There are several types of trenchless technology applications for new installations. The following are some of the most prominent applications.

Similar documents
TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING)

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING)

SPECIAL CONDITIONS FOR HORIZONTAL AUGER BORING (HAB) October, 2006

SPECIAL CONDITIONS FOR MICROTUNNELING (MT) October, 2006

1. All underground utilities under railroad tracks shall be encased in a larger pipe or conduit called the casing pipe.

Martha Lake Gateway Sewer. An Introduction to Trenchless Methods and Evaluation for the Installation of New Pipelines

SPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006

SPECIFICATION : BORING AND JACKING

SECTION BORING AND/OR JACKING PIPE

Pipe Jacking/Microtunnelling. Dr. Mark Knight. Centre for Advancement of Trenchless Technologies (CATT) University of Waterloo.

SECTION TRENCHLESS INSTALLATION

How to Apply the Virginia Underground Utility Damage Prevention Act to a Jack and Bore Operation: A Case Study. Jessica M. W. Hou, P.E.

INDEX FOR SPECIFICATIONS FOR JACKING CULVERTS THROUGH EMBANKMENTS SCOPE... 2

Trenchless Technology

H. Underground Transmission System Design

CS-13 TRENCHLESS TECHNOLOGY TABLE OF CONTENTS

Analysis of Design When You Should Consider Pipe Ram Over Traditional Auger/Jack & Bore

HORIZONTAL BORING HORIZONTAL BORING. Underground Electric Distribution Standards I. GENERAL

DIVISION 33 - UTILITIES SECTION UTILITY PIPE BORING AND JACKING DIVISION 33 UTILITIES SECTION UTILITY PIPE BORING AND JACKING

THE TRENCHLESS TREND. Traditionally, pipeline shore crossings have integrated the by shallow waters, which are typically subject

Expert in Tunneling Systems & Trenchless Technology (HDD, Microtunneling, Pipe Jacking, Thrustboring, Sheet Piling)

CONSTRUCTION SPECIFICATION FOR TUNNELLING

HDD Training. Mitigation. Mark Miller, PE Jon Robison, PE

ARTICLE 26 UTILITY LINE INSTALLATION REQUIREMENTS

CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING

MAINE TURNPIKE AUTHORITY ADDENDUM NO. 2 CONTRACT EXIT 44 SOUTHBOUND ON RAMP IMPROVEMENTS MILE 44.3

CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING

SECTION HORIZONTAL DIRECTIONAL DRILLING

WARNING DO NOT BID ON THIS PROJECT

The Regional Municipality of Peel Basis of Payment

Trenchless Pipeline Crossings

CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING

TS 803 DUCTS DUCT INSTALLATION, PROTECTION AND MARKING WITHIN A TRENCH OPEN TRENCH DUCT INSTALLATION PROFILE

B. All materials to be installed shall be purchased in accordance with all applicable provisions of the Buy American Act.

1993 SPECIFICATIONS CSJ SPECIAL SPECIFICATION ITEM 4110 CONCRETE ENCASED DUCT BANK

GUIDE SPECIFICATIONS For STRUCTURAL PRECAST HOLLOW CORE SLABS SECTION 03410

TRENCHLESS INSTALLATION OF ROAD DRAINAGE & SERVICE DUCTS

4th International Engineering and Construction Conference - July 28, 2006

SECTION 1 GENERAL NOTES

Table of Contents TOC. Chapter 14 - Trenchless Construction. 14A General Information. 14B New Construction. 14C Rehabilitation

F. Provide at least 2 feet of vertical separation between a water line and any utility or stormdrain crossing it.

III. TECHNICAL SPECIFICATIONS DIVISION 56 BORED PIPE

Section WATER LINE IN TUNNELS

Technology. Trenchless. Planning, Equipment, and Methods. Mohammad Najafi. Mc Gravu Hill

5/16/2018. New Jet Pump Technology for HDD & Long-distance Pipe Jacking in small diameters. Dr. Marc Peters, Herrenknecht AG. Highlights.

CONSTRUCTION SPECIFICATION FOR INSTALLATION OF DUCTS

Horizontal Directional Drilling

UNIVERSITY OF MISSOURI Hydronic Energy Distribution 2016 Q1

ITEM 460 REINFORCED CONCRETE PIPE Description. This Item shall govern for the furnishing of reinforced concrete pipe.

SECTION A1 EXCAVATION AND BACKFILL GENERAL

SECTION DRILLED CONCRETE PIERS AND SHAFTS

SUPPLEMENTARY SECTION: STANDARD SPECIFICATIONS PAGE 1 STORMWATER MAINS & CULVERTS MAY 2018

The work required for this project includes, but is not limited to, the following items, not listed in order of execution.

Special Provisions for Pavement Open Cuts

North End and South End Section Hauled Wastewater Receiving Facilities Page 1 Bid Opportunity No

STANDARD SPECIFICATIONS SECTION BORING AND JACKING. A. Section includes requirements for boring and jacking casing pipe.

CHAPTER 11 CONDUITS AND FITTINGS

APPENDIX I. Conceptual Design - Salem Road and McKay Road Trunk Watermain and Sanitary Sewer

CC1602 Microtunneling

ITEM NO SLIPLINING SANITARY SEWERS

No-Dig Technology is the art and science of pipes, ducts and cables using techniques that minimizes / eliminates the need for excavation, i.e.

SECTION UTILITY HORIZONTAL DIRECTIONAL DRILLING (HDD)

CONDUITS AND FITTINGS

CONSTRUCTION SPECIFICATION FOR INSTALLATION OF DUCTS

CONSTRUCTION SPECIFICATION FOR INSTALLATION OF DUCTS

CONSTRUCTION SPECIFICATION FOR CRACK REPAIR - CONCRETE

REQUIREMENTS FOR SERVICES UNDER THE RAILWAY CORRIDOR (NON-QR SERVICES)

SITE SERVICES GUELPH TRANSIT OPERATIONS & MAINTENANCE SECTION WATSON ROAD FACILITY PAGE 1 OF 6 WATER RECLAMATION PROJECT JUNE 2013

MODEL SPECIFICATIONS: Hydraulically Driven Steel Underpinning Pile Specifications

SECTION 39 - MANHOLES TABLE OF CONTENTS

YOUR GROUND DRILLING PARTNERS.

CONSTRUCTION SPECIFICATION FOR INSTALLATION OF DUCTS

American Concrete Pipe Association. Precast Box Culvert Installation Procedures

1.01 GENERAL. l.02 PIPELINE TRENCH EXCAVATION PIPELINES AND STRUCTURES REVISION: SECTION 1 PAGE : 1-1

WATER LINE IN TUNNELS

Sample Bid Specification Revision 2 PVC Expanded-in-Place Pipeline Reconstruction

Short Drive Microtunnelling (MTBM) TRENCHLESS TECHNOLOGY ROADSHOW May 28-29, 2014 Scotiabank Convention Centre, Niagara Falls, ON

SPECIAL SPECIFICATION 6666 Charter Communications System

Public Works and Utilities Department RIGHT-OF-WAY USE PERMIT APPLICATION

Design Data 4. Jacking Concrete Pipe

SECTION CONCRETE CURBS, GUTTERS AND SIDEWALKS

SECTION TRENCHING, BACKFILLING, COMPACTION AND GENERAL GRADING

7/17/2017 Page 1 of 5

3ft, 4 ft., 6 ft., and 8 ft. First Defense HC Handling and Installation Instructions

of GENERAL. A. Description

Design Data 4M. Jacking Concrete Pipe

SECTION PATHWAYS FOR COMMUNICATIONS SYSTEMS

SECTION EXCAVATION AND FILL

SECTION FACILITY SANITARY SEWERS

Wastewater Capital Projects Management Standard Construction Specification

Special Provision No. 421F01 April 2006

CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL AND ROCK BY HORIZONTAL DIRECTIONAL DRILLING (HDD)

SECTION 2831 ITEM F-162 CHAIN-LINK FENCES

SceptaCon Trenchless Raceway for Electrical and Telecommunication Cables

PRECAST CONCRETE GIRDER ERECTION

CONSTRUCTION SPECIFICATION FOR CHAIN-LINK FENCE

Transcription:

Applications for New Installations There are several types of trenchless technology applications for new installations. The following are some of the most prominent applications. Note that some specifications described in the following content may not be the same as the specifications followed by your agency. Always check with your State agency's standards and specifications when using these guidelines. Sections General Specifications for New Installations Jack and Bore/Auger Bore Pipe Ramming Moles and Small Rammers Pipe Jacking Microtunneling Horizontal Directional Drilling (HDD) General Specifications for New Installations Site investigation must be completed Materials, equipment, method, and sequence of operations are approved Materials are in accordance with requirements Operations do not interfere with, interrupt, or endanger the roadway surface and activity, including: Surface Structures Utilities 1

Alternate route for pedestrian use of sidewalk areas has been determined Excavation is the minimum necessary to complete the work Jack and Bore/Auger Bore Jacking pit is of sufficient size for operations Excavation method is compatible with expected ground conditions Length of bore is the minimum required Dewatering may be required All excavated material should be removed from the casing pipe as excavation progresses with no accumulation of such material occurring Driving ends of the casing pipe should be properly protected against spalling and other damage Any section of conduit showing signs of failure should be removed and replaced All voids should be grouted immediately after jacking operations have finished Extreme care should be exercised to maintain line and grade Pipe Ramming Soils are homogeneous and free of rock, boulders, stumps, and debris Steel bands ½-in. thick allowed On the outside of the leading edge of the pipe to reduce friction On the inside of the pipe to compact the spoil and to prevent plugging Install at the appropriate minimum depth of cover 2

Spoil is contained with the casing during ramming, removed afterwards using compressed air, and cleaned Limit air pressure to less than the rating of the pipe Lubricants are used as needed Moles and Small Rammers Launching pits are sufficient length, width, and depth Depends on the equipment and operation logistics Typically 4 6 ft. long Longer pits installed as series of shorter pits Should be back-sloped and shored for safety Correct alignment of tool in insertion pit After mole is 1/3 in ground, check alignment and correct; repeat until in the ground Tool should advance in a straight line Operator has little control over path once launched Operator does all steering according to planned route Evidence of appropriate lubrication of tool visible Small mist of oil as exhaust air from the tool Type of oil recommended by manufacturer is used Boring done in appropriate temperature conditions or mitigation strategies used Cold temperatures may stop mole through icing Hot temperatures may require more oil for lubrication 3

Product pipe is typically pulled into place after borehole is completed, or: Pushed into place using special driving heads Simultaneously pulled into place using special pulling accessories Pipe Jacking Dewatering effort is satisfactory Pipe characteristics are consistent with permit requirements. Jacking pipe is certified for jacking Pipe has a smooth interior and exterior surfaces Used within the entire influence area of the roadbed Clean and square ends Joints are watertight Defective pipe is not used Damaged pipe is jacked through to the receiving access pit and removed Jacking head fits square with the pipe Back thrust block is structurally adequate, jacking force is within the range of calculated jacking force, and the jacking force is recalculated whenever the operation is stopped Lubrication fluid is used, and a lubrication system properly injects lubricant on the inside and outside of the pipe Each end of the pipe is enclosed; restoration is completed Microtunneling Systems are operated following manufacturer s instructions 4

Copies of operations manuals are available to engineer and operational personnel at all times Tests are run before key activities: Test full system on completion of set up and before commencing drive Before commencement of any drive, demonstrate to engineer that required set-up procedures and system checks are complete and required materials are at hand to commence drive Receiving pit constructed prior to the start of the drive Horizontal Directional Drilling (HDD) Pipe reamed/pulled according to size of the drilled hole 6 in. or less pulling the pipe into hole within 8 hours More than 6 in. simultaneously pulling pipe or casing into hole as reaming occurs Multi-pass reaming larger than 6 in. requires certification by the contractor's engineer that the soils are self-supporting of the dead and live loads Drilled or reamed holes limited to 2 in. larger than the pipe Depth of cover is maintained, as specified Bores are begun at locations that allow transitioning the bore to meet the depth of cover requirements Drilling fluids are used as appropriate for the type of soil, and only used while drilling/reaming Drilling fluid pumping capacity, pressures, density, composition, and flow rates Monitor materials being removed from the trenchless operation 5