UPGRADE OF SHAFT CONVEYOR USING HIGH SPEED TRIPPER DRIVE TECHNOLOGY (CASE STUDY MATLA COAL NO. 2 MINE, SHAFT CONVEYOR) Alan Exton

Similar documents
VERTICAL CONVEYORS FOR BULK MATERIALS - THE ECONOMIC SOLUTION K. GRABNER - BINDER+CO AG, GLEISDORF/AUSTRIA K. FRANZ - THE UNIVERSITY OF LEOBEN/AUSTRIA

Underground Conveyor Systems Product Overview

ABOUT COMMON MATERIALS:

IJSRD - International Journal for Scientific Research & Development Vol. 3, Issue 1, 2015 ISSN (online):

Minerals. WARMAN Centrifugal Slurry Pumps WBV Vertical Cantilever Slurry Sump Pump Series

Introduction to Longwall Mining and Subsidence

RESOURCE GOLD PTY. LTD.

DESIGN CONSIDERATION FOR RADIAL ADJUSTABLE BELT CONVEYOR SYSTEM

2015 UTAH ASPHALT CONFERENCE AGGREGATE PRODUCTION 101. Kilgore Companies and Kimball Equipment

Belt Conveyor Catalog

6.9 KM HORIZONTALLY CURVED TROUGHED CONVEYOR SYSTEM USING AN ELEVATED TRIANGULATED GANTRY David J. Kruse and Collen Gibbs

LONG OVERLAND CONVEYORS. W.A.C. Smith Chief Mechanical Engineer G.H. Spriggs Materials Handling Engineer Bateman Engineering (Minerals) INDEX

System-50 Material Flow

IN-PIT CRUSHING AND CONVEYING MINE PLANNING AND OPERATIONS Skillings Mining Review, June 1, 1985 by: Independent Mining Consultants, Inc.

Quality Handling Systems Pty Ltd. Sampling Solution Specialists. Sampling Systems for Bulk Materials

FUMES DESULFURIZATION HANDLING SYSTEMS COAL HANDLING SYSTEMS MECHANICAL PROCESSING OF COAL

6. METALLURGICAL PROCESSING

New Coal Handling Transfer Chute Technologies

Highwall Mining. Extend Mine-able Reserves

HORIZONTAL CONCRETE MIXING PLANTS. Horizontal Concrete Mixing Plants HN 1.5 HN 4.0 H 5 H 6

GROUP SAFETY CODE OF PRACTICE BELT CONVEYORS SAFETY

Trommel 830 INTRODUCING THE

MUCON KEK GARDNER PPS. kemutec. Specialists in Powder Processing Technology. Discharge Aids. Discharge Aids. Discharge Aids

The Sixth Edition of the CEMA Belt Book Belt Conveyors for Bulk Materials

- 2 - GUIDELINES FOR SAFE UNLOADING OF 20 LINED BOX CONTAINERS CONTENTS

Feed Handling Systems

Resource Efficient Mining Processes of Tomorrow

The entire document shall be read and understood before proceeding with a test. ISTA 3B Page 1 of 35

New mill grinds down costs and boosts efficiency at Savage River

AUMUND completes Modernisation of the Handling and Storage Systems at OAO Mordovcement

B-95S. Food Equipment Metal Separation, METAL Detection AND Material Handling

Product Directory. Material Handling Solutions.

ADVANTAGES: OVERVIEW: Sortation Solutions Section 5.1 Single Paddle Diverter (SPD)

METSO MULTI-FLO MINING SCREENS METSO MF MINING SCREENS TECHNICAL SPECIFICATION

Wear Property and Impact Test Rig Design for Comparing Wear Liners used in Transfer Chutes

Design of Belt Conveyors with Horizontal Conveyors in Special Consideration of the Belt Speed

Development Of Condition Based Maintenance For Coal Handling Plant Of Thermal Power Stations. By: Makarand M. Joshi

Conveyor belts for toughest transport demands. Conveyor Belt Group

RYSON SPIRAL CONVEYORS

Automatic Strapping. PS-Range VR-Range OR-Range Side Sealing Strapping Head Special Solutions. PS-range VR-range OR-range

Omega seals Trelleborg Ridderkerk BV

Case Study BHP Billiton Appin Drift Australia

INVENTION ON SAMPLING BY YUNEL

INSTALLATION OF A STEP-SCREEN & VORTEX GRIT REMOVAL SYSTEM AT THE GRIFFITH SEWAGE TREATMENT PLANT. Peter Shanahan. Griffith City Council

Motorized Pulleys Solve Materials Handling Problems in North America

2200 SERIES COMMON DRIVE PACKAGE Special Capabilities Specification Sheet

INVESTIGATION OF SORTING TECHNOLOGY TO REMOVE HARD PEBBLES AND RECOVER COPPER BEARING ROCKS FROM AN AUTOGENOUS MILLING CIRCUIT

How to Increase Conveyor Line Efficiencies by Removing. Change-over

We are now interested to do a project of Down Hill Conveyor System for our Indian customer : A New, 7 MTPA Iron Ore design

For Recovering Materials Ensuring Product Purity Protecting Your Equipment

Information on the proper handling and transportation of scrap

How to Select a Feeder

Horizontal and Vertical End Suction Pumps

For personal use only

h Installation Manual

RPM & RPMF Rotor Impact Mill. The Sand Maker

Incline Conveyors Modular Belts KFM-P 2040

the Mine Health and Safety Act, 1996 (Act No. 29 of 1996) and after

Improving Belt Conveyor Safety With Better Procedures and Training

AuRico Gold Provides Monthly Update on Young-Davidson Ore Processing Underway

Scraper Reclaimer Technology. Optimal solutions for Bulk Materials Handling

SPEC# PART# TEMP. THICKNESS 2-PLY 150# 1/32 X BARE BACK GRADE 2 SPEC# PART# TEMP. THICKNESS 2-PLY 150# 1/32 X 1/32 GRADE 2

BEAM & BLOCK SYSTEM. 108mm. 175mm Deep (160mm) Wide Beam. 160mm

integrated solutions in material handling

Prof. Nichols St. Nooshin Ahmadi Yasaman Bagheri Farzad Golestanirad. An Iconic Building And A Successful Stadium

Product and. &AvailabilityG. Low Relaxation (LR) Strand. Proudly Australian Made. Effective From: August 2016 Applicable For: Australia

COAL STOCKPILES IN INDIAN POWER PLANTS. H Ramakrishna TCE Consulting Engineers Limited 73/1, St Marks Road, Bangalore , Karnataka, India

WOOD SAWYER PLUS & WOOD SAWYER

Your defined goals and objectives:

DRY BULK CARGO HANDLING

Container Handling Systems Corporation

GROUND ANCHOR TENDONS IN CARBON FIBRE-REINFORCED POLYMERS

KOCH Technology, Management and a Passion for Projects. The KOCH Pipe Conveyor. KOCH Transporttechnik GmbH

CONTEC SCREW CONVEYOR

ARCOPLATE TM. The World s most Wear Resistant Fused Alloy Steel Plate YOUR GUARANTEE AGAINST WEAR HANG UP CARRY BACK

BELT CONVEYOR CONVEYING CONVEYING DRYING SEED PROCESSING ELECTRONIC SORTING STORAGE TURNKEY SERVICE

Hydro Electric Power (Hydel Power)

total quality total service Total Steel

Drawdown Hoppers Maximize Active Reclaim

Magnetic Separator. Self-Cleaning Suspended Electro Magnetic Separator. Features

COMPANY PROFILE. We are big enough to do any job and small enough to be responsive!

Managing the geotechnical aspects of longwall face recovery

Design of a Small Movable Lifting Machine Overall Structure. Yingchun Liu

Karara Iron Ore TSF design considerations for a unique large scale dry stack facility

ARCHIVE GUARDING OF BELT CONVEYORS INDUSTRIAL HEALTH SAFETY WELFARE. Published by the DEPARTMENT OF LABOUR - New Zealand

Cristal Australia Pty Ltd

Solutions for Wear Protection in Power Plants

KONE TransitMaster 120 escalators

COMMINUTION CIRCUIT OPTIMISATION

The Impact Wear Behavior of Large Rocks on Slurry Pump Materials and Equipment.

We support your performance

BEUMER MATERIALS HANDLING ECONOMICAL TRANSPORT OF BULK GOODS. Conveying technology

SECTION 14.0 CAPITAL COST ESTIMATES

HMA GROUP AUSTRALIA - NEW ZEALAND - INDONESIA - SOUTH AFRICA SINCE 1966

North America Heavyweight Conveyor Belt Catalog.

Capacity Enhancement and Energy Conservation in Cement Plant

Forged Chains This design is the exclusive property of JOHN KING CHAIN Ltd and copyright protected under the Designs and Patents Act 1988

Hydrocarbon Management PROCEDURE

EXPOMIN 2012, Santiago, Chile

From Colonia Jardín to Cuatro Vientos

Transcription:

UPGRADE OF SHAFT CONVEYOR USING HIGH SPEED TRIPPER DRIVE TECHNOLOGY (CASE STUDY MATLA COAL NO. 2 MINE, SHAFT CONVEYOR) Alan Exton INTRODUCTION The continuous requirement to upgrade existing conveyor infrastructure in order to increase production from existing operations is ongoing in mining. Mines that were designed 30 years ago had conveying capabilities to suit the current requirement plus a certain margin for expansion. Today these mines require major upgrading to meet their new conveying requirements resulting from more efficient underground production sections and the increase in the number of sections to produce more coal at a lower operational cost. Shaft conveyors are often the bottleneck in the system as sufficient time cannot be made available to upgrade and rectify previous design criteria. A further problem is that shaft space is limited prohibiting an upgrade to a wider higher capacity conveyor. There are also major restrictions on the capacities of the trestles and gantries taking the coal from the pit head to the silo or the stockpile. The cost of sinking a new shaft in an existing older mine is thus not viable unless the life of mine can be extended by a considerable period of time. This paper will identify all the problems encountered in the current design and discuss the methods and reasons employed for the new design, in order to increase the conveying capacity of the shaft from 2250 t/h to 3500 t/h, an increase of 56%, in order to meet the mine's new requirements. This upgrade took place over a period of approximately 12 months and included considerable changes to the loading of the conveyor from the underground bunker where new feeders were installed to feed material onto a variable speed sacrificial conveyor before loading the ROM coal onto the 1800kW tripper driven shaft conveyor with a conveying speed of 5.5 m/sec @ 17 degrees. In order to meet these new drastic conveyor capacity requirements, whilst using the existing infrastructure as far as tensions on the head pulley, loading of the trestles and gantries etc., tripper driven technology was the only alternative. These conveyor modifications were done using fluid couplings on a steelcord belt. BACKGROUND The, Exxaro Coal, Matla 2 Mine shaft conveyor upgrade was commissioned in order to accept an increased production capacity from 2 seam longwall and the production from the chain road development. This required a total re-think and included many modifications to the existing conveyor. These modifications to the shaft withdrawal system also included modifications to the bunker by replacing the coal feeders with higher capacity feeders that could be controlled with a VFD to allow for accurate loading of the shaft conveyor. This further necessitated the inclusion of a sacrificial conveyor in order to load the shaft conveyor accurately, whilst also accelerating the ROM coal and fitting a suitable magnet to remove any tramp iron, prior to loading the material onto the high speed shaft conveyor which was fitted with a high strength steelcord belt. Copyright is vested in IMHC 1

473 (+127) 54 (0) 419 (+127) T-Head 5 1 T2 T1 6 Silo T-Tail Take Up Load Point 3 4 2 17 54 (0) 292 (-82) 127 (-45) ORIGINAL SHAFT CONVEYOR PROFILE POINTS FOR CONSIDERATION The following points were considered, to give meaning and understanding to the issues at hand. The shaft was sunk and commissioned in the early 1980 s and was designed for a 1350 mm wide conveyor at 17 fitted with a ST1600 belt. Access for maintenance on either side of the conveyor structure was one of the major limiting factors that prohibited increasing the belt width within the shaft. A further major limitation was that the existing gantries could not accommodate a wider belt. The topography from the shaft head to the underside of the silo drops off considerably, which necessitates large gantries and high trestles. (see photographs above and below) The supporting steelwork for the drive, HT snubs, LT snubs and head pulley is huge and could not be modified to accept wider pulleys for an increased belt width. Together with the replacement or modification of the gantries and trestles, the cost 2

due to the loss of production as a result of the extended duration for the upgrade would have compromised the benefit. Figure 1: Shaft view with 1350 Structure Figure 2: Top of Silo towards 2 Mine Pithead 3

OTHER ISSUES TO BE CONSIDERED The following points needed to be considered The original induced design tensions in the gantries and the vertical loading on the trestles needed to be carefully considered. The tensions were thus re-calculated for the original 2250 t/h scenario and these tensions were adopted for the gantries and the appropriate vertical loadings were considered for the trestles. The troughing angle for the ROM structure in the shaft had to be increased from 35 to 45 and the idlers were increased from 127 mm diameter to 152 mm diameter. The transition radius in the shaft bottom area could not be changed, and thus the new conveyor needed to accommodate the vertical curve. A sacrificial conveyor utilising a lower solid woven belt class became a requirement in order to load the shaft conveyor accurately, whilst also accelerating the ROM coal to a suitable speed in order to achieve a smooth transition onto the shaft conveyor with a minimum of spillage. A suitable magnet needed to be placed at the head end of the sacrificial conveyor to remove any unwanted tramp iron prior to loading the material onto the higher speed shaft conveyor. The tensioning device for the shaft conveyor was to be at the tail end. This necessitated the sacrificial conveyor being placed above the tail area of the shaft conveyor. The feed rates of the two new bunker feeders needed to be controlled accurately in order to place the required tonnage onto the shaft belt. In order to achieve this, VFD drives were used on the feeders. The drive of the sacrificial conveyor needed to be controlled to accurately place the ROM coal at the correct position on the shaft conveyor allowing for a consistent trajectory to minimise any spillage. The sacrificial conveyor also speeded up the material so that an acceptable differential velocity could be achieved. The discharge at the head end feeding into the Silo was fitted with a spoon type deflector to discharge the coal into the centre of the Silo, such that damage is limited to the inner walls of the concrete silo. The power to accelerate and run the conveyor needed to be increased drastically to accommodate the 56% increase in capacity. From a project duration and cost point of view, the use of the existing equipment had to be maximised. 4

Capacity Calculation to ISO 5048 Original Final Input Data: UoM # 35 # 45 Sac 1 Belt Width mm 1350 1350 1800 2 Belt Speed m/sec. 3.6 5.5 3.2 3 Trough Angle Deg. 35 45 20 4 Surcharge Angle Deg. 20 20 20 5 Design Tonnage TPH 2250 3500 3500 6 Bulk Density kg/m^3 900 900 900 7 Center Idler Face Width mm 500 500 660 8 Belt Incline Deg. 17 17 0 9 Length of Conveyor m 490 460 30.5 Volumetric Capacity to ISO 5048 1 Maximum Loaded Width to ISO 5048 mm 1165 1165 1570 2 Maximum Capacity of Belt @ 100% Loading TPH 2119 3608 3199 3 Belt Percentage Loading % 106.19 97.01 109.43 4 Load Mass @ 100% Loading Tonnes 80 84 8 5 Load Mass @ Design Tonnage Tonnes 85 81 9 6 Load Mass / Linear Meter @ Design Tonnage kg 174 177 304 7 Cycle Time - (Load to Discharge) Minutes 2.3 1.4 0.2 100% Flooded Capacity - (Volumetric) 1 Flooded Load Width = Belt Width mm 1350 1350 1800 2 Maximum Capacity of Belt = Flooded TPH 2412 4034 3814 3 Belt Percentage Loading % 93.28 86.76 91.76 4 Load Mass @ Flooded Tonnage Tonnes 91 94 10 5 Load Mass @ Design Tonnage Tonnes 85 81 9 6 Load Mass / Linear Meter @ Design Tonnage kg 174 177 304 7 Cycle Time - (Load to Discharge) Minutes 2.3 1.4 0.2 RESULTS OF THE CONSIDERATIONS TO REACH THE CAPACITY COST AND SHUT DOWN DURATION REQUIREMENTS In order not to exceed the above restraints, the following design was put forward, accepted and executed. A SACRIFICIAL CONVEYOR A 1800 wide sacrificial conveyor with a VFD was installed under the two plate feeders attached to the underside of the 4 seam to 2 seam bunker. This conveyor is fitted with a tail take up trolley that is tensioned by means of two grease-jacks. The plate feeders are also VFD controlled. The belting used is solid woven Class 1000. The length of the sacrificial conveyor is 30.5 meters long and normally runs at 3.2 m/sec. A cross magnet is fitted above the stainless steel head pulley to remove unwanted tramp iron. A 5 metre impact station with skirt boards is fitted to stabilise the coal once loaded onto the shaft conveyor. 5

SACRIFICIAL CONVEYOR BUNKER T-Tail Take Up Load Point Plate Feeder Plate Feeder 30,5 Meters Speed 3.2 m/sec Width 1800 mm Capacity 3500 TPH Magnet # Conveyor Load Point Figure 3: Sacrificial Conveyor B SHAFT CONVEYOR In order not to exceed the original tensions in the gantries and minimise the increase in loadings on the trestles, the additional power required needed to be applied at a different location within the conveyor. The obvious and acceptable position was to apply the additional power by means of a tripper drive situated at the shaft head driving the carry strand of the belt. The tripper would effectively haul the coal from the feed point to the pit head reducing the tension sufficiently and the existing outbye drive would haul the coal along the gantry to the top of the Silo. The tripper drive comprised 2 off 400 kw power packs with pulleys sized to give a belt speed of 5.5 m/sec. The original head drive was driven by 4 off 250kW drives fitted with TSS fluid couplings. The pulleys which were originally sized to give a belt speed of 3.6 m/sec. were replaced with pulleys to take the belt speed up to 5.5 m/sec. A new electrical panel was supplied for 6 motors, (2 x 400 kw & 4 x 250 kw = 1800 kw), which is a PLC controlled drive panel. The starting delay times and sequence could easily be selected to offer a smooth acceptable start, all controlled through the PLC. The new belting chosen was a ST 2000 in 1350 mm belt width. With the shaft inclination being 17 and the requirement to maintain the same beltline, the transition to raise the belting leading up to the tripper pulley needed to be carefully considered. For this reason the intersection point where the belting commences the increase in angle is 100 meters from the first tripper drive pulley. The result is that the conveying angle only increases from 17 to 17,57 A new deflection chute was placed at the head pulley to redirect the coal stream vertically into the centre of the silo to accommodate the revised rather flat trajectory. The idlers and bases were replaced with 1350 wide 5 roll 152 diameter sets. The tensioning was done at the tail end by means of an existing gravity take up unit. It must be noted that the shaft conveyor is positioned under the sacrificial conveyor. Note: The use of fixed fill delay fluid couplings cannot be used on long centre distance conveyors when using belts with a low modulus of elasticity. In this case where the conveyor length is generally short, with a high lift, and using high strength high modulus belting, fluid couplings were a viable option. Fluid couplings are, in certain cases, acceptable for Mass Gravity Height conveyors when using steelcord belting. 6

473 (+127) Shaft Conveyor 473 meters Run with 127meter Lift @ 17 Inclination 141 (+41) T-Head 8 278 (+86) 54 (0) 100 Tripper T2 7 IP 6 Tripper T1 1 T2 T1 9 Silo T-Tail Take Up 3 Load Point 4 5 39 (0) 15 (0) 2 17 14m Ref. 54 (0) 292 (-82) 127 (-45) FINAL SHAFT CONVEYOR PROFILE Transition 100mtr 17 17.57 800mm Drive Pulleys 2 x 400 kw Power Packs Primary & Secondary Scrapers TRIPPER LAYOUT Figure 5: Tipper layout 7

Figure 6: Tripper view from bottom CONCLUSIONS The following points with the relative resulting conclusions were achieved after the upgrade of the Matla 2 Mine Shaft Conveyor. The capacity of the conveyor was increased by 56% from 2250 t/h to 3500 t/h with minimal structural change. The only negative result is that the vertical loading in the trestle section has increased by 15% when compared to the original design. This is mainly attributable to the increase in the belt mass as a result of using the higher class heavier belting, having an additional mass of 17 kg/linear meter. The loading at the feeders onto the 1800 belt allows for a spillage-free zone which takes the material speed up to 3.2m/sec. From here the material is loaded onto the shaft conveyor with a differential velocity of 2.3m/sec, also providing a reasonably spillage-free transfer. The conveyor has now been operational for 1 ½ years and the overall performance has been found to be satisfactory. SUMMARY Diff. % U of M Before After Value Change ROM Coal Capacity TPH 2250 3500 1,250.0 56 Belt Type Steelcord ST1800S ST2000 Belt Operational Tension Limit kn 364 405 40.5 11 Belt Induced Tension (Running) kn 314 240-74.0-24 Belt Running Factor of Safety FoS 1.16 1.69 0.5 45 Belt Speed m/sec 3.6 5.5 1.9 53 Belt Width mm 1350 1350 Power to Run Fully Loaded kw 896 1415 519.0 58 Installed Power kw 1000 1800 800.0 80 Reserve Power kw 104 385 281.0 270 Vertical Loading on Trestles kg/lin m 254 291 37.0 15 Compressive Load in Gantry Section kn 627 453-174.0-28 8

ACKNOWLEDGEMENTS Nepean Conveyors (Pty) Ltd Main Contractor Exxaro Coal, Matla Colliery Client Mr Pieter Boshoff Manager Matla Mine 2 Mr Chris Silver Operations Manager Mine 2 & 3 AUTHOR S CURRICULUM VITAE ALAN EXTON The author of this paper has been involved in the mining industry since 1969 when he commenced his training West Rand Consolidated Mines Ltd as an apprenticed Fitter & Turner. During his apprenticeship he obtained a National Technical Diploma in Mechanical Design. After 7 years employment in the mines, he joined the private sector in the Mining Division of Dowson & Dobson (Pty) Ltd. as a Design Engineer. He was involved in the design field of both coal & hard rock mining equipment for various companies until 1990. In July 1995 Nepean Conveyors (Pty) Ltd. was formed in South Africa and the author was appointed as the founding Managing Director, which position he held until 30 June 2008. Subsequently the author retired in 2008 and is currently the Managing Director of Accrete Consulting (Pty) Ltd., consulting on conveyors to the Bulk Material Handling industry. Relevant Affiliations: Director of Companies Member of the South African Institution of Mechanical Engineers. Professional Member of South African Institute of Materials Handling. Past Chairman of the Conveyor Manufacturers Association of South Africa Ltd. Director of the CMA Past Member of Beltcon 8, 9, 10, 11, 12, 13 & 14 Committees. Member of IMHC, Beltcon 15 Committee. 9