POTOMAC ELECTRIC POWER COMPANY

Similar documents
Rochelle Municipal Utilities TRANSMISSION PLANNING CRITERIA. March 21, 2017

DUQUESNE LIGHT COMPANY TRANSMISSION PLANNING CRITERIA

April 26, PJM Mr. Mark J. Kuras Senior Lead Engineer NERC and Regional Coordination 2750 Monroe Blvd. Audubon, PA 19403

East Kentucky Power Cooperative (EKPC) Transmission System Planning Criteria

FERC Form No. 715 Part 4 TRANSMISSION PLANNING RELIABILITY CRITERIA

Standard TPL System Performance Following Extreme BES Events

TRANSMISSION PLANNING ASSESSMENT METHODOLOGY AND CRITERIA

Transmission Planning Standards for the Baltimore Gas & Electric Company Transmission System

Standard TPL (i) System Performance Under Normal Conditions

Standard TPL-002-0b System Performance Following Loss of a Single BES Element

Standard Development Timeline

Standard TPL-004-0a System Performance Following Extreme BES Events

Mapping Document for FAC-010-3

Standard Development Timeline

NERC PLANNING STANDARDS

Table of Contents. To provide a methodology for determining the System Operating Limits (SOL) for the Planning Horizon at the California ISO.

Standard Development Timeline

Standard MH-TPL Transmission System Planning Performance Requirements

Standard TPL-003-0b System Performance Following Loss of Two or More BES Elements

A. Introduction 1. Title: Automatic Underfrequency Load Shedding Requirements

Standard TPL Transmission System Planning Performance Requirements

SRRTEP Meeting 2019 Annual Assumptions for Pepco

5.4 Post Contingency Local Load Relief Warning

Standard TPL-003-0b System Performance Following Loss of Two or More BES Elements

Standards de planification du NERC

PID 276 Feasibility Study Report 4.4MW Distribution Inter-Connection Mermentau Substation

Standard TPL System Performance Under Normal Conditions

Planning Coordinator and/or Transmission Planner TRANSMISSION SYSTEM PLANNING GUIDELINES

Seasonal Assessments and Modeling of Sub-100 kv Elements (Southwest Outage Recommendations 5, 6, 7 and NERC2) May 7, 2014

B-R1 TRANSMISSION SYSTEM PLANNING PERFORMANCE REQUIREMENTS

A. Introduction 1. Title: Automatic Underfrequency Load Shedding Requirements

Designated Entity Design Standards Task Force (DEDSTF) Minimum Design Requirements for FERC Order 1000 Projects. System Protection Subgroup

NYSRC RELIABILITY RULES For Planning And Operating the New York State Power System

Standard TPL-003-0a1a System Performance Following Loss of Two or More BES Elements

Standard Development Timeline

TPL 001 AB 0 System Performance Under Normal Conditions

INTERPRETATION REQUEST FORM

SYSTEM OPERATING LIMITS IN THE PLANNING HORIZON FAC-010 COMPLIANCE

PSE&G Assumptions Overview. November 2018

Platte River Power Authority. Ten-Year Transmission Plan ( )

BULK ELECTRIC SYSTEM PLANNING CRITERIA

Generation Interconnection System Impact Study Report. For. PJM Generation Interconnection Request Queue Position AA1-038

ASSOCIATED NERC STANDARD(S): TPL (referred to as TPL-001 in this document) IMPLEMENTATION: In effect when approved.

DRAFT STUDY PLAN FOR 2018

AESO TRANSMISSION PLANNING CRITERIA BASIS AND ASSUMPTIONS

Project Single Points of Failure TPL-001 Cost Effectiveness

PID275 Feasibility Study Report 9.33 MW Distribution Inter-Connection Valentine Substation

Feasibility Study Report

Generation Interconnection Feasibility Study Report. For. PJM Generation Interconnection Request Queue Position AA1-038

July 15 July 31. August First ballot September 1 10, Drafting Team considers comments and makes any revisions indicated

Criteria. C~/v~ ~ ~ ~ G! " A1A "~"" T"""g"'~10N COr'P""''~ P LG -C R-0001-V T~c~e: Transmission System Planning Criteria

Facility Interconnection Requirements

TABLE OF CONTENTS. UNCONTROLLED WHEN PRINTED 2 USA Operations

Load Shed Philosophy

FACILITY CONNECTION REQUIREMENTS NERC TO-FAC 001-0

Transmission Planning Procedures and Planning Criteria TDOG108

Standard 600 Determine Facility Ratings, System Operating Limits, and Transfer Capabilities

AESO System Operating Limits Methodology for the Planning Horizon (R1 FAC-010-AB-2.1)

This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective.

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Delaney to Colorado River 2014

Standard Development Roadmap

NERC Reliability Functional Model

Standard FAC System Operating Limits Methodology for the Planning Horizon

11. TRANSMISSION AND INTERCONNECTION FACILITIES

AMERICAN RENEWABLES GAINESVILLE REGIONAL UTILITIES GAINESVILLE RENEWABLE ENERGY CENTER

LONG-RANGE TRANSMISSION PLAN

Requirements for the Connection of Facilities to The Dayton Power & Light Co. Transmission System

Seminar on African Electrical Interconnection. Module 8 - Interconnected Systems Operating Conditions

AMERICAN RENEWABLES GAINESVILLE REGIONAL UTILITIES GAINESVILLE RENEWABLE ENERGY CENTER

Stakeholder Communication. Inputs, Assumptions, and Preliminary Assessment. Base Model. Needs, Solutions, Sensitivity: Yr 5

Security Guideline for the Electricity Sector: Identifying Critical Assets

SPP RTO Compliance Forum TPL Jason Terhune

Updated October 2, 2014 TITLE: System Operator Transmission - Senior DEPARTMENT: System Operations

Reliability Analysis Update

1.3 Planning Assumptions and Model Development

Mapping Document. Project Phase 2 of System Protection Coordination. Revisions or Retirements to Already Approved Standards

Project Revisions to TOP and IRO Reliability Standards Mapping Document Updated December 2014

Connection Study Requirements

PJM White Paper. Transource Independence Energy Connection Market Efficiency Project

Glossary of Terms Used in Reliability Standards. Preliminary Draft Version 0 Reliability Standards September 1, 2004

Standard PRC-002-NPCC-01 Disturbance Monitoring

DOCUMENT A-11 DU NPCC

Project Consideration of Commission Directives in Order No. 693

Methodology for Determining and Communicating System Operating Limits for the Planning Horizon (FAC-010 & -014) Revision Log

2012 Grid of the Future Symposium. Innovations in Bulk Power System Reliability Assessment: A North American View

Transmission Expansion Advisory Committee

FRCC - PROC - RC - EOP-004. FRCC Disturbance Reporting Procedure

Fault Current Contributions from Wind Plants Dean Miller PacifiCorp July 25, 2012

Generator Interconnection Affected System Impact Study. Plains & Eastern Clean Line Final Report

EXELON UTILITIES TRANSMISSION FACILITY INTERCONNECTION REQUIREMENTS

Energy Management System (EMS) Model Updates and Quality Assurance (QA)

Definition of Adequate Level of Reliability

Review of Data Change Management Processes for RTCA and Planning Models (Recommendation 16) March, 2017

Project System Operating Limits

Implementation Plan for IRO Reliability Coordination Facilities Prerequisite Approvals Adoption of IRO-001-2, IRO-010-0, COM-001-2

Transmission Interconnection Requirements. Table of Contents

2015 Operational Practices Survey Questions

Capacity Shortages RE Module. Interconnection Training Program PJM State & Member Training Dept.

Approved RMWG Discussion was held. ??? John Simpson need to assign SMART rating

EXELON UTILITIES TRANSMISSION FACILITY INTERCONNECTION REQUIREMENTS

Transcription:

POTOMAC ELECTRIC POWER COMPANY FERC Form 715 (Part 4) - Transmission Planning Study Guidelines Transmission Reliability Guidelines 1. General Overview The reliability guidelines used to plan the transmission system of Potomac Electric Power Company (Pepco) are the criteria by which the ability of the transmission system to serve the future load is determined. In addition to load growth, any significant changes to the generation capacity on Pepco s system or neighboring utility systems must also be included in any evaluation. Pepco s bulk transmission system shall be planned and constructed in such a manner that it can be operated so that the more probable contingencies can be sustained with no loss of load. Less-probable contingencies will be examined to determine their effect on system performance. These standards apply to bulk power transmission facilities including the facilities which have the primary function of giving Pepco a point of interconnection to generation and to the PJM and neighboring transmission systems. These Criteria do not apply to facilities affecting the reliability that only supply local loads. Exceptions are the 138kV/Bells Mill Road/Buzzard Point Network System and the 115kV/Benning Network System. These two systems are networked, with supply entering from either end of the tied system. Each of these two systems supply in excess of 1000 MVA of summer peak load, much of which is downtown area network government and large commercial load. The significant amount of load at risk and the type of load at risk necessitate more conservative planning criteria beyond that which is applied to the rest of the internal transmission and subtransmission systems. The recent retirement of Benning and Buzzard generation furthers the need for heightened transmission planning criteria within this part of the system. 2. Transmission Criteria The Pepco service territory is governed by the reliability standards established by the North American Electric Reliability Corporation (NERC), ReliabilityFirst (RF), and PJM Interconnections, LLC (PJM). The exact planning requirements of these regulated institutions can be found on their websites and external publications. Pepco will adhere to any requirements directed by these agencies in order to meet their established reliability planning criteria. In addition to these external organizations, Pepco also has its own internal planning criteria which will meet or exceed the strict standards above. The following criteria will be used for all transmission facilities within the Pepco zone:

The bulk transmission system shall be developed so that it can be operated at all load levels to meet the following unscheduled contingencies without instability, cascading, or interruption of load. Normally, maintenance is expected to be scheduled so that these criteria are not violated. Thermal Requirements The loss of any single generating unit, transmission line, transformer, circuit breaker or bus, in addition to normal scheduled outages including maintenance outages, without exceeding the applicable Emergency Rating of any facility or the applicable voltage criteria. After the outage, the system must be capable of readjustment so that all equipment will be loaded within Normal Ratings. After occurrence of the outage and the readjustment of the system specified above, the subsequent outage of any remaining generator, line, or transformer without exceeding the applicable Short Time Emergency Rating of any facility. After this outage, the system must be capable of readjustment so that all remaining equipment will be loaded within the applicable Emergency Rating and the voltage criteria will be met for the probable duration of the outage. The loss of any double-circuit line or the combination of facilities resulting from a line fault and a stuck breaker, in addition to normal scheduled outages including maintenance outages, without exceeding the applicable Short Time Emergency Rating of any facility. After the outage, the system must be capable of readjustment so that all remaining equipment will be loaded within the applicable Emergency Rating and the voltage criteria will be met for the probable duration of the outage. Perform a Generation Deliverability test that includes the following: (1) For normal system conditions with no line, transformer, or generation unit out of service all transmission facilities should not exceed their normal (continuous) rating; (2) For a contingency loss of any one facility (line, transformer, or generator), the system should not exceed its emergency (4 hour) rating: (3) For a contingency loss of any one facility (line, transformer, or generator) and the discrete outage of one generator, the system should not exceed its emergency (4 hour) rating; and (5) For generating stations where new generation is being added, all generation at the plant will be modeled at full output.

Voltage and Reactive Requirements The Transmission System shall have controls capable of maintaining the voltages at levels which will not exceed the limits of the connected equipment and will allow for meeting the voltage limits specified below. PEPCO Zone Base Line Voltage Limits Limit 500 kv 230 kv 138 kv 115 kv High 550 1.10 Normal Low 500 1.00 Emergency Low 485 0.97 Load Dump 475 242 1.05 219 212 0.92 207 0.90 145 1.05 131 130 0.92 124 0.90 121 1.05 109 108 0.92 103.5 0.90 Note These values may be different than the PJM base line voltage limits listed in Section 3, Exhibit 3 of the PJM Transmission Operations Manual MO3. These differences are recognized by PJM and provide more conservative operational limits for the PEPCO transmission zone Sufficient reactive compensation with adequate controls will be planned to allow supply of the reactive load and losses requirement in order to maintain acceptable voltage profiles, generally within ±5% of nominal voltage, on the Pepco Transmission System at all load levels during normal conditions and any of the contingencies described in {II} above. 3. Stability Requirements Pepco s Transmission Planning team conducts stability studies to ensure the system can withstand NERC criteria disturbances and maintain stable operation throughout its territories. This analysis is to ensure nearby changes to the system configuration do not adversely impact the stability of the system. Studied Contingencies The stability of the system shall be maintained without loss of load during and after the following types of contingencies occurring at the most critical locations at all load levels: A three-phase fault with normal clearing time. A single-phase-to-ground fault with stuck breaker or other cause for delayed clearing. The loss of any single facility with no fault.

Generation Dispatch As outlined in PJM Manual 14B, it is generally accepted that units operating at their highest possible power output and generating as little reactive power as necessary to maintain voltages are likely to be less stable. Under most circumstances, the units in the vicinity of a project under study will be turned to their maximum real power output with unity power factor at the high side of the GSU, or units VAR output will be adjusted to hold scheduled voltages. Generators should be evaluated utilizing a 50/50 forecast under normal conditions or for single contingencies. Studied Plant Selection Pepco should evaluate system stability for areas where generators are connected to the BES system. Stability evaluation for generators not connected to a BES system should be determined on a case-by-case basis depending on impact and may be less stringent. Monitoring Requirement Rotor angle, real power output, and terminal voltage are monitored. Bus voltage in the area of study is monitored. Following the disturbance, the voltages of the monitored buses maintain voltages within +/- 5% of the pre-contingency voltages. Evaluation Frequency Pepco shall conduct stability analysis every five years, or as needed when there have been significant changes to the transmission system and/or generation profile. 4. Tests by Simulation for the Ability of the Pepco System to Withstand Abnormal Disturbances It is recognized that it is impossible to anticipate or test for all of the contingencies that can occur on the present or future Pepco system. The system, therefore, will be tested by simulation to determine the effect of various types of abnormal disturbances on system performance. These sensitivity tests serve primarily as a means to measure the ability of the system to withstand less probable contingencies, some of which may not be readily apparent. These tests are prescribed not on the basis of a high level of probability, but rather as a practical means to study the system for its ability to withstand disturbances beyond those which can reasonably be expected. Recognition should be given to the occurrence of similar contingencies in neighboring systems and their effect on the Pepco system.

Examples of less probable contingencies to be studied are: A. The sudden loss of the entire generating capability of any station for any reason. B. The outage of the most critical transmission line on any one of the interconnected systems as the result of a three-phase fault immediately following (i.e., before adjustment) the tripping of another critical line on the same or an adjacent system. C. A single-phase-to-ground fault coupled with the malfunction of a protective device. D. The sudden loss of all lines of one voltage emanating from a substation. E. The sudden loss of all lines on a single right-of-way. F. The sudden dropping of a large load or a major load center. G. The occurrence of a multi-phase fault with delayed clearing. 5. Relaying and Protective Devices Independent devices shall be installed to the extent necessary to provide backup for the primary protective devices and components so as to limit equipment damage, to limit the shock to the system and to speed restoration of service. The design of a particular line s relay protective schemes shall recognize the need for an appropriate balance between dependability (assurance that relays will operate when required) and security (protection against relay operation when not required). In cases where the requirements of Sections {II-A} and/or {IV} are not met, additional security against the over tripping of critical facilities may be considered. Relaying installed shall not restrict the normal or the necessary realizable network transfer capabilities of the system. 6. Ratings Generally, ratings are defined as Normal, Emergency, or Short Time Emergency. All ratings are based on PJM rating methods and are provided by the responsible Engineering Department. A. Normal Operation -- All loads must be within the facility's normal rating.

B. Emergency Operation 1. The Emergency Rating referred to is a generic term for equipment emergency ratings of various durations depending on the type of equipment: Underground Pipe-Type cable = 300 hours All other underground cable = 36 hours All other equipment, generally = 24 hours 2. The Short Time Emergency Rating referred to is a generic term for equipment emergency ratings of various durations depending on the type of equipment: Overhead conductors = 10 hrs. Transformers = 4 hrs. Underground Pipe-Type cables for all 230kV & 115kV & for Feeder 13851 = 300 hrs. Underground Pipe-Type cables for all 138kV except Feeder 13851 = 4 hrs. C. The capacities of existing circuits at 115kV up to 500kV have been determined, generally by using actual construction parameters. D. In planning studies for adding new circuits, the thermal capacities to be used are to be based on the ratings and designed voltage-class of the cable or wire size to be installed, taking into account existing and proposed infrastructure installations along the route and the normal operating voltage. 7. Design Standards Pepco applies specific design criteria to new and existing facilities, as applicable. Refer to the publically available documentation on PJM s website.