SMALL HYDRO BIG CHALLENGES Renewable Energy World Asia 2016 Martin P. Bieri. September 21, 2016

Size: px
Start display at page:

Download "SMALL HYDRO BIG CHALLENGES Renewable Energy World Asia 2016 Martin P. Bieri. September 21, 2016"

Transcription

1 SMALL HYDRO BIG CHALLENGES Renewable Energy World Asia 2016 Martin P. Bieri September 21, 2016

2 CONTENT Introduction Potential in Southeast Asia Challenges in Small Hydro Main Design Steps (Bad) Examples What can go wrong, will go wrong! (Selected) Design Basic Studies Hydraulic Design Small Dams and Weirs E&M Equipment Conclusion Lessons Learnt

3 INTRODUCTION Small Hydropower Potential in Southeast Asia In Southeast Asia some large hydropower projects currently under development, but also high potential for small hydro: Target of 15% of renewable energy in the total power supply by 2020 Renewable generating mix relies almost exclusively on hydro (12%) Installed small hydropower capacity: Vietnam: 622 MW (<30 MW) Philippines: 248 MW Thailand: 146 MW (<10 MW) Small hydropower potential: Vietnam: 2,205 MW (about 175 projects) Philippines: 1,876 MW Indonesia: 1,267 MW (about 125 projects) Asia 65% Global distribution of small hydropower resources (<10 MW) [UNIDO and ICSHP 2013] "SMALL HYDRO - BIG CHALLENGES" 3

4 INTRODUCTION Small Hydro Big Challenges What is Small Hydro? No consensus on definition Generally installed capacity <30 MW Where are the Big Challenges? Low budget for design (3 to 5% investment) of complex infrastructure Local not experienced designers Lack of robust standardized designs, costing procedures, specifications, and contract documents Unsustainable plants due to inappropriate design (Low efficiencies, power loss, shortages, high O&M cost, short lifetime) "SMALL HYDRO - BIG CHALLENGES" 4

5 INTRODUCTION Large Hydro versus Small Hydro Large Hydro Small Hydro Budget for design High Low Designer experienced (international) unexperienced (local) Risk of errors resulting in poor performance Installed Capacity Example: Investment Design Fee (5%) Low 200 MW USD 400 million USD 20 million High 20 MW USD 40 million USD 2 million "SMALL HYDRO - BIG CHALLENGES" 5

6 INTRODUCTION Main Design Steps Objective: Satisfactory functional structure at a minimum total cost. Topography and geology of the site Evaluation of water resource (potential) Site selection and layout (alternative study) Hydraulic and structural design E&M equipment including control-command Environmental impact assessment and mitigation measures Economic evaluation of the project and financing potential Institutional framework and administrative procedures to attain necessary consents [ESHA 2004] "SMALL HYDRO - BIG CHALLENGES" 6

7 EXAMPLE FLOOD SAFETY Inappropriate Flood and Sediment Study before 1.2 MW HPP, Philippines: Complete destruction of powerhouse during Typhoon Nona in December 2015 Lessons learnt: Check Flood levels Powerhouse foundation on rock after "SMALL HYDRO - BIG CHALLENGES" 7

8 EXAMPLE SEDIMENTS Inappropriate Flood and Sediment Study before 1.2 MW HPP, Philippines: Complete destruction of powerhouse during Typhoon Nona in December 2015 Lessons learnt: Check Flood levels Powerhouse foundation on rock Sediment assessment after "SMALL HYDRO - BIG CHALLENGES" 8

9 EXAMPLE PLANT PERFORMANCE Inappropriate Hydraulic Design 10 MW HPP, Indonesia: Rather high head losses of approx. 10 m for gross head of about 160 m and power waterway of approx. 2.5 km length (mean velocities of 2.5 m/s): Sedimentation Air entrainment in the waterways Head losses due to too high installation of Francis units (loss of about 10 m head) "SMALL HYDRO - BIG CHALLENGES" 9

10 EXAMPLE DESIGN Inappropriate Geotechnical and Hydraulic Design Cut-slopes 8.8 MW HPP, Indonesia: High intensity rainfalls expected in the project area Initial design with very steep cut-slopes, large excavation and insufficient drainage, leading to potential slope instabilities Inappropriate design of desander High O&M costs in case of slope failures and forced outages due to sediment entrainment in the headrace system Desander "SMALL HYDRO - BIG CHALLENGES" 10

11 EXAMPLE SEDIMENTS Inappropriate Hydraulic Design 10.5 MW HPP, Vietnam: Desander with turbulent flow pattern inefficiently performing to sediment entrainment (missing coarse racks or baffles) Due to severe abrasion damage runners to be changed every 2 to 3 years Spare runner available at site, but not properly stored "SMALL HYDRO - BIG CHALLENGES" 11

12 EXAMPLE SEDIMENTATION Inappropriate Sedimentation Management 6.7 MW HPP, Switzerland Cascade of three hydropower plants (operation for longer than 80 years) 10 m high weir with a lateral intake, a 2470 m long power tunnel, a 710 m long steel-lined surface penstock and a powerhouse with three generating units Need of extensive rehabilitation due to completely silted-up reservoir and lack of efficient sediment flushing devise "SMALL HYDRO - BIG CHALLENGES" 12

13 DESIGN Basic Studies Topography Often missing data base or old maps ASTER or World DEM for preliminary assessment of alternatives (potential) Drone survey Field survey at relevant locations Geology Walk-over of experienced geologist Engineering aspects Field investigations (drilling etc.) required? Hydrology (Inflow, floods and sediment) Often no flow data series available Empirical approaches or extrapolation Installation of river gauging station? "SMALL HYDRO - BIG CHALLENGES" 13

14 DESIGN Hydraulics Understanding basics of hydraulics: Optimize the performance of waterways to reduce energy losses Design spillways and flood prevention Design energy dissipation Control erosion and sediment transportation Controling phenomena such as: Air, sediment and debris entrainment Surges in long waterways Instability in waterways (transients) Cavitation of structures and equipment Prevent reservoir sedimentation [ESHA 2004] "SMALL HYDRO - BIG CHALLENGES" 14

15 DESIGN Small Dams and Weirs Small dams are being defined by ICOLD as any dam with: maximum height (H), measured from deepest foundation level to highest structure crest level, less than 15 m, expect 10 m < H < 15 m, and the following conditions: Dam length more than 500 m, Reservoir storage capacity more than 3 million m 3 Flood discharge more than m 3 /s Unusual characteristics in dam type or foundation Reduced safety requirements [ICOLD 2011] "SMALL HYDRO - BIG CHALLENGES" 15

16 DESIGN Small Dams and Weirs Good Practices for the design of small dams: Investigation of foundations and excavation of organic and other inappropriate soils at dam foundation Hydrology study (inflow, flood and sediment) Cohesive materials for embankment, stable during overtopping Use appropriate and durable material for slope protection Standard design for filters and drains Appropriate equipment for construction (compaction) Permanent monitoring of construction quality Access to outlet works during floods and for maintenance No cattle on dam slopes and abutments No pipes through or over embankments Monitoring and routine inspections during dam operation [ICOLD 2011] "SMALL HYDRO - BIG CHALLENGES" 16

17 DESIGN E&M Equipment Standardized electromechanical equipment including turbine, gear, generator, inlet valve, control-protectionmeasuring systems and complete mechanical and electrical balance of plant equipment Modular design minimizing number of components and sizes: Single source responsibility Simplification of interfaces Short installation time Short commissioning time Only one software and hardware solution Single source training of customer s operating personal [Andritz 2016] "SMALL HYDRO - BIG CHALLENGES" 17

18 CONCLUSION LESSONS LEARNT Large Hydro versus Small Hydro Topography Hydrology Geology Hydraulic Design Construction Technologies Generation Equipment Large Hydro LiDAR and survey Detailed analysis (inflow/floods/sediments) Investigations Underground structures, model tests, simulations Experienced contractor (sophisticated technologies) Specific specifications (model tests etc.) Small Hydro Drone survey and survey of selected sites Detailed analysis (inflow/floods/sediments) Walk-over, limited investigations Approved design (expert knowledge) Local contractor (simple technologies) Functional specifications (standardized concepts) "SMALL HYDRO - BIG CHALLENGES" 18

19 CONCLUSION LESSONS LEARNT Objective: Satisfactory functional structure at a minimum total cost. Robust design considering availability of resources (construction material, construction techniques and manpower) Use of standardized designs, costing procedures, specifications, and contract documents Standardized design for hydro-mechanical and electromechanical equipment (minimizing complexity and number of interphases) Conceptual design by an experienced consultant (hydrology, geology, hydraulic, geotechn. and structural design, specifications) Detailed design by local consultants (access roads, stone masonry, outline and reinforcement etc.) Flexibility of adjustments (if required) "SMALL HYDRO - BIG CHALLENGES" 19

20 Consulting. Engineering. Projects. Operations.

21 DESIGN Small (Embankment) Dams Wrong Practices for the design of small dams: Foundations not investigated or investigated to a limited standard Inappropriate hydrology study (less data available) Inappropriate soil compaction Seepage control not designed to standard Inappropriate material used (e.g. dispersive clays) Inappropriate equipment used during construction Erodible by-wash spillways, cutback erosion of spillway Inappropriate slope protection No adequate features around outlet pipes No full time construction monitoring No regular inspection during its life No monitoring instruments Adoption of lower cost with higher risk. [ICOLD 2011] "SMALL HYDRO - BIG CHALLENGES" 21

CASE STUDY OKUYOSHINO, JAPAN

CASE STUDY OKUYOSHINO, JAPAN SEDIMENT MANAGEMENT CASE STUDY OKUYOSHINO, JAPAN Key project features Name: Okuyoshino Country: Japan Category: bypass channel/tunnel Reservoir volume (original): 15.47 Mm 3 Installed capacity: 1,206 MW

More information

SEMINAR ON WATER SECURITY IN BULGARIA SOFIA, SEPTEMBER 18-19, 2017 DAM SAFETY IN ROMANIA

SEMINAR ON WATER SECURITY IN BULGARIA SOFIA, SEPTEMBER 18-19, 2017 DAM SAFETY IN ROMANIA SEMINAR ON WATER SECURITY IN BULGARIA SOFIA, SEPTEMBER 18-19, 2017 DAM SAFETY IN ROMANIA Overview Romania has built 2,617 dams out of which 246 are large and medium dams and 1260 are small dams, as per

More information

Seismic Design and Safety Aspects of Bottom Outlets, Spillways and Intake Structures of Large Storage Dams

Seismic Design and Safety Aspects of Bottom Outlets, Spillways and Intake Structures of Large Storage Dams Seismic Design and Safety Aspects of Bottom Outlets, Spillways and Intake Structures of Large Storage Dams Blank line 11 pt Blank line 11 pt M. Wieland Chairman, Committee on Seismic Aspects of Dam Design,

More information

Created by Simpo PDF Creator Pro (unregistered version) Asst.Prof.Dr. Jaafar S. Maatooq

Created by Simpo PDF Creator Pro (unregistered version)  Asst.Prof.Dr. Jaafar S. Maatooq Lect.No.9 2 nd Semester Barrages, Regulators, Dams 1 of 15 In order to harness the water potential of a river optimally, it is necessary to construct two types of hydraulic structures, as shown in Figure

More information

Water Control Structures Selected Design Guidelines Alberta Environment Page 13-1

Water Control Structures Selected Design Guidelines Alberta Environment Page 13-1 Alberta Environment Page 13-1 13.0 DROP INLET SPILLWAYS 13.1 General The drop inlet spillway is commonly used for providing flood protection for earth dams which have smaller reservoirs and/or smaller

More information

Lyon Creek Cedar Way Stormwater Detention Dam Operation and Maintenance Manual

Lyon Creek Cedar Way Stormwater Detention Dam Operation and Maintenance Manual Lyon Creek Cedar Way Stormwater Detention Dam Operation and Maintenance Manual Prepared by: Mike Shaw Stormwater Program Manager City of Mountlake Terrace January 2010 Section I General Information This

More information

Small Hydropower Projects (SHPP) Training Workshop Project Documentation for Project Assessment. Yerevan, 12./

Small Hydropower Projects (SHPP) Training Workshop Project Documentation for Project Assessment. Yerevan, 12./ Consulting Services for the Programme for the Promotion of Renewable Energies: German-Armenian Renewable Energy Fund (GAF-RE) Phase II, BMZ ID 2009.70.285 Small Hydropower Projects (SHPP) Training Workshop

More information

LOW HEAD HYDROPOWER SOLUTIONS

LOW HEAD HYDROPOWER SOLUTIONS HYDRO LOW HEAD HYDROPOWER SOLUTIONS ALEXANDER BIHLMAYER NEPAL POWER INVEST MENT SUMMIT, KAT HMANDU, JANUARY 27, 2018 ALEXANDER BIHLMAYER 06.09.1967 Technical University in Graz, Austria: Master (DI) Mech.

More information

FEASIBILITY STUDY GUIDELINES

FEASIBILITY STUDY GUIDELINES FEASIBILITY STUDY GUIDELINES Pakhtunkhwa Energy Development Organization (PEDO) Energy and Power Department, KP Prepared by Pakhtunkhwa Energy Development Organization Feasibility Study Guidelines Volume

More information

CASE STUDY JHIMRUK, NEPAL

CASE STUDY JHIMRUK, NEPAL SEDIMENT MANAGEMENT CASE STUDY JHIMRUK, NEPAL Key project features Name: Jhimruk Country: Nepal Category: modifying operating rule (focus or redistribute sediment); adaptive strategies Reservoir volume

More information

Asst.Prof.Dr. Jaafar S. Maatooq. 1 st Semester HYDRAULIC STRUCTUER, KINDS & FUNCTIONS 1 of 26

Asst.Prof.Dr. Jaafar S. Maatooq. 1 st Semester HYDRAULIC STRUCTUER, KINDS & FUNCTIONS 1 of 26 1 st Semester HYDRAULIC STRUCTUER, KINDS & FUNCTIONS 1 of 26 1 st Semester HYDRAULIC STRUCTUER, KINDS & FUNCTIONS 2 of 26 Water is often more useful to people when it is properly controlled, conveyed,

More information

MCKAYS CREEK HYDRO-ELECTRIC POWER SCHEME ENHANCEMENT FEASIBILITY AND SCOPING REPORT PREPARED FOR SCHEME RECONSENTING

MCKAYS CREEK HYDRO-ELECTRIC POWER SCHEME ENHANCEMENT FEASIBILITY AND SCOPING REPORT PREPARED FOR SCHEME RECONSENTING i MCKAYS CREEK HYDRO-ELECTRIC POWER SCHEME ENHANCEMENT FEASIBILITY AND SCOPING REPORT PREPARED FOR SCHEME RECONSENTING ii Table of contents 1 Enhancement Scope of Work 1 1.1 Introduction 1 2 McKays Intake

More information

Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control [1] Soil Treatment Permanent

Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control [1] Soil Treatment Permanent Slope Drains DRAINAGE CONTROL TECHNIQUE Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control [1] Soil Treatment Permanent [1] Slope drains can act as outlet

More information

Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control [1] Soil Treatment Permanent

Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control [1] Soil Treatment Permanent Slope Drains DRAINAGE CONTROL TECHNIQUE Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control [1] Soil Treatment Permanent [1] Slope drains can act as outlet

More information

Report on the completion of HPP POBREG RAIFFEISEN BANK SH.A. ALBANIA. Evaluation and Business Plan Supervision of Hydropower Plants

Report on the completion of HPP POBREG RAIFFEISEN BANK SH.A. ALBANIA. Evaluation and Business Plan Supervision of Hydropower Plants Head Office Augustaanlage 62-64 D-68165 Mannheim Germany Reinhold Metzler Project manager Tel: +49-7531 3620 882 email: metzler@enerm.de RAIFFEISEN BANK SH.A. ALBANIA entecag Consulting & Engineering Bahnhofstr.

More information

Abstract. 1. Main features of the Cua Dat scheme. Hong Giang VNCOLD. Hanoi Vietnam. the Northern Central The reservoir storage purposes: - water

Abstract. 1. Main features of the Cua Dat scheme. Hong Giang VNCOLD. Hanoi Vietnam. the Northern Central The reservoir storage purposes: - water The diversion works for the Cua Dat CFRD in Vietnam Michel Ho Ta Khanh, Dinh Sy Quat, Prof Pham Hong Giang VNCOLD No 95/10 Chua Boc Street Dong Da District Hanoi Vietnam Abstract The Cua Dat CFRD is constructed

More information

2 FINDING OF THE POTENTIAL SITES

2 FINDING OF THE POTENTIAL SITES EXECUTIVE SUMMARY 1 Background S-1 2 User of Manual S-1 3 Applicable Range of Micro-hydro power in the Indonesia S-2 4 How to use this Manual S-2 Chapter 1 INTRODUCTION 1-1 1.1 Purpose of the Manual

More information

Water Control Structures Selected Design Guidelines Alberta Environment Page 14-1

Water Control Structures Selected Design Guidelines Alberta Environment Page 14-1 Alberta Environment Page 14-1 14.0 LOW LEVEL OUTLET WORKS 14.1 General In general, a low level outlet structure can be used to provide one or more of the following functions: Supply adequate water to meet

More information

Earth Brickwork Concrete Plain Radial Drum Roller Flap. fixed. Weirs Barrages. mobile. rockfills. Gravity butress Arch Arch-gravuty Cupola.

Earth Brickwork Concrete Plain Radial Drum Roller Flap. fixed. Weirs Barrages. mobile. rockfills. Gravity butress Arch Arch-gravuty Cupola. Dams type 1 Weirs Barrages fixed mobile Earth Brickwork Concrete Plain Radial Drum Roller Flap embankment Earthfills rockfills Dams Concrete gravity Arch Gravity butress Arch Arch-gravuty Cupola 2 Dams

More information

Chapter 4. Main problems in a canal network 4.1 INTRODUCTION

Chapter 4. Main problems in a canal network 4.1 INTRODUCTION Canals 21 Chapter 4 4.1 INTRODUCTION This chapter looks at problems which are frequently encountered in irrigation canal systems. Some of these are described in detail. The last section of this chapter

More information

TEMPORARY SEDIMENT TRAP CODE

TEMPORARY SEDIMENT TRAP CODE ILLINOIS URBAN MANUAL PRACTICE STANDARD TEMPORARY SEDIMENT TRAP CODE 960 Source: DEFINITION A small temporary stormwater storage structure designed to trap sediment. PURPOSE The purpose of this practice

More information

Elko Project Water Use Plan. Revised for Acceptance by the Comptroller of Water Rights

Elko Project Water Use Plan. Revised for Acceptance by the Comptroller of Water Rights Elko Project Water Use Plan Revised for Acceptance by the Comptroller of Water Rights 7 April 2005 B Elko Project Water Use Plan Revised for Acceptance by the Comptroller of Water Rights Elko Project

More information

Tender Call No.: Likhu/GVN/Pkg-03/2012 OLUME III A 1 TABLE OF CONTENTS SALIENT FEATURES 1.0 SCOPE SALIENT FEATURES... 1

Tender Call No.: Likhu/GVN/Pkg-03/2012 OLUME III A 1 TABLE OF CONTENTS SALIENT FEATURES 1.0 SCOPE SALIENT FEATURES... 1 Table of contents OLUME III A 1 TABLE OF CONTENTS SALIENT FEATURES 1.0 SCOPE... 1 1.1 SALIENT FEATURES... 1 1.2 TRANSPORT LIMITATIONS... 8 1.3 DEVIATIONS FROM SPECIFICATIONS... 9 1.4 APPROVAL OF DRAWINGS...

More information

Volume II: Hazard Annex Dam Failure

Volume II: Hazard Annex Dam Failure Volume II: Hazard Annex Dam Failure Causes and Characteristics of Dam Failure Dam Characteristics Dams are impervious structures that block the flow of water in a river or stream, capturing water behind

More information

Formal Annual Inspection It is recommended that you customize this form to fit your dam. Pre-Inspection Information

Formal Annual Inspection It is recommended that you customize this form to fit your dam. Pre-Inspection Information Formal Annual Inspection It is recommended that you customize this form to fit your dam. Pre-Inspection Information Name of Dam: Inspection Date: Current Weather: Weather During Last Week: Name of Creek,

More information

Vinnie Naidoo Technical Executive GIBB (Pty) Limited South Africa

Vinnie Naidoo Technical Executive GIBB (Pty) Limited South Africa Vinnie Naidoo Technical Executive GIBB (Pty) Limited South Africa Structure of Presentation Outline of the Project Development Phases Key Attributes of the Project Environmental Considerations Scheme Layout

More information

11/10/2009. Lake Uist - BAKER PT. Distributor from bore to penstocks Lowest level in draft tube FSL Top of surge tank.

11/10/2009. Lake Uist - BAKER PT. Distributor from bore to penstocks Lowest level in draft tube FSL Top of surge tank. Parametric Analysis of Pump- Turbine Sites J. L. Gordon, P. Eng. Fellow CSCE 190.0 FSL 203.6 Top of surge tank. Lake Uist - BAKER PT 193.0 Deck El. 2120.6 Surge tank required? Yes 169.5 Bottom of surge

More information

Hydropower retrofitted onto existing water infrastructure assets

Hydropower retrofitted onto existing water infrastructure assets Hydropower retrofitted onto existing water infrastructure assets Marco van Dijk Lecturer and Principal Researcher University of Pretoria / Water Research Commission South Africa Presentation Layout How

More information

TUG - Institute of Hydraulic Engineering and Water Resources Management 1

TUG - Institute of Hydraulic Engineering and Water Resources Management 1 Large Dams Design, Construction and Performance Gerald Zenz Graz - University of Technology 1 Dam Structures & Geotechnique Design Construction / Observation Operation / Monitoring Cooperation & Transfer

More information

HydroHelp 5 AN EXCEL PROGRAM DEVELOPED FOR PRE-FEASIBILITY ASSESSMENT PUMP-STORAGE HYDROELECTRIC SITES. J. L. GORDON P.Eng.

HydroHelp 5 AN EXCEL PROGRAM DEVELOPED FOR PRE-FEASIBILITY ASSESSMENT PUMP-STORAGE HYDROELECTRIC SITES. J. L. GORDON P.Eng. HydroHelp 5 AN EXCEL PROGRAM DEVELOPED FOR PRE-FEASIBILITY ASSESSMENT OF PUMP-STORAGE HYDROELECTRIC SITES BY J. L. GORDON P.Eng. January, 2009 HydroHelp 5 for pump-turbine sites. A continuation of the

More information

Filter Tube Barriers (Instream)

Filter Tube Barriers (Instream) Filter Tube Barriers (Instream) INSTREAM PRACTICES Flow Control No Channel Flow Dry Channels Erosion Control Low Channel Flows Shallow Water Sediment Control High Channel Flows Deep Water Symbol Photo

More information

HYDROPOWER AND WATER RESOURCES

HYDROPOWER AND WATER RESOURCES HYDROPOWER AND WATER RESOURCES Shaping our world A company of D-ZM-14137-01-00 Head of Certification body OUR EXPERTISE Hydropower and Water Resources The development, planning, design, and construction

More information

Performance improvement of headworks: a case of Kalignadaki A Hydropweor Project through physical hydraulic modelling

Performance improvement of headworks: a case of Kalignadaki A Hydropweor Project through physical hydraulic modelling Performance improvement of headworks: a case of Kalignadaki A Hydropweor Project through physical hydraulic modelling Dr. Ing. Meg B. Bishwakarma General Manager, Hydro Lab Pvt. Ltd., Nepal ABSTRACT: The

More information

Hydropower and Water Resources

Hydropower and Water Resources Hydropower and Water Resources Hydropower and Water Resources The development, planning, design, and construction of hydropower as well as large-scale irrigation schemes and special hydraulic structures

More information

DIVERSION CHANNEL OF BELO MONTE HPP

DIVERSION CHANNEL OF BELO MONTE HPP DIVERSION CHANNEL OF BELO MONTE HPP INTRODUCTION The diversion channel of Belo Monte HPP is an important engineering work which required the engagement of several specialties to be able to address all

More information

Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap (3 MW)

Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap (3 MW) Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap (3 MW) Monthly Progress Report Prepared by : Sano Milti Khola Hydropower Limited www.smi.com.np smi.investment.limited@gmail.com Date : August,

More information

Appendix 3-G SWM AND BMP CONSTRUCTION INSPECTIONS

Appendix 3-G SWM AND BMP CONSTRUCTION INSPECTIONS Appendix 3-G SWM AND BMP CONSTRUCTION INSPECTIONS Table of Contents APPENDIX SECTION HEADINGS 3-G.1.0 INTRODUCTION 3-G-2 3-G.1.1 Construction Inspections 3-G-2 3-G.1.2. As-Built Survey and Plan 3-G-2 3-G.1.2.1

More information

Techno-Economic Assessment Study Rogun HPP. Phase II Considerations. Riparian Consultations

Techno-Economic Assessment Study Rogun HPP. Phase II Considerations. Riparian Consultations Techno-Economic Assessment Study Rogun HPP Phase II Considerations Riparian Consultations July 2014 Engineering and Dam Safety Panel of Experts Presenters: R.Gill (Chair), L.Spasic-Gril, Prof. Dr. E. Todini

More information

Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent [1]

Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent [1] Diversion Channels DRAINAGE CONTROL TECHNIQUE Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent [1] [1] The design of permanent

More information

DAMS AND OTHER HYDRAULIC STRUCTURES

DAMS AND OTHER HYDRAULIC STRUCTURES GAP.2.9.1 A Publication of Global Asset Protection Services LLC DAMS AND OTHER HYDRAULIC STRUCTURES INTRODUCTION The purpose of a dam evaluation is to review the design, construction and performance history

More information

10 Project Cost Estimation

10 Project Cost Estimation 10 Project Cost Estimation Contents 10 Project Cost Estimation... 1 10.1 Project Overview... 1 10.2 Principles of Project Cost Estimation... 2 10.3 Data Basis and Assumptions for Project Cost Estimation...

More information

Block & Aggregate Drop Inlet Protection

Block & Aggregate Drop Inlet Protection Block & Aggregate Drop Inlet Protection SEDIMENT CONTROL TECHNIQUE Type 1 System Sheet Flow Sandy Soils Type 2 System [1] Concentrated Flow Clayey Soils Type 3 System Supplementary Trap Dispersive Soils

More information

PRE FEASIBILITY REPORT NUKULOA MICRO HYDRO POWER PROJECT

PRE FEASIBILITY REPORT NUKULOA MICRO HYDRO POWER PROJECT Ministry of Infrastructure and Transport PRE FEASIBILITY REPORT NUKULOA MICRO HYDRO POWER PROJECT Prepared by : Department of Energy August, 2013 [DOE] 1 Table of Contents Summary... 3 1. Geographical

More information

1 Small Hydro Power Plants Wetzmann

1 Small Hydro Power Plants Wetzmann 5 th Bulgarian-Austrian Seminar SMALL DAMS AND HPP 30 March 2012, Sofia R.9 REFURBISHMENT OF TWO SMALL HYDRO POWER PLANTS IN AUSTRIA P. Tschernutter Abstract: A weir at the River Gail, which was used for

More information

FORM B: DAMMING AND DIVERSION OF WATER

FORM B: DAMMING AND DIVERSION OF WATER APPLICATION FOR RESOURCE CONSENT FORM B: DAMMING AND DIVERSION OF WATER NOTES Resource use activities must meet all the conditions of any relevant Permitted Activity Rules in the Waikato Regional Plan

More information

Mining, Tailings and Dam Safety: the Mt. Polley Disaster and Next Steps. Dr. Andrea Kennedy, Ph.D. Bridgeway Consulting for Adams Lake Indian Band

Mining, Tailings and Dam Safety: the Mt. Polley Disaster and Next Steps. Dr. Andrea Kennedy, Ph.D. Bridgeway Consulting for Adams Lake Indian Band Mining, Tailings and Dam Safety: the Mt. Polley Disaster and Next Steps Dr. Andrea Kennedy, Ph.D. Bridgeway Consulting for Adams Lake Indian Band 11 August 2014 Presentation Outline General Introduction

More information

COMMENTS BY LAO PDR ON THE MRCS TECHNICAL REVIEW REPORT OF THE PROPOSED XAYABURI DAM PROJECT

COMMENTS BY LAO PDR ON THE MRCS TECHNICAL REVIEW REPORT OF THE PROPOSED XAYABURI DAM PROJECT COMMENTS BY LAO PDR ON THE MRCS TECHNICAL REVIEW REPORT OF THE PROPOSED XAYABURI DAM PROJECT 4. Technical Review 4.1 Xayaburi Hydropower Dam Design and Operation 4.1.1 Basic information on project layout,

More information

(b) Discuss in brief shaft spillway with neat sketches. Marks 04. OR Q (2) Explain in brief USBR stilling basin. Marks 08

(b) Discuss in brief shaft spillway with neat sketches. Marks 04. OR Q (2) Explain in brief USBR stilling basin. Marks 08 (b) Discuss in brief shaft spillway with neat sketches. Marks 04 OR Q (2) Explain in brief USBR stilling basin. Marks 08 Stilling Basins The basins are usually provided with special appurtenances including

More information

REHABILITATION OF THE LANGETENTAL FLOOD DIVERSION TUNNEL

REHABILITATION OF THE LANGETENTAL FLOOD DIVERSION TUNNEL REHABILITATION OF THE LANGETENTAL FLOOD DIVERSION TUNNEL Roger BREMEN Engineer of the Hydraulic Department Lombardi Engineering Limited Via Simen 19 CH 6648 Minusio Switzerland ABSTRACT: A 7.5 km long

More information

Module 4 Hydraulic Structures for Flow Diversion and Storage

Module 4 Hydraulic Structures for Flow Diversion and Storage Module 4 Hydraulic Structures for Flow Diversion and Storage Lesson 9 Reservoir Outlet Works Instructional objectives On completion of this lesson, the student shall learn: 1. Functions of outlet works

More information

Client: Budhi Gandaki Hydroelectric Project Development Committee. General Presentation

Client: Budhi Gandaki Hydroelectric Project Development Committee. General Presentation Client: Budhi Gandaki Hydroelectric Project Development Committee General Presentation 1. Background and objectives 2. Project location 3. Project information/features 4. Project performances 5. Environmental

More information

Inflow pipe. Drain. Drain

Inflow pipe. Drain. Drain Inflow pipe Screened overflow Drain Foul flush diverter Screened intake Manhole cover Maximum water level Seal Inspection cover Possible local drainage through screen Drain Bottom sloped Screened outlet

More information

Tips with Creation of your Erosion and Sediment Control Plan

Tips with Creation of your Erosion and Sediment Control Plan Tips with Creation of your Erosion and Sediment Control Plan By Chris Droste, CESCO Senior Erosion Control Specialist Westmoreland Conservation District Forming Your Narrative Use the DEP checklist. Page

More information

Types of Inspections. Prior to Inspection. Types of Inspections. Typical Inspection Equipment. Embankment Dams

Types of Inspections. Prior to Inspection. Types of Inspections. Typical Inspection Equipment. Embankment Dams BIA Summer Water Resources Training Dam Safety Inspections Part 4 - Inspections July 28, 2012 Presented by Michael Johnson, Ph.D., P.E. Types of Inspections Periodic Inspections A comprehensive visual

More information

Cost Analysis for High Head SHP Projects

Cost Analysis for High Head SHP Projects 2012 International Congress on Informatics, Environment, Energy and Applications-IEEA 2012 IPCSIT vol.38 (2012) (2012) IACSIT Press, Singapore Cost Analysis for High Head SHP Projects Sachin Mishra 1,

More information

Hydropower & Dams Services

Hydropower & Dams Services Hydropower & Dams Services We represent a world-class concentration of hydropower and dam expertise. Since 1920, we have designed hundreds of new hydropower and dams globally, producing clean reliable

More information

A dam and a reservoir are complements of each other.

A dam and a reservoir are complements of each other. A dam is a hydraulic structure of fairly impervious material built across a river to create a reservoir on its upstream side for impounding water for various purposes. A dam and a reservoir are complements

More information

PARR HYDROELECTRIC PROJECT PARR HYDRO DEVELOPMENT & FAIRFIELD PUMPED STORAGE FACILITY DEVELOPMENT FERC PROJECT No SC SEPTEMBER 19, 2012

PARR HYDROELECTRIC PROJECT PARR HYDRO DEVELOPMENT & FAIRFIELD PUMPED STORAGE FACILITY DEVELOPMENT FERC PROJECT No SC SEPTEMBER 19, 2012 PARR HYDROELECTRIC PROJECT PARR HYDRO DEVELOPMENT & FAIRFIELD PUMPED STORAGE FACILITY DEVELOPMENT FERC PROJECT No. 1894 - SC SEPTEMBER 19, 2012 PARR AND FAIRFIELD LOCATIONS Lockhart Neal Shoals Monticello

More information

International Panel of Experts. Safety of Nenskra Hydropower Project - Georgia

International Panel of Experts. Safety of Nenskra Hydropower Project - Georgia International Panel of Experts Safety of Nenskra Hydropower Project - Georgia STAGE II REPORT - Part 2 & Final Prepared by: Roger Gill (Chair) Ljiljana Spasic-Gril Georg Schaeren Frederic Giovannetti Tomoyuki

More information

DORDI KHOLA HYDROPOWER PROJECT. Lamjung, Nepal. Progress Report. January 2018

DORDI KHOLA HYDROPOWER PROJECT. Lamjung, Nepal. Progress Report. January 2018 DORDI KHOLA HYDROPOWER PROJECT Lamjung, Nepal Progress Report January 2018 --------------------------------------------------- Himalayan Power Partner Limited Energy Sector Research, Development & Consulting

More information

INVITATION OF BID (INTERNATIONAL COMPETITIVE BIDDING)

INVITATION OF BID (INTERNATIONAL COMPETITIVE BIDDING) INVITATION OF BID (INTERNATIONAL COMPETITIVE BIDDING) Bid Title : EPC Bid for Planning, detailed design& engineering, construction/manufacturing of civil, electro-mechanical, hydro- mechanical and switch

More information

More Creek Hydroelectric Project Prefeasibility Study

More Creek Hydroelectric Project Prefeasibility Study Alaska Hydro Corporation More Creek Hydroelectric Project June 2015 E6348 SIGMA ENGINEERING LTD 1444 Alberni Street, 4th Floor, Vancouver, BC, Canada V6G 2Z4 Phone: (604) 688-8271 Fax: (604) 688-1286 TABLE

More information

More Creek Hydroelectric Project Prefeasibility Study

More Creek Hydroelectric Project Prefeasibility Study Alaska Hydro Corporation More Creek Hydroelectric Project March 2018 E6348 SIGMA ENGINEERING LTD 1444 Alberni Street, 4th Floor, Vancouver, BC, Canada V6G 2Z4 Phone: (604) 688-8271 Fax: (604) 688-1286

More information

Compact Hydro.

Compact Hydro. Compact Hydro www.andritz.com 02 COMPACT HYDRO ANDRITZ HYDRO Worldwide leader in hydropower business The ANDRITZ GROUP is a global market leader for customized plant, process technologies and services

More information

Xayaburi Hydroelectric Power Project

Xayaburi Hydroelectric Power Project The MRC Regional Workshop on Discharge and Sediment Monitoring and Geomorphological Tool for the Lower- Mekong Basin, 21-22 22 October 2008 Xayaburi Hydroelectric Power Project TEAM Consulting Engineering

More information

Installation and Maintenance of Erosion Control BMPs

Installation and Maintenance of Erosion Control BMPs Installation and Maintenance of Erosion Control BMPs Or Common BMPs Applications Specifications Installation Problems Maintenance Utility Design Professionals Clarifications, proactive problem solving

More information

Fabric Drop Inlet Protection

Fabric Drop Inlet Protection Fabric Drop Inlet Protection SEDIMENT CONTROL TECHNIQUE Type 1 System Sheet Flow Sandy Soils Type 2 System Concentrated Flow Clayey Soils [1] Type 3 System Supplementary Trap Dispersive Soils [1] Block

More information

Some aspects of the sediment transit on the Mekong river in relation with hydropower development

Some aspects of the sediment transit on the Mekong river in relation with hydropower development Some aspects of the sediment transit on the Mekong river in relation with hydropower development Daniel Loudière Société Hydrotechnique de France A presentation in three parts - the situation when starting

More information

Water Resources. Associate Prof. Ahmed Moustafa Moussa Lecture -1 Lecture 4

Water Resources. Associate Prof. Ahmed Moustafa Moussa Lecture -1 Lecture 4 Water Resources By Associate Prof. Ahmed Moustafa Moussa Lecture -1 Lecture 4 High Aswan Dam Project 1. Location The High Aswan Dam (HAD) location was determined to fit the topographical features of the

More information

Construction Inspection Checklists

Construction Inspection Checklists III. Construction Inspection Checklists 33 Bioretention - Construction Inspection Checklist Project: Location: Site Status: Date: Time: Inspector: Construction Sequence Satisfactory / Unsatisfactory Comments

More information

THE STUDY ON INTEGRATED URBAN DRAINAGE IMPROVEMENT FOR MELAKA AND SUNGAI PETANI IN MALAYSIA FINAL REPORT

THE STUDY ON INTEGRATED URBAN DRAINAGE IMPROVEMENT FOR MELAKA AND SUNGAI PETANI IN MALAYSIA FINAL REPORT THE GOVERNMENT OF MALAYSIA PRIME MINISTER S DEPARTMENT ECONOMIC PLANNING UNIT THE STUDY ON INTEGRATED URBAN DRAINAGE IMPROVEMENT FOR MELAKA AND SUNGAI PETANI IN MALAYSIA FINAL REPORT VOL. 5: TECHNICAL

More information

USACE LEVEE RISK ASSESSMENT PROCESS LESSONS LEARNED

USACE LEVEE RISK ASSESSMENT PROCESS LESSONS LEARNED USACE LEVEE RISK ASSESSMENT PROCESS LESSONS LEARNED 1 237 237 237 217 217 217 200 200 200 80 119 27 252 174.59 255 255 255 0 0 0 163 163 163 131 132 122 239 65 53 110 135 120 112 92 56 62 102 130 102 56

More information

2.16 NAM POT HYDROPOWER PROJECT

2.16 NAM POT HYDROPOWER PROJECT 2.16 NAM POT HYDROPOWER PROJECT Nam Pot is a hydropower project of around 20 to 25 MW located in Xiangkhouang Province. Due to its size, location and economics, Nam Pot project is best suited to a domestic

More information

RÍO AMOYÁ - LA ESPERANZA Hydroelectric Power Plant

RÍO AMOYÁ - LA ESPERANZA Hydroelectric Power Plant RÍO AMOYÁ - LA ESPERANZA Hydroelectric Power Plant The power plant is located in southern Tolima, in the municipality of Chaparral, approximately 150 km from Ibague. It has an installed capacity of 80

More information

Justus B.C Mtolera Mtera Hydro plant Manager TANESCO TANZANIA

Justus B.C Mtolera Mtera Hydro plant Manager TANESCO TANZANIA Justus B.C Mtolera Mtera Hydro plant Manager TANESCO TANZANIA MAINTENANCE & REFURBISHMENT OF MTERA HYDRO POWER PLANT Layout: 1. Introduction 2. Technical data of Mtera Hydro Power Plant 3. Maintenance

More information

Chakachamna Hydro. AEA Geothermal Conference

Chakachamna Hydro. AEA Geothermal Conference Chakachamna Hydro AEA Geothermal Conference August 2007 Chakachamna Hydro 300+ MW hydro opportunity identified Preliminary FERC License application filed in May 2006 Initial scoping/informational meetings

More information

ABSTRACT. Energy is a critical factor in developing countries for economic growth as well

ABSTRACT. Energy is a critical factor in developing countries for economic growth as well ABSTRACT Energy is a critical factor in developing countries for economic growth as well as for social development and human welfare. Hydropower is a renewable source of energy, which is economical, non-polluting

More information

Feasibility Assessment of Hydroelectric Power Plant in Ungauged River Basin: A Case Study

Feasibility Assessment of Hydroelectric Power Plant in Ungauged River Basin: A Case Study Arab J Sci Eng (2013) 38:1359 1367 DOI 10.1007/s13369-013-0590-5 RESEARCH ARTICLE - CIVIL ENGINEERING Feasibility Assessment of Hydroelectric Power Plant in Ungauged River Basin: A Case Study M. Cihat

More information

Ingula Pumped Storage Scheme: Project Management Case Study

Ingula Pumped Storage Scheme: Project Management Case Study Ingula Pumped Storage Scheme: Project Management Case Study Colin Logan Project Manager Gibb Engineering & Science South Africa BRAAMHOEK CONSULTANTS JOINT VENTURE Definition of Project Management Planning,

More information

Modern Dam Safety Concepts and Seismic Safety Aspects of Sustainable Storage Dams

Modern Dam Safety Concepts and Seismic Safety Aspects of Sustainable Storage Dams Modern Dam Safety Concepts and Seismic Safety Aspects of Sustainable Storage Dams Dr. Martin WIELAND Chairman, ICOLD Committee on Seismic Aspects of Dam Design Poyry Switzerland Ltd., Zurich, Switzerland

More information

Ponds. Pond A water impoundment made by excavating a pit, or constructing a dam or an embankment.

Ponds. Pond A water impoundment made by excavating a pit, or constructing a dam or an embankment. POND SITE SELECTION AND CONSTRUCTION Uses, Planning, & Design David Krietemeyer Area Engineer USDA-NRCS June 20, 2008 Uses Considerations for Location of Commonly Used Terms Pond A water impoundment made

More information

10(a) Bridge and culvert design information

10(a) Bridge and culvert design information 10(a) Bridge and culvert design information The following information is required to accompany resource consent applications for bridges or culverts on waterways. Please answer all questions if possible.

More information

DOORNVALLEI EXT 5 & 6

DOORNVALLEI EXT 5 & 6 DOORNVALLEI EXT 5 & 6 Proposed township establishment on portion 107 the farm Doornkloof 391 JR Sewer Pipe Crossings - Sesmylspruit Construction Method Statement April 2016 Revision 3 PREPARED FOR: PREPARED

More information

Annex 4. Technical Guideline

Annex 4. Technical Guideline Annex 4 Technical Guideline 1 Contents 1. Purpose of Technical Guideline 2. Scope of Feasibility Study 3. Socio-economic and social/natural environments survey 4. Topographical survey 4.1 Collection of

More information

Estimating Hydropower Potential of an Ungauged Stream

Estimating Hydropower Potential of an Ungauged Stream Estimating Hydropower Potential of an Ungauged Stream Umaru Garba Wali Water Resources and Environmental Management Programme, Department of Civil Engineering, School of Engineering, College of Science

More information

Types of Inspections

Types of Inspections BIA Summer Water Resources Training Dam Safety Inspections Part 4 - Inspections July 28, 2012 Presented by Michael Johnson, Ph.D., P.E. Types of Inspections Periodic Inspections A comprehensive visual

More information

MIEL I Hydroelectric Power Plant

MIEL I Hydroelectric Power Plant MIEL I Hydroelectric Power Plant The Miel I Power Plant, which is located in the municipality of Norcasia, forms part of the hydro potential in western Caldas. This region comprises the basins of the rivers

More information

STANDARDS/MANUALS/ GUIDELINES FOR SMALL HYDRO DEVELOPMENT

STANDARDS/MANUALS/ GUIDELINES FOR SMALL HYDRO DEVELOPMENT STANDARDS/MANUALS/ GUIDELINES FOR SMALL HYDRO DEVELOPMENT General Works Guidelines for Layout of SHP Plants Sponsor: Ministry of New and Renewable Energy Govt. of India Lead Organization: Alternate Hydro

More information

DRAFT SEDIMENT and EROSION CONTROL PLAN. BLUE LAKE HYDROELECTRIC PROJECT (FERC No. 2230) EXPANSION. Prepared by:

DRAFT SEDIMENT and EROSION CONTROL PLAN. BLUE LAKE HYDROELECTRIC PROJECT (FERC No. 2230) EXPANSION. Prepared by: DRAFT SEDIMENT and EROSION CONTROL PLAN BLUE LAKE HYDROELECTRIC PROJECT (FERC No. 2230) EXPANSION Prepared by: Electric Department 1.0 INTRODUCTION The Electric Department ( City ) is in the process of

More information

CHAPTER 8 SEEPAGE CONTROL IN EMBANKMENTS

CHAPTER 8 SEEPAGE CONTROL IN EMBANKMENTS CHAPTER 8 SEEPAGE CONTROL IN EMBANKMENTS 8-1. General. All earth and rock-fill dams are subject to seepage through the embankment, foundation, and abutments. Seepage control is necessary to prevent excessive

More information

ANNEXURE-III SALIENT FEATURES OF DUGAR HYDRO ELECTRIC PROJECT. Himachal Pradesh. Latitude. Longitude Nearest Railhead; Udhampur (J&K)

ANNEXURE-III SALIENT FEATURES OF DUGAR HYDRO ELECTRIC PROJECT. Himachal Pradesh. Latitude. Longitude Nearest Railhead; Udhampur (J&K) ANNEXURE-III SALIENT FEATURES OF DUGAR HYDRO ELECTRIC PROJECT Project Location State District River Vicinity Latitude Longitude Nearest Railhead; Udhapur (J&K) Hiachal Pradesh Chaba Chenab River Luj village

More information

Tailings Facility Risk, Resilience, and Robustness

Tailings Facility Risk, Resilience, and Robustness Tailings Facility Risk, Resilience, and Robustness Andrew Robertson and Jack Caldwell Robertson Geoconsultants Tailings and Mine Waste 2017 It is all about Judgment THE THESIS OF THIS PAPER Summary of

More information

Temporary Watercourse Crossing: Culverts

Temporary Watercourse Crossing: Culverts Temporary Watercourse Crossing: Culverts DRAINAGE CONTROL TECHNIQUE Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent Symbol

More information

Comments on failures of small dams in the Czech Republic during historical flood events

Comments on failures of small dams in the Czech Republic during historical flood events Comments on failures of small dams in the Czech Republic during historical flood events J. RIHA, Brno University of Technology, Zizkova 17, 66237 Brno, CZ. SYNOPSIS. During the catastrophic floods, namely

More information

Effect of the Entrance Zone on the Trapping Efficiency of Desilting Tanks in Run-of-River Hydropower Plants

Effect of the Entrance Zone on the Trapping Efficiency of Desilting Tanks in Run-of-River Hydropower Plants Effect of the Entrance Zone on the Trapping Efficiency of Desilting Tanks in Run-of-River Hydropower Plants S. B. Weerakoon and U. S. Rathnayake Department of Civil Engineering, University of Peradeniya,

More information

Lower Erkhuwa Hydropower Project (14.15 Mw) 1. INTRODUCTION. 1.1 General. 1.2 Establishment of the Company. 1.3 Special Features of the Project

Lower Erkhuwa Hydropower Project (14.15 Mw) 1. INTRODUCTION. 1.1 General. 1.2 Establishment of the Company. 1.3 Special Features of the Project Lower Erkhuwa Hydropower Project (14.15 Mw) 1. INTRODUCTION 1.1 General The Lower Erkhuwa hydropower Project is located in Kulung and Chauki Danda VDCs of Bhojpur District, in East Nepal. It is located

More information

Dam Safety and Low Cost Spillway Designs

Dam Safety and Low Cost Spillway Designs Dam Safety and Low Cost Spillway Designs By F. Lempérière & J.P. Vigny (Hydrocoop France) THE CHALLENGE 5 th International Conference on Dam Engineering Lisbon 14-16 February 2007 Increasing dams safety

More information

Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap (3 MW)

Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap (3 MW) Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap (3 MW) Monthly Progress Report Prepared by : Sano Milti Khola Hydropower Limited www.smi.com.np smi.investment.limited@gmail.com Date : August,

More information

USE OF GABIONS IN SMALL HYDRAULIC WORKS

USE OF GABIONS IN SMALL HYDRAULIC WORKS USE OF GABIONS IN SMALL HYDRAULIC WORKS SECTION 1 SITE SELECTION FOR SMALL DAMS Table of Contents 1.1 CLASSIFICATION ACCORDING TO USE... 2 1.2 CLASSIFICATION BY HYDRAULIC DESIGN (site and basin requirements)...2

More information

Checklist for Joint Agency Review Stormwater Management / Erosion and Sediment Control

Checklist for Joint Agency Review Stormwater Management / Erosion and Sediment Control Page 1 of 7 Updated 12/28/2017 Checklist for Joint Agency Review Stormwater Management / Erosion and Sediment Control Project Name: Tax Map: Parcel: Lot: Disturbed Acreage: Engineering Firm: Phone Number:

More information