CLWA Recycled Water Master Plan

Similar documents
1) Venue host presentation: CLWA Overview, CLWA Recycled Water Phase 2 (Shadi Bader)

ADMIN DRAFT (SECTIONS 1-7) Castaic Lake Water Agency Recycled Water Master Plan

12:00 noon 7. Tour of the Silicon Valley Water Advanced Water Purification Center

Implementing Recycled Water at SFIA with a Long-Term Goal of 100% Reuse

Valencia Water Company. Groundwater Softening Demonstration Project

Soquel Creek Water District s Groundwater Recharge Feasibility Study. Lydia Holmes

MMWD Drought Resiliency Committee Meeting

City of San Diego Pure Water Project October 2014

CHAPTER 5 WASTEWATER FLOWS

SCAMA / NOGALES WATER STORAGE STUDY APPRAISAL STUDY

FUNDING WATER REUSE PROJECTS. Stephen M. Jenkins, P.E., CFM

Indirect Reuse with Multiple Benefits The El Monte Valley Mining, Reclamation, and Groundwater Recharge Project

Water Resources Management Strategy

Santa Clarita Valley Family of Water Suppliers WATER USE EFFICIENCY STRATEGIC PLAN. June 24, 2015 WESTERN POLICY RESEARCH

Transforming Wastewater to Drinking Water: How Two Agencies Collaborated to Build the World s Largest Indirect Potable Reuse Project

WATER RECYCLING AND POTABLE REUSE

CHAPTER 5 EXISTING AND PROJECTED WATER AND WASTEWATER CHARACTERISTICS

Amortized annual capital cost ($) + Annual Operating Cost ($) = Unit Cost ($/acre-foot) Annual beneficially used water production in acre-feet (AF)

Carpinteria Valley Recycled Water Facilities Plan Final Report

Meeting California s Water Needs

Regulatory & Research Aspects of the San Gabriel Valley Indirect Reuse Replenishment Project (IRRP)

Becoming the Green-Blue City by Meeting LA s Water Challenges

Alternatives Analysis

Water Reuse in Arizona

Committee on Water. Desalination as a Water Source

U.S. EPA Guidelines for Water Reuse: 2012 Update

STATUS OF POTABLE REUSE IN CALIFORNIA: HISTORY, REGULATIONS AND PROJECTS. Abstract. Key Words. Indirect Potable Reuse Projects in California

Water Supply Water Quality Water Reuse and Conservation Watershed Management Interagency Coordination

WATER STORIES WEST BASIN, CA

Recovery & Concentrate Management

SLIDES: Status of Southern Nevada Water Authority (SNWA): Third Intake into Lake Mead and Groundwater Project

City of Redlands Wastewater Treatment Plant. Redlands, CA LOCATION: Carollo Engineers; CH2M HILL MBR MANUFACTURER: COMMENTS:

Bradley M. Hill, R.G. Utilities Director City of Flagstaff

Latest Developments and Trends in Water Reuse Research and Policies

Beneficial Use of Produced Water: A Case Study of Projects in Colorado and Wyoming

City Council Work Session Handouts. July 21, I. Review and Discuss North Texas Municipal Water District Water Supply Plan and Projects

Raw Water Supply Master Plan Development

Potable Water Supply, Wastewater & Reuse Element

Los Angeles 3 rd Regional

GROUNDWATER RESOURCE MANAGEMENT FUNDAMENTALS: GROUNDWATER BASIN CONNECTIVITY. Open-File Report May 2014

LOS ANGELES. City of Los Angeles. Adel Hagekhalil 1 Marty Adams 2 Inge Wiersema 3. 1 Los Angeles Bureau of Sanitation

Fillmore, CA. Fillmore Wastewater Treatment Plant LOCATION: MBR MANUFACTURER:

Utility in Transition

Feasibility of Aquifer Storage and Recovery in the Upper Colorado River Basin

Raw water sources, facilities, and infrastructure

Managed Groundwater Recharge to Support Sustainable Water Management. A Sacramento Valley Perspective November 8, 2017

The Regulatory Framework

Long Term Water Supply Board of Directors Workshop. March 10, 2015

DEVELOPMENT OF A WATER SUPPLY PLAN FOR POLK COUNTY & ITS MUNICIPALITIES

Stormwater as an Alternative Source of Water Supply: Feasibility and Implications for Watershed Management 1

LEED-2009 Green Building Rating System. New Construction & Major Renovations

A joint effort of the Orange County Water District and Orange County Sanitation District

Overview of Truckee Meadows Water Resources

Water Tomorrow: Foundational Actions Funding Program Metropolitan Water District of Southern California February 23, 2017

United Water Conservation District November 2016 Hydrologic Conditions Report 2017 Water Year. December 6, 2016

3.0 MANAGEMENT ISSUES AND RECOMMENDATIONS

VENTURA RIVER WATER DISTRICT (VRWD) Drought Update and Water Rate Changes

John M. Stomp III, PE

2015 Urban Water Management Plan for Mojave Water Agency

Subsurface Desalination Intake & Potable Reuse Feasibility Studies. TAP Workshop #1 City of Santa Barbara, California August 5, 2015

CITY OF SANTA BARBARA SUBSURFACE DESALINATION INTAKE AND POTABLE REUSE FEASIBILITY STUDIES WORK PLAN POTABLE REUSE.

SOUTHERN NEVADA WATER BRIEFING Prepared for the Legislative Commission's Subcommittee to Study Water

2015 IRP Issue Paper Addendum. Draft Outline. Summary of process and results

Alamogordo Desalination Project

Texas Groundwater Summit

San Diego, A Cadillac Desert; Presentation by: Dana Fi Friehauf, fpe P.E. Water Resources Manager

Apple Valley, CA; Hesperia, CA

PIMA COUNTY COMPREHENSIVE PLAN CO PIMA COUNTY REGIONAL COMPREHENSIVE PLAN POLICY MAJOR PLAN AMENDMENT

TAHOE TRUCKEE SANITATION AGENCY WASTEWATER TREATMENT INQUIRY

Desalination Plans to Solve Water Scarcity

Citizen s Guide: A Handbook to the Draft Environmental Impact Report and Review Process

POTABLE WATER ELEMENT

MAJOR THEMES IN ARIZONA S WATER FUTURE

Partnership Funding for Water Reuse Revenue for Municipalities, Insurance for Industry

Fillmore One to seven million acre-feet in storage depending on calculation assumption; surface area is 20,100 acres.

Constructed Wetlands

THE SANTA YNEZ RIVER CONSERVATION DISTRICT IMPROVEMENT DISTRICT NO. 1 INTRODUCTION

2015 Urban Water Management Plan for Santa Clarita Valley

LOW FOULING REVERSE OSMOSIS MEMBRANES: EVIDENCE TO THE CONTRARY ON MICROFILTERED SECONDARY EFFLUENT

Development of a Groundwater Sustainability Plan

Water Recycling and Reuse

TIERED APPROACH TO EVALUATION AND MANAGEMENT OF PRODUCED WATER IMPACTS ON GROUNDWATER RESOURCES

Option 11. Divert Water from Miocene and Hendricks Canal to Supply the Ridge

Long-Term Reliable Water Supply Strategy Strategy Phase II Final Report

Water and Environment. Monterey Peninsula, Carmel Bay and South Monterey Bay Integrated Regional Water Management Draft Plan

Lake County Success. support through synergistic local partnerships that not only mitigate, but also produce

A Division of The Newhall Land and Farming Company Valencia Boulevard Valencia, CA 91355

SUSTAINABLE WATER BRIEFING. MWRA Advisory Board

WATER SYSTEM MASTER PLAN UPDATE FINAL DRAFT

Task 3: Recycled Water Distribution System Master Plan Cambria Community Services District Cambria, California July 2004 K/J

CFWI STORMWATER SUBTEAM PROJECTS REPORT. Steering Committee Meeting

EXECUTIVE SUMMARY STORMWATER CAPTURE MASTER PLAN

Water, Agriculture and the Environment Conference April 16-17, 2013 Lethbridge, Alberta. Irrigation Development in Saskatchewan

City of Moscow University of Idaho Water Reclamation and Reuse Program

Guide to the Santa Margarita Water District Records. No online items

Summary of Issues Strategies Benefits & Costs Key Uncertainties Additional Resources

Colorado River Challenges Impacts to Southern Arizona

FEASIBILITY ASSESSMENT OF APPROACHES TO WATER SUSTAINABILITY IN THE NORTHEAST METRO SUMMARY DECEMBER 2014

Calleguas TMDLs 2012 Annual Progress Report

Brackish Desalination: Zero Discharge. Thomas F. Seacord, P.E.

Transcription:

CLWA Recycled Water Master Plan WateReuse LA Chapter Meeting @ Castaic Lake Water Agency October 11, 2016 Shadi Bader, PE, PMP Project Manager for CLWA Dawn Taffler, PE, LEED Project Manager for Kennedy/Jenks

Recycled Water Master Plan Introduction and Background Recycled Water Supplies Recycled Water Market Project Alternatives Alternatives Evaluation Recommended Project Next Steps

Study Goal and Objectives Goal: Update the 2002 Recycled Water Master Plan based on recent developments affecting recycled water sources, supply availability and demand, and explore opportunities to maximize the utilization of recycled water in the Santa Clarita Valley. Near-Term Objective: Incorporate updates for Phase 2 Recycled Water System expansion. Support upcoming design work. Assist in pursuit of currently available grants and loans. Mid-Term Objective: Optimize expansion of the non-potable recycled water system. Further investigate next steps for potable reuse. Long-Term Objective: Continue exploration and/or implementation of potable reuse through surface water augmentation and/or direct potable reuse.

Recycled Water Supply Recycled Water Supply (AFY) Total Existing 7,000 15.3 mgd Total Future 17,000 Total SCV Supply 24,000 6.3 mgd Available RW Not all flows can be utilized Limited Saugus after discharge requirement Limited use near Vista Canyon Water Factory Limited use near Newhall Ranch WRP

Recycled Water Market: Non-Potable Reuse Irrigation Demands (AFY) Total Existing 12,500 Total Future 8,400 Total SCV Demand 20,900 Existing demands based on 2013 meter data. Future demands based on includes planned developments through 2035

Future Recycled Water Supply and NPR Demand (2050) Supply Shortfall For Irrigation Opportunity for Potable Reuse

Recycled Water Market: Potable Reuse GWRR = Groundwater Replenishment Reuse SWA = Surface Water Augmentation DPR = Direct Potable Reuse

Recycled Water Market: Potable Reuse Potential Benefits Potable Reuse Opportunities GWRR Surface Spreading Ultimate Demand (AFY) 1,100 to 3,700 GWRR Direct Injection 4,250 Surface Water Augmentation 4,250 Direct Potable Reuse 4,250 * The ultimate demand is based on anticipated available supply in 2050 after non-potable demands are served. Local, drought-proof, sustainable supply Reduce reliance on imported water Use of RW in off-peak irrigation months Supply redundancy in case of SWP interruption Reduce discharges to the Santa Clara River Repurpose unused capacity in the SCVSD AWTF Recharge groundwater basin(s) Maintain lake levels Integrated approach solving multiple issues Potential Challenges High treatment and brine disposal costs High conveyance costs Additional permitting requirements Public acceptance Development of partnerships and agreements Regulatory uncertainty

Project Alternatives Alternative Description Range of Annual Demands (AFY)* Alternative 1 - Non-Potable Reuse Expansion (Phase 2) Phase 2A, 2B, 2C, 2D 186 to 1,374 Alternative 2 - Non-Potable Reuse Expansion (Future Phases) Alternative 3 - Groundwater Recharge (Surface Spreading) Future Expansion North, Future Expansion South, Westside Communities Spreading Site #1 and/or Spreading Sites #3a/b 1,900 to 7,180 1,660 to 3,410 Alternative 4 - Advanced Treatment for Potable Reuse GWRR Direct Injection, SW Augmentation Direct Potable Reuse 4,250 to 4,810 * Some of the Alternative 2 project demands include serving Phase 2 demands. There is insufficient supply to meet all demands for Alternatives 1-4

Alternative 1 Non-Potable Expansion (Phase 2) Phase 2A Phase 2C Phase 2D Phase 2B

Alternative 2 Non-Potable Expansion (Future) Future Expansion North (Alignments E-H) Future Expansion South Kennedy/Jenks (Alignments Consultants A-D)

Alternatives 1 & 2 Non-Potable Expansion Source Water (Tertiary) Valencia WRP....Existing Phase 1, Phase 2a, 2c, 2d, Future Expansions North/South, Part of Westside Communities Newhall Ranch WRP...Part of Westside Communities Vista Canyon Water Factory.Phase 2b Limitations Total NPR Demand in SCV Available supply in summer limits future expansion

Alternative 1 Engineers Opinion of Probable Costs Highest flow Lowest unit cost Capital Cost ($mil) $20.2 $23.6 $24.8 $6.7 $23.5 $3.3

Alternative 2 Engineers Opinion of Probable Costs Highest flow Lowest unit cost Capital Cost ($mil) $77 $71 $123

Alternative 3 GWRR via Surface Spreading Site #1 Off-Stream Site #1 Booster Pump Station (potential site) Phase 2a Alignment Alignment to IPR Pipeline btw Basins Recharge Basin Kennedy/Jenks SCR Diversion Consultants

Alternative 3 GWRR via Surface Spreading Site #3a/b Off-Stream Site #3b Valencia WRP Saugus WRP In-Stream Site #3a Pump Stations (potential sites) Recharge Basin Proposed Phase 2a Alignment Alignment to Recharge Location #3a SCR Diversion

Alternative 3 GWRR via Surface Spreading Site #1, #3a/b Repurpose Infrastructure Off-Stream Site #3b Valencia WRP Saugus WRP In-Stream Site #3a Off-Stream Site #1 Pump Stations (potential sites) Existing Honby Pump Station Recharge Basin SCR Diversion Proposed Phase 2a Alignment Alignment to Recharge Location #3 Existing 14 -dia Honby Pipeline Existing 30-33 -dia Honby Lateral alignment

Alternative 3 GWRR via Surface Spreading Source Water Tertiary RW from Valencia WRP Advanced Treated RW from SCVSD Chloride Compliance Project (Valencia Blend = 70% Tertiary + 30% AWTF) Limitations Available supply of RW Prioritize stormwater capture for recharge Other Considerations Diluent water source (underflow) Interagency agreements (LACFCD) Groundwater management and operations Land acquisition

Alternative 3 Engineers Opinion of Probable Costs High flow Lowest unit cost Capital Cost ($mil) $76 $95 $108 $62 $98

Alternative 4 GWRR via Direct Injection Source Water 100% Advanced Treatment of Valencia WRP Potential Area for Direct Injection Valencia WRP Saugus WRP Other Considerations Brine disposal AWTF siting Injection well siting

Alternative 4 Surface Water Augmentation Castaic Lake Earl Schmidt Filtration Plant Source Water 100% Advanced Treatment of Valencia WRP Limitations Meeting 6-month retention time Other Considerations Brine disposal AWTF siting Interagency Agreements Regulatory Uncertainty Advanced Water Treatment Facility (potential sites) Pump Stations (potential sites) Pipeline alignment (Valencia WRP to Lake) Pipeline extension (to increase retention time)

Alternative 4 Direct Potable Reuse Rio Vista Filtration Plant Earl Schmidt Filtration Plant Source Water 100% Advanced Treatment of Valencia WRP Other Considerations Brine disposal AWTF siting Regulatory Uncertainty Advanced Water Treatment Facility (potential sites) Pump Station (potential sites) Proposed Phase 2a Alignment Short extension to AWPC

Alternative 4 Engineers Opinion of Probable Costs Highest flow Lowest unit cost Capital Cost ($mil) $279 $262 $283

Alternative Evaluation Considerations High Performing / Few Issues Low Performing / More Issues Cost Comparison Water Supply Availability Readiness to Proceed Permittability Required Agency Coordination/ Collaboration Ease of Implementation Environmental Considerations Lowest $ = Alt 2 (Westside Com.) Low $ = Alt 1 (Phase 2B, 2C, 2D) Highest $ = Alt 4 (DPR) High $ = Alt 4 (SWA, Direct Inject) Sufficient = Alt 1 and Alt 4 Uncertain / Limited = Alt 2 and Alt 3 In Progress = Alt 1 Current Permit = NPR (Alt 1 and 2) New Permit = GWRR (Alt 3 and 4) Dependencies = Alt 2 (Supply/New Developments), Alt 3 and Alt 4 (Feasibility Study) Uncertain Permit Requirements = SWA / DPR (Alt 4) Minimal = NPR (Alt 1 and 2) Greater = Alt 3 and Alt 4 Easiest = NPR (Alt 1 and 2) Hardest = Alt 4 Challenging = Alt 3 To be addressed in the Programmatic EIR

Alternative 1 Non-Potable Reuse Expansion (Phase 2) Phase 2B Decision Phase Flow 2CProcess Phase 2D Alternative 3 Groundwater Recharge GRR Feasibility Study Near-Term Projects (Next 5 years) Phase 2A Decision Flow Process

Alternative 1 Non-Potable Reuse Expansion (Phase 2) Phase 2B Decision Phase Flow 2CProcess Phase 2D Alternative 3 Groundwater Recharge GRR Feasibility Study Near-Term Projects (Next 5 years) Phase 2A Alternative 2 - Non- Potable Reuse Expansion (Future Phases) Yes Is GRR Feasible No Mid-Term Projects (5 to 10 years) Yes Is Westside Communities Ready to Go? No Alternative 4 Advanced Treatment for Potable Reuse Westside Communities Future Expansion North Surface Spreading Project DPR Feasibility Study Decision Flow Process

Alternative 1 Non-Potable Reuse Expansion (Phase 2) Phase 2B Decision Phase Flow 2CProcess Phase 2D Alternative 3 Groundwater Recharge GRR Feasibility Study Near-Term Projects (Next 5 years) Phase 2A Alternative 2 - Non- Potable Reuse Expansion (Future Phases) Yes Is GRR Feasible No Mid-Term Projects (5 to 10 years) Yes Is Westside Communities Ready to Go? No Alternative 4 Advanced Treatment for Potable Reuse Westside Communities Future Expansion North Surface Spreading Project DPR Feasibility Study Other Dependencies Future SCR Discharge Requirements Stormwater Diversion Requirements Timing of New Developments Interagency Agreements Public Acceptance Kennedy/Jenks Political Climate Consultants Land Purchase Yes Direct Potable Reuse Is DPR Feasible No Explore other Water Supplies Long -Term Projects (>10 years)

Recommended Project Implement Phases 2B, 2C and 2D of Alternative 1 Non-Potable Reuse Expansion Projects Total Demand = 1,860AFY Complete preliminary design and environmental work for Phase 2A of Alternative 1 - Non-Potable Reuse Expansion Project. Total Demand = 560 AFY Initiate a GRR Feasibility Study to evaluate the viability of Alternative 3 GRR projects. Total Recharge = 1,100 to 3,700 AFY

Recommended Project Phase 2A Phase 2C Phase 2D Phase 2B

Phasing Plan Calendar Year 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 Fiscal Year FY 2015/16 FY 2016/17 FY 2017/18 FY 2018/19 FY 2019/20 FY 2020/21 FY 2021/22 FY 2022/23 FY 2023/24 Y 24/2 Project 1Q 2Q 3Q 4Q 1Q 2Q 3Q 4Q 1Q 2Q 3Q 4Q 1Q 2Q 3Q 4Q 1Q 2Q 3Q 4Q 1Q 2Q 3Q 4Q 1Q 2Q 3Q 4Q 1Q 2Q 3Q 4Q 1Q 2Q 3Q 4Q 1Q 2Q RECCOMMENDED PROJECT Phase 2B P D C S Phase 2D P D C S Phase 2C P D ROW D C S Phase 2A P D D C S GRR Feasibility Study FS Explore DPR Legend Feasibility Study (FS) Decision Point on Feasibility Interdependence Alternate Path if NOT Feasible Planning Phase (P) Design Phase (D) ROW Land Acquisition (ROW) Construction (C) Conversions-Start-up (S)

Implement Phase 2 Projects Next Steps Development of Agreements for Phase 2 Projects Initiate GRR Feasibility Study Track Chloride Compliance Project outcomes (instream flow requirements)

QUESTIONS