TECHNICAL MEMORANDUM

Similar documents
Technical Memorandum

Run-on and Run-off Control System Plan

Technical Memorandum Sycamore Tailings and Barrel Waste Alternative Stormwater Assessment

Technical Memorandum

2015 ANNUAL ENGINEERING INSPECTION REPORT ENTERGY INDEPENDENCE PLANT CLASS 3N LANDFILL PERMIT NO S3N-R2 AFIN:

Technical Memorandum Barrel Only Alternative Stormwater Assessment

Details of the Proposed Action

2017 ANNUAL ENGINEERING INSPECTION REPORT ENTERGY INDEPENDENCE PLANT CLASS 3N LANDFILL PERMIT NO S3N-R2 AFIN:

Bioreactor Landfill Design

Technical Memorandum Barrel and McCleary Alternative Stormwater Assessment

MOUNT POLLEY MINING CORPORATION MOUNT POLLEY MINE REPORT ON FEASIBILITY DESIGN OF TEST HEAP LEACH PAD (REF. NO. VA /15-2) EXECUTIVE SUMMARY

Brickhaven No.2 Mine Tract A Structural Fill

VISUAL SITE INSPECTION REPORT

Closure Plan Limited Purpose Landfill TransAlta Centralia Mine

CCP Annual Inspection Report

2015 ANNUAL ENGINEERING INSPECTION REPORT ENTERGY WHITE BLUFF PLANT CLASS 3N LANDFILL PERMIT NO S3N-R3 AFIN:

Leachate Management Leachate Control and Collection

Rosemont Copper Project Dual Phase Heap Leach Facility

Muskeg River Mine Dedicated Disposal Area (DDA) Plan for In-pit Cell 1

2015 ANNUAL ENGINEERING INSPECTION REPORT PLUM POINT ENERGY STATION CLASS 3N LANDFILL PERMIT NO S3N AFIN:

Inspection Report. David Burton, Facility Manager (NRG Indian River Generating Station)

Technical Memorandum

CCP Annual Inspection Report

(Instructions and explanations of bid items and sources of unit costs are provided on the back of this page.)

Technical Memorandum Mine Plan of Operations Stormwater Assessment

High Density Polyethylene (HDPE) Lined Evaporation Ponds

December 19, GEI Project No Mr. Tim Muehlfeld, P.E. WEC Business Services, LLC 333 W. Everett Street, A231 Milwaukee, Wisconsin 53203

Upland Landfill Waste Discharge Application 7295 Gold River Highway Campbell River, British Columbia

Technical Memorandum

Abandoned Mine Waste Repositories: Site Selction, Design, and Cost

LANDFILL CLOSURE PLAN. Submitted To: Dominion Chesapeake Energy Center 2701 Vepco Street Chesapeake, Virginia 23323

High Density Polyethylene (HDPE) Lined Produced/Frac Flowback Water Evaporation Ponds

Attachment D-1: Civil/Structural Scope of Work

Intended Construction Sequence East Brine Pond

LESSONS LEARNED FROM A LANDFILL SLOPE FAILURE INVOLVING GEOSYTNTHETICS

VISUAL SITE INSPECTION REPORT 2018

NICO Tailings and Mine Rock Co-disposal Facility (CDF) Design Concept

Mr. Michael Malone CPS Energy 145 Navarro Street San Antonio, Texas Project No

UPPER MISSISSIPPI RIVER COMPREHENSIVE PLAN

Bowling Green, Kentucky Stormwater Best Management Practices (BMPs) Sediment Management Practices (SMPs) Activity: Temporary Inlet Protection (TIP)

2016 ANNUAL STRUCTURAL STABILITY INSPECTION REPORT

WELSH POWER PLANT ASH LANDFILL. Run-on and Run-off Control System Plan

Suggested Stormwater Management Practices For Individual House Lots

Coal Combustion Product Risk Assessment Using a Probabilistic Cost Modeling Approach

Jacobi, Toombs, and Lanz, Inc.

0 TRC. Closure Plan for CCR Surface Impoundments. Clover Power Station, Clover, Virginia. October 2016

Stage One North Detail Refer to Geoscience Drawings

Niagara Falls Storage Site Safety Measures During Remediation

5/25/2017. Lumpkin Detention Basin Houston, Texas By Brian Whitney, P.E., CFM Victor Rendon. Lumpkin Basin. Lumpkin Road Overall Description

Lessons Learned from the On-Site Disposal Facility at Fernald Closure Project

ATTACHMENT 5 Rosemont Area-Wide Fate and Transport and DIA Summary Tetra Tech August 31, 2010

Capping of Landfill Containing Hazardous Materials. Water Resources Research Center Conference

Written Closure Plan. Comanche Station - Active CCR Landfill Public Service Company of Colorado Denver Colorado. October 17, 2016

Structured Geomembrane Liners in Landfill Base and Closure Systems

A Comparison of Actual vs. Predicted Leachate Generation

More information on the site soil needs, soils balance, and borrow soil evaluations is provided in Section 4.15, Soil Borrow Sources. 4.

Closure Plan Ash Disposal Area PGE Boardman Power Plant

2017 Annual Landfill Inspection Report

SE-6 GRAVEL BAG BERM. Objectives. Potential Alternatives

INITIAL RUN-ON AND RUN-OFF CONTROL PLAN 40 C.F.R. PART 257

AMERICAN ELECTRIC POWER (SWEPCO)

Integrated Mine Waste Storage Concept, Krumovgrad Gold Project, Bulgaria

m³ R R m 3.km R 8.00 R

Page 1 of 6 Permit No: MN R J. Mineral Mining and Dressing

2017 Annual Inspection Report

CLOSURE AND POST-CLOSURE CARE PLAN JAMES RIVER POWER STATION UTILITY WASTE LANDFILL CITY UTILITIES OF SPRINGFIELD, MISSOURI

LANDFILL CLOSURE PLAN ENTERGY ARKANSAS, INC. INDEPENDENCE PLANT CLASS 3N CCR LANDFILL PERMIT NO S3N-R2 AFIN

- Earthwork Operations & Equipments

PROJECT SCOPE OF WORK CITY OF TOWN AND COUNTRY STORMWATER PROGRAM

ADDENDUM NO. 1. DATE ISSUED: June 1, 2018

CCR Impoundment Closure: Reshaping your Ash! 2017 MWCC Technical Conference

LANDFILL CLOSURE PLAN PLUM POINT ENERGY STATION CLASS 3N CCR LANDFILL PERMIT NO S3N AFIN:

GRADING, EROSION AND SEDIMENTATION CONTROL

Appendix B Addendum 1 - Revisions to the Operation and Training Plan (dated November 2015) for the Indian River County Class I Landfill

BIG BEND POWER STATION NORTH AND SOUTH ECONOMIZER ASH PONDS CLOSURE PLAN. Prepared for

Leachate Management Plan

- TAILINGS AND WATER MANAGEMENT FOR A COLD REGIONS MINE - Dr. Michael Davies, P.Eng., P.Geo. and Mr. Mathieu Veillette, P.Eng., P.E.

TOWN OF MOUNT PLEASANT WESTCHESTER COUNTY, NEW YORK

Consulting Engineers and Scientists. Closure Plan. Submitted by: GEI Consultants, Inc Voyager Drive Green Bay, Wisconsin

PROJECT SCOPE OF WORK CITY OF TOWN AND COUNTRY STORMWATER PROGRAM

WATER TREATMENT PLANT PRELOADING AND SEDIMENT CONSOLIDATION AREA 2010 CONSTRUCTION WORK PLAN

VICINITY MAP AND SITE MAP. Page 1 of 9

Technical Specifications Okeechobee Landfill

NRG BRANDYWINE ASH STORAGE SITE BRANDYWINE, MARYLAND 2015 ANNUAL CCR INSPECTION REPORT

Table of Contents. Attachments Attachment A Photos Attachment B Inspection Map. Pages 3 of 10

Las Pulgas Landfill Phase I Clean Closure Marine Corps Base Camp Pendleton, Ca

HOLLOW ROCK FACILITY 2016 ANNUAL LANDFILL INSPECTION REPORT FOR COAL COMBUSTION RESIDUALS (CCR) EXISTING LANDFILL

STATE OF ARIZONA AQUIFER PROTECTION PERMIT NO. P PLACE ID , LTF 49639

CCR Rule Operating Criteria Closure Plan

Greenfield Pond B Rehabilitation

DATE: October 31, 2016 FILE: /CV TO: Chair and directors Comox Valley Regional District (Comox Strathcona waste management) board

Technical Memorandum

BALLAST PRODUCTION CURRY QUARRY

Table of Contents. Attachments Attachment A Photos Attachment B Site Map. Pages 3 of 9

Timber Sale Appraisal More Cow Bell Sale FG W

Closure/Post-Closure Care Plan Unit 3 AQCS Solids Landfill

INITIAL RUN-ON AND RUN-OFF CONTROL PLAN 40 C.F.R. PART 257

SMART GYPSUM STACK MANAGEMENT FROM CONCEPT TO REALITY

HISTORY OF CONSTRUCTION 40 CFR (c)(1)(i) (xii) PLANT HAMMOND ASH POND (AP 2) GEEORGIA POWER COMPANY

Evaluation of Drainage Layer Alternatives for Proposed Landfill Liner at the E.W. Brown Generating Station

Transcription:

FOR INTERNAL DISCUSSION PURPOSES ONLY TECHNICAL MEMORANDUM TO: Augusta Resource Corp. ATTENTION: Jamie Sturgess FROM: Troy Meyer Project Manager, Vector Colorado LLC (Vector) DATE: June 5, 2006 SUBJECT: Conceptual Heap Leach Pad Design Layout PROJECT #: Rosemont Mine / 06.50.0300 1.0 General As requested by Augusta as part of the Preliminary Economic Assessment for the Rosemont Mine, this report presents conceptual design and cost estimates for the development of the Heap Leach Pad proposed for the Project. The conceptual design work for this report was requested by Augusta to determine the general level of pad layout for a +/-35% cost estimate. The preliminary general facilities arrangement for the project is presented on Figure 1. The leach pad layout is shown on Figure 2 with a typical section and details shown on Figure 3. An Excel spreadsheet of calculations for approximate pad tonnage limits and lift placement time for pad startup and expansion siting purposes is shown on Table 1. 1.1 Background The Rosemont project site lies in a high, sparsely populated intermountain area approximately 35 miles southeast of Tucson, Arizona on the east slope of the Santa Rita Mountains. Access to the site is via Highway 83 which connects Interstate 10 with the town of Sonoita. Augusta controls a large portion of the site including the Hidden Valley Ranch and Rosemont Ranch. The Coronado National Forrest is custodian of much of the slopes of the Santa Rita Mountains. Rosemont Heap Leach Conceptual Design Page 1

Vector Colorado Technical Memorandum Page 2 FOR INTERNAL DISCUSSION PURPOSES ONLY 1.2 Site Visit Troy Meyer, P.E. of Vector visited the Rosemont property March 8 through 9, 2006 to perform site reconnaissance and familiarize Vector with the proposed facility locations, site features, surficial geology and soils. Photographs taken during this site visit are presented in Attachment A. 2.0 Leach Pad Siting The general leach pad siting location was determined by Vector, Augusta and WLR Consulting as part of the overall mine and waste rock dump layout as shown on Figure 2. Ore production and process flows for conceptual siting purposes were discussed with Washington Group International (WGI) to be 11,000 tons per day (tpd) with 3,100 gpm flow to the PLS flow and recycle flow from a mid-grade PLS pond of 3,857 gpm. The preliminary design incorporates a raffinate bleed rate of 1,500 gpm to agitation leach and a raffinate pond flow of 4,600 gpm resulting in an overall total application rate of 6,957 gpm including recycle (see Table 1). Pad drainage toward the pit was preferred for optimizing waste rock layout around the pad and associated process ponds and for closure drainage planning. The total ultimate ore tonnage is currently planned at approximately 60 million tons. The pad site will require significant grading to achieve this configuration with initial grading via cut/fill operations and borrow from the nearby pit area. Subsequent expansion pad grading can then be performed by controlled waste rock placement. The drain fill for the pad overliner system likely will include selected durable crushed rock from the pit overburden supplemented with closely spaced 3 inch diameter perforated drain pipes. 3.0 Ore Stack Layout The ore stacking sequence assumed approximate 25 ft ore lifts stacked in 10 lifts to the 250 ft heap height at overall 2H:1V side slopes. A conceptual cross section of the pad and ore stack is shown on Figure 2. The ore tonnages and ore lift times are approximate and presented on Table 1 attached. The Phase I pad can accommodate approximately 17.3 mt (4.3 years of production at 11,000 tpd) to the 125 ft height. The Phase II pad will accommodate approximately 21.5 mt (5.3 years of production) to the 125 ft height with the remaining tonnage stacked over the entire pad area to the 250 Rosemont Heap Leach Conceptual Design

Vector Colorado Technical Memorandum Page 3 FOR INTERNAL DISCUSSION PURPOSES ONLY height. An ore density of 1.6 tons per cubic yard was assumed for the conceptual layout. 4.0 Conceptual Pad Design 4.1 General The startup pad construction will include the site grading fill for controlled drainage to the collection ditch and ponds, perimeter and interior pad cell berms as needed, the pad drain fill cover, the drain pipes within the drain fill, and the temporary diversion ditch uphill of the pad limits. The state of practice composite pad, collection ditch and pond liner systems are the major cost components for the startup pad. The intermediate Phase II expansion pad will require an additional downhill collection ditch but will not require additional pond liner. The ultimate heap stack above the startup and expansion pad heaps will require minimal additional pad costs. 4.2 Startup Pad The startup (Phase I) and Phase II pad areas are about 3.1 million sq. ft. each and will include 60 mil LLDPE pad liner. The downhill collection ditch tie-in to the pad toe berm is about 35 ft wide by 1390 ft long at about 48,000 sq ft of 80 mil HDPE liner. The liner system will include a geosynthetic clay liner (GCL) underlying the geomembrane to form a double lined pad. The process pond will be double lined and the storm overflow will be single lined with an 80 mil HDPE top liner and the process ponds (PLS and midgrade) bottom liner will be 60 mil LLDPE liner with geonet leak detection between liners. The process pond may include netting or bird balls for bird protection. The downhill toe site grading for the ultimate 250 ft ore stack will require about a 375 ft of textured geomembrane liner for adequate slope stability based on previous experience. The site grading volume for Phase I startup pad is about 1.7 million cubic yards (cy) of cut to fill and 630,000 cy of fill from borrow without considering any bulkage or shrinkage from borrow to fill conditions. Future design may allow optimization of the pad layout with respect to grading costs, however this is thought to represent a conservative estimate of the required grading. The temporary uphill diversion channel south of the pad is about 2100 ft long and could be eliminated once waste rock is placed in this area. The permanent uphill diversion Rosemont Heap Leach Conceptual Design

Vector Colorado Technical Memorandum Page 4 FOR INTERNAL DISCUSSION PURPOSES ONLY channel west of the pad is about 5900 ft long. The diversions are likely less than 3 ft in depth in a V ditch cut along a 0.5% contour grade. 4.3 Expansion Pad The Phase II expansion pad costing will include additional 10 million cy pad grading fill which was assumed to be waste rock placed and compacted by mine haul trucks. The downhill collection ditch tie-in to the pad toe berm is about 35 ft wide by 3640 ft long (including the northern ditch) for about 127,400 sq ft of 80 mil HDPE liner. The liner system will include a geosynthetic clay liner (GCL) underlying the geomembrane to form a double lined pad. Lump sump costs were estimated for diversion ditches, perimeter and interior berms, sumps, pumps and pipelines. Raffinate pond construction costs were not estimated and were assumed to be included in work by others for the SX/EW plant. Unit rate or lump sump cost assumptions for this conceptual design estimate are included in Table 2 attached. Attachments: Table 1 Ore Stack Tonnage Estimates Table 2 Quantities and Cost Estimate Figure 1 General Facilities Arrangement Figure 2 Leach Pad Layout Figure 3 Leach Pad Sections and Details Rosemont Heap Leach Conceptual Design

TABLE 1 - ORE STACK TONNAGE ESTIMATE PROJECT: ROSEMONT PROJECT DATE: APR 2006 PROJECT # 06-5003 ORE PRODUCTION: 11,000 TONS/DAY LEACH CYCLE TIME: 93 DAYS ORE HEAP SLOPE: 2 H TO 1 V ACTIVE AREA: 688,889 SQUARE FT ORE DRY DENSITY: 1.6 TONS/CUBIC YARD APPLICATION RATE: 0.0045 GPM/SF LEACH RATIO: 3.8 TON SOLUTION/TON ORE TOTAL APPLICATION FLOW: 6,957 GPM FLOW TO HIGH GRADE POND: 3,100 GPM (from WGI) RECYCLE FROM MID-GRADE POND: 3,857 GPM RAFFINATE BLEED TO AGITATION LEACH: 1,500 GPM (from WGI) RAFFINATE POND FLOW: 4,600 GPM ORE LIFT BOTTOM BOTTOM TOP TOP LIFT TOP LIFT LIFT ACCUM. ACCUM. LIFT ACCUM. ACCUM. NUMBER LENGTH1 LENGTH2 LENGTH1 LENGTH2 AREA HEIGHT VOLUME VOLUME TONNAGE TIME TIME TIME (#) (FT) (FT) (FT) (FT) (SQ FT) (FT) (CU FT) (CU FT) (TONS) (DAYS) (DAYS) (YRS) Starter Pad 1 2,300 1,410 2,200 1,310 2,882,000 25 76,562,500 76,562,500 4,537,037 412 412 1.13 2 2,200 1,310 2,100 1,210 2,541,000 25 67,787,500 144,350,000 8,554,074 365 778 2.13 3 2,100 1,210 2,000 1,110 2,220,000 25 59,512,500 203,862,500 12,080,741 321 1,098 3.01 4 2,000 1,110 1,900 1,010 1,919,000 25 51,737,500 255,600,000 15,146,667 279 1,377 3.77 5 1,900 1,010 1,800 910 1,638,000 25 44,462,500 300,062,500 17,781,481 240 1,616 4.43 Expansion Pad(s) 1 Expansion Phases 1 2,300 1,410 2,200 1,410 3,102,000 25 79,312,500 79,312,500 4,700,000 427 2,044 5.60 2 2,200 1,410 2,100 1,410 2,961,000 25 75,787,500 155,100,000 9,191,111 408 2,452 6.72 3 2,100 1,410 2,000 1,410 2,820,000 25 72,262,500 227,362,500 13,473,333 389 2,841 7.78 4 2,000 1,410 1,900 1,410 2,679,000 25 68,737,500 296,100,000 17,546,667 370 3,212 8.80 5 1,900 1,410 1,800 1,410 2,538,000 25 65,212,500 361,312,500 21,411,111 351 3,563 9.76 Ultimate Expansion Pad 1 1,800 2,320 1,700 2,220 3,774,000 25 99,332,624 99,332,624 5,886,378 535 4,098 11.23 2 1,700 2,220 1,600 2,120 3,392,000 25 89,532,546 188,865,170 11,192,010 482 4,580 12.55 3 1,600 2,120 1,500 2,020 3,030,000 25 80,232,455 269,097,625 15,946,526 432 5,013 13.73 4 1,500 2,020 1,400 1,920 2,688,000 25 71,432,346 340,529,971 20,179,554 385 5,397 14.79 5 1,400 1,920 1,300 1,820 2,366,000 25 63,132,216 403,662,188 23,920,722 340 5,738 15.72 Total Tons 63,113,315 15.72

TABLE 2 - QUANTITIES AND COST ESTIMATE Rosemont Heap Leach and Site Civil Estimated Costs based on Conceptual Designs FOR INTERNAL DISCUSSION ONLY Description Unit Quantity Unit Cost Cost Comments Phase I Leach Pad and Process Ponds Pond Pad Clearing and Grubbing Acre 259 $1,000 $259,412 Heap and Pond Foundation Preparation (Cut to Fill) yd 3 1,744,000 $0.80 $1,395,200 Includes estimate for perimeter fill to provide possitive drainage to diversion Heap and Pond Foundation Preparation (Fill from Borrow) yd 3 629,000 $1.20 $754,800 Assumes borrow source is within 1/2 mile of the pad Diversion Ditches lump sum 1 $250,000 $250,000 Approx. 8000' v-ditch 2' deep Perimeter & Interior Berms and Ditches lump sum 1 $150,000 $150,000 18' wide perimeter berms and 25' wide permiter ditches Heap Geomembrane Liner ft 2 3,243,000 $0.45 $1,459,350 60 mil LLDPE Perimeter Ditch Liner ft 2 49,000 $0.45 $22,050 80 mil HDPE Heap Liner Bedding (GCL) ft 3 3,243,000 $0.40 $1,297,200 Assumes fill can be compacted for suitable surface Pad Drain Piping ft 2 3,243,000 $0.10 $324,300 3" dia perforated secondary pipes and 6" perforated primary pipes Drain Cover Fill (2ft thickness crushed rock) yd 3 240,222 $5.00 $1,201,111 Assumes durable rock is available from pit Pregnant Solution Pond (PLS) Excavation yd 3 111,000 $2.20 $244,200 Assumes soil or rippable rock Pregnant Solution Pond Liner (Double) ft 2 135,000 $0.90 $121,500 60 mil HDPE top liner, 80 mil LLDPE bottom liner Pregnant Solution Pond Liner Bedding (GCL) ft 2 135,000 $0.40 $54,000 Assumes excavation can be compacted for suitable surface Mid Grade PLS Pond Excavation yd 3 100,000 $2.20 $220,000 Assumes soil or rippable rock Mid Grade PLS Pond Liner (Double) ft 2 125,000 $0.90 $112,500 60 mil HDPE top liner, 80 mil LLDPE bottom liner Mid Grade PLS Pond Liner Bedding (GCL) f t2 125,000 $0.40 $50,000 Assumes excavation can be compacted for suitable surface Leak Detection Geonet and Sumps lump sum 1 $100,000 $100,000 Pumps and Pipelines lump sum 1 $750,000 $750,000 Includes PLS and raffinate systems Stormwater Pond Excavation yd 3 268,000 $2.20 $589,600 Assumes soil or rippable rock Stormwater Pond Liner ft 2 298,000 $0.45 $134,100 60 mil HDPE liner Stormwater Pond Bedding (GCL) ft 2 298,000 $0.40 $119,200 Assumes excavation can be compacted for suitable surface Subtotal $9,608,523 Phase II Leach Pad Expansion Heap Foundation Preparation (Compaction Only) yd 3 9,963,000 $0.20 $1,992,600 Assumes waste rock fill will be supplied by the Mine and compacted by haul trucks Perimeter & Interior Berms lump sum 1 $150,000 $150,000 18' wide perimeter berms and 25' wide permiter ditches Heap Geomembrane Liner ft 2 3,243,000 $0.45 $1,459,350 60 mil LLDPE Perimeter Ditch Liner ft 2 127,400 $0.45 $57,330 80 mil HDPE Heap Liner Bedding (GCL) ft 3 3,243,000 $0.40 $1,297,200 Assumes fill can be compacted for suitable surface Pad Drain Piping ft 2 3,243,000 $0.10 $324,300 3" dia perforated secondary pipes and 6" perforated primary pipes Drain Cover Fill (2ft thickness crushed rock) yd 3 240,222 $5.00 $1,201,111 Assumes durable rock is available from pit Subtotal $6,481,891 TOTAL HEAP LEACH $16,090,415

APPENDIX A SITE PHOTOS

Rosemont Project Appendix A - Page 1 Tailings Facility Siting Study A_Site Photos_Heap Leach.doc Barrel Canyon Area Near proposed heap leach site Barrel Canyon Basin near top of basin looking north

Rosemont Project Appendix A - Page 2 Tailings Facility Siting Study A_Site Photos_Heap Leach.doc Arcosic near surface soils in Barrel basin Typical rocky ground surface at Rosemont site