LACHEL FELICE & Associates. Advances in Finite Element Modeling Using PLAXIS SILVER REEF HOTEL/CASINO EXPANSION

Similar documents
RIGID INCLUSIONS. Rigid Inclusions offer an economical approach for building on sites underlain by soft soil.

GEOTECHNICAL INVESTIGATION I-15 SIGN BRIDGES LAS VEGAS EA JANUARY

In preparation for constructing buildings on a property, the builder. Site Preparation CHAPTER

Lecture 21: Groundwater: Hydraulic Conductivity

April 7, Webster Street Sub-Surface Stormwater Storage System Bid No Bid Date: 4/13/17 ADDENDUM NO 1

Typical Subsurface Profile. November 28, 2016

A CASE HISTORY ON DESIGN, CONSTRUCTION, AND PERFORMANCE OF STONE COLUMN GROUND IMPROVEMENT BENEATH AN MSE EMBANKMENT

Applied GeoScience, Inc Hammond Dr., Suite 6 Schaumburg, Illinois

Subsurface Investigation Report. Proposed New 1-Story Building 6447 Grand Avenue Gurnee, Illinois

Steven Dapp, Ph.D., P.E. Steven Dapp, Ph.D., P.E. Dan Brown and Associates

See the IRC for additional information. See CPD-DS Information Bulletin 100 for Requirements for 1 & 2 Family Dwelling plan submittals.

Oweninny Wind Farm. Oweninny Environmental Impact Statement Appendix 5. Turbine Foundation Construction Method Statement

GEOTECHNICAL REPORT B-1942

ADVANCED GEOSOLUTIONS INC AGI FOUNDATION CONTRACTORS, ULC (Canada Subsidiary) The premier design-build ground improvement contractor TM

Subsurface Environmental Investigation

SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 5/8/7)

Prof. Dipl.-Ing. H. Quick Ingenieure und Geologen GmbH provides geotechnical engineering services e. g. for high-rise buildings in Germany and abroad.

aggregate piers / vscs

Ground Improvement for Mitigation of Failure Risks to Existing Embankment Dams

Geotechnical Engineering Report

Module 4:Preloading and vertical drains Lecture 10:Introduction to preloading and vertical drains. The Lecture Contains:

Nonlinear Modeling of Dynamic Soil-Structure Interaction: A Practitioner s Viewpoint

Study of Various Techniques for Improving Weak and Compressible Clay Soil under a High Earth Embankment

CHALLENGES AND SUCCESSES OF OPEN SHIELD PIPE JACKING CONSTRUCTION IN A CONGESTED NEIGHBORHOOD

Ground Improvement. Martin G. Taube, P.E., P.G. February 4, 2003

Low Maintenance Slabs Supports Are Needed for Long-Term Performance of Welded Wire Reinforcement In Slabs-On-Grade

Marina Bay Sands Hotel Arch 631 Kayla Brittany Maria Michelle

Foundation/Site Work Code Requirements

Application of Vibro Techniques for Infrastructure Projects in India

Table of Contents. July

Subsurface Investigation Report

Determination of Design Infiltration Rates for the Sizing of Infiltration based Green Infrastructure Facilities

Case study of deep excavation in existing underground structure of three-story basement and diaphragm wall

Geotechnical Engineering Report

UNDERPINNING A CRANE FOUNDATION

Geotechnical Engineering Report

November 13, IP3406. Mr. Uriah Sowell Rooney Engineering 115 Inverness Drive East, Suite 300, Englewood, CO 80112

August 15, 2006 (Revised) July 3, 2006 Project No A

Subsurface Investigations PDCA Professor s Driven Pile Institute. Loren R. Anderson Utah State University June 25, 2015

CE 6012 Ground Improvement Techniques Question Bank

EARTHQUAKE RESISTANT DESIGN OF FOUNDATIONS: DESIGN PRINCIPLES

SUBSURFACE EXPLORATION & GEOTECHNICAL ENGINEERING EVALUATION

Design of Deep Foundations for Slope Stabilization


C. Foundation stabilization for pipe and utility structures.

GROUND IMPROVEMENT USING DYNAMIC REPLACEMENT FOR NCIG CET3 COAL STOCKYARD

Preliminary Geotechnical Exploration Armstrong Tract Rivers Avenue and Hanahan Road North Charleston, South Carolina S&ME Project No.

Case study on a deep excavation in Baku: Flame Towers project earth retaining system

U.S. Army Corps of Engineers Jacksonville District Sediment Quality Control/Quality Assurance Plan For Maintenance Dredging with Beach Placement

Purpose. Utilize groundwater modeling software to forecast the pumping drawdown in a regional aquifer for public drinking water supply

HIGH BRIDGE AREA ROADWAY SLIDE, LETCHWORTH STATE PARK PORTAGEVILLE, NEW YORK

GEOTECHNICAL STUDY HIDDEN VALLEY SPORTS PARK RESTROOM FACILITY MABEL JONES DRIVE CANYON LAKE, TEXAS

City of Hughson Building Safety Division 7018 Pine Street Hughson, CA (209)

SECTION AGGREGATES

GENERAL SOILS EVALUATION REPORT. For

SECTION 1 BIO-INFILTRATION BUMP OUTS (BIBO)

The following sections provide the approved standard infiltration testing specifications.

Ground Improvement Specialists

PROJECT NO A. ISSUED: February 29, 2016

Observations and Performance of a Soil Nail Shoring Wall in Seattle Silts and Clays

Ground Improvement Techniques: Dynamic Compaction Martin Larisch & Tim Pervan

REPORT OF SUBSURFACE EXPLORATION AND GEOTECHNICAL ENGINEERING SERVICES

SOILS AND FOUNDATIONS

November 13, IP3406. Mr. Uriah Sowell Rooney Engineering 115 Inverness Drive East, Suite 300, Englewood, CO 80112

Grade separated interchange at the intersection of U.S. Hwy 17 Bypass and Farrow Parkway

geotechnical and construction materials consultants

UPDATED 04 OCT GEOTECHNICAL INVESTIGATIONS

Minimum Guidelines for the Design and Use of Underpins When Performing Foundation Stabilization and/or Supplementation UP-08

Washtenaw Community College Design & Construction Facilities Management 4800 East Huron River Drive Ann Arbor, MI

REPORT OF SUBSURFACE EXPLORATION

Geotechnical Engineering Software GEO5

BLEINC. August 17, Black & Veatch Corporation 201 Brookfield Parkway, Suite 150 Greenville, SC 29607

PVD Ground Improvement System

Red Fox Run Property Owner s Association, Inc. P.O. Box 194 Tryon, NC 28782

PD - 6 THRUST RESTRAINT DESIGN EQUATIONS AND SOIL PARAMETERS FOR DUCTILE IRON AND PVC PIPE

This report presents the findings of the subsurface exploration concerning the design of the taxiway rehabilitation. Description

Geotechnical Testing Laboratory, Inc. Engineering and Construction Materials Testing Services

Applied GeoScience, Inc Hammond Dr., Suite 6 Schaumburg, Illinois

Suitability of Different Materials for Stone Column Construction

Time-Dependent Strength Behavior of Soil-Bentonite Slurry Wall Backfill

Experiences on embankment fill in land expressway over soft ground

NOTE ON WELL SITING AT CORNER OF CASTLE VALLEY DRIVE AND SHAFER LANE FOR TOWN OF CASTLE VALLEY, GRAND COUNTY, UTAH

MEMORIAL SLOAN-KETTERING CANCER CENTER

GROUND IMPROVEMENT SITE INVESTIGATON

The Why and How of Greens Reconstruction from an Agronomy Point of View. Jon Scott, VP Agronomy

Bi-Directional Static Load Testing of Driven Piles

is a possibility of the existence of permafrost as a result

Structural Design Challenges for Plaza 66 Tower 2

Introduction to Foundations on Fill and Backfilling

Taxiway embankment over soft ground using staged construction

Reclamation of a Conventional Tailings Facility for Long Term Dry Stacking Operations in Western Australia

2. Pavement Materials: Consist of flexible or rigid pavements, typically HMA or PCC, respectively, or a composite of the two.

SOIL MECHANICS Assignment #2: Soil Classification Solution.

Transitioning from the Percolation Test to Soils Evaluation Colorado Environmental Health Association Annual Education Conference 2015

Design and development of a decline shaft through poorly consolidated Kalahari deposits at Ghaghoo Diamond Mine.

LAYING IBSTOCK CLAY PAVERS FOR PERMEABLE PAVEMENTS

GEOTEK ENGINEERING & TESTING SERVICES, INC. 909 East 50 th Street North Sioux Falls, South Dakota Phone Fax

A. Texas Department Transportation 2004 Standard Specifications for Construction of Highways, Streets and Bridges (TxDOT):

Transcription:

LACHEL FELICE & Associates Advances in Finite Element Modeling Using PLAXIS SILVER REEF HOTEL/CASINO EXPANSION

The Design/Construction Team OWNER: Silver Reef Casino; Harlan Oppenheim Architect: Morris and Brown Architects Kathy Perrino Contractor: AECON Greg Evans Stone Columns: Hayward Baker Mark Koelling, PE Geotechnical Engineer: LACHEL FELICE & Associates

Presentation Outline Existing & Proposed Site Features Geology & Other Constraints Geotechnical Parameters Preliminary Recommendations & Settlement (by others) LF&A Recommendations Geotechnical Data & Design Approach (Explorations, Tests, Settlement History) FEM (Plaxis ) Model & Geotechnical Soil Properties Wick Drains (Spacing) Final Comments

Existing and Proposed Site Features Existing Casino 48,000 sq. ft. Expansion includes: 23,360 sq. ft. of New Construction 6-Story Cast-in-Place Concrete Hotel 60,000 Gallon Water Tank Related Grading/Landscaping/Parking Additional Future Expansion Possible Complex Previous Grading and Settlement This Project

Complex Previous Grading At least three episodes of previous grading Fill Thickness varies from 0 to 10 feet No Settlement Monitoring performed following mass grading This Project Grey contour lines Phase I grading Pink Contour lines Phase II grading Orange contour lines Phase III Grading

Geology (1 of 4) Bellingham (Glaciomarine) Drift Typically consists of unsorted, unstratified silt and clay with varying amounts of sand, gravel, cobbles, and occasional boulders derived from sediment melted out of floating glacial ice that was deposited on the sea floor (WSDOT GDM). Alluvial Material from Nearby Nooksack & Lummi Rivers Very Soft Clay (CH) Overlain by 20 to 45 feet of Loose Liquefiable Sand (SP, SP-SM) Natural Ground Surface and Groundwater at Approximately Elevation 3-Feet.

Geology (2 of 4) Fill SP & SM-SM Liquefiable Sand (Improved with Stone Columns) SP & SP-SM Liquefiable Sand CL; Soft Clay CL; Very Soft to Med Stiff Clay CL; Very Soft to Med Stiff Clay CL; Med Stiff to Stiff Clay CL; Very Stiff to Hard Clay Existing Casino 60 100

Geology (3 of 4) 7 Borings 4 Cone Penetration Tests (2 after the preload) >17 Atterburg Limit / Grain Size Determinations >34 Moisture Content Evaluations 5 Consolidation Tests

Geotechnical Data Fill SP & SP-SM (Improved with Stone Columns) SP & SP-SM CL; N=3; Cc= 0.19, 0.25, 0.28, 0.32 CL; N=1; Cv=3.4*10-3 ; Cc = 0.42 CL; N=1; Cv=1.6*10-3 ; Cc = 0.46 CL; N=13; Cv=4.0*10-3 ; Cc = 0.36 CL; N>25???; problems with data reporting 5 TESTS 13 TESTS

Geotechnical Data Selection of Soil Properties for (FEM) Model 4 Compressible Soil Layers Clay Layer 2 is Typical Soil Parameter Based on Lab Tests Only Based on Verification Exercise After Preload Unit Weight (pcf) 110 114.5 116.5 E oed (lb/ft 2 ) 86607 138666 635555 K X&Y (ft/day) -- 0.005 0.005 G ref (lb/ft 2 ) 32076 32000 113333

Other Constraints Existing casino is 60 from the new hotel. Maximum Differential Settlement: Existing Casino = 2.5 ; How much is left? Cast-in-Place Hotel: 0.5 inches Existing casino must remain operational. What do we KNOW and what do we THINK? (Regarding settlement we re not sure) You want it when? IN CASINO CONSTRUCTION, TIME IS MONEY!!

Other Constraints (An Example) What do we KNOW and what do we THINK? We know settlement has occurred. We just do not know when or how much. Not Possible to verify calculated settlement due to lack of elevation readings Figure Taken From LF&A Geotechnical Report; Silver Reef

Preliminary Recommendations (by others) 18 to 24 inches of Settlement Settlement will take 20 years Use Stone Columns to Prevent Liquefaction Recommended Length (35 ) Fully Compensating Foundation Build a basement that removes an amount of soil equal to the weight of your building $$$ >1 Million Build Somewhere Else Bottom Line: The project is DEAD About 12 weeks before Construction Starts

LF&A Recommendations Support Mitigation of Liquefaction using 48 Stone Columns installed at 8 on centers; L-40 Preload Hotel Tower using equivalent Preload/Surcharge Incorporate Expansion Joints into New Construction Accelerate Consolidation Settlement Using Wick Drains-Installed at 4 feet on centers Mat (or Raft) Foundation-No basement excavation Results in savings of ~$1 Million Project is Still Alive

Geotechnical Design Approach Settlement Considerations Control Geotechnical Design Step #1: Step #2: Select worst case soil profile and analysis plane Select conservative soil properties based on available lab test results Step #3: Step #4: Step #5: Refine selected soil properties to predict previously observed settlement thereby verifying FEM Model. Compare results with tolerable settlement performance criteria. Refine as required & stop refining ASAP. Because of time constraints LF&A decided to provide broad but reasonable estimates of settlement and focused our analysis on accurately estimating differential settlement.

FEM (PLAXIS) Model Analysis Parameters Plane Strain Model Long Axis of New Structure and Existing Casino (Over-predicts settlement) Wick Drain Spacing Discussed Below Consolidation & Staged Construction Analysis Methods Installation of stone columns during Phase 1 Construction; Placement of fill during Phase 1 & time delay of 90 days; Construction of the Phase 1 Casino; Time delay of about 3 years; Installation of wick drains and installation of stone columns; Construction of a preload/surcharge; Time delay to allow for consolidation induced by preload; Removal of the preload; Construction of rigid mat foundation; Fourth time delay to allow for final consolidation settlement.

Wick Drains Not installed below stone columns Did not consider permeability of stone columns Wick Drains installed at 4-feet on centers Modeled using a spacing of 2.8 Predicted and observed rate of settlement show the difference between reality and the simplified model

Wick Drains MEBRA-DRAIN MD-7407 Wick Drains were used. The wick drain spacing is 4 feet on centers as shown: 8 4 = SQRT (4 2 *4 2 ) Drainage Distance: = 0.5 SQRT (4 2 *4 2 ) = 4 Diameter Stone Column (Hayward Baker) = Wick Drain = 2 Effective Drainage Distance

Observed & Predicted (Long Direction) Settlement 0 Total Estimated Settlement (inches) -2-4 -6-8 -10-12 -14-16 5/27/2005 Preload 90% complete on 6/7/05 Preload complete on 6/10/05 6/6/2005 6/16/2005 6/26/2005 7/6/2005 7/16/2005 7/26/2005 8/5/2005 SP#1 SP#2 SP#3 SP#4 SP#5 SP#6 SP#7 SP#8 SP#9 SP#10 REBAR#1 REBAR#2 REBAR#3 REBAR#4 REBAR#5 8/15/2005 REBAR#6 MP#1 MP#2 MIN Predicted MAX Predicted

Observed & Predicted (Long Direction) Settlement An excerpt from the LF&A Geotechnical Report

Predicted Settlement Short Direction PLAN to ADD PLAXIS PLOT IN SHORT DIRECTION THE PLAXIS WORK IS DONE JUST NEED THE PLOT FROM TIM FYI PLOT shows predicted settlement much closer to what was observed

Conclusions Project is a success. PLAXIS is a useful tool; but laboratory testing and site history are very important to developing an accurate model. Modeling the short direction of the hotel more accurately predicts observed settlement. LF&A method for modeling wick drain spacing is appropriate. Placement of settlement monitoring points sooner may have shown more settlement than currently reported.