALIFORNIA NLD SYSTEM ID #

LOS ANGELES RIVER/RIO HONDO DIVERSION 2 LEVEE SYSTEM LOS ANGELES COUNTY, CALIFORNIA NLD SYSTEM ID #

TSAILE DAM MODIFICATION PROJECT Unearthing a Safer Dam

Performance Assessment of Taunsa Barrage Subsidiary Weir for Long Term Rehabilitation Planning

Water Control Structures Selected Design Guidelines Alberta Environment Page 13-1

WELCOME TO POND 101 OREGON WATER RESOURCES DAM SAFETY SECTION. John Falk, PE

Strategies to Mitigate Scour Critical Structures

4. Present Activities and Roles

Transcription:

SEMINAR ON WATER SECURITY IN BULGARIA SOFIA, SEPTEMBER 18-19, 2017 DAM SAFETY IN ROMANIA

Overview Romania has built 2,617 dams out of which 246 are large and medium dams and 1260 are small dams, as per ICOLD classification 75% of all dams have been built between 1965 and 1989 32 dams wait for commissioning as are still in various stages of construction Total storage capacity of large dams commissioned = 12.35 billion m 3 2

Overview (2) Dams ownership is shared mainly by the Romanian Waters Administration (ANAR) and the hydropower company Hidroelectrica, with six dams owned by various industrial plants 61 % of dams have multiple purposes (water supply, hydropower, irrigation and almost all have flood protection purpose) 3

Legal and regulatory arrangements for dam safety Water Law #107/1996 is the main regulatory act for dam safety setting the guiding rules for dam safety Complementary implementation regulations and technical norms ICOLD (2012) risk analysis methodology Responsibilities: Dam Manager (local) Dam Owner (central) Line ministry (central) CONSIB (consultative technical body) pivotal role in dam safety system reviews organization of dam monitoring system reviews periodic technical reports on dams safety operation advises upon the operational rules for dams recommends the preparation of technical reviews of hydraulic infrastructure with high failure risk recommends the structural interventions to enhance the safety of infrastructure at risk 4

Distribution of roles and responsibilities for dam safety 5

Dam accidents and incidents Belci Dam failure (July 1991) Conditions: high flood, technical defections at micro-hydropower plant power supply to action the hydro-mechanical equipment failed because of heavy rainfall Consequences: dam failed, 25 fatalities, 250 households washed away Certej Tailings Dam (October 1971) - the tailings dam failed after a long period of heavy rainfalls, spilling cyanide over the town Consequences: 89 fatalities, four apartment buildings and five households washed away Incidents: Vidraru Dam over discharge of reservoir without early warning alerted the local population Paltinu Dam severe seepage through shoulders required grouting and consolidation 6

Belci Dam Paltinu Dam 7

Enhancing Safety of Dams at Risk (1) Assessment of safety risk done by ANAR and CONSIB in 1999-2001 for most dams 9 large dams found with safety problems and operational restrictions recommended WB technical and financial support requested in 2002 Hazard Risk Mitigation and Emergency Preparedness Project (HRMEP) 2005-2012 1 project dam (Dridu Dam) further damaged by heavy floods in 2005 Initial project cost US$204 Million / Floods and Dam Safety component US$ 101 Million Works costs share: US$ 88.3 M, of which US$ 39 M floods and US$ 49.3 M for dams Project scope: 12 flood protection sites and 13 dams Final project component costs US$ 101 M with US$ 88.5 M for works Works costs share: US$ 35.5 M floods and US$ 53 M dam safety Project scope: 9 flood protection sites and 6 dams mainly because of costs overrun 8

Enhancing Safety of Dams at Risk (2) HRMEP Project financed safety interventions for 4 large dams and 2 small dams All dams had restrictions in operations imposed by their deficiencies, mainly with respect to stability and seepage All dams operated at water free board level lower than designed for safety Safety restrictions imposed limitation of services for all users Serious deficiencies of feasibility studies found at engineering design stage! Inaccurate identification of scope of interventions led to substantial increase of costs 89% - the overall cost overrun for dam projects 180% - the cost overrun in the most expensive contract Consequence: 7 dams (including the most unsafe) could not be addressed! 9

Enhancing Safety of Dams at Risk (3) Population at Risk - initial Name Population At risk Affected Total Dams in Program 338,085 1,225,000 1,563,085 Dridu 10,435 40,000 50,435 Varsolt 10,800 155,000 165,800 Berdu 138,000 138,000 276,000 Poiana Uzului 30,000 80,000 110,000 Maneciu 42,000 224,000 266,000 Valea de Pesti 8,000 30,000 38,000 Siriu 85,000 100,000 185,000 Lesu 280 35,000 35,280 Sanmihaiu 1,060 160,000 161,060 Taria 5,200 18,000 23,200 Catamarasti 950 80,000 80,950 Buftea 3,500 120,000 123,500 Pucioasa 2,860 45,000 47,860 Population Protected 79% Name Population At risk Affected Total Completed dams 208,445 787,000 995,445 Varsolt 10,800 135,000 145,800 Berdu 138,000 138,000 276,000 Maneciu 42,000 220,000 262,000 Taria 5,200 16,000 21,200 Catamarasti 950 78,000 78,950 Dridu 10,435 40,000 50,435 Sanmihaiu 1,060 160,000 161,060 10

Enhancing Safety of Dams at Risk (4) Main deficiencies addressed through the Project: Seepage through the foundation and/or dam body Stability of foundation and dam shoulders Obsolete / nonfunctional hydro-mechanical equipment (bottom outlets, gates, spillway) Obsolete / nonfunctional instrumentation for monitoring, early warning Erosion of side slopes or downstream dam face 11

Brief description of Project interventions (1) Varsolt Dam medium size (17 m height, 40 mill. m 3 ) Reservoir: multipurpose water supply, flood protection Operation experience: the reservoir was originally designed as non-permanent and commissioned for permanent use later. A dam foundation sealing was not necessary for a non-permanent used reservoir. Risk assessment: evaluated, category of importance a exceptionally important - high risks. Rehabilitation measures: Sealing of dam body and foundation treatment (concrete cut-off wall 0.6 m thick from the dam crest, 25 m deep). Reshaping of dam body (stability, drainage at the dam toe and downstream channel rehabilitation. Drilling of drains in the new gallery. Rehabilitation of the bottom tunnel and sealing of the old gallery. Construction of new bottom outlet structures on the left bank. Measures for sanitary protection and water quality assurance. Anti-erosion measures upstream of the reservoir. Rehabilitation of the monitoring system and upgrading of the alarm and warning system as well as seismic activities detection system. Estimated costs US$ 7.4 Mill. Actual costs US$ 20.7 Mill. 12

Brief description of Project interventions (2) Maneciu Dam Large dam; Earth rock-fill dam with central clay core; H 78 m; W 58 Mm 3 Reservoir: multipurpose water supply, flood control, irrigation and generating electricity. Operation experience: the dam was operated at a restricted water level compared to originally designed parameters. Bottom outlet operation restricted due to too high flow velocities (valves, energy dissipater, no steel lining at concrete structures and damages in downstream areas etc.). Seepage in spillway and damaged concrete. Slope instability occurred on the left downstream bank. Risk assessment: evaluated, category of importance b significant important, - medium risks Earthquake risk assessment: the dam is located in a zone of a very high seismicity (zone A). Rehabilitation measures: Rehabilitation of the bottom outlet: steel lining between valve chamber, dissipater and injections; improvement of other structures, new energy dissipater. Rehabilitation of the spillway channel: sealing of joints in the concrete structures with various methods, improvement of the concrete quality in sections with high flow velocities through usage of highly resistant concrete (20 cm thick). Rehabilitation of the downstream left slope: protection with riprap between elevation 557 and 610 m a. S. L.; Rehabilitation works above 610 m a. S. L.; Additional local measures. Rehabilitation of the monitoring system, alarm and warning system as well as the seismic system. 13

Brief description of Project interventions (3) Dridu Dam: Gated weir, main fill dam; Medium dam; H=18 m, W=45 M m 3 Operation experience : severe local erosions of river banks caused by wave actions, seepage through dam body; cavitation problems in spillway section; locally damaged sealing and revetment in channels; damaged hydraulic weir gates; seepage under right side foundation after 2005 flood. Risk assessment: evaluated, category of importance b significant important, medium risks. Earthquake risk assessment: the dam is located in a medium high seismic zone (zone C). Rehabilitation measures: Cut-off wall executed through soil mixing - innovative method in Romania Rehabilitation protection - of the river banks to stop erosion Rehabilitation of the existing dam drainage system: new collecting system and pumping facilities. Rehabilitation of the main dam: drillings and drains from the inspection gallery, construction of a new sealing blanket depth 7 m from dam crest. Rehabilitation of the spillway channel: reconstruction of bottom sills, riprap and reinforced concrete structures Rehabilitation of the hydro-mechanical equipment. Implementing a new information system for the water management, warning and alarm system, etc. 14

Deferred intervention - example Siriu Dam: Large, earth-rock-fill dam central clay core; H=122 m; W=155 Mm 3 Reservoir: multipurpose water supply, irrigation, hydropower, flood protection; Operation restricted Operation experience: seepage rates of 15 to 18 l/s were observed in drainage gallery during impounding at an elevation 50 m below normal water board level; problems at hydro-mechanical equipment (bottom outlet, intake gallery, valve chamber etc.); slope instabilities on the left bank downstream; reduced operation capacity of spillway. Risk assessment: evaluated, category of importance A exceptional important - high risks. Earthquake risk assessment: the dam is located in a highly seismic zone (zone b). Proposed repair and rehabilitation measures: Grouting and drainage works in existing galleries plus new, exceeding gallery and piezometers to stabilize the left slope and to decrease seepage. Refurbishment and rehabilitation of hydro-mechanical, electrical equipment and drainage system Bottom outlet, valve chamber Intake gallery, valve chamber Spillway valves and gates Intermediate (semi depth) outlet, gates Water supply system, pipe Rehabilitation of the monitoring system, emergency and alarm system, seismic system etc. Rehabilitation of the dam crest and repair works at the downstream dam slope. 15

Lessons Learned Slow adaptation process of technical staff (designers, planners) to technological progress and changed economics of public investment Poor planning capacity at administrative levels (ministry, water authority), unable to do a reasonable prioritization of investment led to The change of generations occurred in early 90s did not enable preservation of the same innovative capacity in staff lacking practical experience in design, planning Insufficient understanding of changes in procurement practice introduced by the harmonization with international principles and rules Reluctance to accept presence of foreign specialists, challenging their capacity to understand the local traditions 16

THANK YOU Gabriel Ioniță, Irrigation Engineer gionita53@gmail.com 17