John Hart Generating Station Replacement Project. October 2014 Community Construction Update Report #16

Similar documents
John Hart Generating Station Replacement Project. December January 2014 Community Construction Update Report #8

John Hart Generating Station Replacement Project. June 2017 Community Construction Update Report #48

John Hart Generating Station Replacement Project. July 2016 Community Construction Update Report #37

John Hart Generating Station Replacement Project. March 2017 Community Construction Update Report #45

John Hart Generating Station Replacement Project. January 2016 Community Construction Update Report #31

John Hart Generating Station Replacement Project. December 2017 Community Construction Update Report #54

John Hart Generating Station Replacement Project. January 2018 Community Construction Update Report #55

John Hart Generating Station Replacement Project. February 2018 Community Construction Update Report #56

John Hart Generating Station Replacement Project. November 2017 Community Construction Update Report #53

John Hart Generating Station Replacement Project. May 2017 Community Construction Update Report #47

John Hart Generating Station Replacement Project. October 2017 Community Construction Update Report #52

John Hart Generating Station Replacement Project. November-December 2018 Community Construction Update Report #65

Condition of Improvements 30 December 2014 Snettisham, Alaska (CWIS No )

TRANSFORMING CHALLENGES INTO OPPORTUNITIES

DRAFT SEDIMENT and EROSION CONTROL PLAN. BLUE LAKE HYDROELECTRIC PROJECT (FERC No. 2230) EXPANSION. Prepared by:

SCHEDULE 23 PUBLIC SAFETY AND PUBLIC USE

CEAA ENVIRONMENTAL ENVIRONMENTAL IMPACT ASSESSMENT AMBASSADOR BRIDGE ENHANCEMENT PROJECT. Replacement Span and Plaza Expansion APPENDIX E

Eglinton Crosstown LRT Construction Liaison Committee

Lower Churchill Project Gilbert Bennett, Vice President St. John s Board of Trade - May 22, 2013

Albany Park Stormwater Diversion Tunnel

Albany Park Stormwater Diversion Tunnel

Site C Clean Energy Project. Monthly Environmental Monitoring Summary Report - February 2017

SITE C FIELD WORK FOR 2019

PROJECT BRIEF for the John Hart Generating Station Replacement Project

Annex F Scoping Checklist

Facts and Figures. Greater Victoria Water Supply Area. May 2015

BC s Magazine for Trenchless Construction

TRAFFIC MANAGEMENT PLAN REQUIREMENTS FOR COMMERCIAL/LARGE DEVELOPMENT SITES

Welcome. Metro North Transmission Project Burnaby Community Information Open House March 8, About the Metro North Transmission Project

Constructability Guidelines

MONTHLY FIELD STUDIES SUMMARY

21 July Anthony Yeates RATCH-Australia Corporation Limited Level 7, 111 Pacific Highway North Sydney NSW 2060

Lower Glade and Upper McPhee Harvest Update November 2018

Frequently Asked Questions

Port Granby Project Work Sequence. 5 Multi-year waste excavation, transport and placement in mound begins

Preferred Elevated Tank Site

The Drainage Basin. From Peaks of Colorado to Mexico 1,400 miles Drains 242,000 square miles of Western US Colored River because of sediments

Rain and Shine CHAPTER

DETROIT RIVER INTERNATIONAL CROSSING STUDY MAG

Exploratory Works. Community Information Booklet April/May 2018

SITE C CLEAN ENERGY PROJECT

Côté Gold Project. Where is the Côté Gold Project located? Who owns the Côté Gold Project? Frequently Asked Questions. May 2018.

Yukon Energy. Rural Generating Facilities

Santoy 8 Satellite Mine at the Seabee Gold Mine. Technical Review Comments. on the. Environmental Impact Statement.

EMERGENCY STORAGE PROJECT Lake Hodges Projects Update Meeting Summary

Dry structural excavation is usually done with front-end loaders, bulldozers or backhoes.

Skeena Sawmills Ltd SFI Surveillance Audit

Keeyask Generation Project. Physical Environment. Supporting Volume. Environmental Impact Statement

Chapter to our times: Societal Choices in Contemporary Quebec. Section 5: Environmental Choices in Contemporary Quebec Part 2

Chakachamna Hydro. AEA Geothermal Conference

APPENDIX D: COST ESTIMATES

Reclamation Manual Design Data Collection Guidelines Chapter 5 Typical Design Data Package Template

Elko Project Water Use Plan. Revised for Acceptance by the Comptroller of Water Rights

Nonmetallic Mining Reclamation & Operation Plan. Amendment No. 1 (Includes modifications for Wash Plant construction) DRAFT

Environmental Management on a Mega Project. NewLEEF Oct

WAKULLA SITE PLANNING

Amisk Hydroelectric Project Update

kpmg TimberWest Forest Corporation 2018 SFI Forest Management Surveillance Audit

Alberta Transportation The City of Edmonton The City of Calgary

A natural resource is a source of products that are inherent to earth Natural resources include renewable and nonrenewable

ANCHORAGE, ALASKA AR No , As Amended

Water Pollution Control for Work in Sensitive Areas

Draft Mine Closure Plan. 17 October 2018 Longlac & Geraldton

(1) Bridge, Road and Railway (Adaptation Project) (2) Bridge, Road and Railway (BAU Development with Adaptation Options)

PUBLIC ANNOUNCEMENT. development project of a quarry in Campeau township. The meeting will be held on

Infrastructure Priorities

LAND DISTURBANCE PERMIT

Peace Region Electricity Supply Project open house

Photomontages SECTION 10

Imperial s Sarnia Products Pipeline Mississauga, Ontario. Credit River Valley Project

Quatse Salmon Stewardship Centre

YUCE HYDROELECTRIC POWER PLANT (HEPP) ENVIRONMENTAL MANAGEMENT PLAN

Our Strategy for Climate Action

Lloydminster to Spruce Lake 138kV Transmission Line Projects

Kane County Natural Hazards Mitigation Committee

EMERGENCY STORAGE PROJECT San Vicente Pipeline and San Vicente Dam Raise Update Presentation Summary

SURREY COASTAL FLOOD ADAPTATION STRATEGY (CFAS) General Phase 1 Workshop Presentation (February 3 through March 8, 2017)

CAMLICA ELEKTRIK URETIM A.S. CAMLICA III RESERVOIR AND HYDROELECTRIC POWER PLANT (HEPP) ENVIRONMENTAL MANAGEMENT PLAN (EMP)

Crenshaw/LAX Transit Project Construction Update Meeting July 28, 2015

DOORNVALLEI EXT 5 & 6

Linfairn Wind Farm Addendum Chapter A3: Project Description

SECTION 55A1 ROBINSON TOWNSHIP, WASHINGTON COUNTY

The Social and Economic Importance of Canada s Privately Owned Forest Lands

Table of Contents. Nov. 2008

September 15, Via Electronic Filing

CONSTRUCTION PHASE ENVIRONMENTAL ISSUE MITIGATION REQUIREMENTS 1. Access road selection and construction

Timber Sale Appraisal More Cow Bell Sale FG W

Timber Sale Appraisal Iron Nelson Sale WL W

January 23, Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, D.C

water, forestry, fossil fuels, metallic and non-metallic minerals

Scheduling Activities. THE SALVAGE, RECLAMATION AND ABANDONMENT OF THE GRANDUC MINE by M.R. Walker INTRODUCTION

K2 WIND POWER PROJECT DECOMMISSIONING PLAN REPORT. Prepared by: K2 Wind Ontario Limited Partnership Suite 105, 100 Simcoe Street Toronto, ON M5H 3G2

TRANSPORT and INFRASTRUCTURE

Storm Water Pollution Prevention Plan (SWP3) Checklist

Protect Your Water S urce. A Guide to Managing Surface Water Drinking Sources

THE WATER CYCLE IN GREATER VICTORIA

Timber Sale Appraisal Iron Mountain Sale WL W

Construction Best Management Practices Handbook BEST MANAGEMENT PRACTICES

Preconstruction Community Meeting

SUMMARY OF COMMENTS/RECOMMENDATIONS

Transcription:

John Hart Generating Station Replacement Project October 2014 Community Construction Update Report #16 Prepared by: Stephen Watson, BC Hydro (O) 250-755-4795 or (C) 250-616-9888 steve.watson@bchydro.com 1

Project Update And Schedule Project Status Update: Overburden clearing and removal from north portal ongoing. Stream relocation underway; Blasting scheduled to begin in early November at surface; New parking site on Surge Tower Road, next to the city s water treatment plant; Laydown area on north side of penstocks in progress; Set up of Frontier-Kemper laydown site, concrete pad for mechanical shop poured; Geotechnical test drilling continues to assess underground powerhouse plans; and Site set up continues near the intersection of Hwy 28 and Hwy 19, at the former Campbellton Elementary site, for the John Hart construction staging area. 2

Project Update And Schedule Estimated schedule from November 2014 February 2015: Early November: Blasting expected to begin on site, related truck traffic for hauling; Early November: Substation commissioning; Late November: Blasting expected to move underground; November: New project office and staging area opened near the intersection of Hwy 28 and Hwy 19; January 2015: Estimated closure date for Brewster Lake Road; and February-April 2015: Focus on the tunneling and underground generating station cavern excavation. Victoria Times Colonist 3

Construction Pictures Aerial Pictures From Time Lapse Camera October 2 October 10 October 16 October 23 4

Construction Pictures Aerial Pictures From Time Lapse Camera October 31 5

Construction Pictures Around the South Portal Entrance 6

Construction Pictures Around the South Portal Entrance 7

Construction Pictures Around the North Portal Entrance 8

Construction Pictures Around the North Portal Entrance 9

Rock Drilling A big part of the project's innovative design is the underground generating station, all in rock, that will provide good earthquake withstand; Further geotechnical drilling has been undertaken to assess the quality, quantity and location of rock in key blasting sites so that final plans can be confirmed; This is continuing to confirm the best location and orientation of the generating station cavern; and Results continue to show good rock conditions. Example of some borehole cores. 10

Brewster Lake Road Bridge Bridge design and construction plan under development for construction access and hauling; Road and existing bridge closure anticipated for January 2015; Road closure could run up to three years; and Alternate route identified for the public. 11

Brewster Lake Road Bridge Road detour shown in bold red lines 12

Environment Tree Compensation BC Parks approved the removal of select trees on park land adjacent to the work site because the trees posed a danger to worker and site safety; North portal had 13 trees removed, the south portal had 7 trees removed, and the parking area had 2 trees removed; and There were also six trees that were topped; To compensate for the removal of these trees, InPower BC will replant various trees and bushes. The compensation includes: 58 new trees that include Douglas-fir, Western hemlock and Western redcedar; and 265 shrubs such as Oceanspray, Red huckleberry and Sword fern. The tree compensation plan was developed by independent environmental monitors and approved by InPower BC and BC Parks. The re-plantings will take place at the entrance to the new public parking area for the Elk Falls day use area and John Hart Project Interpretive Centre; and Site preparation is underway and the plantings are expected to be complete by the first week of November. There will be post-planting monitoring for five years. 13

Environment Water Management As fall and winter storms begin there is a focus on protecting the provincial park from runoff, particularly in light of changes made at the site; The project team has undertaken many measures to stop water from running into the area including, full coconetting, hydroseeding, rock crush drains, sediment fencing, straw dams and hay bales. Sand bags have been used where an unexpected flow direction arises, until another mitigation measure can be in place; Water flows and runoff are monitored by three reviewers: independent, InPower BC, and BC Hydro environmental managers; and There is particular focus on Wetland J (on the west side of Surge Tower Road) where some turbid waters have appeared. InPower BC is working with BC Hydro and BC Parks to assess measures to protect the wetland in the long-term. Hydroseeding and bouldering along a diversion stream (above), and crush placed at traffic areas to allow heavy rains to go back into the ground more easily. 14

Economic - Business Events in October Site workers: About 70 full-time people. There were two local and one regional business sessions that had John Hart project participation: Vancouver Island Construction Association/NIEFS - Building Your Foundation: Careers in Trades and Construction (Campbell River) Campbell River Chamber of Commerce Business Expo Vancouver Island Economic Alliance Island Summit Questions focused on: Job and subcontractor opportunities. Emphasis for workers to contact relevant union halls (contact information available at www.majorprojects.ca, Job Seekers Overview Subcontractors should send email to johnhartproject@snclavalin.com with company/service information to be added to vendor database. 15

Local Business Profile T-Mar Industries Background: For 30 years, Campbell River s T-Mar Industries has provided engineering, machining, mechanical and fabrication support to industries on the south coast. From service of existing equipment to the development and creation of entirely new products, T-Mar has provided much needed solutions to forestry, mining and hydroelectric sectors among others for decades. What you may not know about us: This month, T-Mar completed and delivered the first new grapple yarder to be built in Canada in 14 years to a logging industry client. The yarder was entirely designed in-house at T-Mar, with their engineering department producing detailed drawings, and machinists, welders, mechanics and millwrights on site bringing it to life. It is an innovative design that increases power, reduces fuel consumption and can be moved on roads unlike equipment of its kind built in the past. Project role: T-Mar is supporting the John Hart project by providing mechanical services for rock drills and other equipment used in the excavation of the two portal entrances. With full mechanical, machining and fabrication capabilities and a large local facility, their involvement will be able to grow as the project progresses. People working: There are roughly 50 people working at T-Mar industries. Currently one or two people are dedicated to John Hart project-related work each week. 16

Local Business Profile T-Mar What makes Campbell River a great place to live and work: Campbell River is a natural hub for a range of industrial activity on the south coast from Courtenay north to Powell River and the Sunshine Coast. With easy access to water, highways, experienced workers and progressive industries, it s the perfect location for an expert machining and services shop. Quote: Being involved in the John Hart project means sustainability and employment. It s not so much for us it s for our employees. Keeping people employed makes a healthy community and having a project like this keeps the train going. Chris Leikermoser, Engineering Services Manager (pictured below at the T-Mar site) 17

People Profile Jeanette Cyr About Jeanette: Background: Jeanette started working in first aid in logging camps along the BC coastline and joined the BC Ambulance service in 2000 as a Primary Care Paramedic, working in Port Hardy and Campbell River. Most recently, she provided first aid services for the transmission lines at the Cape Scott wind farms, then up to Northern BC and Alberta in oil and gas projects. She still works part time with the ambulance service in Campbell River. Home: She grew up and lived in Port Hardy until moving full-time to Campbell River last year. Hobbies: Favourite pastimes include hiking and kayaking and travelling. Project responsibility: Jeanette works for the ASL-JV and is a First Aid Attendant and general labour. I love having the opportunity to work on the John Hart project an exciting project and I m learning so much about the construction industry. Working alongside a beautiful water system, in surrounding forests and a great group of fellow workers, I can t help but smile every day. 18

Construction Point of Interest Each month, BC Hydro and InPower BC will provide a construction fact, occurrence, or situation. With rock blasting planned to start next month, the project team is planning carefully to prevent impacts from the work. Vibration monitors will be set up on concrete during blasts and will be monitored regularly to ensure that existing infrastructure including the aging powerhouse are protected. Safe levels have been determined and the impacts of blasts will be recorded and reported. 19