The Jeffreys Bay Wind Farm

Similar documents
South African Mainstream Renewable Jeffreys Bay Pty Ltd

Positioning Nelson Mandela Bay for Renewable Energy Manufacturing Opportunities

Unlocking the Green Economy and Solar PV Industries

CONTENTS 2. PROJECT DESCRIPTION NEED FOR THE PROJECT ABOUT THE PROPONENT SITE SELECTION OVERVIEW OF THE PROJECT 2 5

NERSA Public Hearing InnoWind / IDC Round 2 Projects

South African Mainstream Renewable Power De Aar PV Pty Ltd

Nxuba Wind Farm NERSA PUBLIC HEARINGS. 10 September 2015

Soetwater Wind Farm NERSA PUBLIC HEARINGS. 09 September 2015

NERSA Public Participation Process Klipheuwel Dassiesfontein Wind Energy Facility March 1, 2012

NERSA Public Hearing Dyason s Klip 1 (Pty) Ltd

Information on a joint Agricultural and Renewable Energies Program at Sandfontein Farm, Bonnievale Bonnievale Solar Farm

Technical Requirements for for Wind Power Projects. James Murphy Manager, Project Development Ontario Sustainable Energy Association

BOLAND ENVIRONMENTAL CONSULTANTS CC

7-8 NOVEMBER 2018 CAPE TOWN, SOUTH AFRICA

White Rock Wind Farm Project Update for Community Consultative Committee 4th February 2016

Our Activities, Our Commitment

South African IPP Procurement Programme. December 2016

Steps in Building a Wind Farm

AFRICA. Transforming Africa s energy landscape today

REIPPPP focus on Eastern Cape. at a glance. March 2015 (including Bid Window 4 preferred bidders) New photos. The IPPPP partnership between

Belle River Wind Project

TO ALL SUPPLIERS SEEKING REGISTRATION ON JOHANNESBURG CITY PARKS AND ZOO DATABASE

Tilting at Windmills: Wind Power in the Twenty-First Century. October 6, 2012

Liquefied Natural Gas to Power IPP Procurement Programme

PROPOSED WAAIHOEK WIND ENERGY FACILITY UTRECHT KWA-ZULU NATAL

Role of Eskom in SA context

Electricity Slide Index Slide 2: Generating Electricity Slide 3: SA Power Grid

Liquefied Natural Gas to Power IPP Procurement Programme

BIOMASS POWER PLANT NEAR MKUZE, KWAZULU-NATAL

Lakeshore Looks to the Future with Renewable Energy

ENVIRONMENTAL IMPACT ASSESSMENT: PROPOSED PHOTOVOLTAIC ENERGY PLANT ON FARM KLIPGATS PAN NEAR COPPERTON, NORTHERN CAPE

Eskom s Single Buyer Office Perspective on renewable energy procurement. Clean Power Africa Conference. 5 September 2012.

T1.2: Tender Data. The tender documents issued by the Employer comprise: F.1.2. Part T1: Tendering procedures

Derisking Renewable Energy Investment

Chris le Grange & Pierre Pisterman Project Manager Hydro Tasmania & CEO HPP South Africa & France

APPLICATION FOR A GENERATOR AND A SUPPLY CONNECTION AT THE SAME POINT OF SUPPLY TO THE ESKOM NETWORK. Revision September 13 July 2016

Overview of the South Africa s Independent Power Producers Procurement Programme

A PV, diesel, ESS hybrid case study: The DeGrussa solar project

Independent Power Producer procurement Improving integration with municipal distributors

South Africa s hydroelectricity success. A case study of the first hydro power project in South Africa since the mid 1980 s.

ACEF Deep Dive Workshop. 5 8 July 2017 Manila, Philippines

ESP ENERGY SYSTEM PLANNING (PTY) LTD COMPANY EXPERIENCE (PROJECTS) Cons ulting Group

38.5 MW Sleaford Biomass Power Plant under construction, Lincolnshire, the UK. April 2013

NAVITUS BAY WIND PARK SUPPLY CHAIN ENGAGEMENT. Dan Bainbridge. 28 November 2014

Appendix C9 - Scoping Phase Focus Group Meetings

Concentrating Solar Thermal Power Stations Sustainable Green Energy Infrastructure for Peak, Mid-Merit & Base Load Electricity Supply

OVERVIEW OF ELECTRICITY DEMAND AND SUPPLY SITUATION. Public meeting 29 November 2004 Braamhoek Road EIA

F e b Des Muller Chairman for NIASA Supply Chain Development Subcommittee

EIA FOR THREE 10MW PHOTOVOLTAIC (SOLAR) ENERGY FACILITIES PROPOSED FOR MARIENTAL, OMARURU AND OKAHANDJA BACKROUND INFORMATION DOCUMENT

ADAMS SOLAR PV PROJECT. Northern Cape PV Project 82,5MW PUBLIC HEARING KIMBERLEY 18 FEBRUARY 2014

NIAGARA REGION WIND FARM. By Hugues Girardin and Michael Weidemann. ENERCON Forum 2016 The Global Energy Revolution November 16, 2016

Garob Wind Farm. NERSA Hearings Port Elizabeth 10 September NERSA Hearing

WIND ENERGY FACILITY AND ASSOCIATED INFRASTRUCTURE. COMMENTS AND RESPONSE REPORT: I&APs & STAKEHOLDERS EIA Phase

CFT REFERENCE DOCUMENT CFT GLOSSARY

business, government and civil society. It is also providing energy at rapidly decreasing cost to the consumer.

Functionality Evaluation Phase 3 : Preferential Point System Points Price 80 B-BBEE status level of contribution 20 Total 100

Briefing paper Solar Gardens

STRATEGIC CONTEXT FOR ENERGY PLANNING CHAPTER 2

Western Power Company Ltd. Ngonye Falls Hydroelectric Project October 2014

Quantifying the capital requirement: 19% RE by 2030

Alessandro Bragantini Chief Operating Officer Building Energy S.p.A. Italy

CFT REFERENCE DOCUMENT CFT GLOSSARY

Background Information Document

We are here to:

General Procurement Notice

White Rock Wind Farm Project update Community Consultative Committee 3 August 2017

ELECTRICITY SUPPLY INDUSTRY OF SOUTH AFRICA

BACKGROUND INFORMATION DOCUMENT

Update on the Power System and the Build Programme: A Presentation to the Media

POWER INDABA CONFERENCE

INITIAL PUBLIC MEETING

PUBLIC MEETING B3.1 ATTENDANCE REGISTERS. A record of attendance from the provided in the following pages.

A Case Study of Wind Power

at a glance REIPPPP focus on Eastern Cape Provincial Report Volume 2 September 2016 The IPPPP partnership between

Solar PV resource for higher penetration through a combined spatial aggregation with wind

Small scale Hydro Electric Power IPP compliance with legislation and REBID process

REQUEST FOR PROPOSAL

Renewable Energy in South Africa Resources and Opportunities STIAS Energy Workshop 5 March2013 Stellenbosch

HORNS REV 1 OFFSHORE WIND FARM

Sri: Sustainable Power Sector Support Project

TO ALL SUPPLIERS SEEKING REGISTRATION ON JOHANNESBURG CITY PARKS DATABASE

Introduction. Michigan Energy Providers Conference. July 27, 2018 JULY 2018

SSE Research, Development and Demonstration

Background Information Document

Bokpoort CSP and the Future of Solar in South Africa. Nandu Bhula Deputy Managing Director (Southern Africa) CEO Redstone CSP (designate)

New technologies for small hydro Geographical Information Systems (GIS): Eastern Cape Case Study

Promoting Utility Scale Solar using Viability Gap Financing (VGF) modality in Nepal

The Greening of Energy. Eskom s role in the Renewables Industry in South Africa

Global Wind Power; Wind Power opportunities in Australia; Why Wind Power for Australia? Wind Power for Australia. Wind Power environmental impacts;

The joint Danish-South African cooperation on climate and energy

Wild Horse Solar Photovoltaic Project

How to stimulate the South African rooftop PV market without putting municipalities financial stability at risk A Net Feed-in Tariff proposal

TOWN OF LABRADOR CITY FORM OF TENDER TLC SUPPLY & INSTALLATION OF CONCRETE FLOOR

The South African Renewable Energy Independent Power Producers Procurement Programme (REIPPPP) Lessons Learned

The Republic of South Africa. Department of Energy

Support for Competitive Procurement of Renewables in Mongolia

WIND ENERGY AND YOUR LAND

DEVELOPMENT OF RENEWABLE ENERGY MARKET IN JAMAICA

(Draft Captive and Renewable Energy Generating Plants) Regulations

Transcription:

The Jeffreys Bay Wind Farm African Utility Week Cape Town, 15 th May 2013 Presented by : Tom Thorogood & Davin Chown Mainstream South Africa

A Lead Project with a pioneering history in SA 2001 : Project started by Genesis Eco-Energy & land owner On part of Sunnyside dairy farm, outside Jeffrey s Bay Originally 16MW wind and 5MW pumped storage 1 st EIA s for wind farms Focus on supplying energy to strengthen grid in the area poor supply 2009: Genesis and Mainstream form JV to take project forward - announce R11bn energy development programme 2011: Project awarded preferred bidder status in REIPPPP 2012: Financial Close, 5 November 2012: NTP 15 November 2013: Ground breaking Feb 2013

Project Description Jeffreys Bay Location: adjacent to the N2 between the towns of Humansdorp and Jeffrey s Bay, in the Eastern Cape Total number of landowners = 8 including the Fatman Cooperative Farming Trust The Project will be spread across cover a total area of approx 3574 ha. All land is currently used for grazing. Installed Capacity: 138 MW consisting of 60 x 2.3 Megawatt Siemens Wind Turbines Grid Connection: into the 132kv line that crosses site & connects into Melkhout substation 2 km s from site DOE PPA scheme via REIPPPP- 20 year contracts for the purchase of electricity

Jeffreys Bay Site Layout

Site Layout

Project Benefits Savings Volume Unit Electricity Produced 138MW 362,664 MWh/per year Power for SA Homes Annual Tonnes of CO2 emissions avoided 241,776 306,451 Houses per year Tonnes per year Lifetime CO2 emissions avoided 6,129,022 Lifetime of project Water Savings 520,000,000 Liters per year Transmission loss savings 9 million Lower Wholesale Price of Electricity for the SA system kwh/per year (power 8 000 households) De-risk the local, Provincial, National Economies = increase in GDP

Secure the land Long Term Lease Agreements with all landowners 20 years. Wind Farm are located on low value agricultural land- grazing Wind Farms and associated component take up 2% of the land No disruption to farming activities - continue as normal Farmers benefit from long term income affords opportunity to expand farming operations and investments Ability to raise additional capital with banks due to long term security in place Emerging farmers supported

Economic Benefit for Operations Wind farm construction skills to small enterprises New construction skills turbine foundations; turbine erection Operational Jobs - Minimum of 15 full time positions for the 20 year operational life of the project Community Trust Commitment of 1.4% of annual gross revenue to SED Commitment of 0.52% of gross revenue to Enterprise Development Beneficiaries will be the community within a 50KM radius Focus areas so far: education, healthcare, social infrastructure Procurement from local enterprises Income for local farmers farmer development with emerging new landowners

Project Construction

Critical Milestones - Overview Mobilisation NTP 13 November 2012, site mobilisation 22 November 2012 Construction 1 st Turbine Pour: 19 th March 2013 (T24). Total 60 turbines split into 8 circuits. Siemens components to arrive in port mid july. Turbine erection to commence 1 st of August 2013 Final Turbine foundation complete 22 nd Nov 2013 Substation Construction Commence: 19 th Feb 2013 Eskom access to Substation for Commissioning- 23 rd October 2013 construction complete & hand over to Eskom Energisation of Grid Connection by Eskom 5 th December 2013 ( Pivotal key date for us as we need an energised substation to start commissioning the turbines) COD: 15 th of May 2014.

Challenges - Procurement Local Procurement DOE definition of local within 50km radius of projects Local Municipalities not necessarily briefed on Bid criteria Specialised Equipment required: so goods and services not always available in locality Local goods and services must compete with quality and price

Challenges Goods and services Availability of Local Goods and Services Local business encouraged to register on project database CLO manages this process Eligible business must have, a Company Registration Number, Tax Clearance, UIF, COIDA, Valid Letter of good standing, BBBEE certificate, Company Profile with references and photos Selection criteria to be chosen to supply: Safety, Quality, Previous Experience (References),Price. Uptake of process from local business has been poor to date.

Construction Programme Construction on schedule Construction Start November 2012. Commercial Operation Date May 2014. Total construction period 18 months. WTG installation August 2013. Grid connection December 2013.

Contracting Structure Project Company Jeffreys Bay Wind Farm Balance of Plant EPC Murray Roberts Concor Consortium Turbine Supply and Installation EPC Siemens Wind

Environmental Compliance Majority of environmental permits in place before DoE bid submission. Environmental Control Officer (ECO) engaged for construction period. ECO Audits ongoing. Flora and Fauna search and rescue ongoing

Roads and Hard Standings Good ground and topographical conditions for construction. Design complete. 14Km of roads built, another 39Km to go.

Foundation Construction Good geotechnical conditions. Design complete, standard GBS. Construction period 30 days / foundation

10 Complete 50 to go

Substation Eskom 132kV grid line traverses site 160 MVA Transformer. Manufacture South Africa. Steps up voltage from 33kV to 132kV. Earthworks complete.

Thank you for your time Tom Thorogood Project Construction Director Tom.thorogood@mainstreamrp.com Davin Chown Director Corporate Affairs & Business Development davin.chown@mainstreamrp.com Tel:021 657 4040 PO Box 45063, Claremont, 7735 4 th Floor, Mariendahl House, Main Road, Claremont, Cape Town