Subsurface Desalination Intake & Potable Reuse Feasibility Studies. TAP Workshop #1 City of Santa Barbara, California August 5, 2015

Similar documents
Subsurface Desalination Intake & Potable Reuse Feasibility Studies. TAP Workshop #3 City of Santa Barbara, California October 26, 2016

Subsurface Desalination Intake & Potable Reuse Feasibility Studies. TAP Workshop #2 City of Santa Barbara, California January 27, 2016

Subsurface Desalination Intake & Potable Reuse Feasibility Studies. TAP Workshop #2 City of Santa Barbara, California January 27, 2016

Charles Meyer Desalination Plant

CITY OF SANTA BARBARA SUBSURFACE DESALINATION INTAKE FEASIBILITY STUDY TECHNICAL MEMORANDUM NO. 1 INTRODUCTION, BACKGROUND, AND PROJECT ALTERNATIVES

Figure Initial Alternatives Numbering Characteristics Matrix

Implementing the California Ocean Plan - Desalination Amendments - Analysis of Subsurface Intake Feasibility

CITY OF SANTA BARBARA SUBSURFACE DESALINATION INTAKE AND POTABLE REUSE FEASIBILITY STUDIES WORK PLAN POTABLE REUSE.

Feasibility Study of Subsurface Seawater Intakes West Basin Municipal Water District s Proposed El Segundo Desalination Facility

Montecito Water District Desalination Facilities Status Update. Board of Directors Meeting March 17, 2015

CITY OF SANTA BARBARA, CALIFORNIA SUBSURFACE DESALINATION INTAKE AND POTABLE REUSE FEASIBILITY STUDIES WORKSHOP #3 RESPONSES TO PUBLIC COMMENTS

CITY OF SANTA BARBARA SUBSURFACE DESALINATION INTAKE AND POTABLE REUSE FEASIBILITY STUDIES WORK PLAN SUBSURFACE DESALINATION INTAKE.

Demonstration of Ocean Plan Consistency during CEQA Review Subsurface Intake Feasibility Analysis (Case Study)

WASTEWATER TREATMENT PLANT UPGRADE PROJECT APPEAL NO. A-3-MRB

Effluent Disposal Feasibility Alternatives Study of Morro Valley

Executive Summary. Monterey Peninsula Water Management District. Sand City Desalination Project Feasibility Study. Executive Summary.

Desalination. Section 10 SECTION TEN. Desalination

Cypress Chamber of Commerce. John Kennedy Executive Director of Engineering & Water Resources Orange County Water District July 11, 2017

JOINT MANAGEMENT PLAN REVIEW DRAFT ACTION PLAN: Coastal Development: Desalination

DRAFT Master Water Reclamation Plan. City Council Meeting March 28, 2017

APPENDIX C 2012 RECYCLED WATER FEASIBILITY STUDY PUBLIC COMMENT RESPONSES

Supplemental Supply Option: Desalination DEEP WATER DESAL PROJECT

City of Santa Cruz Water Supply Advisory Committee Solutions Phase -- Technical Summary Consolidated Alternative 07 - Deepwater Desalination

Summary of Issues Strategies Benefits & Costs Key Uncertainties Additional Resources

8-5. Special Committee on Desalination and Recycling. Board of Directors. 3/9/2010 Board Meeting. Subject. Description

Carpinteria Valley Water District Carpinteria Advanced Purification Project

Next Steps in Potable Reuse for Padre Dam. WateReuse San Diego Chapter Meeting October 9, 2013

Brian Villalobos, CHG, CEG GEOSCIENCE Support Services, Inc. American Water Works Association California-Nevada Section Reno, Nevada

Potable Reuse as an Alternative Water Supply. AWRA Conference Orlando, FL

Aligning Seawater Desalination in California with Key State Policies

Desalination Intake Approaches: Open Ocean Intake vs Subsurface. Monterey Bay Water Works Association

Potable Reuse or Subsurface Intake Study Potable Reuse. Commenter and How Conveyed (meeting or ) Edo McGowan (at Meeting) Potable Reuse

Santa Barbara County Region

Soquel Creek Water District s Groundwater Recharge Feasibility Study. Lydia Holmes

Planning for Our Water Future: City of Santa Cruz & Soquel Creek Water District. September

Doheny Desalination Project. Technical Studies. October 31, 2017

AGENDA ITEM SUBMITTAL. Meeting Date: January 7, 2015 Budgeted Amount: N/A. Funding Source: N/A Program/ Line Item No. N/A

Appendix N. IID Capital Projects

400,000. MILLION GALLONS of water per day. The Desalination Plant and Process Locations. Welcome and Overview. people in San Diego County

CONCEPTUAL WASTEWATER TREATMENT ALTERNATIVES TECHNICAL MEMORANDUM. Cost Estimates... 3

Rehoboth Beach Effluent Disposal Study. Evaluation of Wastewater Discharge Alternatives. Center for the Inland Bays STAC Meeting January 13, 2006

Aquifer Storage and Recovery Using Reclaimed Water: Successful Applications and Critical Opportunities

IV. ENVIRONMENTAL IMPACT ANALYSIS G. HYDROLOGY/WATER QUALITY

Brackish Desalination Water Supply Planning for Resiliency and Growth

WATER QUALITY STATUTORY AND REGULATORY COMPLIANCE OVERVIEW

Overview Our local water resources (Vai)

San Mateo Plain Groundwater Basin Assessment Stakeholder Workshop #8 17 APRIL 2018

IPR Case Studies and Issues for DPR

Groundwater Replenishment with Purified Water Injection Provides Drought Protection & Environmental Benefits

Business Development Association of Orange County. Nov. 16, Chris Olsen, PE Director of Engineering Orange County Water District

San Benito County Water District Groundwater Sustainability Agency. Community Workshop. November 14, 2018

Are micro-porous pipes able to eliminate environmental concerns when installing intakes? Anthony T. Jones, Ph.D.

Current Drivers Toward Potable Reuse

San Antonio. Water System BRACKISH GROUNDWATER DESALINATION PROJECT. Bill Stein, PG. LBG-Guyton Associates. San Antonio AMTA/AWWA 1

Got Desalination. In Your Water Portfolio? Mark Lambert, CEO IDE Americas. Texas Desalination Association, 2016

Direct Potable Reuse

WATER RECYCLING PLANT IN WAFRA. Feras Al Salem

DESALINATION TASK FORCE MEMORANDUM

Overview of Conjunctive Management in California Let s Have a Frank Discussion

Carpinteria Valley Water District. Q&A Carpinteria Groundwater Basin (CGB) August 20, 2014

South Orange County Watershed Management Area Public Workshop. September 19, 2012

Water Reuse in the USA. Shivaji Deshmukh, P.E. Orange County Water District Istanbul, Turkey March 20, 2009

D.G.S.W. Pitakumbura Manager (Groundwater Studies) Groundwater Section NWS&DB. Groundwater recharge or deep drainage or

Carlsbad Seawater Desalination Project ( Project ) consists of 50 MGD (56,000 AFY)

DRAFT. APPENDIX F Groundwater Flow Model Proposed El Segundo Desalination Facility

Morro Bay Water Reclamation Facility Draft Environmental Impact Report Public Meeting

City of Vacaville Recycled Water Master Plan Feasibility Study

Orange County Water District. SCAP May 4, 2015

Appendix A: Project Characteristics

Miami-Dade Water & Sewer Department. Miami-Dade Water and Sewer Department 1

Coachella Valley Regional Water Management Group (CVRWMG)

Salt or Sewer? Supplemental Water Supplies for Santa Cruz County

The Evolution of the World s Largest Advanced Water Purification Project for Potable Reuse

Planning Today For Water Tomorrow

Desalination Concentrate Disposal Using Injection Wells: Technical Challenges

An Update of Coastal Desalination Status in the West Coast

12:00 noon 7. Tour of the Silicon Valley Water Advanced Water Purification Center

3.1 Desalination Cost Trends

Advanced Water Treatment (DESALINATION) PART 5. Instructor : Dr. Yunes Mogheir. Page 1

SANTA CRUZ NEIGHBORS FEBRUARY 21, 2012

INTRODUCTION. Trusted Partners Delivering Value Today for a Better Tomorrow BUILDING STRONG

The Future of Alternative Water Supplies in the SWFWMD. Workshop: Practicable Sustainability: Implementing Water Reuse/Supply/Resource Projects

MAKING THE SWITCH FROM LIME TO MEMBRANE SOFTENING: WHEN IS IT THE RIGHT TIME? Introduction

4B.6 Desalination 4B Description of Option. Desalination of Lake Granbury Water for Johnson County Regional Plan.

DRAINAGE AND NATURAL AQUIFER GROUNDWATER RECHARGE ELEMENT

Groundwater Management

Prop 50 Project Completion Report Project 50-4 Ray Stoyer Water Recycling Facility Demonstration Project

Indirect Potable Reuse for Groundwater Recharge Succession Strategy for Recycled Water

Indirect Reuse with Multiple Benefits The El Monte Valley Mining, Reclamation, and Groundwater Recharge Project

STORMWATER HARVESTING FOR ALTERNATIVE WATER SUPPLY IN VOLUSIA COUNTY, FLORIDA

Citizen s Guide: A Handbook to the Draft Environmental Impact Report and Review Process

WHEREAS, the Board has previously so adopted a wastewater supply system comprehensive plan, and

Subsurface Seawater Intake Gallery

Amortized annual capital cost ($) + Annual Operating Cost ($) = Unit Cost ($/acre-foot) Annual beneficially used water production in acre-feet (AF)

Notice of Preparation of an Environmental Impact Report and Scoping Meeting

Desalination Innovation & Trends. Tom Pankratz, Water Desalination Report

Aquifer Storage & Recovery (ASR) and Reuse

ADOPT A RESOLUTION OF THE CITY COUNCIL IN SUPPORT OF THE CALIFORNIA WATERFIX AND CALIFORNIA ECO RESTORE

Transcription:

Subsurface Desalination Intake & Potable Reuse Feasibility Studies TAP Workshop #1 City of Santa Barbara, California August 5, 2015

Agenda Project History Feasibility Study Background & Objectives Feasibility Study Scope Subsurface Intake Study Basis of Design Feasibility Criteria & Fatal Flaws Potable Reuse Study Basis of Design Feasibility Criteria & Fatal Flaws Implementation Schedule, Cost Estimate & Feasibility Analysis Technical Advisory Process 2

Project History 3

Charles Meyer Desalination Plant Constructed as emergency supply Capacity @ 7,500 AFY (6.7 mgd); 10,000 AFY (8.9 mgd) expansion Operated March - June 1992 Delivered ~419 AF of desalinated water Long-term standby mode 1994 Permanent facility 1991 - City voters overwhelmingly approve adding desalination as a permanent facility 1994 Long-Term Water Supply Plan 1996 - Permanent facility permits Charles Meyer Desalination Plant 2010 and 2011 - City Council reaffirms desalination as a permanent part of City s water supply 4

Overview of desalination facilities Intake: 2,500 feet off shore Pump Station/Chemical Area: 420 Quinientos Street Desalination Plant: 525 Yanonali Street Outfall: 8,720 feet off shore (shared with El Estero WWTP) 5

The City has diversified their water supply portfolio to improve reliability 1980s Current Cachuma Cachuma Groundwater Gibraltar/ Mission Tunnel Groundwater Gibraltar/ Mission Tunnel State Water Project Desalination Conservation Program Recycled Water 6

Drought supply as called for by the Long-Term Water Supply Plan Increased groundwater (GW) pumping Import banked and purchased water Demand reduction Rates Regulations Desalination Charles Meyer Desalination Plant Based upon current drought, City will need desalinated water supply by Fall 2016 (start of Water Year 2017) 7

Supply strategy/desalination timeline (based on no reservoir inflows, no State Water) 8

The City is moving forward with the desalination plant reactivation June 2015 City selects DBO contractor IDE/Kiewit July 2015 City Council approved $55-million SRF Loan August 2015 DBO notice to proceed October 2016 Desalination Plant operating 9

Desalination facilities are updated with modern technology while maintaining consistency with existing permits 10

Feasibility Study Background & Objectives 11

Both City Council & RWQCB have directed Public Works to study feasibility of subsurface intakes & potable reuse September 23, 2014 City Council directs public works staff to report back with a plan to evaluate: Subsurface intakes Potable reuse (IPR/DPR) January 30, 2015 RWQCB amended NPDES permit with a special condition requiring this study: Work Plan approved by August 2015 Complete feasibility studies by June 2017 12

Objective & scope Work Plan Objective: Present methodology and procedures used to perform studies per RWQCB requirement City Council: direct staff [to evaluate the] feasibility, cost, and timeline associated with both converting the offshore facility to a subsurface intake and look at the options about potable reuse Scope does not include: Determining best alternative Scope does include: Identifying feasible alternatives 13

Project team is complemented by engineering, environmental & geotechnical experts June 16, 2015 City hires Carollo team Carollo PM: Tom Seacord PE: Eric Cherasia Fugro Paul Sorensen Dudek Joe Monaco Austin Melcher Global Water Consulting Nikolay Voutchkov MBI Scott Jenkins GSI Jeff Barry Tim Thompson 14

Three work authorizations allow incorporation of feedback from prior activities Work Authorization 1: Work Plan development Both subsurface intake and potable reuse Work Authorization 2: Subsurface intake fatal flaw an analysis and potable reuse feasibility study Work Authorization 3: Subsurface intake feasibility study 15

Work Plan has 7 areas that define how the study will be conducted 1. Introduction 2. Basis of Design 3. Feasibility Criteria (& Fatal Flaws) 4. Implementation Schedule Development 5. Cost Estimating Methodology 6. Feasibility Analysis 7. Technical Advisory Process 16

Subsurface Intake Programmatic WPD 17

Subsurface Intake Programmatic WPD 18

Subsurface Intake Programmatic WPD 19

Potable Reuse Programmatic WPD 20

Potable Reuse Programmatic WPD 21

Permitting deadlines drive the project schedule Work Plan Due: August 2015 Final Presentation to RWQCB: June 2017 22

Basis of Design Subsurface Intake Study 23

Project capacity Replace City s existing open ocean intake Provide seawater for buildout capacity of 10,000 AFY Design capacity: 15,898 gpm Includes: 45% RO recovery Volume of raw water needed for pretreatment backwashing 24

Site alternatives Onshore/Offshore considered Dependent on intake tech Offshore areas within ½ mile offshore considered Simplifies property acquisition 25

Intake technologies Based on state of intake technology and recent studies conducted by others: Vertical Wells Lateral Beach Wells (onshore infiltration galleries) Horizontal Collector Wells (i.e., Ranney Wells) Slant Wells SIG offshore HDD wells (i.e., Neodren) 26

Geotechnical & hydrogeologic properties Literature review Numerous sources presented in Work Plan Additional data collection If hydrologic data is not available, alternative is potentially feasible and additional data collection is recommended 1. Geophysical survey along beach and shore area 2. Drilling of core holes and installation of piezometers Permitting for field data collection may have schedule impact 27

Oceanographic hazards Tsunami (Coastal) Hazard Analysis Two phases: Landside Waterside Fundamental inputs: 1. Extreme wave height 2. Local water depth 3. Depth/slope sediment cover over bedrock Coastal Evolution Model (CEM) Sediment Transport Analysis Optimal neither erosional or depositional Feasible hydraulic pathway to CMDP Littoral Cell: complete cycle of sedimentation Sources, paths, sinks Santa Barbara Littoral Cell CEM model Used during validation 28

Water quality & treatment needs Subsurface intake systems may reduce RO pretreatment needs Literature data will be used to establish pretreatment requirements e.g., Long Beach, Morro Bay, Doheny Beach Pretreatment process exists at desalination plant already Compatibility of pretreatment will be assessed Avoided costs (±) will be estimated using subsurface intake 29

Design & construction constraints Estimate intake yield, facility spacing, and length of beach required Standard analytical equations & numerical methods used to estimate flow & yield Spacing to minimize interference/drawdown Percentage of ocean water Based on literature, aquifer data, analytical models Impacts to local GW and sensitive habitats Potential capture of known GW contamination 30

Project life & reliability 20-year project life assumed Reliability based upon: Intake type Hydrogeology Geochemistry Other site specific factors Safety factor established to address Downtime for maintenance/repairs Decrease in production (plugging) 31

Feasibility Criteria & Fatal Flaws Subsurface Intake Study 32

Feasibility Definition in 2012 CEQA Statute & Guidelines Feasible means capable of being accomplished in a successful manner within a reasonable period of time, taking into account economic, environmental, social, & technological factors Ocean Plan Amendments (Adopted May 6, 2015) Identify 13 factors to determine feasibility of subsurface intakes 33

Feasibility factors for subsurface intakes 1. Geotechnical data 2. Hydrogeology 3. Benthic topography 4. Oceanographic conditions 5. Presence of sensitive habitats 6. Presence of sensitive species 7. Energy use 8. Impact on freshwater aquifers, local water supply, and existing water users 9. Desalinated water conveyance 10. Existing infrastructure 11.Design constraints (engineering constructability) 12. Project life cycle costs 13.Other site & facility specific factors 34

Feasibility criteria (see Table 3.1 in Subsurface Intake Work Plan) Feasibility Criteria Geotechnical factors Technological Factors CEQA Feasibility Criteria Social Factors Environmental Factors Hydrogeology factors X X X Benthic topography X X Economic Factors Oceanographic factors X X Presence of sensitive habitats X Energy use X X X Design and construction constraints X X X X Other site-specific factors X X Economic factors X X X 35

Fatal flaw Technological factors in CEQA definition referred to as technical feasibility Certain technical feasibility criteria are fatal flaws Fatal Flaw: Those technical factors that would not allow a full-scale system to be successfully constructed or operated, or would result in a high risk of failure, immitigable impact, or unacceptable performance of the City s desalination plant at the raw water volume required for build-out conditions. 36

Fatal flaw criteria Fatal Flaw Geotechnical Hazards Seismic hazard Hydrogeologic Factors Operation of subsurface intake adversely impacts existing fresh water aquifers, local water supplies, or existing water users Operation of subsurface intake adversely impacts sensitive habitats such as marshlands, drainage areas, etc. Insufficient length of beach available for replacing full yield derived from the existing open ocean intake Definition Project facilities would cross a known fault line, or be exposed to a seismic hazard that could otherwise not be protected from loss by design Volume of groundwater in storage is reduced due to subsurface intake pumping, impacting drought supply and requiring additional desalination to make up for loss of groundwater Operation of subsurface intake causes salt water intrusion into groundwater aquifers Operation of subsurface intake drains surface water from sensitive habitat areas or adversely changes water quality Small individual facility yield, large number of facilities required, and minimum spacing between facilities requires more shoreline than is available 37

Fatal flaw criteria (cont d) Fatal Flaw Definition Benthic Topography Land type makes intake construction infeasible Depth to bedrock too shallow (i.e., less than 40- feet deep); rocky coastline; cliffs Oceanographic Factors Erosion, sediment deposition, sea level rise or tsunami hazards Presence of Sensitive Habitats Proximity to marine protected areas Oceanographic hazards make aspects of the project infrastructure vulnerable in a way that cannot be protected and/or would prevent the City from being able to receive funding or insurance for this concept Location would require construction within a marine protected area 38

Fatal flaw criteria (cont d) Fatal Flaw Design and Construction Constraints Adequate capacity Lack of adequate linear beach front for technical feasibility Lack of adequate land for required on-shore facilities Lacking adequate land for on-shore construction staging Precedent for subsurface intake technology Definition Subsurface material lacks adequate transmissivity to meet target yield of at least 15,898 gpm (i.e., build-out intake capacity necessary to produce 10,000 AFY) Length of beachfront available is not sufficient for construction of the required number of wells of all or portion of intake to meet target yield Surface area needed for on-shore footprint of an intake unit is greater than the available onshore area Requires condemnation of property for new onshore intake pumping facilities The amount of land available to stage construction does not meet need Intake technology has not been used before in a similar seawater or fresh water application at a similar scale) 39

Basis of Design Potable Reuse Study 40

Production capacity Replace City s existing open ocean intake Provide up to the CMDP s buildout capacity of 10,000 AFY City produces 1,400 AFY of non-potable recycled water Combined potable and non-potable reuse capacity must be 11,400 AFY El Estero WWTP effluent available depends upon: Avg, min, max annual flow Avg, min, max day flow Min/max hour flows 41

Production capacity (cont d) Capacity of each alternative based on: 1. Avg day flows with storage used to buffer changes in diurnal flow rates Sizing plant on average day flow condition ensures facility s equipment well utilized. 2. Full treatment by reverse osmosis for potable reuse stream @ 80% RO recovery 3. Recycle of BW water from microfiltration and other non-potable reuse treatment filter systems to head of WWTP Optimize recovery and reuse of flow streams 42

Project site & potable reuse alternatives New info from USGS may update boundaries 43

Project site & potable reuse alternatives 1 2 3 Possible Treatment Facility Locations 525 E. Yanonali Street (Repurposing existing CMDP) 401 E. Yanonali Street (i.e., City Corporation Yard) 103 S. Calle Cesar Chavez 1 3 2 44

Project site & potable reuse alternatives 1 4 2 3 1 2 3 4 Possible Groundwater Recharge Locations Recharge wells in Foothill basin (near Route 154 & Highway 101) Recharge wells in groundwater basin Storage Unit 1 Enhanced infiltration of water (spreading basin) in Mission Creek Spreading basin in or near Foothill basin 45

Project site & potable reuse alternatives 1 Possible Direct Potable Reuse Options Discharge of advanced treated water into Lauro Canyon Reservoir (raw water production) 1 2 Dilution and off-setting intake volume of seawater to CMDP 2 46

Water quality & treatment needs IPR Alternatives CCR, Title 22 IPR regulations for GW replenishment by surface application Spreading basins IPR regulations for GW replenishment by subsurface application Injection wells DPR Alternatives No CA Regulations yet DDW will review DPR projects on a case by case basis Likely include: Tmt in excess of Title 22 Recent statements indicate 14/12/12 log requirement Engineered storage buffer 47

Geotechnical & hydrogeologic properties Literature review: Numerous sources presented in Work Plan Including County-wide Reuse Study Additional data collection will be recommended if sufficient data is not available 1. Aquifer test at existing locations 2. Geophysical survey near recharge sites 3. Infiltration rate testing using double ring infiltrometers 4. Installation of piezometers; geophysics may be considered 5. Installation of test/observation wells; performance of aquifer/injection tests 48

Design & construction constraints Rate of GW recharge at target locations Surface recharge: infiltration rates, low permeability layers, depth to GW Injection wells: aquifer transmissivity, well design, depth to water, flow limiting barriers Available storage in production zone aquifers City/USGS model for Santa Barbara Basin Existing basin and well yield increases USGS model and analytical methods 49

Other project criteria Impacts to local GW supplies and existing water users Impacts to sensitive habitats Potential capture or mobilize known GW contamination Additional production wells 50

Project life & reliability 20-year project life assumed Reliability based upon: Production capacity Source water quality Potable reuse alternative Hydrogeology Other site-specific factors Safety factor established to address Downtime for maintenance/repairs Decrease in recharge capacity 51

Feasibility Criteria & Fatal Flaws Potable Reuse Study 52

Feasibility criteria (see Table 3.1 in Potable Reuse Work Plan) Feasibility Criteria Geotechnical factors Technological Factors CEQA Feasibility Criteria Social Factors Environmental Factors Hydrogeologic factors X X X X Economic Factors Oceanographic factors X X Presence of sensitive habitats X Energy use X X X Design and construction constraints X X X X Other site-specific factors X X X Economic factors X X X 53

Fatal flaw criteria Fatal Flaw Geotechnical Hazards Seismic hazard Hydrogeologic Factors Operation of groundwater recharge facilities (i.e., injection wells or spreading basin) adversely impacts existing fresh water aquifers, local water supplies or existing water users Operation of groundwater recharge facilities (i.e., injection wells or spreading basin) adversely impacts sensitive habitats such as marshlands, drainage areas, etc. Definition Project facilities would cross a known fault line, or be exposed to a seismic hazard that could otherwise not be protected from loss by design Insufficient travel time (e.g., < 2 months) between groundwater recharge point and other groundwater users Operation of facility adversely changes water quality of habitat (e.g., salt water habitat becomes fresh water). Insufficient storage space Groundwater basin lacks adequate storage capacity to receive 10,000 AFY (or 11,400 AFY) at build-out Groundwater recharge of IPR water causes loss of ability to adequately manage the groundwater basin (e.g., artesian or flooding conditions, loss of stored water, etc.) Groundwater recharge of IPR water does not result in an increase in total basin yield and overall yield of 10,000 AFY (or 11,400 AFY) 54

Fatal flaw criteria (cont d) Fatal Flaw Oceanographic Factors Sea level rise or tsunami hazard Presence of Sensitive Habitats Habitat creation Design and Construction Issues Definition Oceanographic hazards make aspects of the project infrastructure vulnerable in a way that cannot be protected and/or would prevent the City from being able to receive funding or insurance for this concept Facility creates habitat that is unsustainable (i.e., requires continued discharge by IPR facility) or adversely affects local ecosystem Adequate capacity Availability of effluent needed to produce 10,000 AFY (or 11,400 AFY) of recycled water at build-out IPR production capacity and/or aquifer losses result in less than 10,000 AFY (or 11,400 AFY) Lack of adequate land for required for IPR treatment or groundwater recharge facilities of production at build-out Surface area needed for footprint of IPR treatment or groundwater recharge facilities is greater than what is available Requires condemnation of property for new injection well facilities 55

Implementation Schedule, Cost Estimate & Feasibility Analysis* *Only feasible or potentially feasible alternatives are carried forward 56

Implementation schedule development Major components: 1. Planning phase (feasibility studies) 2. Test facility or test well demonstration 3. Implementation of full-scale system Schedule inclusive to all project components: Property easement acquisition Design Permitting Environmental Bid phase Construction Operation 57

Cost estimating methodology Performed for alternatives surviving fatal flaw analysis Prerequisites Additional data collection (if necessary) Regulatory & permit requirements Conceptual design Class 4 estimate Parametric models, specific analogy, trend analysis Includes: Feasibility analysis, environmental review, permitting, public process, property and easement acquisition, design, construction, O&M 58

Feasibility analysis After schedule and costs are complete Considers factors: Technological Social Environmental Economic All factors from Feasibility Criteria table Advantages/Disadvantages presented for each 59

Technical Advisory Process 60

TAP has 3 primary objectives 1. Provide timely review of project work products and guide studies By subject matter experts 2. Facilitate input from project stakeholders Used to inform City s comparison of potentially feasible alternatives 3. Create a record of the review and stakeholder process Included as appendix to feasibility study report 61

Work Plan defined TAP process Facilitated by NWRI Non-profit; has facilitated similar programs for municipal and state regulatory agencies NWRI will: Retain services of TAP members Facilitate project meetings (including stakeholder comment) Document technical review & stakeholder process Moderator: Jeff Mosher, NWRI 62

NWRI has selected TAP panelists with experience in the required project areas Amy Childress, Ph.D., (Panel Chair) University of Southern California Heather Collins Metropolitan Water District of Southern California Martin B. Feeney, P.G., C.E.G., C.Hg. Consulting Hydrogeologist Heidi R. Luckenbach, P.E. City of Santa Cruz Water Department Eric Zigas Bay Area Water Group, Environmental Science Associates 63

Work Plan defines TAP meetings & format Workshop 1: Work Plan Workshop 2: Fatal Flaw Analysis Workshop 3: Potable Reuse Feasibility Study Workshop 4: Subsurface Desalination Intake Feasibility Study Work product to TAP 15 days before a workshop NWRI: Distribute to TAP Post material to project website (@ least 5 days prior) Create and distribute agendas 64

TAP workshop format 65

Stakeholder process Comment cards used to record issues, feedback, or comments Shall be submitted 10 minutes prior to comment period Stakeholders given 2 minutes for comment Can yield time to another individual Not required to attend workshop to record comments Comments can be submitted to NWRI within 5 working days of workshop 66

http://www.nwri-usa.org/santa-barbara-panel.htm PROJECT WEBSITE 67

RWQCB approval of work plan is required by end of August 2015 NWRI provides report of TAP and stakeholder comments to City City addresses TAP comments; responds to stakeholder comments City submits Work Plans & TAP Report to RWQCB for approval 68

Subsurface Desalination Intake & Potable Reuse Feasibility Studies TAP Workshop #1 City of Santa Barbara, California August 5, 2015

Overview of Desalination Facilities 2 Pass Media Filters Cartridge Filters RO Trains Finished Water Intake Filter Feed Pumps Media Filter Backwash Recovery/Treatment Permeate Flush Brine Pump Station 70

Three Phase Reactivation Plan Sludge Treatment Post-Treatment CO 2 Lime Preparation Flush Tank/Pumps Product Pumps UV CIP 7,500 AF-Y 3,125 AF-Y 7,500AF-Y 3,125 AF-Y 7,500 AF-Y Coagulation Tank(s) Suck Back Tank(s) Product Tank(s) 3,125 AF-Y 10,000AF-Y 10,000 AF-Y 71

The City has maintained the permits required to operate its desalination plant Coastal Development Permit Permanent facility CDP approved in October 1996 Repair & Maintenance CDP issued in February 2015 NDPES Permit 2015 Renewal - administrative extension was issued RWQCB Amended the permit in January 2015 to make findings pursuant to Section 13142.5(b) of the Water Code Consistent with the recently approved Ocean Plan Amendments 72

Permit Status (cont d) CA State Lands Lease Intake is exempt Outfall lease extended through 20?? CA Dept of Public Health City s Operating Permit will be amended during the desalination plant reactivation US Army Corps 404/Section 10 Permit Updated in July 2015 City CDP - Substantial Conformance Completed in August 2015 73

Feasibility criteria 74

Feasibility criteria (cont d) 75

Project site & potable reuse alternatives Possible treatment facility locations: 401 E. Yanonali Street (i.e., City Corporation Yard) 103 S. Calle Cesar Chavez 525 E. Yanonali Street (Repurposing existing CMDP) Possible groundwater (GW) recharge locations: Recharge wells in Foothill basin (near Route 154 & Highway 101) Recharge wells in GW basin Storage Unit 1 Enhanced infiltration of water (spreading basin) in Mission Creek Spreading basin in or near Foothill basin 76

Site & reuse alternatives (cont d) Possible direct potable reuse options: Discharge of advanced treated water into Lauro Canyon Reservoir (raw water production) Dilution and off-setting intake volume of seawater to CMDP 77

Potential areas for reuse 78

Feasibility criteria 79

Feasibility criteria (cont d) 80