Independent Consulting Engineers NV Zaegersgut Rd #13 tel +(599) Date: 25 januari 2008 Project: Troy Hill Saba Projectnr:

Similar documents
Bill of Quantities. Bill 1: Site Preparatory Works. Page No. 1/7. Bill 1 Page 1/1. Contract No.

SECTION MEASUREMENT AND PAYMENT

EXTERNAL WORKS EXCAVATION,BACKFILLING & SITE WORKS

VILLAGE OF LOMBARD CONTRACT DOCUMENT NUMBER SS BID PROPOSAL

T. P. Concrete, Inc. Wood Sewer & Excavating, Inc. 589 CY , , , SF

902 - EXCAVATION AND BACKFILL FOR STRUCTURES - OPSS Bridges - Working slabs/pads - footings for piers and abutments - wingwalls

WORKS DESCRIPTION Unit. Quantity Unit price Total USD

SUM i) Carry out calibration of 100,000 litres day tank. ii) Pipes, valves and other fittings connection to fuel offloading SUM

INVITATION TO TENDER ITT / PS VANCOUVER LANDFILL FRONT ENTRANCE REDESIGN - PRELOAD QUESTIONS AND ANSWERS NO.1

YES, we received Addendum No. 1

OKLAHOMA TURNPIKE AUTHORITY JUNE 7, 2018 SCHEDULE OF BID ITEMS EOC JP 26422(10) INTERCHANGE AT I-40

c. Sprinkler layout. Sprinkler layout may be modified to adjust for field conditions provided it complies with part

RFP/GRC/LSV/ : RENOVATION (CIVIL WORKS) AT SKALA SYKAMNIAS CHILDRENS PLAYGROUND BILL OF QUANTITIES

ADDRESS: 122 LIPSCOMBE ROAD, DECEPTION BAY, QLD,

SECTION MEASUREMENT AND PAYMENT

UNOPS UNITED NATIONS OFFICE FOR PROJECT SERVICES PROJECT BOQ. Original Issue Bamyan MAC Site Services - Phase 1 Bamyan, Bamyan, Afghanistan

CITY OF ATLANTA PARTNERSHIP Small Business Development Program Contractor/Consultant Questionnaire

PITTSBURGH TECHNOLOGY CENTER PUBLIC IMPROVEMENTS SITE PREPARATION CONTRACT NO. 11 BID TABULATION BID OPENING DATE: MARCH 11, 2008

CITY AND COUNTY OF DENVER DEPARTMENT OF PUBLIC WORKS CONTRACT NO COLORADO CENTER BICYCLE/PEDESTRIAN BRIDGE OVER I-25

ESTIMATED DISTRIBUTION OF MATERIAL LIST Lomitas Negras Phase 2 Southern Sandoval County Arroyo Flood Control Authority

Employment Intensive Infrastructure Program (EIIP) in Lebanon ANNEX 2

TABULATION OF BIDS DENVER INTERNATIONAL AIRPORT. Denver, Colorado CONTRACT NO. CE CONCOURSE C EAST APRON EXPANSION BID SUMMARY

CONNECTION TO INSPECTION CHAMBERS PRAKTO

Electrical Work. NOV Embankments Over Swamps and Compressible Soils

1. Division 01 Section General Requirements - Temporary Facilities and Controls. 2. Division 31 Section Earthwork.

MATERIAL SPECIFICATION FOR CIRCULAR AND ELLIPTICAL CONCRETE PIPE

Answer 1: The reference to CB 5 is incorrect. The correct reference should be CB 4. Question 2: Have any potential staging areas been identified?

(SIZE) MANHOLES CATCH BASINS AND DITCH INLETS -Item No. ADJUSTING AND REBUILDING MANHOLES, CATCH BASINS AND DITCH INLETS - Item No.

MAY 11, 2017 T-MC-107A & T-MC-107B1

CITY AND COUNTY OF DENVER

2013 ANNUAL AIRFIELD PAVEMENT REHABILITATION CONTRACT NO ADDENDUM NUMBER TWO. Scope of this Addendum

Division IV Section 4100 Measurement and Payment PUBLIC WORKS DEPARTMENT

GWINNETT COUNTY STORM SEWER PIPE STANDARDS

CITY OF ROCKLIN STANDARD DRAWINGS

GILMORE & ASSOCIATES, INC. Engineers - Surveyors Columbus, Nebraska Howard Blvd.; P.O. Box 581 Columbus, NE Telephone: (402)

SINAR AHS BILL OF QUANTITIES Cost code Description Unit Qty 1 SINAR AHS Contractors General Conditions Site Works Setting out works: Rates

Kansas Department of Transportation DISTRICT TE / TA-T045 (501) Project(s): Min: Max:

FORM OF TENDER RITHET RESERVOIR DRAIN PROJECT ( TITLE OF CONTRACT ) T 34/16 ( OWNER S CONTRACT REFERENCE NO. )

PROJECT SCOPE OF WORK CITY OF TOWN AND COUNTRY STORMWATER PROGRAM

CW 3240 RENEWAL OF EXISTING CURBS TABLE OF CONTENTS

REVISED PER ADDENDUM No. 1 - Unit Price Bid Schedule

MINISTRY OF REGIONAL DEVELOPMENT AND PUBLIC WORKS ISPA IMPLEMENTING AGENCY

General Legend Details...100

Highway Drainage 1- Storm Frequency and Runoff 1.1- Runoff Determination

D-1 THE CITY OF HARRISBURG 1 1/2" MIN. ID-2 WEARING COARSE EXISTING STREET SURFACE AC-20 SEALER (ALL AROUND) 1 1/2" MIN. ID-2 BINDER COARSE

MATERIAL SPECIFICATION FOR CIRCULAR AND ELLIPTICAL CONCRETE PIPE

BILL OF QUANTITIES. Construction and Rehabilitation of wadi Gaza Bridges PAL Funded by Government of Brazil

SPECIAL SPECIFICATION 6666 Charter Communications System

The International Committee of the Red Cross

1.00 LS $150, $ 150, $ 150, $ 150, $ 150, $ 150, $ 150, $ 150, $ 150, $ 150,000.

ADDENDUM NO. 2 TO THE TENDER DOCUMENTS FOR THE CORPORATION OF THE CITY OF PENTICTON 2015 Capital Works 2015-Tender-02

ADDENDUM NO. 1 SR163/N 46TH ST TO N 54TH ST INTERSECTION IMPROVEMENT PROJECT REVISIONS TO CONTRACT DOCUMENTS

PRECAST RECTANGULAR CHAMBERS

ADDENDUM NO. 1 TO THE TENDER DOCUMENTS FOR THE CORPORATION OF THE CITY OF PENTICTON 2015 Capital Works 2015-Tender-02

S T A T E O F M I N N E S O T A D E P A R T M E N T O F T R A N S P O R T A T I O N DATE : 01/22/02 PAGE : 1 TABULATION OF BIDS

SECTION A1 EXCAVATION AND BACKFILL GENERAL

Exhibit A Scope Work Inclusions Revised Addendum 2 May 14, 2018

CHECK THE LOWER RIGHT CORNER OF EACH DETAIL FOR THE LATEST REVISION.

A. Introduction 7 1. Purpose 7 2. Authority 7 3. Contact 8 4. Plan Submittal Process 8 B. Design Standards General 11 a. Future Extensions 11

ADVERTISEMENT SET DECEMBER 2013

CW 3235 RENEWAL OF EXISTING MISCELLANEOUS CONCRETE SLABS TABLE OF CONTENTS

TENDER NO TABULATION OF TENDERS INFRASTRUCTURE AND TRANSPORTATION SUMMARY OF PRICES CONTRACTOR SECTION 1 SECTION 2 BID TOTAL

Water Main/Storm Sewer Separation

CHAPTER 12 INSTALLATION OF UTILITIES AND OTHER SYSTEMS TABLE OF CONTENTS

M I N N E S O T A D O T BID TABULATION SUMMARY JOB PAGE 1 ON 03/16/94 MINNESOTA PROJECT NO.S: STP 5822(002)

CONSTRUCTION SPECIFICATION FOR POLE ERECTION

SECTION UNIT PRICES. A. This Section specifies administrative and procedural requirements for the unit prices.

SECTION 303 CULVERTS

MINNESOTA AVENUE NE REVITALIZATION PHASE II CONSTRUCTION MANAGER S WEEKLY PROGRESS REPORT

SCHEDULE OF QUANTITIES AND PRICES

GUIDELINES FOR RETAINING WALLS 4-0 IN HEIGHT OR LESS

APPENDIX F: CALTRANS COST ESTIMATE TEMPLATE (included in Appendix AA of the CALTRANS Project Development Procedures Manual)

SECTION FOUNDATION DRAINAGE

STATE OF MINNESOTA DEPARTMENT OF TRANSPORTATION - TABULATION OF BIDS. Start Dt: 05/05/17 Comp. Dt: 08/20/20

406 - PIPE SEWERS - MTC FORM 406

2015 Financial Assurance (Basic form) 3/17/2015 Estimate Form

SUPPLEMENTAL DRAWINGS

DESIGN STANDARDS. Division 02 Existing Conditions- Site Work. General

SECTION FACILITY SANITARY SEWERS

SPECIAL SPECIFICATION. Water and Sewer System and Appurtenances

BRITISH CONSTRUCTIONAL STEELWORK ASSOCIATION LIMITED

IFB # R Blythe Creek Grinder Pump Eliminations

TS 805 POLES TTS CONSTRUCTION SPECIFICATION FOR POLE INSTALLATION TTS MATERIAL SPECIFICATION FOR STEEL POLES BASE MOUNTED

Q&A: The Block/Parsons Alley Construction RFP

2018 Street Reconstruction Project Woodside/Huron Neighborhood Street Improvements. December 11, 2017 Public Improvement Hearing

The Contract Documents for the referenced project are hereby amended in the following particulars only, with all other conditions remaining unchanged.

Index to Technical Specifications

New Fulton State Hospital Energy Control Center and Services Building (ECC/SVC) Project Number: M

TS 803 DUCTS DUCT INSTALLATION, PROTECTION AND MARKING WITHIN A TRENCH OPEN TRENCH DUCT INSTALLATION PROFILE

To receive future notification of specification revisions, provide your address to Bruce Peters at:

A Provide for Contractor's Office, Store etc. Sum

ADDENDUM #1 TO THE SPECIFICATION FOR THE CONSTRUCTION OF THE 115KV STONEBREAK RD. TRANSITION STATION THE TOWN OF MALTA AND A PORTION OF THE 115KV

ADDENDUM NO. 1 TO THE TENDER DOCUMENTS FOR THE CORPORATION OF THE CITY OF PENTICTON 2017-Tender Capital Works

Addendum No. 1 Issue Date: March 29, 2016

SECTION 39 - MANHOLES TABLE OF CONTENTS 39-1 GENERAL PRECAST CONCRETE MANHOLES

BID FORM (LUMP SUM CONTRACT)

ITEM D-701 PIPE FOR STORM DRAINS AND CULVERTS

Project: King Abdulaziz International Airport KAIA 2

July Bill No.1: Preliminaries

E. GILMAN STREET, N. PINCKNEY STREET, AND N. BUTLER STREET RESURFACING WITH UTILITIES ASSESSMENT DISTRICT CONTRACT NO DATE: 9/22/17

Transcription:

(Na) (Na) (Na) 1 Preparational works 1.1 Survey roads 1 sum 25,000.00 25,000.00 1.2 Clearing terrain roads 1 sum 45,000.00 45,000.00 Main 2 Earth work 2.1 Earth work 2.11 Excavate terrain 8900 m3 30.00 267,000.00 2.12 Backfill of excavated soil 3425 m3 25.00 85,625.00 2.13 Transport of excavated soil 5475 m3 40.00 219,000.00 2.2 Concrete pavement 2.21 Supply and proccess of concrete for the road (B25) 723 m3 600.00 433,800.00 2.3 Reinforcement 2.31 Supply and process reinforcement steel 36150 kg 3.60 130,140.00 2.4 Dowels/Sleeve's 2.41 Supply and process dowels longitudinal joint 2036 kg 3.60 7,329.60 2.42 Supply and process dowels cross joint 3636 kg 3.60 13,089.60 2.43 Supply and process sleeves, PVC 1212 pc 5.50 6,666.00 Gutter 2.5 Concrete 2.51 Supply and proccess of concrete for the road (B25) 90 m3 600.00 54,000.00 2.6 Reinforcement 2.61 Supply and process reinforcement steel 2700 kg 3.60 9,720.00 3 Retaining wall: type A 3.1 Natural Stone 3.11 Supply and process natural stone 364 m2 250.00 91,000.00 3.2 Reinforcement 3.21 Supply and process reinforcement steel 1300 kg 3.60 4,680.00 4 Retaining wall: type B 4.1 Concrete 4.11 Supply and install concrete 15 m3 600.00 9,000.00 4.2 Reinforcement 4.21 Supply and process reinforcement steel base 600 kg 3.60 2,160.00 4.3 Natural Stone 4.31 Supply and process natural stone 375 m2 375.00 140,625.00 4.4 Reinforcement 4.41 Supply and process reinforcement steel 1200 kg 3.60 4,320.00 4.5 Drain pipe 4.51 Supply and process drain pipe d=2" 45 m1 15.00 675.00 5 Retaining wall: type C 5.1 Concrete 5.11 Supply and install concrete 320 m3 600.00 192,000.00 5.2 Reinforcement 5.21 Supply and process reinforcement steel 24000 kg 3.60 86,400.00 5.3 Drain pipe 5.31 Supply and process drain pipe d=2" 200 m1 15.00 3,000.00 70,000.00 571,625.00 433,800.00 130,140.00 27,085.20 54,000.00 9,720.00 91,000.00 4,680.00 9,000.00 2,160.00 140,625.00 4,320.00 675.00 192,000.00 86,400.00 3,000.00 Management Estimation Page 1 27/01/2003

(Na) (Na) (Na) A1 6 Earth work 6.1 Earth work 6.11 Excavate terrain 400 m3 30.00 12,000.00 6.12 Backfill of excavated soil 165 m3 25.00 4,125.00 6.13 Transport of excavated soil 235 m3 40.00 9,400.00 25,525.00 6.2 Concrete pavement 6.21 Supply and proccess of concrete for the road (B25) 61 m3 600.00 36,600.00 36,600.00 6.3 Reinforcement 6.31 Supply and process reinforcement steel 3050 kg 3.60 10,980.00 10,980.00 6.4 Dowels/Sleeve's 6.41 Supply and process dowels longitudinal joint 279 kg 3.60 1,004.40 6.42 Supply and process dowels cross joint 295 kg 3.60 1,062.00 6.43 Supply and process sleeves, PVC 164 pc 5.50 902.00 Gutter 2,968.40 6.5 Concrete 6.51 Supply and proccess of concrete for the road (B25) 11 m3 600.00 6,600.00 6,600.00 6.6 Reinforcement 6.61 Supply and process reinforcement steel 332 kg 3.60 1,195.20 1,195.20 7 Retaining wall: type A 7.1 Natural Stone 7.11 Supply and process natural stone 49 m2 250.00 12,250.00 12,250.00 7.2 Reinforcement 7.21 Supply and process reinforcement steel 248 kg 3.60 892.80 892.80 8 Retaining wall: type C 8.1 Concrete 8.11 Supply and install concrete 43 m3 600.00 25,800.00 25,800.00 8.2 Reinforcement 8.21 Supply and process reinforcement steel 3225 kg 3.60 11,610.00 11,610.00 8.3 Drain pipe 8.31 Supply and process drain pipe d=2" 45 m1 15.00 675.00 675.00 Management Estimation Page 2 27/01/2003

(Na) (Na) (Na) A4 9 Earth work 9.1 Earth work 9.11 Excavate terrain 830 m3 30.00 24,900.00 9.12 Backfill of excavated soil 0 m3 25.00-9.13 Transport of excavated soil 830 m3 40.00 33,200.00 58,100.00 9.2 Concrete pavement 9.21 Supply and proccess of concrete for the road (B25) 52 m3 600.00 31,200.00 31,200.00 9.3 Reinforcement 9.31 Supply and process reinforcement steel 2600 kg 3.60 9,360.00 9,360.00 9.4 Dowels/Sleeve's 9.41 Supply and process dowels longitudinal joint 237 kg 3.60 853.20 9.42 Supply and process dowels cross joint 250 kg 3.60 900.00 9.43 Supply and process sleeves, PVC 139 pc 5.50 764.50 Gutter 2,517.70 9.5 Concrete 9.53 Supply and proccess of concrete for the road (B25) 9 m3 600.00 5,400.00 5,400.00 9.6 Reinforcement 9.63 Supply and process reinforcement steel 270 kg 3.60 972.00 972.00 10 Retaining wall: type A 10.1 Natural Stone 10.11 Supply and process natural stone 42 m2 250.00 10,500.00 10,500.00 10.2 Reinforcement 10.21 Supply and process reinforcement steel 210 kg 3.60 756.00 756.00 11 Retaining wall: type B 11.1 Concrete 11.11 Supply and install concrete 4 m3 600.00 2,400.00 2,400.00 11.2 Reinforcement 11.21 Supply and process reinforcement steel base 160 kg 3.60 576.00 576.00 11.3 Natural Stone 11.31 Supply and process natural stone 100 m2 375.00 37,500.00 37,500.00 11.4 Reinforcement 11.41 Supply and process reinforcement steel 310 kg 3.60 1,116.00 1,116.00 11.5 Drain pipe 11.51 Supply and process drain pipe d=2" 12 m1 15.00 180.00 180.00 Management Estimation Page 3 27/01/2003

(Na) (Na) (Na) BB 12 Earth work 12.1 Earth work 12.11 Excavate terrain 1394 m3 30.00 41,820.00 12.12 Backfill of excavated soil 34 m3 25.00 850.00 12.13 Transport of excavated soil 1360 m3 40.00 54,400.00 12.2 Concrete pavement 12.21 Supply and proccess of concrete for the road (B25) 110 m3 600.00 66,000.00 12.3 Reinforcement 12.31 Supply and process reinforcement steel 5500 kg 3.60 19,800.00 12.4 Dowels/Sleeve's 12.41 Supply and process dowels longitudinal joint 503 kg 3.60 1,810.80 12.42 Supply and process dowels cross joint 533 kg 3.60 1,918.80 12.43 Supply and process sleeves, PVC 296 pc 5.50 1,628.00 Gutter 12.5 Concrete 12.53 Supply and proccess of concrete for the road (B25) 20 m3 600.00 12,000.00 12.6 Reinforcement 12.63 Supply and process reinforcement steel 600 kg 3.60 2,160.00 13 Retaining wall: type A 13.1 Natural Stone 13.11 Supply and process natural stone 89 m2 250.00 22,250.00 13.2 Reinforcement 13.21 Supply and process reinforcement steel 448 kg 3.60 1,612.80 14 Retaining wall: type B 14.1 Concrete 14.11 Supply and install concrete 4 m3 600.00 2,400.00 14.2 Reinforcement 14.21 Supply and process reinforcement steel base 160 kg 3.60 576.00 14.3 Natural Stone 14.31 Supply and process natural stone 100 m2 375.00 37,500.00 14.4 Reinforcement 14.41 Supply and process reinforcement steel 310 kg 3.60 1,116.00 14.5 Drain pipe 14.51 Supply and process drain pipe d=2" 12 m1 15.00 180.00 97,070.00 66,000.00 19,800.00 12,000.00 2,160.00 22,250.00 1,612.80 2,400.00 576.00 37,500.00 1,116.00 180.00 Management Estimation Page 4 27/01/2003

(Na) (Na) (Na) 15 Utilities 15.1 Supply and install utility cables incl. Manholes and meterwalls 1 sum 600,000.00 600,000.00 600,000.00 Subtotal 2,988,569 INDIRECT COST Subtotal 2,988,569 General construction site expenses 8% 239,086 Subtotal 3,227,655 General operating expenses 8% 258,212 Subtotal 3,485,867 Profit Interest Risk Contribution 10% 348,587 Total exclusive estimation 3,834,454 Constingency 5% 191,723 Total inclusive estimation 4,026,176 Management Estimation Page 5 27/01/2003