SECTION 14.0 CAPITAL COST ESTIMATES
|
|
- Virgil Walton
- 6 years ago
- Views:
Transcription
1 SECTION 14.0 CAPITAL COST ESTIMATES Capital Cost Estimates
2 CONTENTS 14.0 CAPITAL COST ESTIMATES Introduction Overall Summary Mining Capital Cost Estimate Pre-Production Mining Capital Cost Estimate Post Production Mining Capital Cost Estimate (Sustaining Capital) Processing Plant Capital Cost Estimate Introduction Summary of Processing Plant Capital Cost Estimates Basis of Estimate Exchange Rates EPCM Costs Mechanical Equipment Piping Painting and Insulation Electrical and Instrumentation Civils, Structural and Buildings Other Direct Costs General Exclusions Summary of Key Quantities Contingency MTO Allowance Design Development Estimating Contingency Processing Plant Capital Expenditure Profiles Water Management Facility Capital Cost Estimate Owners Costs Including Infrastructure Items Overall Capital Cost Expenditure Profile Rehabilitation and Closure Cost Estimates Progressive Rehabilitation Costs Closure Rehabilitation Costs Reference List Capital Cost Estimates
3 TABLES Table 14.1 Contributors to the Capex Table 14.2 Overall Capital Cost Estimate Table 14.3 Summarised Total Capitalised Pre-production Mining Costs Table 14.4 Capital Expenditure Profile Pre-production Mining Costs Table 14.5 Summarised Total Capitalised Post Production Mining Costs (Sustaining Capital) Table 14.6 Summarised Total Capital Costs Table 14.7 Process Plant Work Areas Table 14.8 Estimated EPCM Manhours Table 14.9 Basis of Other Direct Costs Table Summary of Main Quantities Table Contingency Evaluation Table Cash Expenditure Profile Process Plant Table Total Water Management Capital Costs Table Summarised Total Capitalised Pre-production Water Management Costs Table Summarised Owner s Capital Costs Table Capital Expenditure Profile Pre-production Owner s Costs Table Capital Expenditure Profile Overall Pre-production Costs Table Progressive Rehabilitation Cost Estimate Table Closure and Post Closure Rehabilitation Costs FIGURES Figure 14.1 Capital Expenditure Profile Overall Pre-production Costs Figure 14.2 Capital Expenditure Profile Overall Pre-production Costs Capital Cost Estimates
4 14.0 CAPITAL COST ESTIMATES 14.1 Introduction This section of the report describes how the Capital Cost Estimate (Capex) has been derived for the Barruecopardo Tungsten Project. The Capex has been compiled by Jacobs with information provided from various sources as highlighted as illustrated in Table Mining Process Plant Infrastructure Owners Costs Contingency Water Management Environmental and Closure Costs CSA Global Jacobs Jacobs Ormonde Mining/Saloro SLU Ormonde Mining/Saloro SLU ATC Williams IMC/ Ormonde Mining Table 14.1 Contributors to the Capex The purpose of developing the capital cost estimate for the project is fundamentally twofold: i). ii). for use by Saloro SLU in the financial model to assess the financial viability of the project. for use as a base for the initial project budget for the engineering, procurement and construction phase of the project development. The estimate has been prepared based on a typical Engineering, Procurement, Construction and Management (EPCM) contract basis with the selected EPCM contractor providing and awarding sub-contracts for and on behalf of Saloro SLU Overall Summary For the scope of the Project, as defined elsewhere in this report, the overall preoperational capital cost estimate is summarised in Table 14.2 below. Project Component Cost Estimate ( M) Owners Costs 5.2 Mining 3.9 Water Management Facilities 8.2 Process Plant 26.8 Contingency 4.4 Total Project Capital Costs (pre-operation) 48.5 Table 14.2 Overall Capital Cost Estimate Capital Cost Estimates
5 The above summarised capital costs are presented with a Base Date of Q1 2012, on an un-escalated and un-financed basis Mining Capital Cost Estimate This section of the report outlines the pre-production mining Capex estimate for the open pit mine facilities associated with the project prior to actual production mining. It is planned that the mining will be undertaken on a contract mining basis with the selected mining contractor appointed prior to mine operations commencing to enable set up and pre-stripping operations. Thus, the mining contractor s scope will be the establishment of his own offices, workshops and explosive facilities to support the mining operations Pre-Production Mining Capital Cost Estimate The pre-operational mining costs have been determined for the following two main cost components: - Pre-production Capex including the mine contractors facilities, mobilisation and establishment - Waste Rock Mining Capex to produce construction materials Thus the pre-operational costs associated with the mining contractors establishment and waste pre-stripping in the pit being developed in the project presented in this report prior to the commencement of significant ore mining from that pit has been capitalised. The estimated capitalised costs for each of the above identified cost components for the open pit mines are illustrated in Table Mine Pre-Production Set Up Mobilisation Site Preparation Site Establishment Supervision and Overheads Capex ( X10 3 ) Preproduction Sub-Total Set Up 1,588 Pre-Production pre-stripping of Waste Rock 2,306 Total Mining Pre-production 3,894 Table 14.3 Summarised Total Capitalised Pre-production Mining Costs A capital expenditure profile for the pre-production capitalised mining costs during the 19 month Project Implementation Period (Section ) is presented in Table Capital Cost Estimates
6 Project Month Forecast Expenditure Capex Forecast Expenditure as % of Total , , , , , , ,026, , , TOTAL 3,893, % Table 14.4 Capital Expenditure Profile Pre-production Mining Costs Post Production Mining Capital Cost Estimate (Sustaining Capital) After the mine begins operations there will be a number of ongoing mining activities to sustain the operation and these are capitalised to sustain the mining operation. The activities and estimated costs are presented in Table 14.5 and included in the financial model Capital Cost Estimates
7 Mine Demobilisation Site Clean Up Maintenance Total Mining Post Production (Sustaining Capital) Capex ( M) post production Table 14.5 Summarised Total Capitalised Post Production Mining Costs (Sustaining Capital) 14.4 Processing Plant Capital Cost Estimate Introduction This section presents the capital cost estimate that has been developed during this Feasibility Study for the Barruecopardo Tungsten Processing Plant and Supporting Infrastructure. Based upon the level of engineering, costing and planning undertaken during the course of the study the level of accuracy of this estimate is of the order of +15%/-15% which is in line with international standards for a project at the stage of development. The capital costs are presented in this section of the report while the supporting documentation is presented in Appendix 3 of the Cost and Definition study report, Feb prepared by Jacobs E&C Ltd. The capital cost estimate has been prepared for the Barruecopardo Tungsten Process Plant and Infrastructure based on the currently developed scope of the project and implementation of the project on an EPCM contract basis with the contractor providing and awarding purchase orders and sub-contracts on and behalf of Saloro. For all of the elements of the capital cost estimates, Jacobs have utilised standard estimating practise. Costs are based on vendor quotes obtained for some mechanical items of equipment and data available from the Jacobs estimating data bank for metallurgical processing facilities. The total installed constructed capital cost estimated excluding contingency for the Process Plant and Supporting Infrastructure is: Euros 26,815,581 Due to the stage of development of the project, Jacobs have recommended a contingency allowance is considered. The allowance has been developed utilising a Jacobs in-house statistical analysis tool and bench marked against other metallurgical projects and has been evaluated at Euros 2,786,139 for the process plant. Excluded from this contingency allowance recommendation is any project risk associated with escalation, exchange rates, country etc., which is normal practice for the Owner to assess and include in the financial evaluation of the project Capital Cost Estimates
8 For the purposes of economic analysis of the Project (Section 16) Saloro have utilised a contingency of 10% on all project investment capital components. The capital costs are presented in Euros on an un-financed, un-escalated basis with a base date of the 1 st Quarter Summary of Processing Plant Capital Cost Estimates The summarised capital costs excluding contingency for the process plant and supporting infrastructure are presented in Table Item Capex Capex Processing Plant 13,976,987 Supporting Infrastructure (General, Utilities, Infrastructure) 8,872,853 Water Treatment 835,885 EPCM 3,129,856 TOTAL 26,815,581 Table 14.6 Summarised Total Capital Costs Basis of Estimate The capital cost estimate is based on the scope of work developed for the Barruecopardo Tungsten Process Plant and Infrastructure presented in this report. The engineering design and scope of works has been developed based on test work provided by Saloro as reported in Section 6 of this report. The processing plant areas and supporting infrastructure, as illustrated in Table 14.7, are self descriptive and are inclusive of all costs by discipline and associated support and enabling cost elements Capital Cost Estimates
9 Processing Plant Area Number Description 00 General 20 Crushing 21 Pre-Concentration 22 Upgrading 23 Reagents 25 Water Treatment Plant 40 Utilities 50 Infrastructure Table 14.7 Process Plant Work Areas Wherever possible, equipment identification numbers are allocated to all items included in the capital cost estimate. The equipment numbering system used is based on an alpha-numeric arrangement; the alpha designator describes the plant item and a sequential number provides a unique identifier. The estimate has been generated using established methods. Detailed material take-offs have been prepared for all engineering disciplines upon which the estimating group have applied equipment / material prices, construction norms and local rates as obtained from Spain Exchange Rates The exchange rates utilised within the estimate are: 1.00 GBP : Euro 1.00 USD : Euro 1.00 RAND : Euro EPCM Costs EPCM costs have been developed based on the implementation strategy and programme outlined in Section 5. An engineering, procurement, construction management and commissioning resource schedule has been produced which has been costed and included in the capital cost estimate. An allowance for expenses associated with the EPCM services has also been assessed and included in the estimated costs. The estimated manhours for the EPCM services are outlined in Table 14.8 below with the costs assessed at Euros 3,129, Capital Cost Estimates
10 Cost breakdown of the above is as follows: EPCM manhour costs Euros 2,757,538 Expenses costs Euros 372,318 Services Manhours Management 6,042 Engineering 11,875 Procurement 2,023 Construction Management (including local hire) 13,923 Commissioning 1,560 TOTAL 35,423 Table 14.8 Estimated EPCM Manhours EPCM costs are thus 11.7% of the Process Plant Total Installed Costs. These have been satisfactorily benchmarked against other minerals and metals projects. To establish the resource loading it has been assumed that the selected and appointed EPCM contractor will have a proven track record in the design of process plants and have a direct knowledge of the Barruecopardo Tungsten Project. In order to maximise construction management efficiency it is assumed a number of site based personnel will be local hire Mechanical Equipment A detailed equipment list has been compiled by Jacobs for all the defined work areas of the plant. Equipment quotations have been sourced for all major and specialist items of equipment using and fax enquiries. The balance of the equipment, being minor in nature, has been priced using either inhouse data or from similar projects. The detailed equipment list presented in Appendix 2 of the Cost and Definition study report Feb is the driver for the equipment section of the cost estimate which directly follows its content. Quoted costs amounted to Euros 6,595,332 and represents approximately 74% of the overall equipment costs by value. The balance of the equipment costs has been estimated in-house and primarily centres on miscellaneous fabrications where weights have been developed and an appropriate rate for supply and manufacture applied. These shop fabrication items including small storage tanks, chutes, hoppers, pump boxes etc have been priced using a rate of Euros 2,850 tonne; this rate has been obtained from Spanish Contractors Capital Cost Estimates
11 For site built tanks these have been priced using a rate of Euros 4,230 per tonne; this rate has also been obtained from Spanish Contractors. While attempts have been made to secure quotations from three suppliers the response from the market has been poor in many instances and limited responses received for several items. The quotations that have been received have been technically and commercially appraised prior to inclusion within the estimate. In all instances the most competitive quote has been used provided the quotation compliances with the stated requirements. The installation costs for items of equipment has been assessed individually, using construction manhour norms and then applying a local all in rate to the manhours. This rate has been built up using cost data received from Spain. Costs attributable for laboratory equipment and workshops have been estimated and are clearly identifiable in the estimate Piping A line list and material take-off has been developed by the Jacobs Engineering Department for the pipework. The material take-off details pipework by specification and nominal bore. A valve schedule has also prepared detailing valves by type, nominal size and material. Materials have been priced by applying the appropriate material unit rates to the developed material take-off. Spanish rates have been used where available and in particular for all HDPE Pipework. The rates have been benchmarked and this has indicated that HDPE Pipework is considerably cheaper in Spain than the UK. Carbon Steel Pipework is of a comparable price between Spain and the UK. A Pipework Fabrication & Installation estimate has been carried out using Spanish Fabrication and Installation rates for HDPE Pipework and manhour norms then applying a local all in rate to the manhours for Carbon Steel Pipework. This rate has been built up using cost data received from Spain. An allowance for Pipe Supports has been included within the estimate. A cost has been allowed for non-destructive testing of pipework. A fully detailed piping breakdown is included within the body of the cost estimate and presented in Appendix 3 of the Cost and Definition study report Feb Painting and Insulation Painting and Insulation has been priced by applying the appropriate unit rates to the developed material take off; UK rates have been used. A fully detailed Painting and Insulation breakdown is included within the body of the cost estimate and presented in Appendix 3 of the Cost and Definition study report Feb Capital Cost Estimates
12 Electrical and Instrumentation Detailed material take-offs have been developed by the Jacobs Engineering Department detailing all major equipment and bulk quantities. Quotations have been sourced and utilised for the provision of all major electrical equipment. These quotations have been technically appraised and a recommendation put forward to estimating prior to input into the estimate. Costs for tagged instruments including control valves are based on recently obtained quotations for similar items. All other costs for bulk materials are based upon vendor provided price lists and inhouse data. An Electrical & Instrumentation Installation estimate has been assessed using ` construction manhour norms then applying a local all in rate to the manhours and this rate has been built up using cost data received from Spain. A fully detailed Electrical and Instrumentation breakdown is included within the body of the cost estimate and presented in Appendix 3 of the Cost and Definition study report Feb Civils, Structural and Buildings A detailed bill of quantities has been generated by the Jacobs Engineering Department. A fully detailed priced Civils, Structural and Buildings breakdown is included within the body of the cost estimate and presented in Appendix 3 of the Cost and Definition study report Feb Spanish subcontractor rates have been obtained and applied to the detailed quantities in order to ascertain an overall cost. Various rate comparisons have been carried out to ensure that the most appropriate rates have been used in the estimate build up Capital Cost Estimates
13 Other Direct Costs Allowances have been made within the cost estimate for other costs and the basis of these is presented in Table An allowance from 24 months operating spares included. Operating Spares This is based on 2.0% of the mechanical equipment supply cost. An allowance for commissioning spares has been included. Commissioning Spares This is based on 0.5% of the mechanical equipment supply cost. First Fill Consumables Transport / Shipping Escalation Establishment for EPCM Services Only An allowance of 10,000 has been included. An allowance of 2.5% of the material supply cost has been included. Excluded Determined from the construction programme and includes for site cabins, IT link, toilet facilities etc. Scaffolding has been determined by utilising a historic factor of 10% of the Mechanical Equipment Installation, Scaffold and Heavy Lift Pipework Installation and Electrical Installation costs. Main craneage has been determined by utilising a historic factor of 3% of the Mechanical Equipment Installation, Pipework Installation and Electrical Installation costs. Vendor Representatives Consultants Translation of Maintenance and Operating Manuals An allowance has been made within the estimate for all supervision during both construction and commissioning. No allowance has been made for any Consultancy costs No allowance has been made for any Translation costs. An allowance has been made for Expenses associated with Expenses the EPCM element of the estimate, this allowance has been factored at 10% of the EPCM costs. Table 14.9 Basis of Other Direct Costs General Exclusions No allowances have been included within the estimate for the following items: Sunk Costs Test Work Planning Permission Capital Cost Estimates
14 Land Purchase Way-leave costs Spanish Government Costs All Taxes and Duties Financial charges of any description Bonds, Guarantees etc Insurances Mobile Equipment costs Summary of Key Quantities Table below listed the main quantities generated and priced for inclusion in the capital cost estimate. Item Description No. of items of mechanical equipment Piping metres Quantities 305 No. 5,482 m Earthworks cubic metres 12,065 m 3 Concrete cubic metres 5,597 m 3 Electrical cabling metres Building structural steelwork tonnes 105,485 m 284 Te Table Summary of Main Quantities Contingency Allowances for growth in the material take offs and design and development have been included in the base estimate and are excluded in the contingency assessment MTO Allowance A quantitative adjustment to the engineering disciplines take-off to allow for the final installed bulk quantities is included in the estimate (0% of the Mechanical Equipment costs, 5% of the Civils & Structural costs and 2.5% of the balance of the discipline estimates costs) Design Development An allowance to include for anticipated design changes, likely to increase the final value of procured items as compared to quotations obtained at the bid stage, is included in the estimate (0% of the Mechanical Equipment costs, 5% of the balance of the discipline estimates costs). In quantified terms the growth allowance in the base total installed constructed cost estimate is Euros 344, Capital Cost Estimates
15 In addition to the estimated costs for direct and indirect costs for the project, a contingency allowance has been assessed for risk based on an assessment of the present degree of definition for each of the principal cost categories Estimating Contingency A sum to allow for inadequacies and or inaccuracy of cost and quantitative information used in the estimate preparation such as: Price Sources for the supply of materials Accuracy of Engineering Construction Data and impact on sub-contracts Contingency is intended to cover items of work which may have to be performed or elements of cost which may be incurred and which, although considered to be within the scope of the project, are not specifically defined or foreseen at the present time. Contingency is not intended as a replacement for risk and should be considered as an integral part of the capital cost estimate. The applied and quantified evaluation is presented in Table Item Estimated Cost Capex % Supply of Materials 1,442, % Construction Sub-Contracts 918, % Other Direct Costs 98, % EPCM Costs 325, % Miscellaneous Costs (First Fill of Media) 1, % Total 2,786, % Table Contingency Evaluation The contingency allowance detailed above has not been included in the presented capital cost estimate at the request of Saloro as they wished to apply a single contingency factor to apply to the total project capex for all activities. The above table has been prepared from information contained within the detailed contingency calculation sheet. Note the above figures are indicative only and have been presented for guidance only. The assessed contingency is not included in the project total installed cost estimate. For the purposes of economic analysis of the Project (Section 16) Saloro have utilized a contingency of 10% applied to all project investment capital components Capital Cost Estimates
16 Processing Plant Capital Expenditure Profiles A capital expenditure profile for the pre-production capitalised processing plant costs during the 19 month Project Implementation Period (Section ) is presented in Table Project Month Forecast Expenditure Capex Forecast Expenditure as % of Total 1 62, % 2 125, % 3 188, % 4 188, % 5 847, % 6 1,102, % 7 1,370, % 8 1,497, % 9 1,647, % 10 2,352, % 11 2,770, % 12 3,009, % 13 2,572, % 14 2,572, % 15 2,229, % 16 1,442, % 17 1,143, % , % , % TOTAL 26,815, % Table Cash Expenditure Profile Process Plant 14.5 Water Management Facility Capital Cost Estimate This section presents the capital cost estimate for the Water Management Facilities that has been developed for the building of environmentally sound water management facilities at the plant site and to the dewatering of the open pit as per the design and construction method described in Section Capital Cost Estimates
17 The facilities include the following: Water Dams (A to C) Dam Linings Pumps and Distribution Piping Diversion Channels, Spillway, Drains and Sumps Sulphide Lagoons The pre-production and ongoing sustaining capital costs estimated were established to reflect the staged construction of the dams, the dewatering of the pit and the associated water recovery pumping and distributions systems. The capital costs allocated to the initial build are classified as pre-production investment costs and the subsequent development of the facilities classified as sustaining capital with these costs being summarised in Table Water Management Facilities Capex ( M) Pre-Production Stage Earthworks 3.6 Lining 1.1 Equipment and Piping 3.5 Total Pre-Production Costs 8.2 Production Stage (Sustaining Capital) Earthworks 0.5 Lining 0.3 Equipment and Piping 1.6 Total Sustaining Capital Costs 2.4 Total Water Management Facility Costs 10.6 Table Total Water Management Capital Costs Capital Cost Estimates
18 A capital expenditure profile for the pre-production capitalised water management costs during the 19 month Project Implementation Period (Section ) is presented in Table Project Month Forecast Expenditure Capex Forecast Expenditure as % of Total ,022, ,022, ,022, ,022, ,022, ,022, ,022, , , , , TOTAL 8,200, % Table Summarised Total Capitalised Pre-production Water Management Costs 14.6 Owners Costs Including Infrastructure Items The Owner s Costs as estimated by Ormonde/Saloro as capitalized items during the preproduction stage have been estimated with the itemized costs summarised in Table For further details on the items included in the estimated costs refer to Section (Miscellaneous Pre-Production Costs) Capital Cost Estimates
19 Item 2011 Capex ( M) Land Related Costs 2.6 G & A Costs 0.7 Environmental Support Costs 0.4 Power Line Costs 0.8 Administration and Project Team Costs 0.7 Total Owner s Costs 5.2 Table Summarised Owner s Capital Costs The pre-production owners cost estimate includes all costs associated with preproduction environmental activities including Facilities for collection, segregation and temporary storage of general (non mining, non process waste including signs and labelling; Equipment for the continuous or semi continuous monitoring of weather and ambient levels of total particulate matter and PM 10 in air. These may be specific requirements of the environmental permits; A hand held portable noise meter for periodic measurements at the perimeter of the mining area. Compensatory measures including the creation of wetlands, habitats for rabbits and bats and equipment for surveillance of Perdicera Eagle nest sites. A capital expenditure profile for the Owner s pre-production costs during the 19 month Project Implementation Period (Section ) is presented in Table Capital Cost Estimates
20 Project Month Forecast Expenditure Capex Forecast Expenditure as % of Total , , , , , , , , , , , , TOTAL 5,199, % Table Capital Expenditure Profile Pre-production Owner s Costs 14.7 Overall Capital Cost Expenditure Profile An overall capital expenditure profile for the pre-production capital costs during the 19 month Project Implementation Period (Section ) is presented in Table and Figure 14.1 and Figure The profile excludes post production environmental, rehabilitation, closure costs and contingency Capital Cost Estimates
21 Project Month Forecast Expenditure Capex Forecast Expenditure as % of Total TOTAL 62, , , , , ,102, ,370, ,524, ,184, ,889, ,308, ,337, ,901, ,984, ,433, ,365, ,884, ,770, ,641, ,109, % Table Capital Expenditure Profile Overall Pre-production Costs Capital Cost Estimates
22 Barruecopardo Expenditure Profile 50,000,000 Cumulative Expenditure (EUR) 45,000,000 40,000,000 35,000,000 30,000,000 25,000,000 20,000,000 15,000,000 10,000,000 5,000, Project Month Figure 14.1 Capital Expenditure Profile Overall Pre-production Costs Barruecopardo Expenditure Profile 50,000,000 Cumulative Expenditure (EUR) 45,000,000 40,000,000 35,000,000 30,000,000 25,000,000 20,000,000 15,000,000 10,000,000 5,000, Project Month Figure 14.2 Capital Expenditure Profile Overall Pre-production Costs 14.8 Rehabilitation and Closure Cost Estimates Progressive Rehabilitation Costs The total areas affected by the project and requiring rehabilitation have been estimated, and based on the rehabilitation philosophy outlined in Section 12 of this report the rehabilitation costs for the project have been estimated Capital Cost Estimates
23 The site will be progressively rehabilitated during the life of the mining operation with the estimated rehabilitation costs incurred during the life of the project being presented in Table Capex Production Year 1 487,110 Year 2 476,650 Year 3 309,934 Year 4 565,796 Year 5 523,501 Year 6 463,180 Year 7 472,151 Year 8 631,797 Year 9 86,346 TOTAL 4,016,468 Table Progressive Rehabilitation Cost Estimate Closure Rehabilitation Costs The estimated costs of rehabilitation measures during the closure and post closure phases are summarised in Table The costs involved in the removal of equipment and the demolition and clearance of structures are expected to be covered by the residual sale value of some major equipment items and the scrap value of construction materials Capital Cost Estimates
24 Stage Area Capex Closure Final dump 511,324 North dams 802,052 Plant area 627,710 Sulphide deposit 211,510 Main track 201,935 Inner tip 191,511 General 126,735 Total Closure Capex 2,672,780 Post Closure 234,626 Table Closure and Post Closure Rehabilitation Costs Capital Cost Estimates
25 14.9 Reference List 1. Barruecopardo Feasibility Study: Water Management System ATC Williams, February Barruecopardo Cost & Definition Study Jacobs E&C Ltd Feb Capital Cost Estimates
For personal use only
BALAMA PROJECT UPDATE AS AT MID MARCH 2017 BALAMA GRAPHITE PROJECT (100%) OPERATIONS UPDATE Commissioning remains on schedule for Q2 2017 Capital budget remains unchanged at US$193 million (plus US$7 million
More informationCAPITAL COST ESTIMATE
CAPITAL COST ESTIMATE p76-p85 Photo courtesy of GRES 76 Our mission is to become a reliable and respected uranium producer. Highlights Total capital cost is A$493M inclusive of growth allowance and contingency
More informationOWN The Owner s Estimate Requirements Document
OWN.1393 The Owner s Estimate Requirements Document Larry R. Dysert, CCC CEP Abstract The Estimate Requirements Document is a planning document that should be used by owner companies to clarify goals,
More informationRENISON TAILINGS RETREATMENT PROJECT ( RENTAILS ) UPDATED DFS CONFIRMS HIGH MARGIN PROJECT
4 JULY 2017 RENISON TAILINGS RETREATMENT PROJECT ( RENTAILS ) UPDATED DFS CONFIRMS HIGH MARGIN PROJECT HIGHLIGHTS Robust economics: NPV 8% of A$260M (pre-tax) and IRR of 37% 1 ; Cash operating cost of
More informationFeasibility studies Ulaanbaatar August 2016
Feasibility studies Uranium exploration, development and eventual production, form a series of progressive and logical steps. Each step is part of a progression of activities with the objective of obtaining
More informationMozambique Real Opportunity. Benchmark World Tour Sydney 21 st September
Mozambique Real Opportunity Benchmark World Tour Sydney 21 st September 1 Project 1 Montepuez Montepuez Graphite Project 2 Annual graphite production Capex (pre-production) Opex (concentrate/t) 7 Grade
More informationFive Global Pty Ltd ABN (0) (0)
Five Global Pty Ltd ABN 78 158 704 226 +61 (0) 468 999 561 +61 (0) 427 119 234 Introduction What is the optimum project management model that an Owner should employ to deliver a successful project? It
More informationCAPABILITY STATEMENT PRIZM Engineering Pty Ltd ABN
CAPABILITY STATEMENT PRIZM Engineering Pty Ltd ABN 481 6646 0662 PRIZM Engineering is a full service (Civil, Structural, Mechanical & Electrical) consulting engineering firm with offices in Gladstone and
More informationNORTH RIVER NAMIB LEAD / ZINC PROJECT FEASIBILITY STUDY. Volume 1
NORTH RIVER NAMIB LEAD / ZINC PROJECT Volume 1 Proprietary Information This document has been prepared by and remains the sole property of. It is submitted solely for use in conjunction with the submission
More informationGarden Well Gold Deposit. Reserve Increases to 1.66 Million Ounces
ABN 28 009 174 761 31 March 2011 Manager Announcements Company Announcements Office Australian Securities Exchange Limited Level 4, 20 Bridge Street Sydney NSW 2000 www.regisresources.com Level 1 1 Alvan
More informationFor personal use only
ASX Announcement 19 December 2014 BOARD OF DIRECTORS Paul Murphy (Non-Executive Chairman) Bryan Dixon (Managing Director) Alan Thom (Executive Director) Greg Miles (Non-Executive Director) ASX CODE BLK
More informationDALGARANGA GOLD PROJECT - CONSTRUCTION UPDATE 8 MONTHS TO FIRST GOLD
November 3 rd 2017 Australian Securities Exchange Limited Via Electronic Lodgement 57 139 522 900 DALGARANGA GOLD PROJECT - CONSTRUCTION UPDATE 8 MONTHS TO FIRST GOLD Construction work at Gascoyne s 100%
More informationBALLYMUN REGENERATION LTD. INSTRUCTIONS TO TENDER FRAMEWORK AGREEMENT FOR PSDP CONSULTANT SERVICE
BALLYMUN REGENERATION LTD. INSTRUCTIONS TO TENDER FRAMEWORK AGREEMENT FOR PSDP CONSULTANT SERVICE Issue Date: 12-08-07 Instructions to Tenderers Page 1 of 9 1. INTRODUCTION 1.1 Overview of BRL Ballymun
More informationFEASIBILITY STUDY COMPLETED CONFIRMING ROBUST CASH MARGINS FOR JOGJAKARTA IRON PROJECT
ANNOUNCEMENT TO THE AUSTRALIAN SECURITIES EXCHANGE: 29 AUGUST 2011 FEASIBILITY STUDY COMPLETED CONFIRMING ROBUST CASH MARGINS FOR JOGJAKARTA IRON PROJECT Highlights: Feasibility Study completed on a 2
More informationDrilling, metallurgical test work and a new resource model add 21% to oxide gold reserves
LA ARENA GOLD OXIDE RESERVES INCREASED TO 1.28MM OZ AT AU PRICE OF $1,200 COMPLETION OF THE PRE-FEASIBILITY STUDY FOR THE PHASE II SULPHIDE Cu-Au PROJECT Drilling, metallurgical test work and a new resource
More informationMarket Update Southdown Magnetite Project
MEDIA RELEASE 23 February 2018 Market Update Southdown Magnetite Project Grange Resources Limited (ASX:GRR) (Grange) is pleased to announce that, in conjunction with its joint venture participant, SRT
More informationFor personal use only
ACN 097 088 689 01 DEFINITIVE FEASIBILITY STUDY SUPPORTS A MAJOR EXPANSION OF THE SYAMA GOLD MINE Definitive Feasibility Study completed for multifaceted expansion of Syama operation confirms its technical
More informationSouthern Cross Goldfields Ltd
Southern Cross Goldfields Ltd ASX Announcement - 20 December 2013 Marda Gold Project: Feasibility Study Review Additional Information On 10 December 2013, Southern Cross Goldfields (ASX: SXG SXG or the
More informationWetar Expansion Update September 2015
For ASX Market Release: 15 September 2015 Wetar Expansion Update September 2015 HIGHLIGHTS Mining and earthworks associated with the 25,000 tonne per annum copper cathode expansion project are well advanced
More informationCHAPTER 1 INTRODUCTION
CHAPTER 1 INTRODUCTION Cost is a major factor in most decisions regarding construction, and cost estimates are prepared throughout the planning, design, and construction phases of a construction project,
More informationNorthern Vertex Provides Construction Update on Pilot Plant Phase I
July 4, 2013 Northern Vertex Provides Construction Update on Pilot Plant Phase I Construction of Pilot Plant - Phase I Underway Leach Pad Construction Complete Initial Loading of Agglomerated Mineralized
More informationDALGARANGA GOLD PROJECT CONSTRUCTION UPDATE LESS THAN 5 MONTHS TO FIRST GOLD
December 8 th 2017 Australian Securities Exchange Limited Via Electronic Lodgement 57 139 522 900 DALGARANGA GOLD PROJECT CONSTRUCTION UPDATE LESS THAN 5 MONTHS TO FIRST GOLD Construction at Gascoyne s
More informationSabina Gold & Silver Provides Project Development Update on Back River Gold Project Significant de-risking activities completed in 2018
Suite 1800 Two Bentall Centre 555 Burrard Street Vancouver, BC V7X 1M9 Tel: (604) 998-4175 Tel: (888) 648-4218 www.sabinagoldsilver.com December 4, 2018 SBB NR 18-27 SBB TSX Sabina Gold & Silver Provides
More informationJob Costing (JC) General Features: Interface with other Systems: System Setup and Maintenance:
Job Costing (JC) The system serve in setting up and monitoring the progress of projects and individual work orders. The system is based on a work breakdown structure providing the facility to control costs
More information1. FROM (Bidder): (Name)
Tender No. [ ] Tender Forms Page 1 1. FROM (Bidder): (Name) (Address) TO: Alberta Transportation, Strategic Procurement Branch Main Floor, Twin Atria Building 4999 Avenue 5000 Edmonton, Alberta, T6B 2X3
More informationTRANS-SIBERIAN GOLD PLC
PLC June 2011 Asacha Gold Project ASACHA Project Status Construction Mine development proceeds steadily and stoping started in June 2011 Plant building construction is complete, plant equipment is installed
More informationAppendix K. Clean Water Nashville Overflow Abatement Program GUIDANCE FOR DESIGN ESTIMATING. Version 2.0
Appendix K Clean Water Nashville Overflow Abatement Program GUIDANCE FOR DESIGN ESTIMATING Version 2.0 April 2014 Table of Contents Section 1 Estimating Introduction... 1 1.1 Exception to Designer OPCCs...
More informationJ&P OMAN COMPANY ORGANISATION P.110 PROCEDURE. Page: 1 of 16. Document Title: Issue Date: 13/04/2014. Revision Date: 06/06/2016 Revision No.
OMAN PROCEDURE Page: 1 of 16 Title: Issue Date: 13/04/2014 Revision Date: 06/06/2016 Revision No.: 2 Issued By: QESH Controller Approved By: QESH Management Representative Approved By: Company QESH Management
More informationNullagine Gold Project
Nullagine Gold Project ABN 85 003 257 556 Construction Update June 2012 Construction of the gold process plant and associated infrastructure remains on schedule and within the capital cost estimate of
More informationCONTRACT NO. : MTK11/2017 REHABILITATION OF MSAULI ASBESTOS MINE SCHEDULE OF QUANTITIES SECTION 1: PRELIMINARY AND GENERAL
SECTION 1: PRELIMINARY AND GENERAL SECTION 1: PRELIMINARY & GENERAL 1.1 1200A FIXED CHARGE AND VALUE RELATED ITEMS 8.3.1 CONTRACTUAL REQUIREMENTS 1.1.1 Surety or bank guarantee Sum 1 1.1.2 Common Law Liability
More informationProcurement Options for NZ Construction Contracts
1 P a g e Tool Box Resource Procurement Options for NZ Construction Contracts A wide variety of contract arrangements have evolved in NZ for use on construction contracts. The following describes the most
More informationCharging Arrangements for New Connection Services
Charging Arrangements for New Connection Services 2018-2019 About South East Water Developer Services Developer Services Department For any new connections requests or issues please contact our Developer
More informationGUIDANCE NOTES - CONSTRUCTION DESIGN AND MANAGEMENT (CDM) 3
GUIDANCE NOTES - CONSTRUCTION DESIGN AND MANAGEMENT (CDM) 3 Page 1 Page 2 GUIDANCE NOTES - CONSTRUCTION DESIGN AND MANAGEMENT (CDM) ROLES AND RESPONSIBILITIES The CLIENT must: 1. Be satisfied that all
More informationRe : Completion of the Barnes Hill drill-out
30 March 2010 The Manager Company Announcements Office Australian Securities Exchange By e-lodgement (ASX code: MFC) Dear Sir/Madam Re : Completion of the Barnes Hill drill-out The following comprises
More informationCONTRACT NO. : MTK 11/2018 REHABILITATION OF UITKYK ASBESTOS MINE SCHEDULE OF QUANTITIES SECTION 1: PRELIMINARY AND GENERAL
SECTION 1: PRELIMINARY AND GENERAL SECTION 1: PRELIMINARY & GENERAL SANS 1.1 1200A FIXED CHARGE AND VALUE RELATED ITEMS 8.3.1 CONTRACTUAL REQUIREMENTS 1.1.1 Surety or bank guarantee 1.1.2 Common Law Liability
More informationFORM OF TENDER RITHET RESERVOIR DRAIN PROJECT ( TITLE OF CONTRACT ) T 34/16 ( OWNER S CONTRACT REFERENCE NO. )
PAGE 1 OF 6 FOR USE WHEN UNIT S FORM THE BASIS OF PAYMENT - TO BE USED ONLY WITH THE GENERAL CONDITIONS AND OTHER STANDARD DOCUMENTS OF THE UNIT MASTER MUNICIPAL CONSTRUCTION DOCUMENTS. Owner: Contract:
More informationNOLANS REVIEW COMPLETED DELIVERING SIGNIFICANT COST AND OPERATIONAL BENEFITS
ASX RELEASE 28 June 2016 ASX: ARU NOLANS REVIEW COMPLETED DELIVERING SIGNIFICANT COST AND OPERATIONAL BENEFITS Extensive work programs identify substantial operational and cost efficiencies at Nolans Rare
More informationCost Engineering and Scope of Work
Cost Engineering and Scope of Work Kul B. Uppal, PE Online Constructor, Inc. Tel. 281-218-9101 Email: kbuppal@onlineconstructor.com Project Scope of Work and Management s Perspective Management has preconceived
More informationOMITIOMIRE OXIDE COPPER FEASIBILITY STUDY
INTERNATIONAL BASE METALS LIMITED OMITIOMIRE OXIDE COPPER FEASIBILITY STUDY 21 NOVEMBER 2013 Frank Bethune Ken Maiden Andre Genis Karl Hartmann PRESENTED BY FRANK BETHUNE AND KEN MAIDEN Disclaimer 2 This
More informationANNEX 3 DETAILED PRICE SCHEDULE RELATED TO THE BILL OF QUANTITIES 1. GENERAL DESCRIPTION OF ITEMS PRICES TO BE FULLY INCLUSIVE...
ANNEX 3 DETAILED PRICE SCHEDULE RELATED TO THE BILL OF QUANTITIES 1. GENERAL... 3 2. DESCRIPTION OF ITEMS... 5 3. PRICES TO BE FULLY INCLUSIVE... 5 4. COVERAGE... 6 5. BIDDER TO PRICE EACH ITEM... 6 6.
More informationTEMBANG PRE-FEASIBILITY STUDY DELIVERS POSITIVE OUTCOME
ASX ANNOUNCEMENT 23 February 2012 (8 pages by email) TEMBANG PRE-FEASIBILITY STUDY DELIVERS POSITIVE OUTCOME Sumatra Copper & Gold plc ( Sumatra or the Company ) is pleased to announce that the Prefeasibility
More informationCONTRACT NO. : MTK 5/2018 REHABILITATION OF STEELPOORT ASBESTOS MINE SCHEDULE OF QUANTITIES SECTION 1: PRELIMINARY AND GENERAL
SECTION 1: PRELIMINARY AND GENERAL SECTION 1: PRELIMINARY & GENERAL SANS 1.1 1200A FIXED CHARGE AND VALUE RELATED ITEMS 8.3.1 CONTRACTUAL REQUIREMENTS 1.1.1 Surety or bank guarantee 1.1.2 Common Law Liability
More informationVALUE THROUGH GOLD BRUCEJACK PROJECT PREMIER S NATURAL RESOURCE CONFERENCE
VALUE THROUGH GOLD BRUCEJACK PROJECT PREMIER S NATURAL RESOURCE CONFERENCE January 2016 CAUTIONARY STATEMENT Forward Looking Information This Presentation contains forward-looking information and forward
More informationNorthern Iron. Investor Update March 2010
Northern Iron Investor Update March 2010 Disclaimer Forward-looking statements This presentation may include forward-looking statements. Forward-looking statements are only predictions and are subject
More informationWhite Dam Gold Project Dump Leach
ALTA 2015 White Dam Gold Project Dump Leach A division of Midas Engineering Group Mineral Engineering Technical Services PO Box 5778 St Georges Tce WA 6831 P: (+61 8) 9421 9000 F: (+61 8) 9325 8311 ABN
More informationSTRONG PRE-FEASABILITY STUDY SUPPORTS 1.5 MTPA URQUHART BAUXITE DEVELOPMENT
ASX RELEASE 30 DECEMBER 2016 STRONG PRE-FEASABILITY STUDY SUPPORTS 1.5 MTPA URQUHART BAUXITE DEVELOPMENT HIGHLIGHTS Independent Pre-Feasibility Study (PFS) supports development of the Urquhart Bauxite
More informationFor personal use only
7 August 2012 ASX: PAN Gidgee Gold Project Scoping Study Key Highlights Gold Production estimated at 606,000oz of gold over an initial seven years, average annual production of 87,000oz Operating Cash
More informationdetails on when MTO s are planned for each discipline? for each MTO what scope is planned to be covered? what the procurement action will be?
Project System Audit Material Control Group Note: Not all items of the checklist shall be checked. It depends on the status of the work and whether it is the first, second or third audit. 1. Project Definition
More informationLOWER CHURCHILL PROJECT COST ESTIMATE PROGRESSSION 1998 TO 2011
Page 1 of 15 LOWER CHURCHILL PROJECT COST ESTIMATE PROGRESSSION 1998 TO 2011 Technical Note Date: 29 July 2011 Rec. No. 200 160341 00001 LCP PT MD 0000 IM PR 0003 01, Rev. B1 Page 2 of 15 Contents 1.0
More informationStrong progress made on development of Montepuez Graphite Project
ASX Announcement 27 September 2018 Strong progress made on development of Montepuez Graphite Project Battery Minerals Limited (ASX: BAT) is pleased to advise that the development of its Montepuez Graphite
More informationFor personal use only
ASX Announcement 1st March 2018 Balama Central Graphite Project Scoping Study shows outstanding economics Battery Minerals Limited (ASX:BAT) is pleased to report it has completed a Scoping Study on the
More informationASX Announcement 1st March 2018 Balama Central Graphite Project Scoping Study shows outstanding economics
ASX Announcement 1st March 2018 Balama Central Graphite Project Scoping Study shows outstanding economics Battery Minerals Limited (ASX:BAT) is pleased to report it has completed a Scoping Study on the
More informationSTUDIES CONFIRM COMBINED WILUNA URANIUM PROJECT IMPROVEMENTS
ASX RELEASE 30th January 2014 STUDIES CONFIRM COMBINED WILUNA URANIUM PROJECT IMPROVEMENTS Uranium developer Toro Energy Limited (ASX: TOE) (Toro) today announced the completion of an independent Mining
More informationJemena Electricity Networks (Vic) Ltd
Jemena Electricity Networks (Vic) Ltd 2016-20 Electricity Distribution Price Review Regulatory Proposal Attachment 7-9 JEN cost allocation methodology Public 30 April 2015 Jemena Electricity Networks
More informationOur pursuit of continuous improvement
Western Australia Iron Ore Our pursuit of continuous improvement Mike Henry President HSE, Marketing and Technology 27 October 2014 Disclaimer Forward-looking statements This presentation contains forward-looking
More informationConstruction Waste Measurement Guide
Draft V6 Last updated: February 2013 Construction Waste Measurement Guide A guide to measuring and reporting waste from construction activities 1 Introduction This document provides guidance on how to
More informationFor personal use only
Results of the Phased Implementation Update for the High-Grade Kola Sylvinite Project located in the Republic of Congo Initial project capex reduced to US$908 million After-tax NPV10% of US$1,836 million
More informationADDENDUM NO. 1 FOR CITY OF CUMMING 900-HP RAW WATER INTAKE PUMP. ADDENDUM DATE: February 10, BID DATE: February 15, 2017, 11:30 a.m.
ADDENDUM NO. 1 FOR CITY OF CUMMING 900-HP RAW WATER INTAKE PUMP ADDENDUM DATE: February 10, 2017 BID DATE: February 15, 2017, 11:30 a.m. This ADDENDUM is issued to institute the included changes and/or
More informationFor personal use only
ASX ANNOUNCEMENT / MEDIA RELEASE ASX: ABU 30th September, 2014 ABM s Development Plan & Production Guidance for Old Pirate High-Grade Gold Deposit Highlights: 50,000 to 60,000 ounces of gold production
More informationMorgan Stanley 2013 Emerging Companies Conference An Integrated Australian Mining Services Company June
Morgan Stanley 2013 Emerging Companies Conference An Integrated Australian Mining Services Company June 2013 www.mineralresources.com.au Service Provider Minerals Producer Process Minerals A leading processor,
More informationT S X : R M X N Y S E. M K T : R B Y
T S X : R M X N Y S E. M K T : R B Y News Release A p r i l 1 4, 2015 Rubicon s Phoenix Gold Project Commences Mill Commissioning and Remains on Schedule for Mid-2015 Projected Initial Production TORONTO,
More informationJUNE 2018 QUARTERLY ACTIVITIES REPORT
31 July 2018 JUNE 2018 QUARTERLY ACTIVITIES REPORT HIGHLIGHTS Baobab Expansion Project Feasibility Study due in the fourth quarter of 2018 Processing test work continues with positive results Gadde Bissik
More informationFor personal use only
ABN 79 106 879 690 30 August 2016 The Manager Companies ASX Limited 20 Bridge Street Sydney NSW 2000 (11 pages by email) Updated Internal Scoping Study Delivers Positive Results (ASX: AUK) The Directors
More informationMarket Release Newcrest Mining 15 February 2016
Market Release Newcrest Mining 15 February 2016 Lihir Pit Optimisation Project to progress to Feasibility Study stage As previously advised, a project is being undertaken to optimise the integrated life
More informationWAMBO COAL PTY LTD ENVIRONMENTAL ASSESSMENT. ATTACHMENT 2 Relevant Environmental Planning Instruments and Government Policies
WAMBO COAL PTY LTD NORTH WAMBO UNDERGROUND MINE LONGWALL 10A MODIFICATION ENVIRONMENTAL ASSESSMENT ATTACHMENT 2 Relevant Environmental Planning Instruments and Government Policies A2 PLANNING FRAMEWORK
More informationMining & Metals - EPCM
www.beca.com Mining & Metals - EPCM We make things happen. Problem-solvers with a passion for transforming our world. Beca Mining & Metals Beca is a leading provider in the mining and metals market across
More informationTri-K feasibility study update
Tri-K feasibility study update Feasibility study work to date confirms technical viability of low cash cost operation Mining licence application process commenced, based on technical information submitted
More informationQUALITY INTEGRATED ENGINEERING SERVICES to the energy sector
QUALITY INTEGRATED ENGINEERING SERVICES to the energy sector COMPANY PROFILE offers a complete service including Project Management, Engineering, Procurement, Construction Management, Training and related
More informationTHE KEY ELEMENTS OF QUANTITY SURVEYING WORK
THE KEY ELEMENTS OF QUANTITY SURVEYING WORK A Presentation to the Institution of Surveyors of Uganda by Tom Joseph Mukasa BSc, MSc, MRICS, ICIOB, AISU 2016 1. The following are key elements (divided into
More informationForward Looking Statement
Olympias Forward Looking Statement Certain of the statements made in this Presentation may contain forward-looking statements or information within the meaning of the United States Private Securities Litigation
More informationDoseo Pipeline Project Modularization Overview Advantages/Disadvantages & Drivers
PURPOSE Modularization will be evaluated herein as a cold eyes look into the potential construction technique to be applied to the Doseo Pipeline Project. This analysis will include a review of the drivers
More informationT S X : R M X N Y S E. M K T : R B Y. Rubicon Begins Stockpiling Mill Feed for Projected Production Commencing Mid-2015
T S X : R M X N Y S E. M K T : R B Y News Release D e c e m b e r 1 8, 2014 Rubicon Begins Stockpiling Mill Feed for Projected Production Commencing Mid-2015 TORONTO, Ontario Rubicon Minerals Corporation
More informationSTARVED ACID LEACH TECHNOLOGY (SALT) CONCEPTUAL STUDY. InCoR Holdings Plc MINING AND METALLURGY. April 2014 REPORT Rev. 00 > Internal ref.
STARVED ACID LEACH TECHNOLOGY (SALT) CONCEPTUAL STUDY InCoR Holdings Plc MINING AND METALLURGY April 2014 REPORT Rev. 00 > Internal ref. 140226 Document Number: 140226-0000-49ER-0001 Date: 28/04/2014 Revision:
More information10 CRITICAL STEPS REQUIRED FOR EFFECTIVE EPC BOP COST MANAGEMENT RENEWABLE ENERGY PROJECTS
10 CRITICAL STEPS REQUIRED FOR EFFECTIVE EPC BOP COST MANAGEMENT RENEWABLE ENERGY PROJECTS Engineering, Procurement and Construction Management (EPCM) costs for Balance of Plant (BOP) installations seriously
More informationKoka Project Stands to be a Highly Profitable Gold Mine: Scoping Study
Koka Project Stands to be a Highly Profitable Gold Mine: Scoping Study Chalice Gold Mines Limited ABN 47 116 648 956 30 October 2009 Highlights Scoping Study finds Koka deposit at the Zara Project in Eritrea
More informationThere will be a technical and financial evaluation. Technical evaluation will be 70% and 30% for financial.
ANNEX H (EVALUATION CRITERIA & FINANCIAL PROPOSAL TEMPLATE) There will be a technical and financial evaluation. Technical evaluation will be 70% and 30% for financial. Technical evaluation The returned
More informationBird-in-Hand Gold Project
Bird-in-Hand Gold Project Terramin Australia Limited Economic Opportunities and Regional Development 2 nd August 2017 Presented by: Martin Janes Chief Executive Officer Terramin Australia Limited TERRAMIN
More informationAn introduction to and overview of Shangoni s Approach By Nico Brits
Water Conservation and Demand Management Strategy An introduction to and overview of Shangoni s Approach By Nico Brits Overview Background Introduction to WC/WDM Guidelines Advantages of WC/WDM Plan WC/WDM
More informationMARILLANA MAIDEN HEMATITE ORE RESERVE OF 1.05 BILLION TONNES
ASX Release: 9 September 2010 MARILLANA MAIDEN HEMATITE ORE RESERVE OF 1.05 BILLION TONNES Definitive Mining Studies confirm continuity, quality and quantum of Ore body at MARILLANA Detrital Ore Reserves
More informationEngineering Compliance East London Regional Waste Disposal Site A Case Study
Engineering Compliance East London Regional Waste Disposal Site A Case Study A.S Dookhi, Envitech Solutions (Pty) Ltd, South Africa, nash@envitech.co.za ABSTRACT The East London Regional Waste Disposal
More informationRail Safety Management Procedure General Engineering and Operational Systems - Asset Management of Rolling Stock
1/16 Management of Rolling Stock Revision Date Comments 1 January 2011 Procedure developed to support SMS and legislative requirements. 2 February 2012 Reviewed with RISSB Standards and change of titles
More informationSmartSPEND. KBR SmartSPEND SM. The Economic Approach to Project Development and Execution that Delivers Maximum Project Returns
SM Your Capital Optimized : Project Delivery Execution Strategy Capacity Operations KBR SM The Economic Approach to Project Development and Execution that Delivers Maximum Project Returns KBR SM Approach
More informationAbout Us: 11 Possner Way Henderson WA PO Box 1467, Bibra Lake DC Tel: (08)
About Us: Pozztech Engineering Pty Ltd was founded in 2013 and is 100% Australian owned and operated with our facility located within the Australian Marine Complex, 35km south of the Perth CBD. Pozztech
More informationUpdated Epanko Scoping Study
ASX ANNOUNCEMENT 18 August 2014 Updated Epanko Scoping Study Kibaran Resources Limited (ASX: KNL) is pleased to announce the upgraded Scoping Study ( Study ) completed for its Epanko graphite deposit.
More information45. Feedlot construction delivery
Client Des i gn/ Builder Design Consultant Construction Sub-contractors and suppliers FEEDLOT DESIGN AND CONSTRUCTION 45. Feedlot construction delivery AUTHORS: Rod Davis and Ross Stafford Introduction
More information4 th Drilling Rig Mobilised to drill High- Grade Pipes at SPD Vanadium Project
23 November 2018 4 th Drilling Rig Mobilised to drill High- Grade Pipes at SPD Vanadium Project Figure 1. Drilling equipment being slung into place. Tando Resources (ASX: TNO, Tando or the Company) is
More informationInstructions for completion of full cost recovery budget template: ACCOUNTABLE GRANTS
Instructions for completion of full cost recovery budget template: ACCOUNTABLE GRANTS This guide will assist you in completing the full cost recovery budget template. It explains how to calculate the full
More informationDeveloping Cost Effective Projects
Developing Cost Effective Projects EPCM Contracting in Lower Commodity Cycles Presenter : Darren Naylor Contents Ø SENET Introduction Ø The Mining Industry In Context of Commodity Cycles Ø The EPCM Contractors
More informationRavenswood Expansion Project Update
11 July 2018 Ravenswood Expansion Project Update Highlights AISC down, mine life extended, all required approvals received Significant enhancements have been made to Ravenswood Expansion Project All required
More informationIndustry Employment Day 19th October 2011 Description of required services and products for the SWDWP project
MVV group (EPC contractor and long-term operator) General contact services: André Maurer Robin Scheutzel andre.maurer@mvv.de robin.scheutzel@mvv.de Vacuum tanker services From 2014 throughout the life
More informationJ&K Civil (WA) Pty Ltd Unit 1, 9 Brig Way Bullsbrook 6084 Western Australia Office Phone: (08)
J&K Civil (WA) Pty Ltd Unit 1, 9 Brig Way Bullsbrook 6084 Western Australia Office Phone: (08) 9571 1881 Email: admin@jkcivilwa.com.au Website: www.jkcivilwa.com.au 1 OVERVIEW J&K Civil (WA) Pty Ltd Established
More informationGENERAL DIRECTORATE FOR REGIONAL DEVELOPMENT PHARE FOUNDS
GENERAL DIRECTORATE FOR REGIONAL DEVELOPMENT PHARE FOUNDS M.I.E. IEŞIRE Nr. Ziua «Zi» Luna «Luna» Anul To: «Companie» «Adresa» Fax: «Fax» Dear Ms. / Mr. «Persoana_de_Contact», Subject: Minutes of Meeting
More informationCDM FAQ Sheet
CDM 2015 - FAQ Sheet 1. The change to the regulations means Domestic works are now included. What if you are doing DIY in your own house? Do the regulations apply to this? If the home owner is doing the
More informationDetailed Estimating-Introduction. Dr. Al-Hammad
Detailed Estimating-Introduction By Dr. Al-Hammad Outline Introduction Successful Construction Estimating The Detailed Estimating Procedure The stretch - out - Length concept (SOL) Site Work and Excavation
More informationTHE SISSON PARTNERSHIP
THE SISSON PARTNERSHIP A World-class Tungsten and Molybdenum Deposit in Central New Brunswick NBBTU Conference April 2017 Sisson Project Location Commuting distance from Stanley (26 km) Juniper (22 km)
More informationEnvironmental Management Plan Introduction Environmental Management Objectives Structure, Implementation and Review
Environmental Management Plan Introduction This Environmental Management Plan (EMP) has been prepared for SEF Energy Co. Ltd. for the purpose of providing a stand-alone plan for managing the potential
More informationCompany QESH Management Representative
PROJECT MANAGEMENT Page: 1 of 8 PROJECT MANAGEMENT ISSUE STATUS Issue Date: 11-04-2016 Issued for Use Revision Date: 05-06-2017 Revision No.: 1 Action Position Issued By: Reviewed By: Reviewed By: Approved
More informationCasework Technical Support (Social Welfare - Project Management)
Casework Technical Support (Social Welfare - Project Management) Request for Tenders for Services to MABS NATIONAL DEVELOPMENT The latest date for receipt of tenders is 09 June 2017 Commercial House Westend
More informationRFP/GRC/LSV/ : RENOVATION (CIVIL WORKS) AT SKALA SYKAMNIAS CHILDRENS PLAYGROUND BILL OF QUANTITIES
RFP/GRC/LSV/2017-003: RENOVATION (CIVIL WORKS) AT SKALA SYKAMNIAS CHILDRENS PLAYGROUND BILL OF QUANTITIES 1/7 The Contractor shall consider in his price all costs or expenses of all requirements stipulated
More informationURGENTLY REQUIRED FOR SUDAN Oil Exploration - Operation & Maintenance (O&M) JOBS
URGENTLY REQUIRED FOR SUDAN Oil Exploration - Operation & Maintenance (O&M) JOBS SCOPE OF WORK. Introduction The SCOPE OF WORK as minimum will be carried out within the client oil exploration and development
More information