KenGen's Wellhead Technology Experience and Business Insight

Similar documents
PHASES OF GEOTHERMAL DEVELOPMENT IN KENYA

STRATEGIC ENVIRONMENTAL ASSESSMENT (SEA) FOR ENERGY SECTOR: CASE STUDY OF OLKARIA GEOTHERMAL EXPANSION PROGRAMME IN NAKURU COUNTY, KENYA.

Water Dependency of Geothermal Power Generation Systems

KENYA S PLANS FOR GEOTHERMAL DEVELOPMENT A GIANT STEP FORWARD FOR GEOTHERMAL

INFRASTRUCTURE DEVELOPMENT IN GEOTHERMAL FIELDS: A CASE STUDY FOR MENENGAI GEOTHERMAL PROSPECT, KENYA

GEOTHERMAL PROJECT TIMELINES

GEOTHERMAL DEVELOPMENT IN KENYA COUNTRY UPDATE. Cornel Ofwona Geothermal Development Company

EPRI JOURNAL January/February 2018 No The Need for Large-Scale Energy Storage Grows, but the Business Case Remains Uncertain

PROJECTS MANAGEMENT AT KENGEN, KENYA

Binary Cycle Geothermal Power Systems

Geothermal Steam Turbines for Various Purposes

GEOTHERMAL. snohomish county pud

Lake County Success. support through synergistic local partnerships that not only mitigate, but also produce

Enhanced Geothermal Systems (EGS) Using CO 2 as Working Fluid

OPPORTUNITIES FOR DIRECT UTILIZATION OF GEOTHERMAL ENERGY IN EBURRU AREA, KENYA

Power Africa Geothermal Road Show. Presented by David Kagiri

Challenges of Cementing Olkaria Geothermal Field

ORMAT Nevada, Inc. Expansion and Improvements Raise Power Production 20%

Geothermal Power POWER GENERATION.

Utilizing Vertical Discharge Tests as an Effective Means for Well Decision Making at the Darajat Geothermal Field, Indonesia

CONTRACTING OF GEOTHERMAL PROJECTS

COSTA RICA COUNTRY UPDATE

Ahmad Yani PT. Pertamina Geothermal Energy Lahendong, Jl. Raya Tomohon no. 420, North Sulawesi

DEVELOPMENT OF A GEOTHERMAL TRAINING CENTRE IN KENYA

Outreach Report Water Wall Turbine Inc.

Waste Heat to Power: Emissions Free Power & Industrial Competitiveness

The OriGen. Clean, Renewable Power From Waste Heat. AERCO.com

GEOFAR : Innovative geothermal technologies Last modifications: BINARY PLANTS

DESCRIPTION OF THE GOURIKWA POWER STATION & TRANSMISSION INTEGRATION PROJECT CHAPTER 3

30 Years of Tongonan-1 (Leyte, Philippines) Sustained Production

Design of a H2S Absorption Column at the Hellisheiði Powerplant

Integrated Power Solutions Modular and cost-effective power plant design

OVERVIEW OF GEOTHERMAL RESOURCE EXPLORATION AND DEVELOPMENT IN THE EAST AFRICAN RIFT SYSTEM

The Energy Industry: Structure and Organization. Module 1, Unit B

Dry Flexicycle power plants a closed loop combined cycle with unique operational flexibility

Heat recovery from diesel engines and gas turbines

TECHNICAL INFORMATION ABOUT UNDERGROUND STORAGE RESERVOIRS FOR NATURAL GAS

Discrete Fracture Embedding to Match Injection Returns in a Single Porosity Model

NUCLEAR POWER FOR SALT WATER CONVERSION

Design and Optimization of Kalina Cycle for Geothermal Energy in Kenya

Decline Curve Analysis for Production Forecast and Optimization of Liquid-Dominated Geothermal Reservoir

ARC EXECUTIVE PERSPECTIVE

Energy. Solar Energy. Energy Resource A natural resource that. humans use to generate energy. Can be renewable are nonrenewable.

/ Production.

Developing Geothermal Energy in the Pacific Northwest. The Energy Under Our Feet

Continuous Corrosion and Erosion Monitoring in Geothermal Power Facilities

Leading edge steamfield design After all, the plant is the easy part! Paul Quinlivan March 2010

Low temperature cogeneration using waste heat from research reactor as a source for heat pump

EXERGY ANALYSIS OF OLKARIA I POWER PLANT, KENYA

PureCycle 200 Heat-to-Electricity Power System

Organic Rankine Cycle Technology

Ocean Energy Basics. The ocean contains two types of energy: thermal energy from the sun's heat, and mechanical energy from the tides and waves.

20/06/2011 Seminar on Geothermal Exploitation Santiago de Chile

Solar-powered irrigation: Food security in Kenya's drought areas

Is CCS (Geological Storage) Ready for Prime Time?

Barilla Cogeneration Power Plant main tips

IoT Business Brief Energy & Oil Business DRIVING SOCIETY FORWARD

WIND ENERGY AND YOUR LAND

From surface to the reservoir, solving your geothermal challenges for over 50 years

Renewable energy: Investing in Africa

GEO-HEAT CENTER EXECUTIVE SUMMARY

Westinghouse AP1000. Reactor

Geothermal Power Plant

KS4 Physics. Renewable Energy. 1 of 44. Boardworks Ltd 2005

GEOTHERMAL ENERGY IN THE WORLD FROM AN ENERGY PERSPECTIVE

AREVA Solar Overview. Tom DePonty Director, Government Affairs United States Energy Association May 16, 2012

An Update on Applications to Direct-uses of Geothermal Energy Development in Kenya

Development of HK Electric Gas Receiving Facilities at

Windows Server 2003 migration: Your three-phase action plan to reach the finish line

Process Cooling Technology Forum: Laying the Foundation

V MW. One turbine for one world. vestas.com

The answer is... yes!

Front End Engineering Design (FEED) Challenges in EPC Projects: Design, LLI Strategy & Fast Track

Well Pad Automation Improves Capital Efficiency and Reduces Fiscal Risk Michael Machuca* Emerson Process Management

Carbon Dioxide Capture and Storage in Deep Geological Formations. Carbon Dioxide Capture and Geologic Storage

THE WORLD FACES two energy challenges.

MILESTONE REPORT. Energy & Environmental Research Center, University of North Dakota 15 North 23rd Street, Stop 9018 Grand Forks, ND

WATER RECYCLING PLANT IN WAFRA. Feras Al Salem

Extending value through field redevelopment

A COMPLICATED PROJECT FOR POWER AND WATER CO- GENERATION: THE RAF SITE

SUSTAINABLE USE OF OCEANS IN THE CONTEXT OF THE GREEN ECONOMY AND THE ERADICATION OF POVERTY, PRINCIPALITY OF MONACO, NOVEMBER, 2011

Green Energy for Africa: Stranded Gas or Coal and CO 2 -Enhanced Oil Recovery

Geothermal Power Plant

Carbon Dioxide Capture and Sequestration in Deep Geological Formations

GEOTHERMAL POWER PROFILE

2016 BioCleantech Forum TURBODEN ORC TECHNOLOGY: STATE-OF-THE-ART. Ilaria Peretti. Manager, Sales and Business Development North America

HEat PumP technology FoR underfloor HEatINg comfortheat.com.au

Emission Cuts Realities Electricity Generation Cost and CO 2 emissions projections for different electricity generation options for Australia to 2050

Organic Rankine Cycle Configurations

PES ESSENTIAL. PES: Europe

ENERGY RECOVERY IMPROVEMENT USING ORGANIC RANKINE CYCLE AT COVANTA S HAVERHILL FACILITY

Canada. Iron and Steel Sector - PI Specifics

Terms of Reference AG 2017/01

MLNG DUA DEBOTTLENECKING PROJECT

COST AND REVENUES OF DIRECT USE APPLICATIONS

Cost-effective, reliable solar power for agrofood businesses and sustainable development in Africa

Production/Injection Optimization Using Numerical Modeling at Ribeira Grande, São Miguel, Azores, Portugal

Greentree. Financial Management

German-African Energy Forum 2012

3G Landmass. FY16 Target

Transcription:

Proceedings World Geothermal Congress 2015 Melbourne, Australia, 19-25 April 2015 KenGen's Wellhead Technology Experience and Business Insight Ronoh Kibet and Roy Bwoma OLKARIA rkibet@kengen.co.ke Keywords: wellhead generators, early generation, rapid deployment ABSTRACT Geothermal electricity is generated from geothermal energy. Several modes of technology are used to convert the geothermal energy to electricity but the paper will focus on wellhead generation technology. Kenya is focused to come up with generation of power to meet its acute power shortage and ever rising demand. Traditionally KenGen has been using conventional power plants which involved months of well drilling and years of central power plant construction. The wellhead technology seeks to take advantage the idle time between completion of drilling and start and finish of the central power plant. It yields an overlapping concept that harvests the capped steam as soon as it is available for immediate power and revenue generation prior to the central power plant completion. The paper seeks to address the wellhead (early generation) concept and KenGen s experience is deploying this revolutionary technology 1. INTRODUCTION KenGen has pioneered a new technology in geothermal power generation by installing two wellhead generator units at Olkaria and Eburru. The wellhead units generate 5MW and 2.5MW of electricity respectively. This technology involves tapping steam from wells, which are undergoing tests, or are awaiting connection to permanent plants so as to benefit from early generation. This move by the largest electric power generator comes at a time the country is experiencing an increased demand for electricity. Rapid Economic growth and industrialization has created the need to accelerate the drilling of geothermal wells in order to tap geothermal power potential and avoid over-reliance on the erratic hydroelectric power. Long drought has slashed the capacity of main dams, forcing shutdowns and leading to reliance on costly diesel-powered generators, which have in turn pushed up energy bills. With the success of the Olkaria and Eburru wellhead power generating units, KenGen now intends to install more units with an expected yield of 70MW.Other geothermal areas targeted for this new technology include; Menengai, and Longonot. Through this move, KenGen has gone on record as the first company in Africa to embrace this new technology and therefore moved a step away from traditional methods to achieve the same results. An important point to note is that permanent power plant takes between 24 to 36 months to construct and commission. The well head power plant on the other hand takes 6 months hence a quick return on investment 2. AN OVERVIEW ON PLANNING OF GEOTHERMAL PROJECTS WITH A CASE STUDY ON OLKARIA, KENYA The planning of geothermal development in Kenya comprises the following stages: a) Review of existing information of a prospect b) Detailed surface exploration c) Exploration drilling and well testing d) Appraisal drilling and well testing; e) Feasibility studies f) Production drilling, power plant design and environmental impact assessment g) Power station construction and commissioning h) Reservoir management and further development and i) Shutdown and abandonment The development programme from Project identification to Power station commissioning is about 8 years but can be reduced to 5 years if finances are readily available. From the experience of development at Olkaria, it has been learnt that: 1

a) Timely financing of the projects is very critical; b) Some of the exploration wells could have been used to run pilot plants to generate some power while decisions for further development were being considered; c) Staged development has an advantage of making early use of the existing wells thus reducing early expenditure and producing revenue to take the project forward and build confidence in the resource. d) Appraisal drilling should not be stepped out too far apart from the discovery exploration well. Such step-out wells might destroy confidence in the prospect by being unproductive. Planning for competent staff is a very critical, yet often ignored, aspect of a good geothermal development strategy. 2.1 Drilling Logistics Drilling of geothermal wells takes between 50 to 70 days at depths of between 1.8 and 3.0km. After drilling, the exploration wells are fully tested. Permeability tests are conducted soon after capping the well. A suite of down-hole temperature and pressure measurements follow this when the well is heating up from the cooling experienced during drilling. Good wells recover quickly and within one month they develop enough wellhead pressure to discharge on their own. Other wells may require to be assisted to start discharge by compressing and releasing several times. Discharge tests takes a minimum of three months and a maximum of 1 year to determine the full characteristic and long-term behaviour of the well. During discharge tests, steam and brine measurements are made to determine the amount of steam available. Chemical analysis data of steam and brine is useful during exploitation and also for defining the reservoir characteristics. The current method is to pass the geothermal fluid through a pipe, measure the total flow and direct the fluid to a wellhead separator to separate the steam from the water. The water fraction is measured and the difference between the total mass flow and the water gives the steam fraction. Figure 1: Photo showing OW-38B discharging into the atmosphere. The well has a discharge capacity of 18MW Figure 2: OW 44 series discharging. The wells have a discharge a combined capacity of 20MW Normal well testing in its entirety wastes resources. In most cases, wells are discharged over long periods to assess their response to exploitation as the resource is drawn down without tangible production. 3. KENGEN PIONEERS WELLHEAD POWER GENERATION SYSTEMS Through use of this new technology, KenGen will test the wells while routing the steam through the generators, which will supply power to the grid. Using this approach the country s energy demand will be achieved within as short a time as 70 days of commencing well drilling. 2

It is no longer economical to drill all the wells needed to supply a permanent power station before financing is sought or returns are realized from the wells. In the event that a well is adjacent to a new well that is being drilled, power from the first well can be used to supply the next well to be drilled, thus reducing diesel usage at the drilling rigs. The balance can then be sent to the grid. It is estimated that a drilling rig consumes approximately 350,000litres of diesel from start to completion of a geothermal well. Conversion of the cost at 82KShs to the dollar yields about 426,829.3 USD i.e. By connecting these wells to wellhead generators; more than a quarter of drilling and base camp facility costs can be saved. In addition delays in procurement of diesel fuel will be eliminated hence reducing the drilling period significantly. Maintenance of the diesel generators and auxiliary power supply units to the rig require routine maintenance; they require changing of oil and oil filters as well as fuel filters. It is also the case that Labor required for maintenance comes with both cost and time implication to the drilling process. The use of portable wellhead generators therefore eliminates the use of diesel hence encouraging use of alternative green energy which environmental friendly, cheaper and clean. With this in mind, each completed will start contributing to the grid and could as well be doing this for the next four to six years it takes to complete all wells and build the main power plant. In essence, geothermal wellhead generators achieve environmental friendliness, and early generation of power using renewable resource and provide an early revenue stream that can be used to drill more wells or contribute to financing of the main power plant. 3.1 Effect on the ecosystem The standard method of well testing currently used discharges steam into the atmosphere. This hurts the environment because the temperature of the immediate environment is raised above normal conditions and may result in change of the eco-system. Encouraging the use of wellhead generators minimizes this effect as the steam will pass through the generators with the steam pressure and temperature dropping and ultimately condensed to a liquid, forming a closed loop with very little or no atmospheric venting. 3.2 Design features The wellhead design has a modular design based on standard manufactured components. Being flash based, the wellhead generator is suitable for temperatures above 190 degrees Celsius. The plant can operate independently for each well or be organized in power farms to provide a similar power output to large traditional geothermal power plants. The wellhead generator plant is delivered in 40-foot ISO containers on-site, and the standardization of key components allows for quick installation. The first power online can be expected within 12 months after ordering. Figure 3: Schematic represention of the 2.5MW Olkaria geothermal wellhead generator This solution has been developed to counter both the long term delays in supply of power online and prohibitive investments costs associated with the deployment of traditional geothermal power plants. The wellhead generator delivers power online from the completion of the first well, providing for step-by-step utilization of the geothermal field, without waiting until a critical mass of productive steam wells are drilled. Key benefits: a) Early return on investment; this technology represents a significant advantage over the deployment of traditional power plants enabling the early supply of electricity and importantly access to revenues earlier in the investment cycle 3

b) Optimal energy utilization; the independent well-head power plant enables optimum power to be produced from each individual well regardless of their differing outputs and characteristics. The concept negates the needs of traditional power plants for well redundancy or an excess steam buffer to cater for well failures and allows all wells to be utilized. The wellheads modular design also makes it possible to generate electricity from remote wells that are outside the topographical reach of large traditional plants. c) Rapid deployment; the wellhead s modular design, based on standard manufactured components, allows for significantly reduced lead times and early power online. Delivery of power online can be reduced to within 12 months of ordering the first wellhead generator power plant and thereafter rapid deployment, at a rate of one wellhead generator plant per month, can be achieved. d) Lower risk with modular flexibility; The wellhead generator modular power plant is delivered in 40-foot ISO containers and each module is ready made at the factory allowing for quick installation. It is designed to operate independently for each well, but can be organized in power farms to provide a similar power output to large traditional geothermal power plants. e) In the event of a well failure, the wellhead generator is designed to be decommissioned, transported and redeployed on a second well, maximizing the return on investment. Equally importantly, the failed well can be returned to its original state thus preserving the environment. f) Reduced cost per megawatt; The wellhead generator s modular design based on standard manufactured components enables a highly competitive capital price and allows for easy maintenance and access to spare parts. g) Flexibility and adjustability in power generation; focusing on the characteristics of each well independently, the wellhead generator is able to adjust turbines to achieve a high level of power output efficiency, driving down electricity production costs. h) Ease of operation and maintenance; The wellhead generator also deploys an advanced control system providing realtime operational data, allowing for early remediation action and preventative maintenance thus avoiding unnecessary downtime 4. CASE STUDIES 4.1 Eburru 2.5MW Geothermal Wellhead power station. The Eburru Wellhead Geothermal Power Plant has been commissioned and is now generating up to 2.52 MW for the Kenya Electricity Generating Co. (KenGen). This is a major milestone for KenGen, as it is its first geothermal wellhead power plant in commercial operation. Figure 4: Eburru wellhead power plant 4

Eburru is located approximately 2 hours outside of the capital, Nairobi, in Kenya s Great Rift Valley. The Eburru geothermal field is on the flanks of the Ol Doinyo Eburru Volcano and is situated 11 km northwest of Lake Naivasha. The project is unique because, for the first time, KenGen engineers carried out implementation work without the assistance of external consultants. Civicon served as the General Contractor, responsible for construction of the plant. During the month of January, GDA engineers worked closely with KenGen engineers and operators and Civicon construction crews to complete the commissioning and performance testing. The plant was first synchronized to the grid on January 23rd. The performance testing was completed just six days later on January 29th. GDA designed the plant and the steam field, and supplied all of the major equipment. This included an Elliott GYR steam turbine, Kato generator, Lufkin gearbox, Graham condenser and vacuum pump, Goulds cooling water pumps, and a Cooling Tower Depot single-cell fiberglass tower. GDA also manufactured auxiliary equipment in-house to minimize installation time, including the lube oil system, turbine control valve assembly, compressed air system, fire pump skid, emergency power system, and plant control system. The equipment and materials were shipped from the US to Kenya in 11 shipping containers one month ahead of schedule. 4.2 Olkaria 4.7MW power plant KenGen has partnered with the Green Energy Group (GEG) in constructing the 5MW Olkaria geothermal wellhead power plant. The highly experienced executive team at GEG has assembled a team commanding a wealth of experience within the design, engineering, project management and operation of geothermal plants and is supported by a Board of Directors drawn from both investment banking and the engineering sector. This technology has proved sustainable and KenGen has now commanded the lead into the next phase of power generation in line with the country s vision 2030. It has indeed embarked on an ambitious 70MWe project, which has already kicked off at the Olkaria Geothermal field with the second wellhead plant at 75% completion. This project will be guided by construction of sixteen wellhead power plants. It is notable that this is the first project of its kind in the world. Figure 5: the2.5mw Olkaria wellhead generator Below are photos showing the characteristic long steam lines associated with the conventional power station. Figure 6: photos showing the long steam lines delivering Steam to the conventional Olkaria II power plant -long steam lines are characteristic of the conventional power plant unlike the case of the portable wellhead power plant. 5

5. POWER STATION CONSTRUCTION AND COMMISSIONING A 50-70 MW geothermal power plant takes about 2 years to construct and commission. Remember that two years is the time for construction of the power plant only. On average at the figure of 5mw per well, we would require approximately 14 drilled wells each drilled for 3months therefore 52 months in total i.e. about 4 1/2yrs. This means that it will roughly take eight years to have the plant up and running considering delays in procurement. the construction of the power plant includes; Steam gathering and brine re-injection system; Power house, electromechanical equipment, cooling towers and blow-down re-injection system; Substations and transmission line; and Commissioning. Transmission lines can be an issue particularly if the wayleave acquisition is not handled in good time and professionally. This is because transmission lines can be fairly long and traverse very many land ownerships. Land compensation may be required in some parts while in others outright purchase may be the solution. Power lines, just like power stations require an environmental impact assessment to be conducted. REFERENCES Feasibility Report for the Olkaria Geothermal Project, Report for UNDP Fridleifsson, I.B., 2008: Thirty years of Geothermal Training in Iceland, 30th Anniversary Workshop, August 26-27 2008, Iceland. GENZL, 1980: Scientific Review of Olkaria Geothermal Resevoir. A KPC report prepared by GENZL. KPC, 1988: Proceedings of the Scientific Review Meeting 15-18 May 1988. Virkir and Sweco, 1976. Mwangi, M.N., 2005: Country update report for Kenya. Proceedings of the World Geothermal Congress 2005, Antalya, Turkey Sanyal, S.K., 2000: Forty years of production History of the Geysers Geothermal Field, California. The lessons learned. Geothermal Resources Council Transactions, 24, September 24-27, 2000. Sinclair Knight and RPS International, 1994: Environmental Assessment Final Report. North East Olkaria Development Project. A report for KPC. 6