CONSTRUCTION STANDARDS SECTION CS 3 TRENCH FOUNDATION, BEDDING AND BACKFILL

Similar documents
SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS

BASED ON DFD MASTER SPECIFICATION DATED 2/24/2014

C. Foundation stabilization for pipe and utility structures.

SECTION GRADING AND SITE PREPARATION CITY OF LEE S SUMMIT, MISSOURI STANDARD SPECIFICATIONS

TRENCH EXCAVATION AND BACKFILL

SECTION EXCAVATION AND BACKFILL FOR UTILITIES AND STRUCTURES

INDEX FOR SPECIFICATIONS FOR JACKING CULVERTS THROUGH EMBANKMENTS SCOPE... 2

SECTION TRENCHING & BACKFILLING

CITY OF FARGO SPECIFICATIONS AGGREGATE BASES

B. Subsurface data is available from the Owner. Contractor is urged to carefully analyze the site conditions.

BASE CONSTRUCTION MATERIALS A Aggregate

DIVISION 31 EARTHWORK 2006 Edition, Published January 1, 2006; Division Revision Date: January 31, 2012

A. Texas Department of Transportation 2004 Standard Specifications for Construction and Maintenance of Highways, Streets and Bridges (TxDOT).

Municipality of Waterville Public Sidewalk Repair Policy

SECTION IV. PIPELINE EXCAVATION AND BACKFILL

StormTech Construction Guide

CONSTRUCTION SPECIFICATION FOR TRENCHING, BACKFILLING, AND COMPACTING

SECTION EXCAVATING, BACKFILLING, AND COMPACTION FOR UTILITIES

ITEM 275 PORTLAND CEMENT TREATED MATERIALS (ROAD MIXED)

SECTION UTILITY MANHOLES AND STRUCTURES

SECTION RIPRAP, BOULDERS, AND BEDDING

2.1 Backfill - General

1. All underground utilities under railroad tracks shall be encased in a larger pipe or conduit called the casing pipe.

PERMEABLE INTERLOCKING PAVERS

SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 5/8/7)

CW 3615 RIPRAP TABLE OF CONTENTS

SECTION PERMEABLE INTERLOCKING CONCRETE UNIT PAVEMENT

SECTION AGGREGATES

SECTION BITUMINOUS CONCRETE PAVEMENT

Construction Specification for Concrete Unit Pavers

SECTION FOUNDATION DRAINAGE

1. Initial Backfill: Backfill placed beside and over pipe in a trench, including haunches to support sides of pipe.

Summary of the 2011 Changes

CONCRETE SEGMENTAL RETAINING WALL SYSTEM

DIVISION 33 - UTILITIES SECTION UTILITY PIPE BORING AND JACKING DIVISION 33 UTILITIES SECTION UTILITY PIPE BORING AND JACKING

SPECIFICATIONS FOR STREET CONSTRUCTION WITHIN THE TOWN OF PLAINVILLE

ITEM D-701 PIPE FOR STORM DRAINS AND CULVERTS

SECTION DUCTILE IRON FITTINGS. A. This section includes materials, installation, and testing of ductile iron fittings 48 inches and smaller.

SITE SERVICES GUELPH TRANSIT OPERATIONS & MAINTENANCE SECTION WATSON ROAD FACILITY PAGE 1 OF 6 WATER RECLAMATION PROJECT JUNE 2013

***************************************************************************************************************

SECTION FACILITY SANITARY SEWERS

Table of Contents. Section Trench Excavation and Backfill Section Includes Description of Work 1. 1.

ITEM 6 CONCRETE CURBS, GUTTERS, AND SIDEWALKS

LS 2519 CONCRETE PAVER PAVEMENT RECONSTRUCTION

SPECIFICATIONS FOR BRIDGE CONSTRUCTION SECTION 2 BACKFILL. 2.1 General...2-1

The Work under this Section consists of performing all operations necessary to complete construction of the leveling course on the prepared subbase.

CITY OF TACOMA RIGHT-OF-WAY RESTORATION POLICY. Guidance on restoration of City Rights-of-Way

Best Management Standards / Specifications. For Concrete Slab Raising. Prepared in conjunction with the Concrete Repair Association

SECTION CAST-IN-PLACE CONCRETE

SECTION 20 INDEX PAVING FABRIC 1. SCOPE OF WORK MATERIAL REQUIREMENTS CONSTRUCTION AND INSTALLATION REQUIREMENTS...

CONSOLIDATED EDISON COMPANY OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY DISTRIBUTION ENGINEERING TOOLS AND STRUCTURES

SECTION A1 EXCAVATION AND BACKFILL GENERAL

City of Reno Public Works 1 E. 1 st Street, 8 th Floor P.O. Box 1900 Reno, NV (775) (775) FAX

A. Texas Department Transportation 2004 Standard Specifications for Construction of Highways, Streets and Bridges (TxDOT):

SECTION EXCAVATION BACKFILL AND COMPACTION FOR UTILITIES

STATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENTAL SPECIFICATION 811 CONDUIT AND DRAINAGE STRUCTURES

BIO-AQUIFER STORM SYSTEM

CW 3620 INSTALLATION OF UNDERGROUND TRAFFIC SIGNAL SERVICES TABLE OF CONTENTS

Fox Avenue Improvements From Gamebird Road to Dalton Street Bid # PROJECT SPECIFICATIONS TABLE OF CONTENTS

***************************************************************************************************************

SECTION 26 - COLD PLANE ASPHALT CONCRETE PAVEMENT TABLE OF CONTENTS

BIDDING SCHEDULE SEWER LIFT STATION NO. 2 REPLACEMENT PROJECT CITY OF ALHAMBRA City s Project No. N2M17-83

Installation Specifications for Interlocking Concrete Pavements

OPTIMIZED 3/4" GRADATION LIGHTWEIGHT AGGREGATE REPORT

SECTION SPECIFICATION FOR STONEBRIDGE RETAINING WALL SYSTEM

SECTION C1 DUCTILE IRON PIPE AND FITTINGS GENERAL

PART V TECHNICAL SPECIFICATIONS SANITARY SEWER CONSTRUCTION TABLE OF CONTENTS

BAYFILTER SPECIFICATIONS

4-07 Asphalt Treated Permeable Base (ATPB)

SPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006

Flygt Advanced Low Pressure Sewer System Package

February 22, 2018 BIDDERS WILL ACKNOWLEDGE RECEIPT OF THIS ADDENDUM IN THE SPACE PROVIDED ON THE PROPOSAL PAGE

R-TANK SPECIFICATIONS

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING)

PASSAIC COUNTY TECHNICAL INSTITUTE CCA 1422 NEW S.T.E.M. BUILDING 2017

CHAPTER 7 PAVEMENT DESIGN. 1. Gradation (sieve and hydrometer analysis) 3. Moisture density relationships and curves

CITY OF EDMOND STANDARD SPECIFICATIONS FOR CONSTRUCTION

DESIGN STANDARDS. Division 02 Existing Conditions- Site Work. General

PAVING SLABS ON A CONCRETE BASE

Cement Stabilized Soil (CSS) (Portland cement)

DRAFT Guidance Specification for Porous or Dense-Graded Asphalt Pavement Structures for Storm Water Management Revised July 28, 2016

SPECIFICATIONS FOR FULL DEPTH RECLAMATION WITH CALCIUM CHLORIDE

UNHSC Bioretention Soil Specification February, SOIL PREPARATION (PERFORMANCE SPECIFICATION) for Bioretention Systems

Uwall UNIVERSAL CONSTRUCTION MANUAL

SECTION EROSION AND SEDIMENTATION CONTROLS

Fabrication and Installation Table of Contents

CHAPTER 6. Sanitary Sewer

SOLID WALL PVC SEWER PIPE

BID # REPAIR AREA OF PARKING LOT DAMAGED BY WATER LINE LEAK SECTION C TECHNICAL SPECIFICATIONS OWNER

SOLID WALL PVC SEWER PIPE

File No Supplemental November Geotechnical and Environmental Consulting Engineers

SECTION 820 PUMP STATION DEMOLITION AND SITE RESTORATION

Contact the Jurisdictional Engineer for materials allowed by each jurisdiction.

Stanford University Facilities Design Guidelines SECTION SEAL COATS. C. Section : Traffic Striping and Pavement Markings

SECTION GRAVEL PACKED WATER WELL

PHILADELPHIA GAS WORKS SPECIFICATION BOOK For Common Trenching For Natural Gas Mains and Services

SUBSURFACE INFILTRATION SYSTEM DESCRIPTION. Alternative Names: Sump, Drywell, Infiltration Trench, Infiltration Galleries, Leach Fields

SECTION 402 PLANT MIX BITUMINOUS SURFACE LEVELING

Transcription:

CONSTRUCTION STANDARDS SECTION CS 3 TRENCH FOUNDATION, BEDDING AND BACKFILL CS 3-01 GENERAL: A. The foundation, bedding and backfill for all trenches shall conform with the requirements of the City Standard Specifications and the Drawings. These requirements also apply to non City-owned Utilities located within the City rightof-way. The Project Plans may require more stringent requirements than specified in the City Standard Specifications and Standard Drawings. B. The trench foundation shall be defined as the material below the bottom elevation of the bedding. C. Bedding shall be defined as that material supporting the pipe from the trench foundation surrounding, and extending to one foot above the top of pipe. D. Backfill for all pipe materials other than CAST-IN-PLACE CONCRETE PIPE (CIPCP) shall be defined as that layer of material extending from above the bedding material to the elevation of the subgrade within the proposed or existing paved area. The limits of backfill for CIPCP shall be defined as provided for in Section CS 10-02B CAST-IN-PLACE CONCRETE PIPE. The backfill shall extend to the finish grade and conform to the adjacent grade where the trench is located within an unpaved area. E. No jetting will be allowed for trench bedding or backfill. F. All existing pipes within the trench zone and any other facilities adjacent to the trench shall be supported and protected from damage as a result of the Contractor s operations. CS 3-02 SPECIAL FOUNDATION TREATMENT: A. Special foundation treatment shall be required whenever the bottom of the trench has been over excavated as required in Section CS 2, Trench Excavation, of the City Standard Specifications. B. The over excavated portion of trench shall be backfilled with Crushed Rock in accordance with these City Standards. C. Geotextile filter fabric shall be placed between the Crushed Rock and bedding material where sand is required as the bedding material. Trench Foundation, Bedding, and Backfill Page CS 3-1 CS-SEC 03-REV: 13 Feb 07

D. An additional layer of Geotextile Fabric may be required to stabilize the trench bottom. The specification for this fabric shall be as approved by the Director of Public Works. CS 3-03 BEDDING: A. Particular attention must be given to the placement of the bedding material to ensure that firm support to the pipe is obtained to prevent any change in alignment of the pipe. B. The bedding shall be shaped to accommodate the pipe bell and other related appurtenances to allow the bottom of the pipe to be supported uniformly by the bedding. The bedding material shall be sliced into the haunch of the pipe with a shovel or other hand tool to fill the voids in this area. The remainder of bedding shall be carefully placed and consolidated to the proper depth in eight (8) inch maximum lifts. C. Bedding Material 1. Bedding materials for non City-owned utilities shall conform to the Utility Company specifications except that at a minimum, the material shall conform to the minimum requirements for Bedding Material as specified in these City Standard Specifications whenever the trench is located within the limits of an existing paved area. 2. The requirements for bedding material shall not apply to trenches constructed by the method of Rock Wheel Excavation. 3. Bedding material for ductile iron pipe and all water main and service pipe installations shall consist of sand with 100% passing the #4 sieve and a minimum Sand Equivalent value of a 30. 4. Bedding and backfill for street lighting conduit installation shall conform to Section CS 15, Street Lighting of the City Standard Specifications and the Standard Drawings. 5. Bedding and backfill for traffic signal conduit installation shall conform to the provisions of the Caltrans Standard Specifications except that Asphalt Concrete shall conform to the City Standard Specifications. 6. Bedding material for all other City-owned utilities and structures shall consist of Crushed Rock conforming to the criteria in Table CS 3-1 and other requirements listed. Trench Foundation, Bedding, and Backfill Page CS 3-2 CS-SEC 03-REV: 13 Feb 07

Table CS 3-1 Crushed Rock Gradation Requirements Sieve Size Percent Passing 1 inch 100 ¾ inch 90-100 ½ inch 20-50 No. 4 0-5 90% of the aggregate shall have at least one fractured face. 75% of the aggregate shall have at least two fractured faces. 50% of the aggregate shall have at least three fractured faces. CS 3-04 GEOTEXTILE FILTER FABRIC: A. The contractor shall install nonwoven geotextile filter fabric between the Bedding and Backfill material in such a manner to prevent migration of the backfill material into the bedding whenever Crushed Rock is used as bedding. B. Geotextile Filter Fabric shall conform to the requirements specified in Section CS 7, Geotextile Fabrics, of the City Standard Specifications. CS 3-05 BACKFILL: A. The Contractor shall not place any backfill material until the Inspector has inspected and accepted the placement of the Bedding. B. Backfill shall conform to the Standard Drawings. C. Native material and Class II Aggregate Base Rock backfill shall be placed in uniform layers. The thickness of each layer of backfill shall not exceed eight (8) inches before compaction. Compaction equipment or methods which may cause displacement or damage to the pipe shall not be used. D. EXISTING PAVED AREAS: Trenches located within the existing paved areas shall be backfilled with Class II Aggregate Base Rock (Aggregate Base) conforming to the City Standard Specifications. The Aggregate Base backfill shall Trench Foundation, Bedding, and Backfill Page CS 3-3 CS-SEC 03-REV: 13 Feb 07

be compacted to the requirements indicated on the Standard Drawings. The Aggregate Base shall be placed to the elevation to allow for placement of Asphalt Concrete in accordance with the Standard Drawings. Temporary paving shall be installed and maintained until final pavement is completed. Asphalt Concrete shall conform to the City Standard Specifications and placed in accordance with the Standard Drawings. E. NEW PAVED AREAS: Trenches located within new paved areas (areas required to be paved with the Project Plans) may be backfilled with native material providing that the native material is free of rock(s), rubbish, debris and other objectionable material. The maximum size of any component of the native material shall not exceed 2-1/2 inches in size. The backfill shall be compacted to the requirements indicated on the Standard Drawings. When the required compaction can not be achieved with the native material, select import material shall be required. The backfill shall be placed up to the new pavement subgrade elevation shown on the Project Plans. F. UNPAVED AREAS: Trenches located within unpaved areas may be backfilled with native material providing that the native material is free of rock(s), rubbish, debris and other objectionable material. The maximum size of any component of the native material shall not exceed 2-1/2 inches in size. The backfill shall be compacted to the requirements indicated on the Standard Drawings. When the required compaction can not be achieved with the native material, select import material shall be required. The backfill shall be placed to final grade to conform to the elevation of the adjoining surface elevation. CS-3-06 TUNNELING, BORING, AND JACKING: A. Tunneling, boring, and jacking shall only be permitted when approved by the Director of Public Works. B. Any pipe or facility that is placed underground in any method other than open cut trenching (including rockwheel trenching) shall be considered as tunneling or boring and jacking. C. All existing utilities shall be potholed for actual depth prior to tunneling or boring and jacking. D. All voids between the inside of the casing and the pipe shall be completely backfilled by blowing sand or pumping grout between the casing and the pipe. Trench Foundation, Bedding, and Backfill Page CS 3-4 CS-SEC 03-REV: 13 Feb 07

CS 3-07 ROCKWHEEL TRENCH: Where allowed, rock wheel excavation and backfill shall be performed in accordance with the City Standard Specifications and Sections 19 and 86 of the Caltrans Standard Specifications, except as modified below: A. The conduit shall be placed in the bottom of the trench and the trench shall be backfilled with slurry cement backfill containing not less than 282 lbs. of Portland cement per cubic yard. B. Slurry cement backfill shall be backfilled to within 1-1/2 inches of the finish grade, and then topped with permanent Asphalt Concrete in accordance with the City Standard Specifications. All rockwheel trenching shall be performed prior to any Asphalt Concrete overlay being placed. CS 3-08 UTILITY COMPANY CONDUIT INSTALLATION: Installation of Utility Company conduit shall be done by either open cut trenching (when the trench width is greater than six inches), rockwheel trenching (when the trench width is six inches or less) or by bore and jack. The method of installation shall be shown on the Project Plans and subject to the approval of the Director of Public Works. When Utility Company conduit installation is performed by open cut trenching and the trench width is greater than six inches, the trench, bedding and backfill shall conform to the requirements of Standard Drawing 3-21 and the City Standard Specifications. When the Utility Company conduit installation is performed by rockwheel trenching, the trench, bedding and backfill shall conform to CS- 3-07 and the City Standard Specifications. When the Utility Company conduit installation is performed by bore and jacking, the installation shall conform to CS- 3-06 and the City Standard Specifications. Trench Foundation, Bedding, and Backfill Page CS 3-5 CS-SEC 03-REV: 13 Feb 07